Below please find the monthly update for active City of Miami Beach construction projects under
the purview of the Office of Capital Improvement Projects (CIP).
42"d Street Improvements
Scope: 42nd is a one-way, two lane corridors between Pine Tree Drive and Prairie
Avenue. Traffic studies confirmed that making this a two-way road will improve traffic, and
benefit safety, by providing signalized pedestrian crossings at the intersection of Pine tree
Drive and 42nd street. Existing traffic signals at the intersection of Pine Tree Drive and
42nd street will be retrofitted to serve eastbound traffic.
Status: Project is nearing substantial completion with the installation of signalization items
at the intersection of Pine Tree Dr and 42 Street. The project is 95% complete.
Anticipated Completion: July 2019
Altos Del Mar Park
Scope: Park Improvements include new landscape, irrigation, site lighting, sand volleyball
courts, walkways, terraced lawn, and new restroom building.
Status: The project is 90% complete. The irrigation and landscape activities are nearing
completion. Work on 76th Street is ongoing. The construction progress continues to suffer
which is affecting the completion date.
Anticipated Completion:August 2019
Beach Lifeguard Towers Replacement
Scope: Construction of 35 lifeguard towers.
Status: The construction of the last 2 lifeguard towers is nearing completion, pending
roofing, windows and paint.
Anticipated Completion:August 2019
Carl Fisher Clubhouse Restoration
Scope: Historical restoration of the Carl Fisher Clubhouse (interior and exterior) and
adjacent site and landscaping work. This project is part of the Convention Center
Renovation Project.
Status: The contractor is almost complete with the structural repairs and modifications.
The electrical, mechanical and plumbing rough in work continues. A portion of the concrete
slab has been poured. Roof structure modifications are in progress. The project is
approximately 40% complete.
Anticipated Completion: October 2019
1
Central Bayshore South Neighborhood Improvements
Scope: Neighborhood improvements bounded by 34th St. to the north, Pine Tree Dr. to
the east, 28 St. to the south, Prairie Ave to the west and Meridian Ave from 28 St. to Dade
Blvd.
Status: Water main installation is complete. Drainage design is currently at 75% and on
hold waiting for Commission directive, based on Jacobs Engineering's review of the City's
stormwater criteria and prioritization and sequencing of projects.
Anticipated Completion: TBD
Collins Park Parking Garage
Scope: Demolition of existing structure and construction of a new parking facility which
consists of a seven (7) level parking garage with 513 parking spaces and approximately
15,000 SF of retail spaces at the ground level. Liberty Avenue will be closed and used for
vehicular ingress and egress from 23rd Street to the Collins Park Garage. The balance of
the roadway (to 22nd Street) is planned as a pedestrian plaza with associated amenities.
Status: Installation of the piles and footers is completed. Grade beams, well
structures, trench drain system and foundation systems are expected to be
completed in August. Installation of precast structures expected to start in August.
The project has experienced delays associated with County traffic permit reviews,
the discovery of underground fuel storage tanks, and related DERM clean-up and
dewatering requirements.
Anticipated Completion: May 2020
Convention Center Park (P-Lot)
Scope: A new 5.8-acre park, replacing the existing surface parking lot located across the
street from the newly renovated Convention Center. The park will include open lawn
spaces, shade areas, walkways, lighting, a veteran's plaza, a public restroom facility, and
a flexible area space.
Status: Park currently 35% complete. Currently pouring concrete walkways, installing
irrigation sleeving, grading, FPL duct bank, poured slab for bathrooms.
Anticipated Completion: October 2019
Flamingo Park Fitness Cluster
Scope: Constructing a new outdoor Fitness Area in Flamingo Park to include new ADA
accessible fitness equipment, new concrete pathways, a new canopy shade structure,
added lighting, as well as drainage, landscape and irrigation improvements.
Status: Currently 90% complete. Lighting, shade structure and Irrigation being installed.
Anticipated Completion: August 2019
2
Flamingo Park Handball Courts
Scope: Renovation of existing handball courts to include various electrical upgrades, new
general lighting, stucco repairs, court resurfacing, new frameless windows and doors and
new fencing and painting. The courts will also include seating areas and water drinking
fountains for players and visitors. As a result of community input and requests, the project
was split into two phases, in order to provide uninterrupted usage of the courts.
Status: Project is currently 48% complete. Drainage installation complete, sports lighting
installed, condition of stucco was evaluated and currently stucco remediation is being
added to the project's scope.
Anticipated Completion: December 2019
Flamingo Parkwide Improvements - Phase I
Scope: Park wide renovations to include landscape, irrigation & drainage improvements,
as well as addition and renovation of walkways and pedestrian lighting.
Status: The project is currently 60% complete. Storm drainage has been installed as well
as pedestrian lighting, concrete walkways, irrigation and final grading currently underway.
