LTC 568-2019 G.O. Bond Program - Project Implementation Update No. 4MIAMI BEACH City of Miami Beach, 1700 Co nve ntion Cente r Drive, M ia mi Beach, Flo r ida 33139, www.miamibeachfl.gov OFFICE OF THE CITY MANAGER LTC# 568-2019 LEDER TO COMMISSION TO : Mayor Dan Gelber and Member FROM : DATE : October 24 , 2019 SUBJECT : G.O. Bond Program-Project I plementation Update No.4 The purpose of this Letter to the Commission ("LTC") is to advise you on the status of the implementation of the 38 General Obligation Bond (G .O. Bond) Projects approved by the City Commission for the first tranche of funding (Tranche 1) in the amount of $152,466,449 including issuance costs . The Admin istration continues to meet monthly with the G.O . Bond Oversight Committee (the "Committee") to provide project updates and discuss other Committee business . Two meetings have taken place since the last LTC update. Refer to Exhibit A and Exhibit A 1 for the meeting agendas which took place on September 19, 2019 and October 17, 2019. IMPLEMENTATION STATUS Project Dashboard and Program Progress Report On September 25th, 2019 , the G .O . Bond team formally launched its new Project Dashboard "Dashboard" and scorecard on the website-wwww.GOMBINFO.com , via LTC #517-2019 . The Dashboard provides visuals and analytics of all G.O . Bond projects , including scheduling, budget progress and status . It is an interactive open data system that shows real-time program progress and expense information. On the new website tab "projects", at GOMBINFO.com/projects , there is also a fuii"Dashboard Resource Bank" that includes a "Glossary of Terms", "Project Photos" and more. These website additions were produced after gathering Committee and community input, taking their suggestions into account. The project Dashboard also generates a daily progress report that gets automatically posted to the website every morning in a PDF format. The progress report indicates the same proj ect activity reported on the Dashboard and includes a project list which shows projects by Completed , Active , Pending & Future status with an individual summary sheet fo r every project and sub-project. As of October 17th, 2019 , a t otal of 28 out of 57 G.O. Bond projects are in some form of "Active " status and 1 project is completed. Approximately $23 million dolla rs have been spent and/or are encumbered . A condensed version of the report , showing only Active projects , is attached as Exhibit B. Quick Wins All quick win projects rema in on budget and on schedule to be completed by June 2020 . The Middle Beach Beachwalk is a more involved project and is estimated to be completed by January 2021 , however port ions of the project w ill be completed in phases prior to that date. As of G. 0. Bond Program -Project Implementation Update No. 4 October 24, 2019 Page 2 of4 October 17th, 20 out of the 21 Quick Win projects are either completed, under construction or in some form of "Active" status. The overall status is summarized in Schedule 1 below: Schedule 1 21 Quick Win Projects Status Item GOB Project No. I Name Pre-Design/ Procurement No. Planning Permitting 1 #24 Mid Beach Beachwalk X 2 #32 Palm & Hibiscus X 3 #33 Street Tree Plan\2 X 4 #17 Polo Park 5 #52 LED Lighting in Parks X 6 #2 Collins Park X 7 #4 Fairway Park X 8 #3 Crespi Park 9 #21 Stillwater Park 10 #47 License Plate Readers 11 #57 Cameras in Ent. District X 12 #49 P. Safety Radio System 13 #56 Cameras on Beachwalk 14 #53 Security for Pub. Spaces 15 #26 Roof Replacement2 16 #18 Scott Rakow 2 X 17 #13 North Shore Park2 X 18 #38 Street Pavement 19 #37 Sidewalk Improvement 20 #19 Soundscape Tech Core 21 #42 Traffic Calming Legend 1 Project scope has been modified. 40 Stand Muss Park have been added to the plan. 2 Due to sub-projects, some elements of a project are in different phases. * Red signifies the updated phase from last reporting. Construction Closeout or Execution X X X X X X X X X X X X X X X X X For the implementation timeline of all the Quick Win projects, refer to Exhibit C dated October 17th, 2019. Fire Station No. 1 On October 8, 2019, City staff presented the South Shore Community Center site on 6th street (6th street complex) as the preferred site of the City as a discussion item to the Historic Preservation Board (HPB). The HPB heard the item and provided feedback to the administration. The HPB also requested additional information from Planning staff regarding the history and architectural characteristics of the building. Staff will be presenting the additional requested information to HPB at their December 9th HPB meeting. In light of the proposed and possible relocation of Fire Station No. 1 to the 6th street complex site, the Administration is requesting a dual referral to the Neighborhood/Community Affairs Committee and the Finance and Citywide Projects Committee to discuss the renovation of the G. 0. Bond Program -Project Implementation Update No. 4 October 24, 2019 Page 3 of4 old Fire Station back to its original Morris Lapidus design, and, furthermore, the possible relocation of some entities which would be displaced by the conversion of the 6th street complex into the future facility. This would not be a G.O. Bond funded project but is being recommended to both Committees as part of an overall plan to preserve andre-purpose the existing fire station. The referral is on the October 30th Commission Agenda. Other Major Tranche 1 Projects: #1 72nd Community Complex-$10,800,000 for Tranche 1 • Status: Development of the Design Criteria Package (DCP) has commenced. The DCP is expected to be completed and ready for Design-Builder advertisement in January 2020. On October 16, 2019 Commission approved the payment to FP&L for the design and binding cost estimate to relocate the FP&L transmission lines currently bisecting the site. • Anticipated Completion: 2023 #15 PAR 3 I Community Park-$15,700,000 • Status: The design documents are at 90% phase and the project team has been working with Miami-Dade County Department of Regulatory and Economic Resources (DERM) in the design and implementation of the sustainable and resilient approaches in the park. One of the approaches consists of conveyance and storage of the stormwater in the central lake at the park. Due to the contamination related to the historical use of this park as a golf course there have been some challenges posed by DERM to the original concepts. The project team will continue coordinating with DERM to develop a resiliency concept that includes a gravity well system to address the neighborhood's stormwater runoff. This additional request has affected the anticipated milestones and will delay the previously projected completion timelines. • Anticipated Completion: To be determined once an agreement is reached with DERM. #23 Baywalk Pedestrian Bridge-$10,000,000 • Status: Design is 95% complete. Design of the exterior element was approved by the Design Review Board in September. The project is currently in for permitting at FOOT and the City of Miami Beach. • Anticipated Completion: Summer 2020. #10 Maurice Gibb Park-$3,300,000 • Status: The Design is 60% complete. The permit process with the Army Corps of Engineers, FDEP and Miami Dade County DERM has been initiated. • Anticipated Completion: Spring 2022. #48 Police Headquarter Improvements-$4,000.000 in Tranche 1 • Status: AlE Fee Proposal was received from Leo A. Daly Architecture on 10/18/19. The Property Management Team is vetting the proposal and scheduling a meeting with the design team. • Anticipated Completion: 2028. ART IN PUBLIC PLACES {AiPP) FOR G.O. BOND PROJECTS On September 11, 2019, the City Commission approved Resolution No. 2019-30983 adopting an amendment to the City's AiPP ordinance which exempts some G.O. Bond projects at the recommendation of the G.O. Bond Committee and the Administration. The G.O. Bond Committee was advised of the approval at the September 19th Committee meeting. COMMUNITY INFORMATION AND OUTREACH The summer concluded with a well-attended ribbon-cutting ceremony to celebrate the first of all 57 G.O. Bond projects to reach 100% completion -Polo Park. Earlier this month, a milestone event was celebrated at SoundScape Park for the first-ever WALLCAST concert to be showcased in 4K Technology, which was funded by the G.O. Bond. In a 4-minute introductory G. 0. Bond Program -Project Implementation Update No. 4 October 24, 2019 Page 4 of4 opener, the Mayor addressed residents on-screen to announce the incredible milestone for arts & culture and the importance of the resident-supported G.O. Bond Program. Regular communication is kept-up with neighborhood associations and other community groups. These groups are constantly encouraged to attend G.O. Bond Oversight Committee meetings. In addition, the G.O. Bond Program team is working with the HOA President's on an idea to begin a "GOB Roadshow" in January where each HOA meeting would receive a custom presentation on the website and program Dashboard, followed by an in-depth discussion on the projects happening in their area. In addition, construction notices have continued to go to resident doors and email addresses to inform them of upcoming construction disruption and GO Bond-branded signage has continued to be produced and displayed. All program updates, construction notices, press releases and multimedia postings have also been shared to the public through the City's social media outlets, the G.O. Bond website, constant contact and direct communications. See attached Exhibit D for a summary overview. For more information, please contact Maria Hernandez at mariahernandez@miamibeachfl.gov or x2584. Attachments: Exhibit A-GOB Oversight Committee Agenda for September 19, 2019 Exhibit A1-GOB Oversight Committee Agenda for October 17, 2019 Exhibit B -GOB Projects Progress Report-Active Projects Exhibit C -Quick Wins Implementation Plan Exhibit D -Community Outreach Report JLM I MH F:\cmgr\$ALL\GO Bond Program\Commission\L TCs\05 October 2019\L TC -October 2019 GO Bond Program Implementation Update No. 4.docx • • • • • • • • EXHIBIT A • • • • • • EXHIBIT A1 EXHIBIT B M IAMI BEACH Table of Contents Content Page Summary Project Activity ................................................................................................................................... 