LTC 115-2020 CIP Monthly Construction Projects Update MIAMI BEACH OFFICE OF THE CITY MANAGER NO. LTC# 115-2020 LETTER TO COMMISSION TO: Mayor Dan Gelber and Members o the Cit Commission FROM: Jimmy L. Morales, City Manager I DATE: February 26, 2020 SUBJECT: CIP Monthly Construction Pro •cts Update Below please find the monthly update for active City of Miami Beach construction projects under the purview of the Office of Capital Improvement Projects (CIP). Altos Del Mar Park (Playground) Scope: Fabrication delivery and installation of a themed playground, including play structures, shade canopy, safety surface and perimeter fence. Status: The playground structure installation is complete and the rock base for the safety surface is being installed. The perimeter fence is in fabrication and is expected to be delivered by middle of March. Anticipated Completion: March 2020 Carl Fisher Clubhouse Restoration Scope: Historical restoration of the Carl Fisher Clubhouse (interior and exterior) and adjacent site and landscaping work. This project is part of the Convention Center Renovation Project. Status: The Annex Building interior is approximately 90% complete. The Clubhouse interior is approximately 70% complete. The seawall project has commenced, and the remaining site components have been placed on hold to allow access to the seawall contractor. Once the seawall project is complete, the site components for the Carl Fisher project can be completed. In the meantime, interior work will continue in the Clubhouse and annex buildings. Anticipated Completion: August 2020 Central Bayshore South Neighborhood Improvements Scope: Neighborhood improvements bounded by 34 Street to the north, Pine Tree Drive to the east, 28 Street to the south, Prairie Ave to the West Ave and Meridian Ave from 28 Street to Dade Blvd. Status: Project is on hold waiting for Commission directive, based on Jacobs Engineering's review of the City's stormwater criteria, prioritization and sequencing of projects. Anticipated Completion: TBD 1 Collins Park Parking Garage Scope: Demolition of existing structure and construction of a new parking facility which consists of a seven (7) level parking garage with 513 parking spaces and approximately 15,000 SF of retail spaces at the ground level. Liberty Avenue will be closed and used for vehicular ingress and egress from 23 Street to the Collins Park Garage. The balance of the roadway (to 22 Street) is planned as a pedestrian plaza with associated amenities. Status: The installation of the facade panels, elevators, FPL vault, fire sprinkler system, lighting and interior masonry walls is ongoing. The completion of the water main on Park Avenue and installation of the water main on 23 Street is scheduled to commence during the week of February 24, 2020. Liberty Avenue remains closed to vehicular access and work is ongoing. The temporary pedestrian path along Liberty Avenue remains in place. Infrastructure and hardscape on Liberty Avenue North of 23 Street is scheduled to commence in April 2020. Anticipated Completion: May 2020 Flamingo Park Handball Courts Scope: Renovation of existing handball courts to include various electrical upgrades, new general lighting, stucco repairs, court resurfacing, new frameless windows and doors and new fencing and painting. The courts will also include seating areas and water drinking fountains for players and visitors. As a result of community input and requests, the project was split into two phases, in order to provide uninterrupted usage of the courts. Status: The City's consultant has reviewed all data and made a recommendation regarding how to proceed with the remediation of the failing stucco. The Contractor has reviewed the recommendation and specifications and provided a proposal to perform the work. City staff will prepare a contingency draw or change order to proceed with the work at the Joe Rubin Building. Anticipated Completion: August/September 2020 Flamingo Parkwide Improvements - Phase I Scope: Park wide renovations to include landscape, irrigation & drainage improvements, as well as addition and renovation of walkways and pedestrian lighting. Status: Construction is substantially complete. Contractor working on punch list items. Completion: January 2020 Middle Beach Recreational Corridor— Phase 3 (GOB Project) Scope: Replace the current wooden boardwalk structure that exists between 24 Street and 45 Street with an on-grade pedestrian pathway that connects Mid Beach with South Beach and North Beach Beachwalk portions- providing one seamless oceanside pathway that stretches from 1 Street to 87 Street. 2 Status: Demolition of the existing wooden boardwalk has been completed from 24 Street North to 38 Street and continues to move North. The demolition activity remains on schedule to be completed in March. Trees have been relocated from 24 Street north to 32 Street. The removal of the invasive planting has been completed up to 38 Street. The root raking, earthwork and subgrade stabilization is in progress from 24 Street North to 32 Street. Anticipated Completion: February 2021 North Shore Bandshell Canopy Scope: Design, manufacture and install a custom canopy at the North Beach Band Shell facility. The area of coverage for the canopy is approximately 4,000 square feet. Status: Project is substantially complete. Ribbon cutting ceremony was held on February 20,2020. Anticipated Completion: February 2020 Palm & Hibiscus Island Neighborhood Improvements Scope: Neighborhood improvements on Palm and Hibiscus Islands. Status: The overall project scope of work, including the addition of generators, is 95% complete. The design-builder continues to progress on the design of the private property drainage inlets, for those properties which qualify under the City's new drainage policy. Meetings are being held with property owners to discuss the new inlets. To date two-thirds of all private drainage inlets have been resolved. The closeout package for Hibiscus Island was submitted to DERM on November 29, 2019. Permit modification and closeout package for Palm Island is being completed and will be submitted as soon as storm drain structures have been cleaned. Private property drainage connection packages for both Palm and Hibiscus Islands have been executed by property owners and submitted to DERM for review on February 10, 2020. Contractor has delivered three emergency back- up generators of which two have been installed. The Hibiscus generator location is being coordinated between FPL, HOA and the contractor for the best desirable location. Anticipated Completion: Summer 2020 Palm & Hibiscus Island Landscaping (GOB Project) Scope: Beautify the islands with new landscaping installed along Palm Avenue, Fountain Street and neighborhood medians. Status: Landscaping is in progress installation of trees is 65% and irrigation system is 40% complete. Anticipated Completion: March 2020 3 Pocket Park at 20 Street Scope: A new community park located at the vacant lot at the intersection of 20 Street and North Bay Road, providing a 4,000 square feet playground with nontraditional play equipment for children ages 2-5 and 5-12, to include cornstalks, play mounds and climbing walls. Two picnic areas shall be provided. The play area is designed to be shaded with shade structures and large canopy trees. Status: The park is substantially complete and is in use, as of January 16, 2020. Punchlist items and final inspections will be addressed over the next 30 days. Completion: March 2020 Pride Park Scope: A new 5.8-acre park, replacing the existing surface parking lot located across the street from the newly renovated Convention Center. The park will include open lawn spaces, shade areas, walkways, lighting, a veteran's plaza, a public restroom facility, and a flexible area space. Status: Park is currently 97% complete. TCO has been obtained as of January 8, 2020. Punchlist items include completion of the Veteran's Memorial Plaza, installation of the bathroom façade, electrical panel screening, precast concrete benches and trash receptacles. Anticipated Completion: March 2020 Stormwater Pump Station at 19 Street Scope: Installation of a stormwater pump station, including an emergency generator and seawall reconstruction along Collins Canal. Expansion of the Botanical Gardens to Collins Canal. New seawall at the Carl Fisher Clubhouse. Status: 19 Street Pump Station: Substantial Completion achieved on the Pump Station. Botanical Garden Component Drainage installation has been completed. Installation of electrical conduits and irrigation sleeves are on-going. Due to NFL Superbowl Experience event construction activities were paused and has delayed completion to March. Anticipated completion: March 2020 Carl Fisher Seawall: DERM, SFWMD and USACE permits issued. Construction activities began on February 3, 2020. Contractor has completed site demolition, has mobilized a three-hundred-ton crane, and has commenced the installation of piles. Anticipated completion: June 2020 4 Sunset Island 1 & 2 — Guardhouse Scope: Renovation of the interior and exterior of the existing guardhouse and the construction of a new guardhouse kiosk in the center of the entrance road on W 29 Street. Status: The project is over 60% complete. Due to some unforeseen issues such as underground utility conflicts at the new Kiosk, termite infestation at the existing guardhouse damaging the wood structure and the existing canopy, severely corroded existing bathroom piping and other issues, there have been delays to the project. These issues are currently being discussed and addressed by the City, Architect of Record and Homeowner's Association. Anticipated Completion: March 2020 Surface Parking Lot P2 — Nikki Beach (Penrods) Scope: Reconstruction of the parking lot that includes landscaping, turtle friendly lighting, improvements to storm water drainage, irrigation, paving and signage, and infrastructure for future electric car charging stations. Status: Substantial completion was achieved. The parking lot has been in use since December 16, 2019. Punch list items are being addressed. Substantial Completion: December 2019 Venetian Islands Neighborhood Improvements Scope: Neighborhood improvements on San Marino, Dilido and Rivo Alto Islands. Status: All pumps are now operational. Final restoration to the North Rivo Alto Pump Station easement is completed. Staff has reviewed the draft design for the roadway submitted by the consultant that includes, an improved design life based on the new test results obtained by the geotechnical engineer, and was bringing an item to the February Commission Meeting to address the road construction, however the Venetian Islands homeowner's association has requested additional time to allow for homeowner input and collaboration on the final recommendation. Anticipated Completion: TBD Venetian Islands Seawalls Scope: This project entails seawall replacement, at two (2) locations consisting of precast concrete bulkhead panels, king piles, batter piles and concrete cap; and seawall cap raising at five (5) locations consisting in new concrete cap, batter piles and retaining walls, at all locations within the Venetian Islands. Status: DERM permit modification has been approved. Staff is reconciling any scope changes resulting from design revisions with the contract requirements prior to issuing Notice to Proceed. Revised plans being submitted to the building department. Anticipated Completion: TBD 5 West Avenue Phase II Improvements - North of 14 Street Scope: Neighborhood Right of Way improvements north of 14 Street to Lincoln Lane. Status: Design of the watermain and sanitary sewer systems is complete. Roadway and landscaping plans are 90% complete. Pump Station design is 90% complete, was presented to the stakeholders, and the team is currently analyzing another location option for the above ground components, based on the feedback received by the stakeholders. Directive was given to the contractor to add 15 gravity wells to the design in order to meet DERM's additional Water Quality treatment requirements. Harmonization meetings with properties owners commenced and are ongoing. The team is also hosting open house sessions for the community every Friday, from 10:00 am to 12:00 pm, to answer any questions about the project. Due to design modifications on the pump system and the DERM permitting process the construction start date has been pushed to Early Summer 2020. Anticipated Completion: March 2023 West Avenue Phase II Improvements - South of 14 Street Scope: Neighborhood Right of Way improvements south of 14 Street to 6 Street. Status: Design of the watermain and sanitary sewer systems is complete. Roadway and landscaping plans are 90% complete. It is anticipated that the plans will be submitted to DERM for permitting in the next 30 days. Harmonization meetings with properties owners are ongoing. The team is also hosting open house sessions for the community every Friday, from 10:00 am to 12:00 pm, to answer any questions about the project. Due to design modifications on the pump system and the DERM permitting process the construction start date has been pushed to Spring 2020. Anticipated Completion: December 2021 JL 0.,' DM 6