LTC 212-2019 Implosion of 630 Alton Road site (South Shore Hospital) MIAMI BEACH OFFICE OF THE CITY MANAGER 212-2019 LE IyI'ER TO COMMISSION TO: Mayor Dan Gelber and Members oft City Comr -sion FROM: Jimmy L. Morales, City Manager f • 1 DATE: April 11, 2019 SUBJECT: Implosion of 630 Alton Road site (South Shore Hospital) There have been some questions regarding the implosion permit for the South Shore Hospital site. The purpose of the LTC is to provide the most complete up to date information. Assistant City Manager Eric Carpenter coordinated all the City departments Police, Fire, Public Works, Building and Tourism & Culture to identify the least impactful date and time for the implosion, coordinating around traffic, special events and safety concerns. • The Building Department has been in contact with the contractor BG Group LLC (Steven Greenberg) throughout the process. Blaster Controlled Demolitions Inc., (Field operations manager Thom Doud) will be on site throughout the preparation and blasting process. • The Public Works Department has reviewed the necessary road closures and MOT as well as the facilities protection report and the vibration monitoring plans provided by the engineers. Both the implosion demolition plans, and the necessary road closure permits have been approved. • The Fire Department Fire Prevention Division has reviewed the storage magazines and the distances to buildings and roadways. • Miami-Dade County Environmental Resource Management has reviewed the plans, including the asbestos survey pursuant to 40 CFR 61 subpart M (National Emission Standards for Hazardous Air Pollutants) and F.S. 469.001-015, of the existing building and has approved the permit for demolition by implosion. • The Police Department will secure all the necessary exclusion zones to ensure the safety of residents in the surrounding buildings and area. The entire process should take between one —two hours. The sequence of events is attached. Both the contractor and the owners have been providing notices (Attachment #1) to the neighboring properties. A pre-implosion meeting was held last Thursday April 4th at 6:00 p.m. (Attachment #2). The contractor has also provided a detailed list of the areas and properties and buildings to be protected (Attachment #3). Steven Greenberg has indicated that the dust should dissipate within minutes of the implosion. The Marketing and Communications Department will be disseminating this information using our social media platforms and traffic text system. Finally, the structural modification permit BC1910377 had its approved final inspection prior to issuance of the demolition permit. The County Blast Permit (issued by Miami-Dade Department of Transportation and Public Works Construction Division) is required by the city prior to allowing the explosives to be brought to the site and can be issued now that the building permit is issued. If there are any new developments, we will advise the Mayor and Commission. If you have any questions, please contact ACM Eric Carpenter. Thank you. JLM/SMT/AS M • lir , . a500 vourrio 4 6 : • rf , MI - , fy►S �'' y ...•..4,..;,,.mrip.": 44.. , i{4. ...1- ..rte'. ` _� I dr- 4 %.. _ .%44,...2.-'' b ..mom a .. , I. . . '• - • • ��' 'w ¢f a', 'M` %P- A : ,,> ` 'C C r . t r IN t . y ± ' ' ijP Y t4.0 Y. e� ,, .. ' ': r 7-,. Is` .'tel."_ _ '^ k. 14,i 1 �7 , ,•i y.. a Ff ` yam ' Nib s, I t �`' a Mist's cdRceptual rdnelErmgi ... IMPLOSION LOCATION April 16, 2019 10:00AM 600 Alton Rd. Miami Beach Sequence of Events 8:00-8:30AM 9:59AM -* Setup of barricades commences to secure the -* Sound three (3), 1-second long horns or sirens Exclusion Zone indicating 15 seconds to blast - Police on site Note:If there are any security or other issues that prevent the --, A Command Post will be established on Alton Road, implosion from proceeding,CDI's countdown will go into a"hold" to the north at ten(10)seconds and recommence at this point once such issues have been resolved. 