3 Program Expenditures ..................................................................................................................... 3 Project Status ...................................................................................................................................... 4 Detail Project Details ..................................................................................................................................... 7 www.gombinfo.com 2 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 Parks Infrastructure Public Safety All Spent $3,447,582 $1,265,635 $4,103,137 $8,816,354 Encumbered $5,117,244 $2,046,011 $6,827,941 $13,991,196 Available $78,168,169 $24,688,351 $25,474,917 $128,331,437 Future $81,167,005 $168,000,003 $34,809,005 $283,976,013 Total $167,900,000 $196,000,000 $71,215,000 $435,115,000 PROGRAM EXPENDITURES Parks Infrastructure Public Safety All Complete 1 0 0 1 Active 15 6 7 28 Pending 3 2 4 9 Future 11 6 2 19 All 30 14 13 57 PROJECT ACTIVITY PROJECT CATEGORY PROJECT CATEGORY PROGRAM FUNDS PROJECT STATUS www.gombinfo.com 3 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 Status Active Tranche Category Project Name Tranches Active Phase Anticipated End Date COMPLETE (1) 1 PARKS GO#17: POLO PARK 1 Complete 08/10/2019 ACTIVE (28) 1 PARKS GO#1: 72 ST. COMMUNITY COMPLEX 1 Planning 07/27/2023 GO#2: COLLINS PARK 1 Design 04/30/2020 GO#3: CRESPI PARK 1 Construction 11/30/2019 GO#4: FAIRWAY PARK 1 Planning 04/30/2020 GO#10: MAURICE GIBB PARK 1 Design 03/14/2022 GO#12: NORTH BEACH OCEANSIDE PARK BEACHWALK 1 Design 04/28/2021 GO#13: NORTH SHORE PARK & YOUTH CENTER #13 NORTH SHORE CAMERAS 1 Design 04/27/2020 #13 NORTH SHORE GENERATOR 1 Design 07/12/2020 #13 NORTH SHORE LIGHTS & PAINT 1 Construction 11/13/2019 #13 NORTH SHORE ROOF 1 Construction 01/14/2020 GO#15: PAR 3/COMMUNITY PARK 1 Design 09/01/2021 GO#18: SCOTT RAKOW YOUTH CENTER #18 SCOTT RAKOW CAMERAS 1 Design 04/22/2020 #18 SCOTT RAKOW FIRE ALARM 1 Cancelled 04/01/2019 #18 SCOTT RAKOW GENERATOR 1 Design 06/07/2020 #18 SCOTT RAKOW HVAC 1 Construction 01/30/2020 #18 SCOTT RAKOW PAINT 1 Construction 12/12/2019 #18 SCOTT RAKOW POOL 1 Design 05/31/2020 #18 SCOTT RAKOW ROOF 1 Construction 03/11/2020 #18 SCOTT RAKOW WINDOWS 1 Design 04/26/2020 GO#19: SOUNDSCAPE PARK #19 SOUNDSCAPE 4K TECHNOLOGY 1 Complete 11/01/2019 #19 SOUNDSCAPE RESTROOMS/STORAGE 1 Pending 01/01/2022 GO#21: STILLWATER PARK 1 Construction 11/30/2019 GO#23: BAYWALK #23 PEDESTRIAN BRIDGE 1 Design 08/28/2020 GO#24: MIDDLE BEACH BEACHWALK PH3 1 Construction 02/13/2021 GO#26: ROOFS FOR CULTURAL FACILITIES #26 COLONY THEATRE ROOF 1 Complete 10/14/2019 #26 FILLMORE ROOF 1 Design 02/29/2020 #26 MIAMI CITY BALLET ROOF 1 Design 02/08/2020 GO#29: WEST LOTS 1,2,3 Planning 10/02/2028 INFRASTRUCTURE GO#32: PALM & HIBISCUS LANDSCAPING 1 Design 03/16/2020 PROJECT STATUS www.gombinfo.com 4 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 Status Active Tranche Category Project Name Tranches Active Phase Anticipated End Date 1 INFRASTRUCTURE GO#33: STREET TREE MASTER PLAN #33 PART 1 TREE PLANTING 1 Construction 02/03/2020 GO#37: SIDEWALK IMPROVEMENTS #37 PART 1 SIDEWALKS 1 Construction 01/01/2022 GO#38: STREET PAVEMENT #38 PART 1 STREETS 1 Construction 01/01/2022 GO#40: 41 ST. CORRIDOR 1,2,3,4 Planning 01/01/2031 GO#42: TRAFFIC CALMING #42 NAUTILUS TRAFFIC CALMING 1 Construction 01/31/2020 PUBLIC SAFETY GO#45: FIRE STATION #1 1,2 Planning 03/30/2023 GO#47: LICENSE PLATE READERS #47 71 ST. ENTRANCE READERS 1 Construction 11/06/2019 #47 JULIA TUTTLE CSWY READERS 1 Design 11/29/2019 #47 MACARTHUR CSWY READERS 1 Construction 11/28/2019 GO#49: PUBLIC SAFETY RADIO SYSTEM 1 Construction 02/28/2020 GO#52: LED LIGHTING IN PARKS #52 CRESPI PARK LED LIGHTING 1 Construction 10/21/2019 #52 NORMANDY ISLE PARK LED LIGHTING 1 Design 11/20/2019 #52 OTHER PARKS LED LIGHTING 2 Future 01/01/2025 #52 STILLWATER PARK LED LIGHTING 1 Construction 10/21/2019 #52 TATUM PARK LED LIGHTING 1 Complete 10/14/2019 GO#53: SECURITY FOR PUBLIC SPACES #53 CONVENTION CENTER BOLLARDS 1 Pending 01/01/2022 #53 LINCOLN ROAD BOLLARDS 2 Future 01/01/2025 #53 PORTABLE BOLLARDS 1 Complete 07/31/2019 #53 SOUNDSCAPE PARK BOLLARDS 1 Pending 01/01/2022 #53 SOUTH POINTE PARK BOLLARDS 1 Pending 01/01/2022 GO#56: CAMERAS- BEACHWALK 1 Planning 03/19/2020 GO#57: CAMERAS- ENTERTAINMENT DISTRICT #57 LUMMUS PARK/OCEAN DRIVE CAMERAS 1 Design 02/01/2020 PENDING (9) 1 PARKS GO#5: FLAMINGO PARK & YOUTH CENTER #5 FLAMINGO PARK MASTER PLAN 3 Future 01/01/2028 #5 FLAMINGO YOUTH CENTER FACILITY 1 Pending 07/02/2022 GO#8: LUMMUS PARK 1 Pending 01/01/2022 GO#9: MARJORY STONEMAN DOUGLAS PARK #9 M.S.DOUGLAS PARK IMPROVEMENTS 1 Pending 01/01/2022 #9 M.S.DOUGLAS PARK PLAYGROUND 1 Pending 01/01/2022 INFRASTRUCTURE GO#39: SEAWALLS & SHORELINES 1,2 Pending 01/01/2025 GO#43: BIKE LANES & SHARED PATHS #43 23 ST. STREETSCAPE IMPROVEMENTS 1 Pending 01/01/2022 www.gombinfo.com 5 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 Status Active Tranche Category Project Name Tranches Active Phase Anticipated End Date 1 INFRASTRUCTURE #43 63 ST. STREETSCAPE IMPROVEMENTS 3 Future 01/01/2028 #43 ALTON ROAD SHARED USE PATH 1 Pending 01/01/2022 #43 CHASE AVE/34 ST SHARED USE PATH 1 Pending 01/01/2022 PUBLIC SAFETY GO#48: POLICE HEADQUARTERS FACILITY 1,3 Pending 01/01/2028 GO#50: CAMERAS- BUSINESS DISTRICT #50 41 ST. CORRIDOR CAMERAS 1 Pending 01/01/2022 #50 71 STREET CORRIDOR CAMERAS 1 Pending 01/01/2022 #50 ALTON RD. CORRIDOR CAMERAS 1 Pending 01/01/2022 #50 DADE BLVD. CORRIDOR CAMERAS 1 Pending 01/01/2022 GO#54: MARINE PATROL FACILITY 1 Pending 08/23/2022 GO#55: STREET LIGHTING IMPROVEMENTS #55 PART 1 STREET LIGHTS 1 Pending 01/01/2022 #55 PART 2 STREET LIGHTS 2 Future 01/02/2028 FUTURE (19) 2 PARKS GO#14 PALM ISLAND PARK 2 Future 01/01/2025 GO#16: PINETREE PARK 2 Future 01/01/2025 GO#25: WATERWAY RESTORATION 2,3 Future 01/01/2028 GO#27: LOG CABIN 2 Future 01/01/2025 GO#28: ART DECO MUSEUM 2 Future 01/01/2025 INFRASTRUCTURE GO#31: OCEAN DRIVE CORRIDOR 2,3,4 Future 01/01/2031 GO#34: ABOVE GROUND IMPROVEMENTS 2,3,4 Future 01/01/2031 GO#36: WASHINGTON AVE. CORRIDOR 2,3,4 Future 01/01/2031 GO#41: LA GORCE NEIGHBORHOOD 2,3,4 Future 01/01/2031 3 PARKS GO#7: LA GORCE PARK 3 Future 01/02/2028 GO#11: MUSS PARK 3 Future 01/01/2028 GO#20: SOUTH POINTE PARK 3 Future 01/01/2028 GO#30: SKATE PARK 3 Future 01/01/2028 INFRASTRUCTURE GO#35: FLAMINGO PARK NEIGHBORHOOD 3,4 Future 12/31/2030 GO#44: NORTH SHORE NEIGHBORHOOD 3 Future 01/01/2028 PUBLIC SAFETY GO#51: FIRE STATION #3 3,4 Future 12/30/2031 4 PARKS GO#6: FISHER PARK 4 Future 01/01/2031 GO#22: TATUM PARK 4 Future 01/01/2031 PUBLIC SAFETY GO#46: OCEAN RESCUE NORTH BEACH FACILITY 4 Future 01/01/2031 www.gombinfo.com 6 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 GOB Project #: Location: 01 North Beach Active Phase:Planning Department:Capital Improvement Projects SCOPE Build a new community facility at 72 Street between Collins Avenue and Harding Avenue that includes an olympic-sized roof-top swimming competition pool, a warm-up pool, a library/media center, a community room, an activated liner, a fitness gym with running track, green space and a multi-level parking garage. GOB FUNDING Budget:$53,800,000 Spent:$0 Available:$10,800,000 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 12/17/2018 02/11/2020 02/11/2020 14.07mo Design 02/12/2020 04/01/2021 04/01/2021 13.83mo Permitting 01/10/2021 07/28/2021 07/28/2021 6.67mo Construction 07/31/2021 05/26/2023 07/27/2023 24.23mo Project Category:Parks UPDATE Development of the Design Criteria Package has commenced. Start of Design Builder advertisement early 2020. Anticipated Completion: 2023 GO#1: 72 ST. COMMUNITY COMPLEX - This project has