LTC 637-2019 CIP Monthly Construction Projects Update M ! AMBEACH OFFICE OF THE CITY MANAGER NO. LTC# 637-2019 LETTER TO COMMISSION TO: Mayor Dan Gelber and Members of he City Co 'mission FROM: Jimmy L. Morales, City Manager � DATE: December 6, 2019 SUBJECT: CIP Monthly Construction Project Update Below please find the monthly update for active City of Miami Beach construction projects under the purview of the Office of Capital Improvement Projects (CIP). Carl Fisher Clubhouse Restoration Scope: Historical restoration of the Carl Fisher Clubhouse (interior and exterior) and adjacent site and landscaping work. This project is part of the Convention Center Renovation Project. Status: The contractor continues with the installation of finishes, tile and paint at the Annex Building. The interior of the annex building is approximately 80% complete. The Clubhouse interior is approximately 50% complete, due to delays caused by unforeseen conditions. The contractor continues to install the windows and has advanced the rough- in work. The site grading and concrete sidewalk installation is approximately 75% complete. Anticipated Completion: December 2019 Central Bayshore South Neighborhood Improvements Scope: Neighborhood improvements bounded by 34 Street to the north, Pine Tree Drive to the east, 28 Street to the south, Prairie Ave to the West Ave and Meridian Ave from 28 Street to Dade Blvd. Status: Project is on hold waiting for Commission directive, based on Jacobs Engineering's review of the City's stormwater criteria, prioritization and sequencing of projects. Anticipated Completion: TBD Collins Park Parking Garage Scope: Demolition of existing structure and construction of a new parking facility which consists of a seven (7) level parking garage with 513 parking spaces and approximately 15,000 SF of retail spaces at the ground level. Liberty Avenue will be closed and used for vehicular ingress and egress from 23 Street to the Collins Park Garage. The balance of the roadway (to 22 Street) is planned as a pedestrian plaza with associated amenities. Status: The installation of precast structures is 100% complete and utilities installation is ongoing. Work on Liberty Avenue continues and remains closed to vehicular and pedestrian access. The installation of the FPL duct bank on Liberty Avenue to serve the building and installation of the water main on Park Avenue are ongoing, with 23 Street utilities work starting once this section is completed. A temporary pedestrian walkway on the east side of Liberty between 22nd and 23rd Street will be installed for the Art Basel and Holiday events. Anticipated Completion: May 2020 1 Pride Park Scope: A new 5.8-acre park, replacing the existing surface parking lot located across the street from the newly renovated Convention Center. The park will include open lawn spaces, shade areas, walkways, lighting, a veteran's plaza, a public restroom facility, and a flexible area space. Status: Park is currently 95% complete. All site electrical, concrete walkways and sod installation has been completed. Trees installation will resume after December 9th, 2019. All work is suspended during the week of Art Basel. Anticipated Completion: December 2019 Flamingo Park Handball Courts Scope: Renovation of existing handball courts to include various electrical upgrades, new general lighting, stucco repairs, court resurfacing, new frameless windows and doors and new fencing and painting. The courts will also include seating areas and water drinking fountains for players and visitors. As a result of community input and requests, the project was split into two phases, in order to provide uninterrupted usage of the courts. Status: The project's consultant has met with various contractors and specialty material manufacturers to determine the most effective resolution to the stucco failures. The consultant is currently completing their comparative analysis and preparing their recommendation. Staff expects to have a recommendation on the best path forward by the end of December. Anticipated Completion: May/June 2020 (Contingent on resolution of stucco remediation) Flamingo Parkwide Improvements - Phase I Scope: Park wide renovations to include landscape, irrigation & drainage improvements, as well as addition and renovation of walkways and pedestrian lighting. Status: Construction is 99% complete. Contractor working to complete Building Department inspections. Anticipated Completion: December 2019 Middle Beach Recreational Corridor— Phase 3 (GOB Project) Scope: Replace the current wooden boardwalk structure that exists between 24th Street and 45th Street with an on-grade pedestrian pathway that connects Mid Beach with South Beach and North Beach Beachwalk portions - providing one seamless oceanside pathway that stretches from 1st Street to 87th Street. Status: Construction started on 11/18/2019. The construction sequencing will start on the South end and move North. Demolition of the existing boardwalk is scheduled between December 2019 and March 2020. Anticipated Completion: February 2021 North Shore Bandshell Canopy Scope: Design, manufacture and install a custom canopy at the North Beach Band Shell facility. The area of coverage for the canopy is approximately 4,000 square feet. Status: The first phase of the project, which includes the installation of the foundations, drainage piping and electrical conduits associated with the canopy has been completed. The concrete slab within the Bandshell and the landscaping outside have been restored. 