LTC 517-2019 G.O. Bond Projects Dashboard LaunchMIAMI BEACH
City of Miami Beach, 1700 Convention Center Drive , Miom i Beach , Florida 33 139, www.m iamibeachfl .gov
OFFICE OF THE CITY MANAGER
LTC# 517-2019 LETIER TO COMMISSION
TO : Mayor Dan Gelber and Members o
FROM : Jimmy L. Morales, City Manager
DATE : September 25, 2019
SUBJECT : G.O. Bond Projects Dashboard La
After months of designing and troubleshooting the G.O. Bond Program team is ready to formally
launch its new "Project Dashboard" tab on the website-www.GOMBINFO .com . The Project
Dashboard is the result of a collective city effort to make all G.O. Bond project finance and
timeline information as transparent as possible for the benefit of public review. The Project
Dashboard provides site visitors with real -time expense and activity information for each of the
57 approved G.O. Bond projects, as well as any sub-projects included that are budgeted
separately and therefore tracked as individual project milestones.
On the Project Dashboard landing page, residents can now see a general overview of how the
G .O . Bond Program is progressing with a real-time and interactive chart for "Project Activity" and
for "Program Expenditures" that pulls information directly from the city's Munis and project e-
Builder software.
By navigating the G .O. Bond Dashboard, residents can see the following details for every project
and sub-project under each of the three G.O. Bond project categories (Parks, Infrastructure, and
Public Safety), and in each designated city area (North Beach, Middle Beach, South Beach,
Citywide):
Project Name
Scope of Work
GO Bond Budget
Map Location
Dollars Encumbered
Dollars Spent
Percent of Budget Spent
Current Status (Complete, Active, Pending, Future)
Active Phase (Planning, Design, Construction)
Project Timeline
Start and End Dates
Recent Project Updates
Managing Department
Public Information (PIO) Contact Information
Dashboard data is refreshed automatically every day at 6:00 a.m., ensuring that all financial
information is up-to-date and accurate. This new tool will also produce a Program Progress
Report that will be reviewed and approved by the G.O. Bond Oversight Committee each month,
to then pass along to the City Commission as a monthly prog ram implementation update . This
G. 0 . Bond Projects Dashboard Launch
September 25, 2019
Page 2 of2
innovative website feature and report function was made possible by Microsoft's business
intelligence tool, Power Bl.
The making of the new Project Dashboard was the result of extensive collaboration, as staff from
multiple city departments worked together for hundreds of hours to produce it to their satisfaction.
The following city departments should be recognized for their exceptional work in creating this
product for the use and benefit of Miami Beach residents: Information Technology, Finance
Department, Office of Management and Budget, Marketing and Communications, Capital
Improvement Projects, and the City Manager's G.O . Bond Program Management Team.
For more information, please contact Maria Hernandez at mariahernandez@miamibeachfl.gov
or x2584 .
JLM I MH