additional sources of funding www.gombinfo.com 7 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 GOB Project #: Location: 02 South Beach Active Phase:Design Department:Parks & Recreation SCOPE Replace the damaged paver pathways throughout the park and plaza with new, smooth and structurally-sound pavement. GOB FUNDING Budget:$640,000 Spent:$0 Available:$640,000 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 07/01/2019 07/31/2019 07/31/2019 31d Design/Permitting 08/15/2019 01/15/2020 01/15/2020 154d Construction 01/16/2020 03/31/2020 03/31/2020 76d Close-out 04/01/2020 04/30/2020 04/30/2020 30d Project Category:Parks UPDATE Currently in the design/permitting phase. GO#2: COLLINS PARK www.gombinfo.com 8 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 GOB Project #: Location: 03 North Beach Active Phase:Construction Department:Parks & Recreation SCOPE Replace the existing perimeter fence with a higher security fencing structure, construct a new walking/jogging path, add fresh paint and new flooring to pavilion and restroom areas. GOB FUNDING Budget:$211,000 Spent:$0 Available:$211,000 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 05/01/2019 06/17/2019 06/30/2019 61d Design/Permitting 07/01/2019 07/05/2019 07/31/2019 31d Construction 08/01/2019 09/09/2019 10/31/2019 92d Close-out 11/01/2019 09/30/2019 11/30/2019 30d Project Category:Parks UPDATE Currently in the construction phase. Project is on schedule for completion on 10/31/19. GO#3: CRESPI PARK www.gombinfo.com 9 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 GOB Project #: Location: 04 North Beach Active Phase:Planning Department:Parks & Recreation SCOPE Replace the aged perimeter fence with higher-quality and higher- security fencing; refresh the pavilion, restroom and office facilities with a new paint job. GOB FUNDING Budget:$260,000 Spent:$0 Available:$260,000 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 10/01/2019 11/14/2019 11/30/2019 61d Design/Permitting 12/01/2019 12/08/2019 12/31/2019 31d Construction 01/01/2020 02/08/2020 03/31/2020 91d Close-out 04/01/2020 03/02/2020 04/30/2020 30d Project Category:Parks UPDATE This project will be performed concurrently with the non-GOB CIP project at this park, which is currently in permitting phase and expected to begin sometime in the Fall. GO#4: FAIRWAY PARK www.gombinfo.com 10 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 GOB Project #: Location: 12 North Beach Active Phase:Design Department:Capital Improvement Projects SCOPE Construct an on-grade, ADA accessible and decorative paver pathway from streets 79 to 87, completing the final link of the city's entire beachwalk system. Redevelop the Beachwalk to expand path networks and dune systems, new landscaping and wayfinding signage and turtle-friendly lighting. GOB FUNDING Budget:$2,000,000 Spent:$0 Available:$2,000,000 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration start 07/14/2015 07/14/2015 07/14/2015 0d Planning 08/13/2015 07/27/2016 07/27/2016 350d Design / Permitting 07/28/2016 11/20/2019 11/20/2019 1211d Contractor Selection - ITB - B 08/28/2019 03/31/2020 03/31/2020 217d Construction 04/01/2020 03/26/2021 03/26/2021 360d Final Completion 03/29/2021 04/28/2021 04/28/2021 30d Project Category:Parks UPDATE The project is in Design. Construction planned to start in April 2020. Anticipated Completion April 2021. GO#12: NORTH BEACH OCEANSIDE PARK BEACHWALK - This project has additional sources of funding www.gombinfo.com 22 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 #13 NORTH SHORE CAMERAS GOB Project #: Location: 13 North Beach Active Phase:Design Department:Property Management SCOPE Install additional security cameras. GOB FUNDING Budget:$205,700 Spent:$23,371 Available:$182,328 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 04/01/2019 08/01/2019 08/01/2019 123d Design/Permitting 08/02/2019 09/30/2019 09/30/2019 60d Construction 10/01/2019 03/28/2020 03/28/2020 180d Close-out 03/29/2020 04/27/2020 04/27/2020 30d Project Category:Parks UPDATE Purchase orders have been issued for Phase 1. The Police Department is currently working on proposals for Phase 2. GO#13: NORTH SHORE PARK & YOUTH CENTER www.gombinfo.com 25 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 #13 NORTH SHORE GENERATOR GOB Project #: Location: 13 North Beach Active Phase:Design Department:Property Management SCOPE Install a generator to the facility, allowing it to function as a city- designated Emergency Operations Activation (EOA) Center during power outages. GOB FUNDING Budget:$500,000 Spent:$456 Available:$499,544 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 04/01/2019 07/02/2019 07/02/2019 93d Design/Permitting 07/03/2019 11/14/2019 12/15/2019 166d Construction 12/16/2019 05/12/2020 06/12/2020 180d Close-out 06/13/2020 06/11/2020 07/12/2020 30d Project Category:Parks UPDATE Permitting underway. GO#13: NORTH SHORE PARK & YOUTH CENTER www.gombinfo.com 26 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 #13 NORTH SHORE LIGHTS & PAINT GOB Project #: Location: 13 North Beach Active Phase:Construction Department:Property Management SCOPE Install LED lighting fixtures; paint building interior. GOB FUNDING Budget:$130,300 Spent:$0 Available:$130,300 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 04/01/2019 07/01/2019 07/01/2019 92d Design/Permitting 07/02/2019 08/15/2019 08/15/2019 45d Construction 08/16/2019 10/13/2019 10/14/2019 60d Close-out 10/15/2019 11/12/2019 11/13/2019 30d Project Category:Parks UPDATE Painting is complete. Lighting is at 95% completion. GO#13: NORTH SHORE PARK & YOUTH CENTER www.gombinfo.com 28 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 #13 NORTH SHORE ROOF GOB Project #: Location: 13 North Beach Active Phase:Construction Department:Property Management SCOPE Replace the existing aged roof with a new durable roof. GOB FUNDING Budget:$400,000 Spent:$0 Available:$400,000 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 03/01/2019 06/14/2019 06/14/2019 106d Design/Permitting 06/15/2019 10/01/2019 10/01/2019 109d Construction 10/02/2019 12/15/2019 12/15/2019 75d Close-out 12/16/2019 01/14/2020 01/14/2020 30d Project Category:Parks UPDATE Permit issued. Contractor mobilizing on October 17. GO#13: NORTH SHORE PARK & YOUTH CENTER www.gombinfo.com 30 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 GOB Project #: Location: 15 Middle Beach Active Phase:Design Department:Capital Improvement Projects SCOPE Develop a brand new park space with environmental remediation and resiliency components; construct an outdoor ampitheatre, a walking trail with a lake overlook, tennis courts and restroom facility, a pavillion shade structure, a dog park, a vita course, a playground, and a butterfly garden. GOB FUNDING Budget:$15,700,000 Spent:$0 Available:$15,700,000 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 08/12/2015 05/30/2016 05/30/2016 293d Design 08/12/2016 01/08/2020 02/08/2020 42.53mo Contractor Selection - ITB 02/10/2020 05/26/2020 06/30/2020 4.73mo Construction 07/01/2020 06/25/2021 09/01/2021 14.27mo Project Category:Parks UPDATE Proceeding towards 90% design. Pending Miami-Dade County Regulatory and Economic Resources (RER) environmental remediation/resiliency strategy approval. Staff continues to meet with RER on addressing some challenges posed by them to the original concepts. Bid advertisement early next year. Anticipated Completion: Summer 2021. GO#15: PAR 3/COMMUNITY PARK - This project has additional sources of funding www.gombinfo.com 32 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 GOB Project #: Location: 17 Middle Beach Active Phase:Complete Department:Parks & Recreation SCOPE Renovate the baseball field to include a new dugout area, additional spectator bleacher seats, higher fencing and safety netting; construct a new concrete perimeter pathway; add new park furnishings; improve irrigation and landscaping. GOB FUNDING Budget:$500,000 Spent:$244,849 Available:$255,150 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 03/18/2019 04/12/2019 26d Design/Permitting 04/13/2019 06/22/2019 71d Construction 06/23/2019 08/10/2019 49d Project Category:Parks UPDATE This project is complete. A ribbon-cutting ceremony was held on 09/05/19. Pending final payment to contractor. GO#17: POLO PARK www.gombinfo.com 34 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 #18 SCOTT RAKOW CAMERAS GOB Project #: Location: 18 Middle Beach Active Phase:Design Department:Property Management SCOPE Install additional security cameras. GOB FUNDING Budget:$250,000 Spent:$410 Available:$249,590 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 03/01/2019 06/15/2019 06/15/2019 107d Design/Permitting 06/16/2019 09/27/2019 09/27/2019 104d Construction 09/28/2019 03/24/2020 03/24/2020 179d Close-out 03/25/2020 04/22/2020 04/22/2020 29d Project Category:Parks UPDATE Infrastructure work has been completed. The Police Department is working on proposals for Phase 2. GO#18: SCOTT RAKOW YOUTH CENTER www.gombinfo.com 36 