Loading...
LTC 157-2020 CIP Monthly Construction Projects UpdateMI A MI BE A CH OFFICE OF THE CITY MANAGER 157-2020 NO. LTC# LETTER TO COMMISSION TO: Mayor Dan Gelber and Members of/ .he City FROM: Jimmy L. Morales, City Manager DATE: April 23, 2020 SUBJECT: CIP Monthly Construction Projects Update Below please find the monthly update for active City of Miami Beach construction projects under the purview of the Office of Capital Improvement Projects (CIP). Altos Del Mar Park (Playground} Scope: Fabrication delivery and installation of a themed playground, including play structures, shade canopy, safety surface and perimeter fence. Status: The rock base for the safety surface is complete and the perimeter fence has been installed. The installation of the safety surface has commenced and should be completed this month. Anticipated Completion: April 2020 Carl Fisher Clubhouse Restoration Scope: Historical restoration of the Carl Fisher Clubhouse (interior and exterior) and adjacent site and landscaping work. This project is part of the Convention Center Renovation Project. Status: The Annex Building interior is approximately 90% complete. The Clubhouse interior is approximately 80% complete. The seawall project has commenced, and the remaining site components have been placed on hold to allow access to the seawall contractor. Once the seawall project is complete, the site components for the Carl Fisher project can be completed. In the meantime, interior work will continue in the Clubhouse and annex buildings. Anticipated Completion: August 2020 Central Bayshore South Neighborhood Improvements Scope: Neighborhood improvements bounded by 34 Street to the north, Pine Tree Drive to the east, 28 Street to the south, Prairie Ave to the West Ave and Meridian Ave from 28 Street to Dade Blvd. Status: Project is on hold waiting for Commission directive, based on Jacobs Engineering's review of the City's stormwater criteria, prioritization and sequencing of projects. Anticipated Completion: TBD 1 C o lli n s P a r k P a r k in g G a r a g e Scope: Demolition of existing structure and construction of a new parking facility which consists of a seven (7) level parking garage with 513 parking spaces and approximately 15,000 SF of retail spaces at the ground level. Liberty Avenue will be closed and used for vehicular ingress and egress from 23 Street to the Collins Park Garage. The balance of the roadway (to 22 Street) is planned as a pedestrian plaza with associated amenities. Status: The installation of the façade panels, elevators, FPL vault, fire sprinkler system, lighting and interior masonry walls and water service laterals on Park Avenue is ongoing. The installation of water main on 23 Street has commenced. Infrastructure and hard scape on Liberty Avenue between 23 Street and 22 Street is ongoing. Other utility (TECO, AT&T, Hotwire) services for the garage are currently being coordinated. Anticipated Completion: June 2020 Flamingo Park Handball Courts Scope: Renovation of existing handball courts to include various electrical upgrades, new general lighting, stucco repairs, court resurfacing, new frameless windows and doors and new fencing and painting. The courts will also include seating areas and water drinking fountains for players and visitors. As a result of community input and requests, the project was split into two phases, in order to provide uninterrupted usage of the courts. Status: A Change Order was approved by City Commission on April 22, 2020, for additional construction services associated with the phasing of construction and the remediation of deficient stucco. It is anticipated to re-start construction by end of April to complete the Joe Rubin building. Anticipated Completion: August /September 2020 Indian Creek - Street Drainage Phase Ill Scope: Storm water drainage improvements on Indian Creek Drive and side streets from 25 to 41 Street, including completing the stormwater pump station at 32 Street. Final pavement restoration of the roadway and sidewalk on Collins Avenue between 25 and 26 Street; as well as rebuilding and raising the roadway and sidewalk on Indian Creek Drive between 26 and 41 Street, new street lighting, signage and pavement markings. Status: Contractor mobilized on site on March 8, 2020. Contractor has implemented Maintenance of Traffic (MOT) on Collins Avenue, Indian Creek Road closure, installation of temp lighting system, demolition, installation of dewatering system, harmonization, and installation of 72-inch drainage pipe. Franchise utility owners have started utility relocation. Anticipated Completion: Winter 2021 Middle Beach Recreational Corridor- Phase 3 (GOB Project) Scope: Replace the current wooden boardwalk structure that exists between 24 Street and 45 Street with an on-grade pedestrian pathway that connects Mid Beach with South Beach and North Beach Beachwalk portions - providing one seamless oceanside pathway that stretches from 1 Street to 87 Street. Status: Demolition of the existing wooden boardwalk was completed in March. Trees have 2 b e e n re lo c a te d fr o m 3 6 S tre e t n o rt h to 4 6 S tre e t. T h e re m o v a l o f th e in v a s iv e p la n tin g h a s b e e n c o m p le te d u p to 4 6 S tre e t. T h e ro o t ra k in g , e a rt h w o r k a n d s u b g ra d e s ta b iliz a tio n is in p ro g r e s s fr o m 3 6 S tre e t N o rt h to 4 6 S tre e t. U n d e rg ro u n d e le c tric a l a n d irrig a tio n m a in a c tiv itie s h a s c o m m e n c e d fr o m 3 6 S tre e t to 4 6 S tre e t. Anticipated Completion: February 2021 Palm & Hibiscus Island Neighborhood Improvements Scope: Neighborhood improvements on Palm and Hibiscus Islands. Status: The overall project scope of work, including the addition of generators, is 95% complete. The design-builder continues to progress on the design of the private property drainage inlets, for those properties which qualify under the City's new drainage policy. Meetings are being held with property owners to discuss the new inlets. To date over 90% of all private drainage inlets have been resolved. The closeout package for Hibiscus Island was submitted to DERM on November 29, 2019. Permit modification and closeout package for Palm Island is being reviewed for submittal as soon as storm drain structures