Anticipated Completion:August 2019
North Shore Bandshell Canopy
Scope: Design, manufacture and install a custom canopy at the North Beach Band Shell
facility. The area of coverage for the canopy is approximately 4,000 square feet.
Status: The 90% Construction Documents were received July 1, 2019, after coordination
with the planning department. The plans were submitted for permit review on July 2, 2019
and are currently under review. Permits are expected for the end of August, at which time
construction will begin.
Anticipated Completion: November 2019
Palm & Hibiscus Island Neighborhood Improvements
Scope: Neighborhood improvements on Palm and Hibiscus Islands.
Status: The project is now 91% complete, which consist of the original contract scope of
work and the additional scope of work (generators and new drainage directive). The
Design/Build team as well as the City staff are working with DERM to complete the design
and permitting of the additional drainage and the harmonization scope work. FPL has
energized the pump station on Hibiscus Island and the 3 pump stations on this project are
now in operation. Design Builder is designing the three (3) generators for the pump
stations.
Anticipated Completion: September 2019
Stormwater Pump Station at 19th Street
Scope: Installation of a stormwater pump station, including an emergency generator and
seawall reconstruction along Collins Canal. Expansion of the Botanical Gardens to Collins
Canal. New seawall at the Carl Fisher Clubhouse.
Status: Construction of the Pump Station is complete. As the Class II permit is tied to the
completion of the Convention Center and the Park, the City is working closely with DERM
to obtain a partial closure of the permit, allowing the pump station to come online. The
Botanical Garden Expansion Project is pending the ongoing removal of the existing power
poles by FPL and electrical work necessary to disconnect the existing overhead lines. Due
to delays in the permitting process, as well as the work required by FPL, the project
schedule has been affected. Commencement of construction for the Carl Fisher seawall
is pending approval of the DERM permit.
Anticipated Completion: September 2019
3
Sunset Island 1 & 2— Guardhouse
Scope: Renovation of the interior and exterior of the existing guardhouse and the
construction of a new guardhouse kiosk in the center of the entrance road on W. 29 Street.
Status: Notice to Proceed (NTP) #1 was issued on April 30, 2019. NTP 2 to commence
construction was issued on June 14, 2019. Construction is in progress.
Anticipated Completion: November 2019
Surface Parking Lot P2 — Nikki Beach (Penrods)
Scope: Reconstruction of the parking lot that includes landscaping, turtle friendly lighting,
improvements to storm water drainage, irrigation, paving and signage, and infrastructure
for future electric car charging stations.
Status: The work required to complete the project, installation of the irrigation system,
landscaping and the electrical wiring for the lighting, is ongoing. The contractor has started
addressing corrective work required by the City.
Anticipated Completion: July 2019
Venetian Islands Neighborhood Improvements
Scope: Neighborhood improvements on San Marino, Dilido and Rivo Alto Islands.
Status: FPL has energized transformers at both pump stations at North and South Rivo
Alto. Testing and start-up for the South Rivo Alto pump station is scheduled to be
completed in July and testing and start-up for the North Rivo pump station scheduled for
the month of August. Staff is currently working with Consultant to obtain additional testing
and complete the design for the roadway, with an improved service life. Atlantic
Broadband (ABB)and FPL have provided preliminary design plans for the undergrounding
of their systems, while preliminary plans for AT&T are still pending. Upon completion of
design and approval by residents, utility companies will provide binding cost estimates.
Anticipated Completion: TBD
Venetian Islands Seawalls
Scope: This project entails seawall replacement, at two (2) locations consisting of precast
concrete bulkhead panels, king piles, batter piles and concrete cap; and seawall cap
raising at five (5) locations consisting in new concrete cap, batter piles and retaining walls,
at all locations within the Venetian Islands.
Status: The Building Department permit is pending. The Contractor is waiting on permit to
submit final schedule prior to issuance of the notice to proceed with construction. The
Consultant is working on DERM permit modification for seawalls.
Anticipated Completion: TBD
West Avenue Phase II Improvements - North of 14th Street
Scope: Neighborhood Right of Way improvements north of 14th Street to Lincoln Lane.
Status: Design of the watermain system has been completed and permitted. Sanitary
sewer plans are 90% complete and are currently being reviewed by the County for permit.
Roadway and landscaping plans are 60% complete. Pump Station design is 40%
complete, and will be presented to the community early in August 2019. Drainage Model
prepared by the Design-builder is currently being reviewed by staff.
Anticipated Completion: November 2022
4
West Avenue Phase II Improvements - South of 14th Street
Scope: Neighborhood Right of Way improvements south of 14th Street to 6th Street.
Status: Design of the watermain system has been completed and permitted. Sanitary
sewer plans are 90% complete and are currently being reviewed by the County for permit.
Roadway and landscaping plans are 60% complete. Drainage Model prepared by the
Design-builder is currently being reviewed by staff.
Anticipated ompletion: October 2021