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 #18 SCOTT RAKOW GENERATOR GOB Project #: Location: 18 Middle Beach Active Phase:Design Department:Property Management SCOPE Install a generator to the facility, allowing it to function as a city- designated Emergency Operations Activation (EOA) Center during power outages. GOB FUNDING Budget:$500,000 Spent:$0 Available:$500,000 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 04/01/2019 06/29/2019 06/29/2019 90d Design/Permitting 06/30/2019 11/06/2019 11/06/2019 130d Construction 11/07/2019 05/08/2020 05/08/2020 184d Close-out 05/09/2020 06/07/2020 06/07/2020 30d Project Category:Parks UPDATE Permitting in process. GO#18: SCOTT RAKOW YOUTH CENTER www.gombinfo.com 39 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 #18 SCOTT RAKOW HVAC GOB Project #: Location: 18 Middle Beach Active Phase:Construction Department:Property Management SCOPE Replace the aged existing HVAC system with a new, energy-efficient air conditioning unit. GOB FUNDING Budget:$150,000 Spent:$0 Available:$150,000 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 04/01/2019 06/10/2019 06/10/2019 71d Design/Permitting 06/11/2019 07/10/2019 07/10/2019 30d Construction 07/11/2019 10/31/2019 12/31/2019 174d Close-out 01/01/2020 11/30/2019 01/30/2020 30d Project Category:Parks UPDATE Two out of the six HVACs have been replaced. The last 4 units are expected to be replaced by mid-December. Construction is phased around operation schedule. GO#18: SCOTT RAKOW YOUTH CENTER www.gombinfo.com 40 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 #18 SCOTT RAKOW PAINT GOB Project #: Location: 18 Middle Beach Active Phase:Construction Department:Property Management SCOPE Paint interior and exterior walls. GOB FUNDING Budget:$130,000 Spent:$0 Available:$130,000 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 04/01/2019 07/29/2019 06/24/2019 85d Design/Permitting 06/25/2019 08/13/2019 08/13/2019 50d Construction 08/14/2019 11/12/2019 11/12/2019 91d Close-out 11/13/2019 12/12/2019 12/12/2019 30d Project Category:Parks UPDATE 100% of exterior painting has been completed. skating rink is the only pending area on interior. GO#18: SCOTT RAKOW YOUTH CENTER www.gombinfo.com 41 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 #18 SCOTT RAKOW POOL GOB Project #: Location: 18 Middle Beach Active Phase:Design Department:Parks & Recreation SCOPE Upgrade pool filtration system and renovate pool restrooms. GOB FUNDING Budget:$538,000 Spent:$0 Available:$538,000 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 05/27/2019 06/22/2019 06/22/2019 27d Design/Permitting 06/23/2019 11/06/2019 11/06/2019 137d Construction 11/07/2019 05/01/2020 05/01/2020 177d Close-out 05/02/2020 05/31/2020 05/31/2020 30d Project Category:Parks UPDATE Currently in the process of finalizing the contractor award process. GO#18: SCOTT RAKOW YOUTH CENTER www.gombinfo.com 42 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 #18 SCOTT RAKOW ROOF GOB Project #: Location: 18 Middle Beach Active Phase:Construction Department:Property Management SCOPE Replace the existing aged roof with a new durable roof. GOB FUNDING Budget:$2,100,000 Spent:$0 Available:$2,100,000 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 04/01/2019 09/30/2019 09/30/2019 183d Design/Permitting 10/01/2019 10/30/2019 10/13/2019 13d Construction 10/14/2019 02/27/2020 02/10/2020 120d Close-out 02/11/2020 03/28/2020 03/11/2020 30d Project Category:Parks UPDATE Permitting underway. GO#18: SCOTT RAKOW YOUTH CENTER www.gombinfo.com 43 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 #18 SCOTT RAKOW WINDOWS GOB Project #: Location: 18 Middle Beach Active Phase:Design Department:Property Management SCOPE Replace the existing standard windows with high-impact windows. GOB FUNDING Budget:$700,000 Spent:$0 Available:$700,000 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 04/01/2019 08/30/2019 08/30/2019 152d Design/Permitting 08/31/2019 09/29/2019 09/29/2019 30d Construction 09/30/2019 03/27/2020 03/27/2020 180d Close-out 03/28/2020 04/26/2020 04/26/2020 30d Project Category:Parks UPDATE NTP 1 issued. Shop drawings underway. GO#18: SCOTT RAKOW YOUTH CENTER www.gombinfo.com 44 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 #19 SOUNDSCAPE 4K TECHNOLOGY GOB Project #: Location: 19 South Beach Active Phase:Complete Department:Tourism & Culture SCOPE Upgrade WALLCAST equipment and technology to have custom- made video screens and 4K HDR visual capabilities. GOB FUNDING Budget:$3,800,000 Spent:$2,997,211 Available:$802,788 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 03/01/2019 04/01/2019 04/01/2019 32d Design/Permitting 04/02/2019 05/27/2019 05/27/2019 56d Construction 05/28/2019 09/30/2019 09/30/2019 126d Close-out 10/01/2019 11/01/2019 11/01/2019 32d Project Category:Parks UPDATE Project complete. New technology unveiled during New World Symphony's 100th WALLCAST Concert on October 12, 2019. GO#19: SOUNDSCAPE PARK www.gombinfo.com 46 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 GOB Project #: Location: 21 North Beach Active Phase:Construction Department:Parks & Recreation SCOPE Replace the existing perimeter fence with a higher security fencing structure, construct a new walking/jogging, add fresh paint and new flooring to pavilion and restroom areas. GOB FUNDING Budget:$145,000 Spent:$0 Available:$145,000 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 05/01/2019 06/12/2019 06/30/2019 61d Design/Permitting 07/01/2019 07/05/2019 07/31/2019 31d Construction 08/01/2019 09/09/2019 10/31/2019 92d Close-out 11/01/2019 09/30/2019 11/30/2019 30d Project Category:Parks UPDATE Currently in the construction phase. GO#21: STILLWATER PARK www.gombinfo.com 49 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 #23 PEDESTRIAN BRIDGE GOB Project #: Location: 23 South Beach Active Phase:Design Department:Capital Improvement Projects SCOPE Construct a custom designed pedestrian bridge to stretch across 5th Street - providing a continuous Baywalk link from the city's entrance at Biscayne Bay and West Avenue to Lincoln Road. GOB FUNDING Budget:$10,000,000 Spent:$51,101 Available:$9,948,898 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 11/06/2018 06/14/2019 06/14/2019 221d Design 04/10/2019 12/10/2019 12/10/2019 8.17mo Construction 12/11/2019 08/28/2020 08/28/2020 8.73mo Project Category:Parks UPDATE Design 95% complete. Currently in Permitting at FDOT and City of Miami Beach. Anticipated Completion: Summer 2020. GO#23: BAYWALK www.gombinfo.com 54 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 GOB Project #: Location: 24 Middle Beach Active Phase:Construction Department:Capital Improvement Projects SCOPE Replace the current wooden boardwalk structure that exists between 23rd Street and 45th Street with an on-grade pedestrian pathway that connects Mid Beach with South Beach and North Beach Beachwalk portions - providing one seamless oceanside pathway that stretches from 1st Street to 87th Street. GOB FUNDING Budget:$4,500,000 Spent:$0 Available:$4,500,000 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 10/22/2015 05/29/2016 05/29/2016 220.88d Design and Permitting 06/07/2016 05/22/2019 05/22/2019 1080d Contractor Selection - ITB 05/22/2019 11/03/2019 11/03/2019 166d Construction 11/15/2019 01/12/2021 01/12/2021 425d Final Completion 01/13/2021 02/13/2021 02/13/2021 31d Project Category:Parks UPDATE Contract is being executed. Construction is expected to start November 2019. Anticipated Completion: January 2021. GO#24: MIDDLE BEACH BEACHWALK PH3 - This project has additional sources of funding www.gombinfo.com 56 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 #26 COLONY THEATRE ROOF GOB Project #: Location: 26 City Wide Active Phase:Complete Department:Property Management SCOPE Replace the roof at the Colony Theatre with a new sustainable roof. GOB FUNDING Budget:$300,000 Spent:$118,090 Available:$181,910 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 03/01/2019 05/14/2019 05/14/2019 75d Design/Permitting 05/15/2019 06/10/2019 06/10/2019 27d Construction 07/08/2019 09/27/2019 10/14/2019 99d Project Category:Parks UPDATE Project complete. Pending closeout and final payment to contractor. GO#26: ROOFS FOR CULTURAL FACILITIES www.gombinfo.com 59 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 #26 FILLMORE ROOF GOB Project #: Location: 26 City Wide Active Phase:Design Department:Property Management SCOPE Replace the roof at The Fillmore with a new sustainable roof. GOB FUNDING Budget:$2,010,000 Spent:$5,625 Available:$2,004,375 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 03/01/2019 06/28/2019 06/28/2019 120d Design/Permitting 06/29/2019 10/01/2019 10/31/2019 125d Construction 11/01/2019 02/29/2020 02/29/2020 121d Project Category:Parks UPDATE Delays in permitting. Completion date remains the same. GO#26: ROOFS FOR CULTURAL FACILITIES www.gombinfo.com 60 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 #26 MIAMI CITY BALLET ROOF GOB Project #: Location: 26 City