9:00-9:59AM -> Final confirmation that the security area is clear -9 Exclusion Zone to be cleared.CDI or BG Group personnel in touch with the Command Post will be 10:OOAM placed in the lobbies of the adjacent residential - An audible countdown ("10,9,8..:')over CDI's radios properties to ensure that residents do not exit the will be performed structure and enter the Exclusion Zone during the - 600 Alton Road Building is imploded countdown. -9 Area security to be checked.Confirmation from local 10:00-10:30AM authorities that the Exclusion Zone is clear,save for -* CDI will inspect the demolition area and sound a five traffic on Alton Road (5)second long signal to designate an"All Clear:' -* Confirm that the Exclusion Zone is clear -, Control of the demolition site and adjacent streets -4 Traffic on Alton Road will be stopped and cleared at will be returned to BG Group for dust cleanup and 9:45AM reopening of streets for traffic in cooperation with -* Sound two (2),5-second long horns or sirens the local authorities. indicating 2-minutes to blast at 9:58AM See Disclaimers Page. ; iiti. 500 ...• v . S. . T.-"'''. Telt 7- Alton - .... ,. . , . __ �+ , CC „� IX i ll a etaar4 '," •Q i t 1 ifs-., -w • 4 • ji .�� ' . . • - . . .. • 1=-- -°- 7• _ Ex •, • • I' I i" i, ! -a- am I , T �.- tPVII "1 1\''.. 1 SIE I1 lIIII OW. .„ Implosion 1 j • '' 1 .. �: e ! ' jt �"'- r , 1 "tClik 4 ,31 \ , Exclusion Zqn , - .4..'� 4' I 4 -47-1 _ , • R *olio. ..,P;�----- r � 5TH S a '� ��- s 4n Conditions Following the Implosion The building will collapse within 12 to 16 seconds after COI will inspect the debris pile and issue the"All Clear;' implosion charges begin to detonate in the initiation turning the site and adjacent streets back over to BG system.The structure will fall to create a debris pile Group for follow-on operations. which will primarily be within the footprint of the structure and slightly to the north and west of that Immediately following the"All Clear,"BG Group's crews footprint. BG Group will have equipment staged,with will begin dust cleanup operations and removal of operators and demolition attachments,on site the any previously-placed adjacent property protection. morning of the implosion to stabilize the debris pile,as The disposition of dust following the implosion will may be needed,to ensure that the debris pile does not be a direct function of the prevailing wind speed and impose any risk to the public on the two (2) adjacent direction at the time of the implosion. streets following the implosion. This project is being developed by TCH 500 Alton,LLC,a Florida limited liability company('Developer".All images and designs depicted herein are artist's conceptual renderings,which are based upon preliminary development plans,and are subject to change without notice in the manner provided in the offering documents.All such materials are not to scale and are shown solely for illustrative purposes.The Developer reserves the right to modify,revise or withdraw any or all of the same in its sole discretion and without prior notice.All improvements,designs and construction are subject to first obtaining the appropriate federal,state and local permits and approvals for same.The Sequence of Events is only the Developer's proposed timeline,and is subject to approval of applicable governmental authorities.The Sequence of Events as stated herein should not be considered the actual sequence of events,and should not be relied upon for any reason.The project graphics,renderings and text provided herein are copyrighted works owned by the Developer.All rights reserved.Unauthorized reproduction,display or other dissemination of such materials is strictly prohibited and constitutes copyright infringement M. YOUR ATTENTION PLEASE South Beach Heights I, LLC (Owner), The BG Group, LLC, (General Contractor), and Controlled Demolition, Inc. ("CDI" - Implosion Subcontractor) would like you to be aware that on April 16, 2019, the vacant South Shore Hospital will be demolished by implosion. Implosion is a process where a small amount of explosives is used to disrupt selected supports in a building. This allows gravity to pull the structure down in a controlled manner. CDI has used this implosion method thousands of times around the world during the past 65 years to assist Property Owners and Contractors in the removal of unwanted structures. There are three (3) points we would like to make you aware of: 1. Dust is an unpreventable byproduct of all types of demolition. With a wrecking ball or high-reach excavator, the building is slowly broken up releasing dust over a lengthy period of time. With implosion, the same overall quantity of dust is released in a matter of seconds, and may linger in the general area for 4 to 6 minutes before crews begin cleanup of same from streets and sidewalks. Depending on wind speed and direction on the day of the implosion, the dust may or may not reach your properties. As a precautionary measure, we recommend you see that all windows, doors and air intakes are closed, and cover any other openings that might allow dust to enter your apartment, house or building. We also recommend you turn off all exhaust fans before or at the time of the implosion as these might draw air in to your building through cracks in walls and windows. 