have been cleaned. Private property drainage connection packages for both Palm and Hibiscus Islands have been executed by property owners and submitted to DERM on February 10, 2020. Contractor has delivered three emergency back-up generators of which two have been installed. The Hibiscus generator location is being coordinated between FPL, HOA and the contractor for the best desirable location. Anticipated Completion: Summer 2020 Palm & Hibiscus Island Landscaping (GOB Project) Scope: Beautify the islands with new landscaping installed along Palm Avenue, Fountain Street and neighborhood medians. Status: Landscaping and irrigation system installation is in progress and is approximately is 75% complete. Anticipated Completion: April 2020 Pride Park Scope: A new 5.8-acre park, replacing the existing surface parking lot located across the street from the newly renovated Convention Center. The park will include open lawn spaces, shade areas, walkways, lighting, a veteran's plaza, a public restroom facility, and a flexible area space. Status: Park is currently at 98%. Items pending include completion of Veteran's Memorial Plaza, installation of bathroom facade, electrical panel screening and precast concrete benches. An extensive punch list was issued to contractor for repairs of portions of concrete walkways, regrading and replacement of sodded areas. Anticipated Completion: May 2020 3 R u e V e n d o m e Scope: A new public plaza shall be created from the closing of Rue Vendome at the area between 71 st Street and Normandy Drive. The plaza shall extend to the area around the Normandy Fountain. New drainage, landscaping, lighting and furnishings, including oolite benches shall be provided. Status: Notice to Proceed was issued, effective on March 5, 2020. Construction has started and demolition is underway. Anticipated Completion: August 2020 Stormwater Pump Station at 19 Street Scope: Installation of a stormwater pump station, including an emergency generator and seawall reconstruction along Collins Canal. Expansion of the Botanical Gardens to Collins Canal. New seawall at the Carl Fisher Clubhouse. Status: 19 Street Pump Station: Pump station is currently operational. DERM final certification is pending. Botanical Garden Component All work completed except for the installation of ground cover landscaping. Anticipated completion: March 2020 Carl Fisher Seawall: Carl Fisher Seawall, work commenced on February 3, 2020, all piles have been installed, currently installing the last 2 panels. Forming of cap to start first week of April. Anticipated completion: June 2020 Sunset Island 1 & 2- Guardhouse Scope: Renovation of the interior and exterior of the existing guardhouse and the construction of a new guardhouse kiosk in the center of the entrance road on W 29 Street. Status: The project is 80% complete. Delays to the project have been caused by recent unforeseen issues such as underground utility conflicts, termite infestation, severely corroded bathroom piping, and water main leak within project limits. In the month of February, the existing guardhouse has been tented to eliminate the termite issue, the watermain leak has been repaired by Public Works, and the Contractor has continued to work on the project. Recent activities include newly installed landscaping, finalizing work at the new kiosk, and installing new security equipment at the project site. The City, Architect of Record, and Contractor are continuing to work on the few remaining project items. Anticipated Completion: April 2020 4 V e n e tia n Islan d s N eig h bo rho o d Im p rov e m e nts Scope: Neighborhood improvements on San Marino, Dilido and Rivo Alto Islands. Status: All Pumps Stations and easement restorations are complete. DERM is performing their final inspections. Following the homeowner's association request, additional studies and discussion are being done in a collaboration effort to the final recommendation on the roadway remediation. Anticipated Completion: TBD V e n e tia n Isla n d s S e a w a ll s Scope: This project entails seawall replacement, at two (2) locations consisting of precast concrete bulkhead panels, king piles, batter piles and concrete cap; and seawall cap raising at five (5) locations consisting in new concrete cap, batter piles and retaining walls, at all locations within the Venetian Islands. Status: Permit modification approved by DERM and SFWM, and currently under the Building Department review. Upon approval of the Building Department contractor will mobilize within 2 weeks. Stakeholders outreach ongoing. Anticipated Completion: November 2020 W e s t A v e n u e P h a s e li Im p rov e m ents - N o rt h of 14 S treet Scope: Neighborhood Right of Way improvements north of 14 Street to Lincoln Lane. Status: Design/build team submitted proposal for the design efforts to include the additional water quality components as requested by DERM. A Change Order was approved by City Commission on April 22, 2020 for additional design costs. It is anticipated to submit to DERM 90 days after approval of proposal. Staff has completed the analysis for the pump station above ground components, and an Item will be discussed at next the USC meeting regarding its location. Harmonization meetings with property owners commenced. The team is working on ways to continue these meetings in a safe way due to the COVID-19. The expected start date has now moved to Fall of 2020. Anticipated Completion: March 2023 W e s t A v e n u e P h a s e li Im p rove m ents - So u th of 14 S treet Scope: Neighborhood Right of Way improvements south of 14 Street to 6 Street. Status: Design of Water and Sewer System is 100% complete. Roadway, Landscaping, lighting, drainage and Pump Station Design is 100% complete. Design/build team submitted proposal for the design efforts to include the additional water quality components as requested by DERM. A Change Order was approved by City Commission on April 22, 2020 for additional design costs. It is anticipated to submit to DERM 90 days after approval of proposal. Harmonization meetings with properties owners commenced, we are working in ways to continue these meeting in a safe way due to the COVID-19. The expected start has moved up to now Fall of 2020 Anticipated Completion: December 2021 06 5