Wide Active Phase:Design Department:Property Management SCOPE Replace the roof at Miami City Ballet with a new sustainable roof. GOB FUNDING Budget:$670,000 Spent:$6,469 Available:$663,530 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 03/01/2019 06/28/2019 06/28/2019 120d Design/Permitting 06/29/2019 10/01/2019 10/31/2019 125d Construction 11/01/2019 12/10/2019 01/09/2020 70d Close-out 01/10/2020 01/09/2020 02/08/2020 30d Project Category:Parks UPDATE Contractor had difficulty receiving MOT permit due to adjacent Collins Park garage project. Construction projected to begin by November 1. GO#26: ROOFS FOR CULTURAL FACILITIES www.gombinfo.com 61 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 GOB Project #: Location: 29 North Beach Active Phase:Planning Department:Economic Development SCOPE Re-develop and re-purpose the area known as the "West Lots" (8 blocks of city-owned land located across the street from North Shore Open Space Park) as cohesive mixed-use space for recreational/civic/ neighborhood activity. GOB FUNDING Budget:$5,000,000 Spent:$0 Available:$1,000,000 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Future 01/01/2020 10/02/2028 10/02/2028 3198d Project Category:Parks UPDATE This project is in Tranche 1,2,3, which is programmed between the years of 2020-2028. GO#29: WEST LOTS www.gombinfo.com 64 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 GOB Project #: Location: 32 South Beach Active Phase:Design Department:Capital Improvement Projects SCOPE Beautify the islands with new landscaping installed to along Palm Avenue, Fountain Street and neighborhood medians. GOB FUNDING Budget:$1,000,000 Spent:$0 Available:$1,000,000 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 02/11/2019 04/09/2019 04/09/2019 58d Design 04/10/2019 07/22/2019 07/22/2019 104d Procurement - NJPA 07/23/2019 10/30/2019 10/30/2019 100d Construction 10/31/2019 02/28/2020 02/28/2020 121d Final Completion 03/02/2020 03/16/2020 03/16/2020 15d Project Category:Infrastructure UPDATE Award of construction contract in October 2019. GO#32: PALM & HIBISCUS LANDSCAPING - This project has additional sources of funding www.gombinfo.com 67 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 #33 PART 1 TREE PLANTING GOB Project #: Location: 33 North Beach Active Phase:Construction Department:Environmental SCOPE Implement Street Tree Master Plan by planting 3,500 to 5,000 trees to provide canopy coverage and shade, while also providing additional storm water treatment and storage capacity. GOB FUNDING Budget:$2,500,000 Spent:$106,073 Available:$2,393,926 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 04/22/2019 05/05/2019 05/05/2019 15.63d Design/Permitting 05/05/2019 07/11/2019 07/11/2019 75.25d Construction 07/11/2019 02/03/2020 02/03/2020 232.75d Project Category:Infrastructure UPDATE Over 150 trees have been planted. Trees have been planted at Normandy Isle, Brittany Bay, and the 5th Street Corridor. Construction for Biscayne Pointe and the Stillwater Neighborhood will begin in November. Construction for Muss Park and 40th Street, between Pine Tree and Chase Ave will begin in December. GO#33: STREET TREE MASTER PLAN www.gombinfo.com 69 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 GOB Project #: Location: 37 City Wide Active Phase:Construction Department:Public Works Department SCOPE Renovate 25% of the City's sidewalks by replacing cracked and faulty sidewalk surfaces in areas citywide. GOB FUNDING Budget:$13,000,000 Project Category:Infrastructure This project is broken down into more than one sub-project. Each sub-project has a full page of detailed information to follow. GO#37: SIDEWALK IMPROVEMENTS No. of Sub-Projects:4 NOTES www.gombinfo.com 74 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 #37 PART 1 SIDEWALKS GOB Project #: Location: 37 City Wide Active Phase:Construction Department:Public Works Department SCOPE Renovate part 1 of deteriorated sidewalks, as per the city's pavement condition index assessment. GOB FUNDING Budget:$3,500,000 Spent:$291,390 Available:$3,208,609 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 03/01/2019 04/01/2019 04/01/2019 32d Design/Permitting 04/02/2019 05/12/2019 05/12/2019 41d Construction 05/13/2019 01/01/2022 01/01/2022 965d Project Category:Infrastructure UPDATE This project is currently under construction. Approximately 5,400 sf has been completed in North Beach, 11,900 sf in Middle Beach, and 19,600 sf in South Beach. GO#37: SIDEWALK IMPROVEMENTS www.gombinfo.com 75 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 #38 PART 1 STREETS GOB Project #: Location: 38 City Wide Active Phase:Construction Department:Public Works Department SCOPE Repave and restore part 1 of deteriorated streets, as per the city's pavement condition index assessment. GOB FUNDING Budget:$7,500,000 Spent:$868,172 Available:$6,631,827 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 03/01/2019 04/01/2019 04/01/2019 32d Design/Permitting 04/02/2019 05/12/2019 05/12/2019 41d Construction 05/13/2019 01/01/2022 01/01/2022 965d Project Category:Infrastructure UPDATE This project is currently under construction. Approximately 37,100 sy has been completed. GO#38: STREET PAVEMENT www.gombinfo.com 80 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 GOB Project #: Location: 40 Middle Beach Active Phase:Planning Department:Economic Development SCOPE Revitalize the 41st Street Cooridor with neighborhood landscaping and infrastructure improvements such as new high-tech street lighting, an expanded shaded tree canopy, and new streetscape designs for better public transportation, pedestrian and driving mobility. GOB FUNDING Budget:$15,000,000 Spent:$0 Available:$1,500,000 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 09/25/2019 01/01/2031 01/01/2031 4117d Project Category:Infrastructure UPDATE This project is in Tranche 1, 2, 3, and 4, which is programmed between the years 2019-2031. Staff is currently drafting a scope of services for the 41st Street initiatives for the issuance of a work order to an Architectural and Engineering consultant from the approved pool. GO#40: 41 ST. CORRIDOR www.gombinfo.com 85 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 #42 NAUTILUS TRAFFIC CALMING GOB Project #: Location: 42 City Wide Active Phase:Construction Department:Transportation SCOPE Implement traffic calming measures in the Nautilus neighborhood. GOB FUNDING Budget:$739,500 Spent:$0 Available:$739,500 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 03/01/2019 04/01/2019 04/01/2019 32d Design/Permitting 04/02/2019 09/11/2019 09/11/2019 163d Construction 09/12/2019 01/15/2020 01/15/2020 126d Close-out 01/16/2020 02/05/2020 01/31/2020 16d Project Category:Infrastructure UPDATE The speed limit sign installation and the green bike lane on target for completion by 10/18. The speed table construction will be completed by 10/31 and the traffic circle construction will be completed by mid- January. GO#42: TRAFFIC CALMING www.gombinfo.com 90 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 GOB Project #: Location: 45 South Beach Active Phase:Planning Department:Capital Improvement Projects SCOPE Replace the deteriorated Fire Station #1 facility with a new and larger building in a location that expands emergency coverage in South Beach; include space for a 911 call center. GOB FUNDING Budget:$10,000,000 Spent:$0 Available:$7,000,000 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 11/06/2018 10/23/2019 10/23/2019 352d Design 10/24/2019 10/12/2021 10/12/2021 720d CM@Risk Selection 09/05/2019 12/28/2021 12/28/2021 846d Construction 01/05/2022 02/28/2023 02/28/2023 420d Final Completion 03/01/2023 03/30/2023 03/30/2023 30d Project Category:Public Safety UPDATE The professional services negotiations for the A/E consultant is complete. Notice to Proceed shall be issued by the end of next week. The procurement process for the Construction Manager at Risk is also underway. Anticipated Completion: 2023. GO#45: FIRE STATION #1 www.gombinfo.com 99 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 #47 71 ST. ENTRANCE READERS GOB Project #: Location: 47 City Wide Active Phase:Construction Department:Police SCOPE Install License Plate Readers (LPRs) to the 71 St. entrance to the city. GOB FUNDING Budget:$240,000 Spent:$0 Available:$240,000 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 03/01/2019 03/26/2019 03/26/2019 26d Design/Permitting 03/27/2019 09/06/2019 09/06/2019 164d Construction 10/01/2019 11/06/2019 11/06/2019 37d Project Category:Public Safety UPDATE Construction underway. GO#47: LICENSE PLATE READERS www.gombinfo.com 102 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 #47 JULIA TUTTLE CSWY READERS GOB Project #: Location: 47 City Wide Active Phase:Design Department:Police SCOPE Install License Plate Readers (LPRs) to the Julia Tuttle Causeway entrance to the city. GOB FUNDING Budget:$200,000 Spent:$0 Available:$200,000 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 03/01/2019 03/26/2019 03/26/2019 