Loading...
LTC 624-2019 Cherokee Avenue Seawall Update - Construction SchedI\ A A/:\1\ I City of Miami Beach. 1700 Convention Center Drive , Miami Beach , Florida 33139 . www.miamibeachfl.gov ~ • \ ~ I ~ • L> • Jimmy L. Morales. City Manager 1 ' Tel : 305-673-7010 , Fax : 305-673-7782 ' 624-2019 NO . LTC# LEITER TO COMMISSION TO : FROM: Jimmy L. Morales, City Manager DATE: November 26, 2019 SUBJECT : Cherokee Avenue Seawall Update Construction Scheduled The purpose of this Letter to Commission is to announce that, thanks to assistance from Miami- Dade County, the U.S. Army Corps of Engineers has issued approval to begin sealing the Cherokee Avenue seawall. Construction of this work is scheduled to begin on Monday, December 2 following a pre-construction meeting with the contractor, the permitting agencies, and City staff. Background In 2011, the City completed a citywide seawall condition assessment. Based on the results of the assessment, the seawall at the Cherokee Avenue street-end was deemed to be in poor condition. Therefore, in spring 2017, the city rehabilitated the seawall as a stand-alone reconstruction project and permitted the work through Miami-Dade County ("the County"), the South Florida Water Management District ("SFWMD"), and the U.S. Army Corps of Engineers ("the Corps "). During construction, the former City Engineer directed the seawall contractor, Shoreline Foundation Inc., to build knock-out plugs in the panels . The plugs were intended to minimize future damage to the new seawall during the construction of planned drainage improvements scheduled to begin in July 2017 in the La Gorce and Lakeview neighborhoods. However, these improvements were halted to allow the City an opportunity to assess its approach. The knock-out plugs were built out of wood with the understanding that they would only be in place for a few months . However, since the neighborhood improvement projects did not move forward, the plugs were left in place for much longer than anticipated. On March 12, 2019, residents in the Lakeview neighborhood brought to the City 's attention that material appeared to be seeping out of the seawall and causing turbidity with wave action. Upon inspection, Public Works staff identified that the wooden plugs had deteriorated and were allowing sediment from the landward side of the seawall to enter the waterway. Temporary Fix (March-April 2019) As soon as the issue was identified, Public Works .staff immediately stabilized the area from the landward side of the seawall using metal plates and rock bags to stop any further discharges. On March 22, 2019, City staff met with County staff to review the on-site conditions and develop a plan of action. From March 29 through April 11, 2019, the City carefully removed the sediment that entered the waterway using shovels and a vacuum truck with oversight from the County. Upon completion of the temporary fix, the permitting agencies asked the City to submit a plan for a permanent fix. Cherokee Seawall November 25, 2019 Page 2 of 2 Permanent Fix (April-December 2019) On April 26, 2019, the City submitted a plan for sealing the openings at the Cherokee Avenue seawall. The scope of work consists of installing steel plates on the landward side of the seawall and placing bricks finished with a layer of hydraulic cement on the waterside. Based on the nature of these activities, the City was required to permit this work again through the County, SFWMD, and the Corps. The County approved the plan and issued authorization to conduct the work under the previous Cherokee Avenue seawall project permit on May 1, 2019. Similarly, SFWMD issued their authorization to conduct the work under their previously issued permit for the project on May 7, 2019 . Federal authorization for the seawall project was initially issued by the County under a delegated authority from the Corps. However, the County rescinded that authorization since the plugs were not a part of the permitted plans, meaning the City had to apply for and obtain a new permit from the Corps before it could begin the work . While the City submitted a new permit application on May 31, 2019, the Corps did not assign a project reviewer until August and had not completed their review as of October 24. As such , the City requested assistance from the County. After weeks of negotiations with the Corps, the County was able to obtain approval from the Corps to reinstate the federal authorization for the project on November 5, 2019. Now that the necessary permitting approvals have been issued , the City can begin constructing the permanent fix at the Cherokee Avenue seawall. Work is scheduled to begin on Monday , December 2 and is expected to be completed in two weeks . A pre-construction meeting has been scheduled on-site with the contractor, the permitting agencies, and staff from the Public Works and Environment and Sustainability Departments to review the approved scope of work and required best management practices, ensuring that all parties are aware of and strictly adhere to the permitting requirements . Should you have any questions, please contact Roy Coley, Public Works Director, at 305-673- 7080 or Elizabeth Wheaton , Environment and Sustainability Director, at 305-673-7010 . ~/ET £~KW