2 Work has been paused to accommodate scheduled activities within the Bandshell and will resume on January 7, 2020 with the installation of the canopy and the completion of the electrical and plumbing (drainage)work. Anticipated Completion: February 2020 Palm & Hibiscus Island Neighborhood Improvements Scope: Neighborhood improvements on Palm and Hibiscus Islands. Status: The overall project scope of work, including the addition of generators, is 95% complete. The design-builder continues to progress on the design of the private property drainage inlets, for those properties which qualify under the City's new drainage policy. Meetings are being held with property owners to discuss the new inlets. The closeout package for Hibiscus Island was submitted to DERM on November 29, 2019. Permit modifications and the private property drainage connection packages are being executed by property owners for submittal to DERM for review. Contractor has delivered three emergency back-up generators of which two have been installed. Anticipated Completion: Spring 2020 Palm & Hibiscus Island Landscaping (GOB Project) Scope: Beautify the islands with new landscaping installed along Palm Avenue, Fountain Street and neighborhood medians. Status: Notice to Proceed to start construction was issued on 11/4/2019. Landscape contractor has commenced demolition and has requested identification of underground utilities. Anticipated Completion: February 2020 Stormwater Pump Station at 19th Street Scope: Installation of a stormwater pump station, including an emergency generator and seawall reconstruction along Collins Canal. Expansion of the Botanical Gardens to Collins Canal. New seawall at the Carl Fisher Clubhouse. Status: 19111 Street Pump Station: Substantial Completion achieved on the Pump Station. Botanical Garden Component Contractor has mobilized onsite; drainage structures have been delivered; clearing and grubbing work is ongoing. Anticipated completion: February 2020 Carl Fisher Sea Wall: DERM and SFWMD permit issued. Project continues to await USACE permit approval. Anticipated completion four months from permit issuance. Anticipated completion: TBD 3 Sunset Island 1 & 2 — Guardhouse Scope: Renovation of the interior and exterior of the existing guardhouse and the construction of a new guardhouse kiosk in the center of the entrance road on W. 29 Street. Status: The new guardhouse kiosk structure is over 60% complete. The traffic lanes have been reconstructed with decorative pavers and are open to vehicular traffic. The landscape related to the exit and entrance lanes including installation of the decorative pavers is complete. Anticipated Completion: February 2020 Surface Parking Lot P2 — Nikki Beach (Penrods) Scope: Reconstruction of the parking lot that includes landscaping, turtle friendly lighting, improvements to storm water drainage, irrigation, paving and signage, and infrastructure for future electric car charging stations. Status: The underground drainage systems have been inspected and received approval from the Public Works Department. Contractor is requesting final inspections for the remaining components. Anticipated Completion: December 2019 Venetian Islands Neighborhood Improvements Scope: Neighborhood improvements on San Marino, Dilido and Rivo Alto Islands. Status: All pumps are now operational. Final restoration to the North Rivo Alto Pump Station easement has commenced and is expected to be completed in December. Staff is currently reviewing the recommended draft design for the roadway, submitted by the consultant that includes an improved service life based on the new test results obtained by the geotechnical engineer. Anticipated Completion: TBD Venetian Islands Seawalls Scope: This project entails seawall replacement, at two (2) locations consisting of precast concrete bulkhead panels, king piles, batter piles and concrete cap; and seawall cap raising at five (5) locations consisting in new concrete cap, batter piles and retaining walls, at all locations within the Venetian Islands. Status: The Building Department permit comments have been addressed. Building permit is pending approval of the DERM permit modification. The Contractor is waiting on permit approval in order to submit final schedule. Staff will reconcile any scope changes resulting from design revisions with the contract requirements prior to issuing Notice To Proceed. Anticipated Completion: TBD West Avenue Phase II Improvements - North of 14th Street Scope: Neighborhood Right of Way improvements north of l4th Street to Lincoln Lane. Status: Design of the watermain and sanitary sewer systems is complete. Roadway and landscaping plans are 90% complete. Pump Station design is 90% complete, was presented to the stakeholders, and the team is currently assessing the feedback received. Harmonization meetings with properties owners commenced and are ongoing. The team 4 is also hosting open house sessions for the community every Friday, from 10:00 am to 12:00 pm, to answer any questions about the project. Due to design modifications on the pump system and the DERM permitting process the construction start date has been pushed to Spring 2020. Anticipated Completion: March 2023 West Avenue Phase H Improvements - South of 14t`' Street Scope: Neighborhood Right of Way improvements south of 14th Street to 6th Street. Status: Design of the watermain and sanitary sewer systems is complete. Roadway and landscaping plans are 90% complete. Harmonization meetings with properties owners commenced and are ongoing. The team is also hosting open house sessions for the community every Friday, from 10:00 am to 12:00 pm, to answer any questions about the project. Due to design modifications on the pump system and the DERM permitting process the construction start date has been pushed to Spring 2020. Anticipated Completion: December 2021 Pocket Park at 20 Street Scope: A new community park located at the vacant lot at the intersection of 20th Street and North Bay Road, providing a 4,000 square feet playground with nontraditional play equipment for children ages 2-5 and 5-12, to include cornstalks, play mounds and climbing walls. Two picnic areas shall be provided. The play area is designed to be shaded with shade structures and large canopy trees. Status: The posts for the shade sails have been installed, and the wall and columns have been finished with stucco. The site drainage grading is 90% complete, and the curbs which delineate the area of the playground have been poured. The walkways have been laid out, and the concrete has been placed. Contractor has commenced the installation of the play equipment and is scheduled to commence landscaping on December 9th. Completion of the project has been delayed due to unforeseen conditions, site constraints and contractor work load. Anticipated Completion: December 2019 JLM/EC/DM 5