26d Design/Permitting 03/27/2019 10/25/2019 10/25/2019 213d Construction 10/28/2019 11/29/2019 11/29/2019 33d Project Category:Public Safety UPDATE Purchase order in process. Contractor expected to begin the week of October 28. GO#47: LICENSE PLATE READERS www.gombinfo.com 103 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 #47 MACARTHUR CSWY READERS GOB Project #: Location: 47 City Wide Active Phase:Construction Department:Police SCOPE Install License Plate Readers (LPRs) to the MacArthur Causeway entrance to the city. GOB FUNDING Budget:$120,000 Spent:$0 Available:$120,000 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 03/01/2019 03/26/2019 03/26/2019 26d Design/Permitting 03/27/2019 09/06/2019 09/06/2019 164d Construction 10/28/2019 11/28/2019 11/28/2019 32d Project Category:Public Safety UPDATE Equipment has been ordered. Purchase order for installation contractor in process. GO#47: LICENSE PLATE READERS www.gombinfo.com 104 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 GOB Project #: Location: 49 City Wide Active Phase:Construction Department:Police SCOPE Replace the city's outdated Motorola analog radio system with a new Harris Corporation satellite radio system, giving first responders access to a state-of-the-art emergency communications technology network with high tech functions such as seamless interoperability and encrypted data. GOB FUNDING Budget:$10,000,000 Spent:$3,501,858 Available:$6,498,141 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Implementation 01/01/2019 02/28/2020 02/28/2020 424d Project Category:Public Safety UPDATE Currently in the implementation phase with site(s) improvements and construction. Factory Acceptance Tests have been completed. GO#49: PUBLIC SAFETY RADIO SYSTEM www.gombinfo.com 107 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 #52 CRESPI PARK LED LIGHTING GOB Project #: Location: 52 City Wide Active Phase:Construction Department:Parks & Recreation SCOPE Upgrade park lights to LED technology. GOB FUNDING Budget:$87,000 Spent:$458 Available:$86,541 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 05/01/2019 06/30/2019 06/30/2019 61d Design/Permitting 07/01/2019 10/31/2019 09/30/2019 92d Construction 10/01/2019 11/15/2019 10/21/2019 21d Project Category:Public Safety UPDATE Construction scheduled to be completed ahead of schedule by October 21. GO#52: LED LIGHTING IN PARKS www.gombinfo.com 115 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 #52 NORMANDY ISLE PARK LED LIGHTING GOB Project #: Location: 52 City Wide Active Phase:Design Department:Parks & Recreation SCOPE Upgrade park lights to LED technology. GOB FUNDING Budget:$715,000 Spent:$0 Available:$715,000 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 05/01/2019 06/30/2019 06/30/2019 61d Design/Permitting 07/01/2019 11/30/2019 10/30/2019 122d Construction 10/31/2019 12/21/2019 11/20/2019 21d Project Category:Public Safety UPDATE Installation expected to begin by the end of October and take approximately 3 weeks. GO#52: LED LIGHTING IN PARKS www.gombinfo.com 116 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 #52 STILLWATER PARK LED LIGHTING GOB Project #: Location: 52 City Wide Active Phase:Construction Department:Parks & Recreation SCOPE Upgrade park lights to LED technology. GOB FUNDING Budget:$87,000 Spent:$458 Available:$86,541 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 05/01/2019 06/30/2019 06/30/2019 61d Design/Permitting 07/01/2019 10/15/2019 09/27/2019 89d Construction 09/30/2019 10/31/2019 10/21/2019 22d Project Category:Public Safety UPDATE Scheduled for completion ahead of schedule by October 21. GO#52: LED LIGHTING IN PARKS www.gombinfo.com 118 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 #52 TATUM PARK LED LIGHTING GOB Project #: Location: 52 City Wide Active Phase:Complete Department:Parks & Recreation SCOPE Upgrade park lights to LED technology. GOB FUNDING Budget:$152,000 Spent:$448 Available:$151,551 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 05/01/2019 06/30/2019 06/30/2019 61d Design/Permitting 07/01/2019 11/15/2019 09/23/2019 85d Construction 09/24/2019 11/30/2019 10/14/2019 21d Project Category:Public Safety UPDATE Project is complete. Pending closeout and final payment to contractor. GO#52: LED LIGHTING IN PARKS www.gombinfo.com 119 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 #53 PORTABLE BOLLARDS GOB Project #: Location: 53 City Wide Active Phase:Complete Department:Police SCOPE Acquire portable barriers to store and deploy for special event use. GOB FUNDING Budget:$600,000 Spent:$599,915 Available:$84 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration PLANNING 04/01/2019 04/21/2019 04/21/2019 21d DESIGN/PERMITTING 04/22/2019 05/13/2019 05/13/2019 22d CONSTRUCTION 05/14/2019 07/31/2019 07/31/2019 79d Project Category:Public Safety UPDATE COMPLETE. GO#53: SECURITY FOR PUBLIC SPACES www.gombinfo.com 123 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 GOB Project #: Location: 56 South Beach Active Phase:Planning Department:Police SCOPE Improve public safety for residents and visitors between 14th Place to 23rd Street by installing several new security cameras along the pedestrian beachwalk path. GOB FUNDING Budget:$400,000 Spent:$0 Available:$400,000 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 04/01/2019 05/05/2019 05/05/2019 35d Design/Permitting 05/06/2019 01/14/2020 01/14/2020 254d Construction 01/15/2020 03/19/2020 03/19/2020 65d Project Category:Public Safety UPDATE Quotes from vendor are under evaluation. Will kick off after the Lummus Park Connectivity is completed. GO#56: CAMERAS- BEACHWALK www.gombinfo.com 130 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 #57 LUMMUS PARK/OCEAN DRIVE CAMERAS GOB Project #: Location: 57 South Beach Active Phase:Design Department:Police SCOPE Install additional security cameras to expand monitored coverage in Lummus Park and Ocean Drive. GOB FUNDING Budget:$815,000 Spent:$0 Available:$815,000 SCHEDULE Phase Description Start Date Original End Date Anticipated End Date Duration Planning 04/01/2019 05/05/2019 05/05/2019 35d Design/Permitting 05/06/2019 11/15/2019 11/15/2019 194d Construction 11/16/2019 02/01/2020 02/01/2020 78d Project Category:Public Safety UPDATE The city is currently in negotiations with three integrators to quote out the work. GO#57: CAMERAS- ENTERTAINMENT DISTRICT www.gombinfo.com 133 Thursday, October 17, 2019 7:00 AM City of Miami Beach GO Bond Program Program Progress Report: October 17, 2019 G. O . B o n d I m p l e m e n t a t i o n P l a n - Q u i c k W i n s - Oc t o b e r 1 7 , 2 0 1 9 Page 1 of 5 Ex p o r t e d o n O c t o b e r 1 7 , 2 0 1 9 3 : 2 1 : 2 8 P M E D T EX H I B I T C P r o j e c t 11 / N I I I l l e T o t a l Qu i c k Wi n S t a r t En d Da t e O r i g i n a l S t a t u s D u r a t i o n Q1 20 1 9 Q 2 20 1 9 Q3 20 1 9 Q4 2019 Q1 2020 Q2 2020 Q3 2020 Q4 2020 01 2021 Bu d g e t Bu d g e t Da t e En d Da t e Ja n Fe b Ma r Ap r Ma y Ju n Ju l Au g Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar CI P 01 1 3 1 / 1 9 01 1 1 2 1 2 1 71 3 d B tl 2 4 Mi d Be a c h e. . c r - n c : $4 , 5 0 0 , 0 0 0 $4 , 5 0 0 , 0 0 0 01 1 3 1 / 1 9 01 / 1 2 1 2 1 10 / 1 6 1 2 0 71 S d t -- - - = =- t- - - - 1 - - 1 - - - - - 1 - - - + f - - - - G _ra _n _l ( '- - a '- -pp _ro v e d _ _ 1. _31 -' - ) _ _ _ _ _ _ + - - - - - - - t - - - - - - + - - 0 - 1 _13 _1 _11 _9 _ + - o _1 _13 _1 _11 _9 _ - - - I _ _ 01 _13 _1 _11 _9 _ - + - - - - - - - - - - - - - - - - - - - + - - 1 _d _ _ f - - - l l Gr a n t i (a p p r o v & d 1. 3 1 ) De s i g n (C o m p l e t a ) 02 1 0 1 1 1 9 02 1 0 5 / 1 9 02 1 0 5 / 1 9 5d ( , De s i g n (C o m p le t e ) f- - - - - - - ~ ~ - ' - - ~ - - - - - - - - - - - - - - - 1 - - - - - - - - + - - - - - - - - - - + - - - - - - - - + - - - - - - - - - + - - - - - - - - + - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - + - - - - - - - + - - - ~ .!-~ - - ~ - ~ ~ ~ ~ DE P Pe r m i t (C o m p l e t e ) 02 1 0 6 / 1 9 05 1 2 4 / 1 9 05 1 2 4 / 1 9 10 8 d -: : 1----+-----1 ---+--+---+ - DE P P e mi l (Co r ~ple t e ) I - = = - ~ -~remenl r ~-1----+-----1 ---t--+---+ Pr o c u r e m e n t 06 / 0 3 / 1 9 10 / 0 1 1 1 9 09 1 3 0 / 1 9 12 1 d l------1-----+ ----1-----+--L - Co n s t r u c t i o n 11 / 1 5 1 1 9 01 / 1 2 1 2 1 10 / 1 6 1 2 0 42 5 d .,.