LTC 346-2019 CIP Monthly Construction Projects Update /\ MAMIBEIALH OFFICE OF THE CITY MANAGER NO. LTC# 346-2019 LETTER TO COMMISSION TO: Mayor Dan Gelber and Members of he City ommission FROM: Jimmy L. Morales, City Manager DATE: June 10, 2019 SUBJECT: CIP Monthly Construction Projects Update Below please find the monthly update for active City of Miami Beach construction projects under the purview of the Office of Capital Improvement Projects (CIP). 42"d Street Improvements Scope: 42nd is a one-way, two lane corridor between Pine Tree Drive and Prairie Avenue. Traffic studies confirmed that making this a two-way road will improve traffic, and benefit safety, by providing signalized pedestrian crossings at the intersection of Pine tree Drive and 42nd street. Existing traffic signals at the intersection of Pine Tree Drive and 42nd street will be retrofitted to serve eastbound traffic. Status: The project is 60% complete. The utilities conflict with the traffic signal has been resolved and the installation is scheduled for mid-June. The tree removal permit has been issued and the notification period is currently on going. The installation of the drainage structures is continuing. Anticipated Completion: July 2019 Altos Del Mar Park Scope: Park Improvements include new landscape, irrigation, site lighting, sand volleyball courts, walkways, terraced lawn, and new restroom building. Status: The project is 85% complete. The irrigation is nearing completion and the landscaping activity has commenced. Work on 76th Street has commenced. The construction progress continues to suffer which is affecting the completion date. Anticipated Completion: July 2019 Beach Lifeguard Towers Replacement Scope: Construction of 35 lifeguard towers. Status: Final two towers are being assembled at the 19th Street staging area. Punchlist and close-out is ongoing. Anticipated Completion: Spring 2019 Carl Fisher Clubhouse Restoration Scope: Historical restoration of the Carl Fisher Clubhouse (interior and exterior) and adjacent site and landscaping work. This project is part of the Convention Center Renovation Project. Status: The project is 30% complete. The contractor continues to perform structural repairs and modifications and the electrical, mechanical and plumbing rough-in work is ongoing. Anticipated Completion: October 2019 1 Central Bayshore South Neighborhood Improvements Scope: Neighborhood improvements bounded by 34th St. to the north, Pine Tree Dr. to the east, 28 St. to the south, Prairie Ave to the west and Meridian Ave from 28 St. to Dade Blvd. Status: Water main installation is complete. Drainage design is currently at 75% and on hold waiting for Commission directive, based on Jacobs Engineering's review of the City's stormwater criteria and prioritization and sequencing of projects. Anticipated Completion: TBD Collins Park Parking Garage Scope: Demolition of existing structure and construction of a new parking facility which consists of a seven (7) level parking garage with 513 parking spaces and approximately 15,000 SF of retail spaces at the ground level. Liberty Avenue will be closed and used for vehicular ingress and egress from 23rd Street to the Collins Park Garage. The balance of the roadway (to 22nd Street) is planned as a pedestrian plaza with associated amenities. Status: Installation of the piles and footers is 70% complete and anticipated to be completed in mid-June. Grade beams, well structures, trench drain system and foundation systems are expected to be completed in mid-July. Installation of precast structures expected to start end of July. The project has experienced delays associated with County traffic permit reviews, the discovery of underground storage tanks, and related DERM clean-up and dewatering requirements. Anticipated Completion: May 2020 Convention Center Park (P-Lot) Scope: A new 5.8-acre park, replacing the existing surface parking lot located across the street from the newly renovated Convention Center. The park will include open lawn spaces, shade areas, walkways, lighting, a veteran's plaza, a public restroom facility, and a flexible area space. Status: The project is 20% complete. The asphalt has been removed and the storm drainage in the southeast quadrant has been installed. The contractor has commenced layout and formwork of the foundations for exhibit tents and underground electric for the exterior lights. Anticipated Completion: October 2019 Flamingo Park Fitness Cluster Scope: Constructing a new outdoor Fitness Area in Flamingo Park to include new ADA accessible fitness equipment, new concrete pathways, a new canopy shade structure, added lighting, as well as drainage, landscape and irrigation improvements. Status: The project is 30% complete. The drainage, footings and the steel columns for shade structure have been installed. The fitness equipment has been delivered to the site. Anticipated Completion: July 2019 Flamingo Park Handball Courts Scope: Renovation of existing handball courts to include various electrical upgrades, new general lighting, stucco repairs, court resurfacing, new frameless windows and doors and new fencing and painting. The courts will also include seating areas and water drinking fountains for players and visitors. As a result of community input and requests, the project was split into two phases, in order to provide uninterrupted usage of the 2 courts. • Status: The project is 45% complete. The storm drainage installation is complete, and sports lighting has been installed. Paint removal for the Joe Rubin building is complete. During paint removal, it was discovered that large areas of stucco were delaminating or failing. The project team is evaluating the condition of the stucco and substrate, in order to determine a plan of action. Anticipated Completion: October 2019 Flamingo Parkwide Improvements - Phase I Scope: Park wide renovations to include landscape, irrigation & drainage improvements, as well as addition and renovation of walkways and pedestrian lighting. Status: The project is 25% complete. The storm drainage is currently being installed in the areas adjacent to the east-west promenade. The electrical rough-in for pedestrian lighting is being installed and the concrete bases for the lighting were fabricated and delivered. Anticipated Completion: August 2019 Middle Beach Recreational Corridor Ph. 2 — Section 2 (Beachwalk) Scope: Construction of an on-grade paver pedestrian walkway, including turtle friendly lighting, landscaping and irrigation, encompassing eight (8) City blocks from 46st to 53 st Status: The project is 99% complete. The contractor is