2. Early Tuesday (April 16th) morning, the City of Miami Beach Police Department will set up an Exclusion Zone around the buildings. This is to prevent people from getting too close. We need your cooperation with the Police and contractors to ensure this is a safe job. Everything they say to you or ask of you is to minimize inconvenience or to promote safety. 3. There will be heavy dust in the block immediately surrounding the demolition site. Dust may also drift outside and downwind of the Exclusion Zone, depending on weather conditions. If you find dust uncomfortable or irritating, or if you have any respiratory conditions that would be aggravated by dust, please stay indoors during the demolition. 4. More than 100 years of vibration/noise monitoring data assembled by the US Bureau of Mines established guidelines for safe vibration and noise levels around blasting sites. For several days prior to the implosion, a pre-demolition photographic survey will be made to document the pre-existing condition of adjacent structures and properties in accordance with State Law. Noise and vibration monitoring instruments will be set up around the demolition site to monitor actual levels of same generated by the implosion/fall of the South Shore Hospital structure. A follow-up post-implosion survey will be made the morning of the implosion to determine whether or not any changes have taken place in the structures previously inspected, as a result of the implosion. The vibration and pre/post-survey reports go to the State of Florida to protect the interests of all parties involved. Should you have any questions, please direct them to: The BG Group, LLC Ivy Fradin 561-998-7997 knirnlhorlcmnlitinn rnm THE BC GROUP! LIB April 10, 2019 Ana M. Salgueiro, P.E., Director, Building Official Building Department 1700 Convention Center Drive, Miami Beach, FL 33139 Re: 600 Alton Protection Dear Ana: I walked the surrounding neighborhood Tuesday and noted the following items to be addressed: CID • Muzzafiato Building. There are 6 doors to be protected that we, The BG Group (BG), will seal with 3" blue painters tape*. i • The Bentley, 520 Alton. The front glass doors on the north side will be closed and taped. * • The Bentley, 540 Alton. A BG employee will remain in the lobby to remove tape after blast. o South side. The front glass doors will be closed and taped. * o North side. There are 3 doors to be taped and 1 vented door that will be sealed with poly sheeting and tape.* • The Floridian. BG will tape and have an employee remain in lobby to unseal the following.* o South side. 2 doors and 3 vents to be protected. o East side. 1 door and 5 vents. Oo Main entrance. 1 door IME o Northeast side. Vented doors will be completely sealed. = o Receiving area. 2 doors and a window AC unit to be wrapped. • Community Health Center. We will wrap roof AC units if permitted. O • Baptist Health. BG will tape and unseal 1 door on the west side.* • CubeSmart. Spoke with owner Ken Edelman. He will not open until after the blast. BG will tape and unseal the following.* o West side. 2 doors o South side. 2 doors o Roof. Wrap AC units • St. Francis Church. AC units and fan/duct will be wrapped and unsealed by BG.* Spoke with office manager who will speak with maintenance about turning AC off and if any additional protection is desired. The doors are all wood and very secure. • Publix. Met with manager and asst. manager. Doors will be locked—9:30 and customers will be allowed to leave via the emergency doors on the east side. We will have a BG employee in the store during the blast to unseal and remove the tape after the dust clears.* o North side. 4 '/2 doors and one ATM to be protected o West side. 1 door. 2 100 yd. trailers will be parked under the Alton Rd. overpass. Sincerely: Steve Ctreev k erg BG will seal on or about 8 am on April 16 and then have someone unseal and remove the tape asap post blast as soon as the dust clears. 15560 Lyons Road•Delray Beach,FL•33446.561-998-1991•sieve@bgdemolition.com•CsC1511135