-,-+ 8 #3 2 1 ' 1 1 1 m & H i b l e c u s $1 , 0 0 0 , 0 0 0 $1 , 0 0 0 , 0 0 0 03 / 0 4 / 1 9 03 / 0 3 1 2 0 05 1 0 1 1 2 0 38 8 d _j_ _ _ #32 Palm & Hibiscus Pr e p l a n n l n g (C o m p l e t e ) 03 / 0 4 / 1 9 06 1 0 6 / 1 9 06 / 1 2 1 1 9 95 d ., . ., . Pr e p l l l n n i n g (C o m p l e t ,_el _ _ f---+-- f - - - - P - ro _cu _ re _m _e _nl _(_lm _·g _a _li o _n _ &_ S _hr u _ bs _) _ _ _ f - _ _ _ - - - I - - - - - - - - I - 0 - 6/_1 _31 _1 _9 _ - + - 1 -0/ 3 _ 11 _19 _ _ - + - _ 09 _1 _14 _11 _9 _ - + G _o _in g _ to _ Co _ m _m _is s _ i _on _o _n _1 _0J _16 _. _ _ _ _ _ _ _ _ _ _ _ t - _ 1 _4 _1 _d _ - + - - - t - - - + - - - + - - + - l - - + - - l - - + - r - - _...._ t rocuremenl(l[rigalion&Shrubs) _1 Co n s t r u c t i o n 11 1 0 1 / 1 9 03 1 0 3 1 2 0 05 1 0 1 1 2 0 12 4 d 1 I .,. T T ,. Cons1 uction - EN V I R O N M E N T A L 04 1 2 2 / 1 9 01 / 1 6 1 2 0 27 0 d ENVIRONMENTAL 8 tl 3 3 81 r a a t TI M Ma M a r Pl a n $5 , 0 0 0 , 0 0 0 $5 0 0 , 0 0 0 04 / 2 2 1 1 9 12 / 3 0 / 1 9 01 / 0 1 1 2 0 2! i 3 d tl33 Street T .....j Master Plan 1 ------1 -- 8 5t h St n l e l Co m d o r 04 / 2 2 1 1 9 09 / 1 3 / 1 9 01 / 0 1 1 2 0 14 5 d 5th Street Conidor f-- - - - P _re~p ~la _n _n _in~g_:_(C _o _m_:_p _le _te_:_) _ _ _ _ _ I - - - - - - - - I - - - - - - - - I - 0 - 4 _12 _21 _1 _9 _ - + - 05 1 - 0 _21 _19 _ _ - + - _ 05 1 0 _ 21 _ 1 _9 _ - t - - - - - - - - - - - - - - - - - - - - - t - - - 1 _1d _ _ l--- - + - - -+- - +-- ~-4 'l Prepl ~n ~ l ~ _j_ 1----l-----1 --r De s i g n / P e r m i t t i n g (C o m p l e t e ) 05 1 0 3 / 1 9 07 / 0 3 / 1 9 07 / 0 3 / 1 9 62 d = De s i g n / P e r m i t t i n g (Co r plele) - =! ~ Pr o c u r e m e n t (C o m p l e t e ) 07 / 0 4 / 1 9 07 / 3 1 / 1 9 09 / 1 3 / 1 9 28 d _ r t ro c u r e m e n t (Cl:omplete) Co n s 1 r u c l i o n ( C o m p l e t e ) 06 / 0 1 / 1 9 09 / 1 3 / 1 9 12 1 1 1 / 1 9 43 t r e e s w e r e p l a n t e d . 44 d ; - - - ~ Co [ls truclion(Com~lete) -----r f-- - ~ ~ ;;; ; ; h ~ ; d e ; ; ; ; e ; ; -- - ~ -- ~ ~ ~'l- ~~ ~ -'l - o . ~~ ~ 1 o ~ ~ g - -'j ~9 J O i ~ ~ - r - - - - - - - - - - - - - - - - - - - - r ~ ~~-~ - ~ - ~- - ~- .. . . . . . . . . --~---- - ~ - - ~ N;;;~~~ ~--f---j _J I R No r m a n d y II I I I an d Br i t l a n y B a y $6 0 , 0 0 0 $6 0 , 0 0 0 04 / 2 2 / 1 9 06 1 3 0 / 1 9 09 / 0 6 / 1 9 13 1 d l No n n a [ld y Isle and Brill8ny Bay Park I Pa r k - : I - -----+--+---+ Pr e p l a n n i n g (C o m p l e t e ) 04 / 2 2 1 1 9 04 / 2 6 / 1 9 04 / 2 8 / 1 9 7d Pr e p l a n n i n g (C o m p l e l e ) - r - - - - - r - - - 1 - - - - + f- - - - - - D _es ~ig _ni _P _erm _itti _n ~g ~(~C _om ~pl _eta _)~- - - + - - - - - - + - - - - - - - + - - o _4 _12 _9 _11 _9 _+ - o _51 _0 _11 _19 _ _ - + - _ 05 1 _ 0 _1 _11 _9 _ - + - - - - - - - - - - - - - - - - - - - - - + - - - 3 _d _ _ f- - - - + - - - + - - + - - ~ Desi g n W e n m i ~ n g ( C o ~ --+---+ Pr o c u r e m e n t (C o m p l e t e ) 06 / 1 3 / 1 9 06 / 2 7 / 1 9 07 / 1 5 / 1 9 15 d - - + P _ro _c _ur e m e n l (C o m p l e t e ) 1----+----+ -----t j_--+--,_ Co n s 1 r u c l i o n (C o m p l e t e ) 07 / 1 2 1 1 9 06 1 3 0 / 1 9 09 1 3 0 / 1 9 10 1 tr e e s we r e pl a n t e d . SO d I ~ Co n s t r u c t i o n (Complete) t ==~~~~~~~ ===== = = = = = = = = = = = ~~~~~==~~~==~ ~ ~~~ =l ~~~ ==~= = ~~~ ==t== = = = = = = = = = = = = = = = = = = = = = = = = = = = = = = = = = = = = = t = ~~===t = = = = t = = = t = = = = l = = ~ ~ ~ ~ ~ ~ ~ § = ~ ~ ~ ~ ~ ~ ~ ~ ~ = = ~ ~ ~ ~~~ ----r 8 Bl l l c a y n e Po l n l a $8 5 , 0 0 0 . 0 0 $8 5 , 0 0 0 04 1 2 2 / 1 9 12 / 3 0 / 1 9 12 1 2 2 1 1 9 25 3 d +- - - I - - - - 1 - - - - Bisca)ll)e ~Pointe __ + Pr e p l a n n i n g (C o m p l e t e ) 04 1 2 2 / 1 9 06 1 1 5 1 1 9 05 1 2 1 / 1 9 11 6 d . L _ , _ . . . _ Pr e p l a n n i n (Complete) +-- - - - 1 t-----+-----1 ---+ De s i g n / P e r m i t t i n g (C o m p l e t e ) 06 / 1 6 / 1 9 06 1 3 0 / 1 9 06 / 0 1 / 1 9 15 d \Des l gr ~ermilling (Complete) Pr o c u r e m e n t 06 1 3 1 1 1 9 11 / 0 1 1 1 9 06 / 1 3 / 1 9 Pr o p o s a l a e x p e c t e d 1 0 1 1 8 . 63 d L ; 1 Procurement f--------,.j_--+_--+ ---+-t -----j_ __ : + 11 1 0 2 1 1 9 12 / 3 0 / 1 9 12 1 0 1 / 1 9 59 d r--Construction j- - - ~ s;;; ~ ~ ; ; ; h ; ; --- - - - - - - - - t -.~~ ~t - ~~~ ,--- ~ ~~ ;--t 1:U , ~ ;----j ~Utlv , e --t - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - t - ~~-- - j - - ~ - - -j ~ - - j-- - ~= = = = ~ = = ~ = = ~ = = = = F = = = ~ = = = * = = = = ~ = = ~~~~ -----,_ 8 St l l w a l a r N a l g h b o l h o o c l $3 0 , 0 0 0 $3 0 , 0 0 0 04 1 2 2 / 1 9 12 / 3 0 / 1 9 11 1 1 6 / 1 9 25 3 d +~ -- - L f----stillwaterNeighbo ±rhood + Pr e p l a n n i n g (C o m p l e t e ) 04 1 2 2 / 1 9 06 1 1 5 1 1 9 05 1 2 1 / 1 9 11 6 d _ r : = -t re p l a n n i n g (Complete) De s i g n / P e r m i t t i n g (C o m p l e t e ) 06 / 1 6 / 1 9 06 1 3 0 / 1 9 06 1 0 1 / 1 9 15 d \ De s i g n / P e r m i t t i n g (Complete) Pr o c u r e m e n t 06 1 3 1 / 1 9 11 / 0 1 / 1 9 07 / 1 5 / 1 9 Pr o p o s a l s ex p e c t e d 10 1 1 6 . 63 d 1 - __._ Procurement Co n s 1 r u c l i o n 11 / 0 2 1 1 9 12 / 3 0 / 1 9 10 / 2 8 / 1 9 59 d - - 1 - - - ....._ Construction 8 40 t h st a n d MI M S Pa r k $2 2 0 , 0 0 0 $2 2 0 , 0 0 0 06 1 2 1 / 1 9 01 / 1 6 1 2 0 14 9 d I~ !E ~ - f ~ ~ E - - - f ~ ~ ~ ~4 ~~~S ~t ~an ~d Muss l?ark 1 - -= - + - - - - ------1 --- ~- - - - - P _re ~p _la _n _n _in ~g _:_(Co _ _ m ~p _lm _e ~)--- - - - - - - - - - I - - - - - - - - - - - I - - - - - - - - - - - - - I - - 0 -612 _ _ 1 _/1 _9 _ _ 4-061 3 -- - ~-19 _ _ _ _ -+ - _ _ 06 1 3 _ _ 0 _11 _9 _ _ - t - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - t - - - - 10 _d _ _ _ _ l - - - - - + - - - - + - - - - + - - - - + - - - - + - - - - t - - - - - r - - - - ~l PPrerepplanni~(Complele)l-----1----+ ---+---r De s l g n / P e i T T l i l l i n g 06 1 3 1 / 1 9 09 / 2 9 1 1 9 09 / 2 9 1 1 9 30 d _ _ 1 - - - -DesignWermilli t!----f----~ Pr o c u r e m e n t 09 1 3 0 / 1 9 11 / 1 3 / 1 9 11 / 1 3 / 1 9 Pr o p o s a l a e x p e c t e d 1 0 / 1 8 . 45 d r-,Procuremel 11 / 1 4 / 1 9 o1 1 1 6 1 2 o 01 / 1 6 1 2 0 s4 d 1 " ~ Construction --r Co n s 1 r u c l i o n -+ Co n s t r u c t i on f---- - - :-:~:-~:a -":-i:~~~:Co -(Com _m_:_p _~~-~~\----- - - - - - - + - - - - - - - - - + - - - - - - - - - - - ~ ~-:-,:-:-:-:--+-~-:-':-:-:-:-----l - - - ~:-':-:-,:-:--+-- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - + - - - :-::----~ - - - l - - - -+---- ~c~~~-~---·~~'·P ~-4 re ::~:~~ Co ~ -f---- De s i g n W e r m i l l i n g (C o m p l e t e ) 05 1 1 6 / 1 9 06 / 2 2 / 1 9 07 / 0 8 / 1 9 38 d l b n/ P e n n i t t i n g (C o m p l e t e ) Co n s t r u c t i o n (C o m p l e t e ) 06 / 2 3 / 1 9 06 / 1 0 / 1 9 06 / 1 0 / 1 9 49 d j c;: : : : . . . . . ~ onstr u c t i o (Complete) ~ --+--+ Cl o s e - o u V F i n a l Pa y m e n t (C o m p l e t e ) 08 / 1 1 / 1 9 09 / 0 6 / 1 9 08 / 2 8 / 1 9 27 d -' Close-ouVFin I Pa ~l (Co ~ -- ~~ ~~ D i ~ ~ ~ ~~-- ~ ~ - - ~ ~~~ ~t-~~vo o o--t ~~~ --~~M9 ---t -,vrn ~ ~t-- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - t - -z ;d --t - - - - t - - -t -- ~ - - - - ~- - ~ - - ~ - - ~ - - ~ - - - - ~ - - ~ - - ~ - - ~~~ ------t rl _ _ EJ __ ~ __ LE _ _ D _L _Ig _~_ng _ _ ln _~ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - + - _ $4 _ ,_50 0 _ _ ,o o o __ - - t _ _ $_1 _,0 4 _ _ 1, _00 0 _ _ _ _ ~ o _510 _ _ 1 _11 _9 _ _ t - 12 1 2 _ _ 4 _11 _9 _ _ -- - 1 _ _ _ 12 1 _ 0 _51 _1 _9 _ _ + - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - + - - - 23 _6 _d _ _ -t- - - - - J - - --- I ~ - - -J- - - -t - - - - ~ - - -t- - - - - - L l t----t-5 _2 _LE _D ~UghtinginPa~ 1-----1-----t -+------t---1 1----+-----1 --+--+---+ -1---~-+ f- - __ _ P _re .c p _la _n _n _in -' -g -- ' -(C o _ m .c . p _le t _e -' -)- - - - - - f - - - - - - - l - - - - - - - - l - o _51 0 _ 1 _i1 _9 _ - + - o _51 _3 _11 _19 _ _ -+ - _ o5 _12 _31 _ 1 _9 _ - + - - - - - - - - - - - - - - - - - - - - + - - 3 _1d _ _ t - - - - + - - - + - - + - - - + r - t re p l a nl n g (C f mp l e t e ) Pr o c u r e m e n t ( C o m p l e l e ) 06 1 0 1 1 1 9 06 1 3 0 / 1 9 06 1 1 7 / 1 9 30 d ~ __ - Pr o c u r e m e n t ( C o m p l e t e ) _ j J --+ De s i g n W e i T T l i l l i n g (C o m p l e t e ) 07 1 0 1 / 1 9 06 1 3 1 / 1 9 06 1 0 3 / 1 9 62 d . . . . . _ ~Desigrj/Penmilting (Complete) - = LJ. 1----+-----1 ---+ Le a d t i m e f o r a i i L E D f o r t u r e s 09 / 0 1 1 1 9 10 / 1 5 / 1 9 09 / 0 1 / 1 9 45 d ~ Lel.dtimeforaULEpfortures - . ----::--t---+ ~-- = 8 = - - M _o _b _ili _za _l _io _ni _Co _n _s _tru _ct _io _n: _ _ _ _ _ - + - - - - - - + - - - - - - - + - - 0 _9 _12 _4 _11 _9 _ - + - 1 _11 _2 _01 _19 _ _ - + - - - - - - t - - - - - - - - - - - - - - - - - - - - - t - - - 58 _d _ _ l - - - - + - - - + - - + - - - + - - - - + _ _ L _ j _ Mob1lizat1 n/Cons1rucuon:1 + St i l l w a t e r Pa r k 09 1 3 0 / 1 9 10 / 2 1 / 1 9 09 / 1 1 / 1 9 22 d ~ Sti l water Park --+--+ CIP +---t---+----+--+----+----+ --T ·r r: --------Construction ----+--+-~---r--+-~---+ +---t--4----t--+----+----+ + -~---------~---+-----~--~--~-' -------r---f---1~~~~==4----+ --T---+---~----+----J----t-----1 ----+ -----I +----t----4-----t----+-----+----+----+----+----+---~ + t + +---+----4----+----+-----+----+----+----+----+---~ + +----+----+-----+----+----+----+----+----+----+---~ +---+-----!