currently working to finish clean- up and fence removal, ahead of the planned ribbon cutting ceremony. Anticipated Completion: Ribbon Cutting scheduled for June 13, 2019 North Shore Bandshell Canopy Scope: Design, manufacture and install a custom canopy at the North Beach Band Shell facility. The area of coverage for the canopy is approximately 4,000 square feet. Status: The 60% design documents were submitted on May 3, 2019. The project received approval at the May 7, 2019 DRB meeting. The consultant is proceeding to the 90% construction documents submittal, currently scheduled for June 14, 2019. The upcoming submittal will address DRB conditions and Planning Department concerns. The anticipated construction start date is August 2019. Anticipated Completion: November 2019 Palm & Hibiscus Island Neighborhood Improvements Scope: Neighborhood improvements on Palm and Hibiscus Islands. Status: The original contract scope of work is 95% complete. Additional scope of work (generators and new drainage directive) resulted in an increase in the contract amount. In order to complete the harmonization scope, the design-builder must first work with DERM to complete the design and permitting of the additional drainage work. Based on the new contract amount, the project is now 89% complete. FPL is working to energize the pump station on Hibiscus Island. Design Builder is designing the three (3) generators for the pump stations. Anticipated Completion: September 2019 Stormwater Pump Station at 19th Street Scope: Installation of a stormwater pump station, including an emergency generator and seawall reconstruction along Collins Canal. Expansion of the Botanical Gardens to Collins Canal. New seawall at the Carl Fisher Clubhouse. Status: Construction of the Pump Station is complete. As the Class II permit is tied to the 3 completion of the Convention Center and the Park, the City is working closely with DERM to obtain a partial closure of the permit, allowing the pump station to come online, allowing sections of the system which are not affected by the Convention Center and the Park to begin normal operations. Commencement of construction for the Carl Fisher seawall is pending approval of the DERM permit. The Botanical Garden Expansion Project is pending the ongoing removal of the existing power poles by FPL. Due to delays in the permitting process, as well as the work required by FPL, the project schedule has been affected. Anticipated Completion: September 2019 Sunset Island 1 & 2 — Guardhouse Scope: Renovation of the interior and exterior of the existing guardhouse and the construction of a new guardhouse kiosk in the center of the entrance road on W. 29 Street. Status: Notice to Proceed #1 was issued on April 30, 2019. Contractor completing submittals required prior to the issuance of NTP 2, to commence construction. The building permit, tree permit and Right of Way permits have been approved, and trees have been tagged for removal. Anticipated Completion: November 2019 Surface Parking Lot P2 — Nikki Beach (Penrods) Scope: Reconstruction of the parking lot that includes landscaping, turtle friendly lighting, improvements to storm water drainage, irrigation, paving and signage, and infrastructure for future electric car charging stations. Status: The project is 85% complete. The pervious concrete and asphalt paving (first lift) has been installed throughout the entire parking lot. Light poles have been installed and the installation of the fixtures is underway. The installation of the landscaping for phase 2 will commence upon the completion of the underground piping for the irrigation system, currently underway. Anticipated Completion: July 2019 Venetian Islands Neighborhood Improvements Scope: Neighborhood improvements on San Marino, Dilido and Rivo Alto Islands. Status: Project remains 97% complete. The roadway pavement is exhibiting signs of premature failure due to a combination of improper base installation by the contractor, and rising ground water levels. City and Consultant are currently reviewing and negotiating additional services to include additional testing and an upgraded design for the roadway. Utility companies are in the process of finalizing design for undergrounding of utilities. Upon completion of design and approval by residents, utility companies will provide binding cost estimate. Pending the timeline, both projects (undergrounding and pavement repairs) may be combined into one contract. Pump stations at North and South Rivo Alto are currently pending the installation of pumps. FPL is working to energize transformers at both Rivo Alto pump stations. Anticipated Completion: TBD Venetian Islands Seawalls Scope: This project entails seawall replacement, at two (2) locations consisting of precast concrete bulkhead panels, king piles, batter piles and concrete cap; and seawall cap raising at five (5) locations consisting in new concrete cap, batter piles and retaining walls, at all locations within the Venetian Islands. Status: The Building Department permit is pending. The Contractor is waiting on permit to submit final schedule prior to issuance of the notice to proceed with construction. The 4 Consultant is working on DERM permit modification for seawalls. Anticipated Completion: TBD West Avenue Phase II Improvements - North of 14th Street Scope: Neighborhood Right of Way improvements north of 14th Street to Lincoln Lane. Status: Sewer plans are 90% complete, have been approved by City and are currently being reviewed by the County for approval. Water plans are 90% complete, comments are being addressed and plans will be re-submitted for final approval by the City, prior to submitting to the County. Roadway plan concepts have been approved and are now being developed to 60%. Preliminary drainage model prepared by Design-builder, currently under review, indicates need to further evaluate storm drainage design. Anticipated Completion: November 2022 West Avenue Phase II Improvements - South of 14th Street Scope: Neighborhood Right of Way improvements south of 14th Street to 6th Street. Status: Sewer plans are 90% complete, have been approved by City and are currently being reviewed by the County for approval. Water plans are 90% complete, comments are being addressed and plans will be re-submitted for final approval by the City, prior to submitting to the County. Roadway plan concepts have been approved and are now being developed to 60%. Preliminary drainage model prepared by Design-builder, currently under review, indicates need to further evaluate storm drainage design. Anticipated Completion: September 2021 LM/f M 5