-----+----+-----+----+----+----+----+---~ + +----t-----J-----t----+-----+----+----+----+----+---~ + + + + +----t----4-----t----+-----+----+----+----+----+---~ + +---+----4----+----+-----+----+----+----+----+---~ + I PARKS I +---4----+----4----+-----+----+----+----+----+----+---4----+----4----+-----l----+----+----+----+----+---4----+----4----+-----l----+----+----+----+----+---4----+----4----+-----l----+----+----+----+-------+----t-----+----+----+----t----4----+----+----t -+--~--~--+---+---+---+---r--+-------+----t----r---+----+----r----J----+---~----+ -t------1~--+----t-----r---+----+----r---+----+----t----+-----+----+-----J----+----+----+----+-----+---~~--+----+-----t----+----+----1----+---­+---4----+----4----+-----l----+----+----+----+-----+---~~--+----t-----l----+----+----t----+----+ + ~- - - - - - - - - - - - - - - - - - - - - - - - - - - - - t - - - - - - - - - + - - - - - - - - - - - 1 - - - - - - - - - t - - - - - - - - - ~ - - - - - - - - + - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - + - - - - - - - - + - - - - + - - ~ ~ - - - l - - - - + - - - - + - - - - - - r - - - - r - - - + - - - - , 1-----+----+-----,.----+---+ f-- - - - - - - - c -~~-i _Pa _rk _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ f - - - - - - - - - + - - - - - - - - - - - + - - 1 _0 _10 _1 _11 _9 _ _ + - 1 _W _2 _11 _19 _ _ _ _ -+ - __ 09 _12 2 1 _ _ 1 _9 _ _ - + - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - + - - - - 2 -1d _ _ _ _ f - - - - - + - - - - + - - - - + - - - - + - - - - + - - - 1 - - - l_ _j _ -~respiPa ~rk ----~--4 _j_ ______ + +---1----+----1----+----+----+----+----+----+---- Ta t u m Pa r k 09 / 2 4 / 1 9 10 / 1 4 / 1 9 10 / 0 2 / 1 9 21 d c:;=:! Tatum Par1< --1----+----+----1----~---+----t-----+----+----+ ~- - - - - - - - - - - - - - - - - - - - - - - - - - - - + - - - - - - - - + - - - - - - - - - - + - - - - - - - - r - - - - - - - -+ -- - - - - - - + - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - + - - - - - - - + - - - - r - - -r - - -1 - - - - r- - - + - - - r---+---~---T---~--,_ + -+--~----+---+----+---1----r---+---~---- L _ _ _ _ _ _ _ _ N _o _nn _ _ a~~- ~-~_Pa _ _ m _ _ _ _ _ _ _ _ _ _ _ _ _ L _ _ _ _ _ _ _ _ _ L _ _ _ _ _ _ _ _ _ _ _ L _ _ 10 _13 _1 _11 _9 _ _ J _ 1 _11 _2 _W _19 _ _ _ _ _ L _ _ 10 _1 _16 _11 _9 _ _ _ L _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ L _ _ _ 2 _1d _ _ _ _ L _ _ _ _ L _ _ _ . L _ _ _ _ J _ _ _ _ . L _ _ _ _ ~ _ _ _ L _ _ _ _ L_ __ _ L_ I __ _L ____ L_ __ ]~No _nm __ ~_d ~y ~ls _le __ P~_L __ _J ____ J_ __ ~----~--_L ____ L_ __ _L ____ L_ __ _L ____ L_ __ _L ____ L_ __ J_ __ Page 2 of 5 Ex p o r t e d o n O c t o b e r 1 7 , 2 0 1 9 3 : 2 1 : 2 9 P M E D T Page 3 of 5 Ex p o r t e d o n O c t o b e r 1 7 , 2 0 1 9 3 : 2 1 : 3 0 P M E D T Th e ci t y Ia cu r r e n t l y In ne g o t i a t i o n s wi t h th r e e ln t a g r a t o r e to qu o t e ou t th e wo r k . Co n a t r u c t i o n st a r t is de p e n d e n t on Lu m m u s Pa r k Co n n e c t M t y Pr o j e c t . +-+-+-+ + + ~ ~ + + ~ ~ + + ~ ~ + + + ~ ~ + + ~ ~ + + ~ ~ + + .. Page 4 of 5 Ex p o r t e d o n O c t o b e r 1 7 , 2 0 1 9 3 : 2 1 : 3 2 P M E D T + + + + + + + + + + + + ~ + ~ ~ + + ~ + ~ ~ + + ~ + ~ ~ + + .. .. .. .,. 1-+ .. .. .,. 1-+ .. .. .,. + t-+ + + + + + 1 00 % af ax t s r i o r pa i n t i n g h u be a n co m p l a t & d . ak a t i n g ri n k ia th e on l y pe n d i n g • .. . , on ln l e l t c r . 1-+ .. .. .,. 1-+ .. .. .,. 1-+ .. .. .,. + + t-+ + + + + + + + + t-+ + + + + + + + + + + + ~ ~ + ~ ~ + ~ ~ + .. + .. .. .,. .,. .. + .. .. .,. .,. .. + .. .,. .,. + + + + + + + + + + + + + + + + + ~ + + ~ ~ + + ~ + + ~ ~ + + ~ + + ~ ~ + + + .. .. .,. + .. .. .,. 1-+ .. .. .,. + + t-+ + + + + + + + t-+ + + + + + Pr o j e c t c o m p l - 10 1 1 0 . Pr o ) o c l M . . _ r c o n d u c t l n g ft n a l wa l k th r o u g h on 10 / 1 8 . + .. .. .,. .. .. .,. + + + + + 1 + + + + + + + + + + + ~ ~ + + ~ ~ + ~ ~ + .. .. .,. .,. + + .. .. .,. .,. + 1-+ + .. .. .,. .,. ~ + + + + + Page 5 of 5 Ex p o r t e d o n O c t o b e r 1 7 , 2 0 1 9 3 : 2 1 : 3 4 P M E D T Ll l m I f l! l ! J I D l: ' l m ! D 6 f m l l ~ t= . m m ~ ~ ~ ~ emi:) l.!'imll " " .. "' " .. ! " • "' " - PU B L I C WO R K S 05 1 1 3 1 1 9 06 1 3 0 1 2 0 41 5 d PUBLIC WORKS B 13 8 8l n l l l t " - l e n t !l l l n n n n n n n $4 . 0 1 1 0 , 0 0 0 05 1 1 3 1 1 9 01 / 1 5 1 2 0 08 1 2 8 1 1 9 24 B d L ...u,.,h t i c . L L L F No r t l l 05 1 1 3 1 1 9 01 / 1 5 1 2 0 06 1 2 7 / 1 9 24 B d '-" t t ~ ~ ... 1 (C o m p l e t e ) t t t t t ~ ~ ... "• t (C o m p l e t e ) t t + t + + 1-1-+ .. • . .. ., (C o m p l e t e ) -~ .. . . . ·C a m t t + + 1-1-+ ·C o m p l e t e 05 1 1 3 1 1 9 07 / 1 6 1 1 9 08 1 1 6 1 1 9 65 d ~ ~late t t + + 1-1-+ ·B i a r r i t z 01 1 0 2 1 2 0 01 / 1 5 1 2 0 01 / 1 5 1 2 0 14 d ~erC Cc.·-··cticr·~ Biarrilz 1-+ + + + + I i !P a y m e n t 07 1 1 7 1 1 9 07 / 2 7 / 1 9 06 1 2 7 / 1 9 11 d ~ .. ~ .. ~ 1-+ + + + + (= . Yd 07 1 2 2 / 1 9 06 1 1 1 / 1 9 08 1 2 0 1 1 9 21 d ,. , . . . 1-+ 1-+ + + + + ··~ - " " " ' ~ ( C o m p l e t e ) t " t ,_ t t + "• t (C o m p l e t e ) l L t t + 1 (C o m p l e t e ) ~~ t + I (C o m p l e t e ) 07 1 2 2 / 1 9 08 1 0 5 1 1 9 06 1 1 4 1 1 9 15 d l ,. , , + 1-+ + + + + I i !P a y m e n t 08 1 0 8 1 1 9 06 1 1 1 / 1 9 08 1 2 0 1 1 9 Bd '"" lf>_ayrh~ + 1-+ + + + + (= . So u t h 05 1 1 3 1 1 9 07 1 2 9 1 1 9 08 1 2 8 1 1 9 78 d 1 So u t h + 1-+ + + + + ··~ - " " " ' ~ ( C o m p l e t e ) t r - " t ,_ t + t + + ~ ~ ... D o t (C o m p l e t e ) - l t + t + + ~ ~ ... ~· ~ " .. . . . . . . . . . ~( C o m p l e t e ) - · - f - t + t + + ~ ~ ... ~· -· - ~ ~ · · ( C o m p l e t e ) 05 1 1 3 1 1 9 08 1 2 6 1 1 9 06 1 1 3 1 1 9 47 d I (' * " p l e t e - + t + ~ L ~ ... I i !P a y m e n t 06 / 2 9 1 1 9 07 1 2 9 1 1 9 08 1 2 8 1 1 9 31 d ... ~ IJ~·-1'-ymen\ t - - + R fi ! S 1 Sl d l w a l k I S1 3 , 0 0 0 . 0 0 0 S2 , 0 0 0 , 0 0 0 1137 Sidewalk .... ~. 05 1 1 3 1 1 9 08 1 3 0 1 2 0 04 1 1 0 1 2 0 41 5 d I ""' + [= . No r t h No r t h 05 1 1 3 1 1 9 07 / 3 1 / 1 9 04 1 1 0 1 2 0 80 d t + r .. ~ (C o m p l e t e ) T r 1-+ + + + + D o t (C o m p l e t e ) + + + + + ~· ~ . . . . . . . . . . . . ~( C o m p l e t e ) + + + + + Co n a t r u c t i o n - Bi s c a y n e Po i n t e & 05 1 1 3 1 1 9 07 / 1 9 1 1 9 08 1 0 6 / 1 9 BB d ... . " " ' . Bisc ~yne I , Normand) Shoras No r m a n d y Sh o r e s I 1-1-+ I i !P a y m e n t 07 1 2 0 1 1 9 07 / 3 1 / 1 9 08 1 1 1 / 1 9 12 d " I •~;· I Payrna')l ----:1 - h ~ -, -N o r m • + + + + + Co n s t r u c t i o n - No r m a n d y Is l e - 07 / 0 1 / 1 9 07 / 1 2 / 1 9 04 1 0 1 / 2 0 12 d ~dy ~l Complete Co m pl a t a I 1 ~~~·· IP. 1-1-+ Cl o s e - o u t / F i n a l Pa y m e n t 07 / 1 3 1 1 9 07 / 2 1 / 1 9 04 1 1 0 1 2 0 5, 3 8 8 SF h u - n co m p l a l o d . 9d ~ i ,_, ~pnf ll'.nmnl,.f..\ (C o m p l e t e ) + + ~ ~ ... E Yd 05 1 1 3 1 1 9 07 / 1 6 1 1 9 02 1 0 7 / 2 0 65 d f t t + + ~ ~ ... , -~ - " ' .. . . ~ (C o m p l e t e ) " t t t + + ~ ~ ... "~ "~ • " ' (C o m p l e t e ) 1-1-+ ... . .. ., (C o m p l e t e ) 1-1-+ -N a u t i l u s - (C o m p l e t e ) 05 1 1 3 1 1 9 07 / 1 6 1 1 9 05 1 2 3 1 1 9 65 d ~"" ' ' " " "'"·Naut '". (Co (n plete) 1-1-+ . (C o m p l e t e ) 08 1 2 0 1 1 9 08 1 3 0 1 1 9 02 1 0 7 / 2 0 11 , 8 9 5 SF h u - n co m p l e t l l d . 11 d • , - . , • • • . D o I (Complete) ~ - ... . . . + + + E So u t h 05 1 1 3 1 1 9 08 1 3 0 1 2 0 02 / 1 9 / 2 0 41 5 d South + + + + ··~ · .. ~ (C o m p l e t e ) + + 1- 1-+ 1-+ ~ + + + D o t (C o m p l e t e ) t t + ~ ~ ... ~- ~ .. "'" " ' " " ~ ( C o m p l e t e ) t t ~ ~ ... I (C o m p l a t a ) 05 1 1 3 1 1 9 07 / 1 6 1 1 9 11 / 0 1 / 1 9 65 d - ' - ,. . , " " ' 1( C o m ~late) L __ t ~ ~ ... 01 1 0 5 1 2 0 05 1 2 9 1 2 0 05 1 2 9 / 2 0 I 37 , 1 1 7 SF h u - n co m p l e t l l d . 14 B d l l l'.n..n. .mnn I .. L ~ ... I i !P a y m e n t 07 1 1 7 1 1 9 08 1 1 4 1 1 9 02 / 1 9 / 2 0 29 d c . ,. , , .~ .. ·~nt I I Pa y m a n t 05 1 3 0 1 2 0 08 1 3 0 1 2 0 08 1 3 0 1 2 0 32 d I I I I .. ,.,, r. .• ~,. I p;;;;;;; r T 1 - TC E D TCED 8 11 1 1 1 l l e d ! C c n $4 , 6 0 0 , 0 0 0 $3 , 8 0 0 , 0 0 0 03 1 0 1 / 1 9 09 1 3 0 1 1 9 07 / 3 1 / 1 9 21 4 d 1119uw .. _,..,Tech Fare l I •> J (C o m p l e t e ) 03 1 0 1 / 1 9 05 1 0 5 / 1 9 05 1 0 5 1 1 9 66 d ,. . ~ .. . . . . 1 .. ~( po mpl ~ ) I + -· ~ · - .. t (C o m p l e t e ) -t t ~. (q omplet. ~·· · · ~ · · '( C o m p l a t a ) 05 1 2 8 / 1 9 09 1 3 0 1 1 9 09 1 3 0 1 1 9 10 0 1 h WA L L . C A S ' l "" " " " r t on 10 1 1 2 . 12 B d I 1 - ~. ; , - - · l l f t i i U n 03 1 0 1 / 1 9 02 1 0 4 / 2 0 34 1 d IIVI"' R 1M 2 Na u l l w Tn 1 1 1 1 c CU n l ~ f, 2 , 0 0 0 , 0 0 0 S5 0 0 , 0 0 0 03 1 0 1 1 1 9 02 1 0 4 1 2 0 01 / 0 3 1 2 0 34 1 d 1142 ~autllua 'raffle cf lmlng .. . ~ .. ~ (C o m p l e t e ) 03 1 0 1 1 1 9 06 1 1 3 1 1 9 08 1 1 3 1 1 9 10 5 d ~ .. ~ <9o mplet ~) ~ ~ - 06 1 1 4 1 1 9 08 1 2 2 1 1 9 07 1 1 2 / 1 9 70 d ,,,.._, ...... C , - - -'-"-----t + - Co n s l r \ J c t i o n 09 1 1 2 / 1 9 01 / 1 4 1 2 0 12 / 1 3 1 1 9 Th e " " " " " li m f t oi g n in o l a l l a l i o n an d lh e 9 " ' " " bi k e la n e wa s 12 5 d _.__, co m p l e b i d on 10 / 1 8 . Th e sp e e d ta b l e co n s l r u d l o n wi l l be g i n 10 1 3 1 '-~f J an d lh e tr a f l l c cl n : l e co n o t r u d l o n wi l l be g i n 11 1 4 . - + t f I Pa y m a n t 01 / 1 5 1 2 0 02 1 0 4 1 2 0 01 / 0 3 1 2 0 21 d I I i I Paymtnt = Preplanning • =Design/Permitting = Procurement = Construction =Close Out/Final Payment =Completed SOCIAL 1 EXHIBIT D BLOG 2 NEWS 3 NEW WEBSITE FEATURES 3 MEETINGS 4 Upcoming: