LTC 477-2020 G.O. Bond Program Project Implementation Update No. 12DocuSign Envelope ID: 0C1778CC-75A4-4C2C-B90C-8A7498693107
MIAMI BEACH
City of Miami Beach, 1700 Convention Center Drive, Miami Beach, Florida 33139, www.miamibeachfl.gov
OFFICE OF THE CITY MANAGER
477-2020
LTC #
LETTER TO COMMISSION
TO: Mayor Dan Gelber and Members of the City Commission
FROM:
DATE:
Raul Aguila, Interim City Manager
December 30, 2020 Œ
DocuSigned by:
Pl J. Ad-
28306240F928450...
SUBJECT: G.O. Bond Program - Project Implementation Update No. 12
The purpose of this Letter to the Commission ("LTC") is to advise you on the status of the
implementation of the 39 General Obligation Bond (G.O. Bond) Projects approved by the City
Commission for the first tranche of funding (Tranche 1) in the amount of $152,466,449 including
issuance costs. For complete meeting agendas, handouts, minutes, presentations and audio
recordings visit the website www.GOMBinfo.com and click on the Oversight Committee tab.
Refer to Exhibits A and A1 for the meeting agendas which took place with the G.O. Bond Oversight
Committee on October 22, 2020 and December 17, 2020. There was no meeting during the month
of November. The meeting calendar for the first 6 months of 2021 is attached as Exhibit A2.
IMPLEMENTATION STATUS
Project Dashboard and Program Progress Report
As of December 11, 2020, a total of 30 out of 39 Tranche 1 projects are in some form of "Active"
status and 6 projects are completed. Chart 1 below shows the full breakdown by Category.
Chart 1
PROJECT ACTIVITY
Trarche 1
39 comp""
Active
30
Per dina
3
- Future
18
PROJECT CATEGORY
Pauls Infrastructure Publ Safety All
PROJECT Complete 5 I o 6 ----, ---- STATUS Active 13 7 10 30
Pending 2 o r 3 -----~
Future 10 6 2 1s
AII 30 14 13 $7
*Note: The Skate Park project was advanced from Tranche 3 to Tranche 1 and therefore increased the current number of
Tranche 1 project to 39.
DocuSign Envelope ID: 0C1778CC-75A4-4C2C-B90C-8A7498693107
G. O. Bond Program - Project Implementation Update No. 12
December 30, 2020
Page 2 of6
Approximately $33.1 million dollars have been expended and another $24.1 million are
encumbered for a total of $57.3 million. Chart 2 below shows the full breakdown of the
expenditures broken down by Category.
Chart 2
PROJECT EXPENDITURES
" sif~;~ "ì ~\
Encumbered
s24.14i [
g. / $93.81M
/
·------/
Future
$283.98M
PROJECT CATEGORY
Parks Infrastructure Public Safety Total
PRGRAM Spent $16,545.249 $6.285.974 $10.354104 $33169.327
FUNDOS naumbe red $12,149.238 $7,428.032 $4.565.183 $24142,453
Available $8.033,469 $14.265,981 $21.,482.684 $93,807,13
Future $81,167,044 $168000,013 $34,809.029 $283,976,086
Total $167,900,000 $196,000,000 $71,215,000 $435,115,000
Tranche 1 Progress
Most of the 39 projects in Tranche 1 have different components which are considered distinct
projects or "subprojects" that are tracked separately and have separate budgets, procurement, and
implementation schedules.
The Tranche 1 Subproject Activity Summary of the Progress Report summarizes the subproject
activity into Status, Category and Funding amount. This information is distributed monthly to the
Committee and presented at every G.O. Bond Committee meeting.
Subproject Tracking Summary by Phase
The tracking summary indicates that 29 (40%) of the 73 total Tranche 1 subprojects have been
completed, 9 (12%) are under construction, 19 (26%) are in a design phase, 12 (16%) are in a
planning phase, and 4 (5%) are pending to become active. Chart 3 shows the status of all
subprojects broken down by Phase and Category.
DocuSign Envelope ID: 0C1778CC-75A4-4C2C-B90C-8A 7498693107
G. O. Bond Program - Project Implementation Update No. 12
December 30, 2020
Page 3 of 6
Chart 3
TRANCHE1
SUBPROJECT ACTIVITY
Tranche I
100%
SUBPROJECT CATEGORY
Pauks Infrastructure Public Safety AII
SUBPROJECT Complete 20 8 29
STATUS - Construction 2 4 3 9
Design 6 6 19
Planning 4 7 I 12
Pending 3 o ! 4 - -
Alt 35 13 25 I 73
The expenditures summary indicates that the 29 completed subprojects equate to $16.9 million of
the budget (11%), $30.2 million (20%) equate to subprojects under construction, $55.7 million
(37%) equate to subprojects that are in the design phase, $26.3 million (17%) equate to
sub projects that are in the planning phase, and a total equating to $22 million ( 15%) are for
subprojects which are pending to become active. The total funding expenditures for each of the
sub-project categories is indicated on Chart 4 below. For a full breakdown, by project, refer to
Exhibit B.
Chart 4
SUBPROJECT EXPENDITURES
Tranche 1
100%
SUBPROJECT CATEGORY
Parks Infrastructure Public Safety Total
SUBPROJECT Complete $13.709.989 1.000.000 $2.200.997 $16,910,986
FUNDS Construction $4.710.000 $14239,499 $11.215.000 $30,164,499
Design $31,981.997 $11,260,495 $12,485.177 $55,727.669
Planning $16.986.999 $1,414.823 $7889.996 $26,291,818
Pending $19.344.000 $0 $2700.000 $22,044,000
Total $86,732,985 $27.914,817 $36,491,170 $151,138.972
DocuSign Envelope ID: 0C1778CC-75A4-4C2C-B90C-8A7498693107
G. O. Bond Program - Project Implementation Update No. 12
December 30, 2020
Page 4 of 6
Project Savings
Also presented at the December meeting was a projection of the total amount of savings which will
be realized over the next 30-day period on projects which have been completed. A total of $3.2
million will be saved in total for 29 completed subprojects with total budgets of $16.9 million. This
depicts a current savings of approximately 19% of the budget so far. A total of $2.2 million have
been saved in the Parks category and $1.1 million have been saved in the Public Safety category.
For a full breakdown of all savings by project, refer to Exhibit B1 attached.
Also presented every month is the Program General Status chart which compares the status of
projects from the previous months to the current month. Chart 5 below indicates the monthly
variances of all subprojects and goes back to October 2019.
Chart 5
SUMMARY SUB-PROJECTS
10/17/19 1/23/20 4/16/20 7/16/20 9/24/20 10/22/20 12/17/20 VARIANCE
No. % No. % No. % No. % No. % No. % No. % %
ACTIVE/COMPLETE 44 40% 56 49% 62 54% 66 57% 66 57% 68 59% 69 59% 1%
CONSTRUCTION 16 15% 13 11% l4 12% 8 7% 9 8% 8 7% 9 8% 1%
PLANNING / DESIGN 23 21% 26 23% 28 25% 30 26% 29 25% 31 27% 31 27% 0%
CLOSED / COMPLETE 5 5% 17 15% 20 18% 28 24% 28 24% 29 25% 29 25% 0%
REMAINING 65 60% 59 51% 52 46% 49 43% 49 43% 48 41% 47 41% -1%
TOTAL SUB-
PROJECTS 109 115 114 115 115 116 • 116
Notes:
ma0 - 41st Street Lighting Upgrade Subproject Added
"Quick Wins"
A total of 37 subprojects are being tracked as part of the original 21 quick win projects listed below.
Of those, 34 are Completed and/or Closed out. A total of 3 public safety projects are remaining
and are targeted for completion between January and February 2021. The Middle Beach
Beachwalk will be completed in mid-2021. All Quick Win projects remain on or below budget. For
the Current status update of the 3 remaining Quick Win Public Safety projects, refer to Exhibit C
attached.
Future Revision to Implementation Plan
At the December 17 meeting, the Committee was advised that staff is analyzing cash flow
projections and looking for opportunities to advance some projects currently planned for later
tranches. The reasoning behind this is to increase expenditures to make up for projects which are
not advancing at the rate originally planned. Staff is also holistically looking at the original
implementation plan to evaluate opportunities to decrease the number of tranches given the lower
than originally anticipated costs of borrowing due to historically low interest rates. The proposed
revised plan will be brought to the Committee in either January or February for support and
recommendation before being presented to the City Commission.
41° Street Corridor Presentation
After a series of community engagements and studies of the business district, city consultants
AECOM have produced a conceptual streetscape design for project GO#40: 41 Street Corridor.
This was presented at the November 6" Neighborhoods and Quality of Life Committee (NQLC),
and it will be presented to the full City Commission at the January 13, 2021 Commission meeting.
At both, the October 22° and December 17 G.0. Bond Oversight Committee meetings, AECOM
presented the conceptual plan options, as well as results of responses to the community survey
conducted on October 1, 2020, and the proposed final "hybrid" design.
DocuSign Envelope ID: 0C1778CC-75A4-4C2C-B90C-8A7498693107
G. O. Bond Program - Project Implementation Update No. 12
December 30, 2020
Page 5 of 6
At the December 17 meeting, the G.O. Bond Committee made a motion to support the conceptual
design, as presented. The presentation and video flyover can be viewed at the following link:
https:l/www.miamibeachfl.qov/residents/neiqhborhood-associationslneiqhborhood-affairs-divisionlactive-
projects/other/41-street-revitalization/
Main and Other Tranche 1 Projects
The following Tranche 1 project updates were discussed at the October 22 and December 17
meetings. Refer to Exhibit D for further details and information for each of the following:
• #01- 72° Street Community Complex
• #04 - Fairway Park Fence
• #12 - North Beach Oceanside Beachwalk
• #15-PAR 3 / Bayshore Park
• #24 - Middle Beach Beachwalk
• #33 - Street Tree Master Plan
• #37 & #38 - Streets and Sidewalks Repaving and Restoration
• #39 - Seawalls & Living Shorelines
• #42 - Nautilus Traffic Calming
• #45 - Fire Station #1
• #53 - Bollards (Convention Center, Soundscape, and South Point Park)
New Design Review Board Ordinance
At the October 22 meeting the Administration advised the Committee of the adoption of Ordinance
No. 2020-4353 which requires the City to obtain an advisory recommendation of the Design Review
Board (ORB) for certain city projects which did not previously require formal ORB approval. Projects
such as new street lighting, new roadway and streetscape projects, medians, traffic circles, etc.
The purpose of the ordinance is to enhance the aesthetics of the city's public infrastructure projects
and allow residents to be advised of projects that are in their general area. The new process would
add approximately 60 days to the timelines of applicable projects when you consider noticing
requirements and public outreach.
COMMUNITY INFORMATION AND OUTREACH
On October 20, the Miami Beach Chamber of Commerce held a virtual Construction and
Development Council meeting where Maria Hernandez and Allison Novack were the guest
speakers. The presentation included a program overview, a Tranche 1 update, a discussion about
citywide impact, and a call to action to the local business community to participate in program
activities.
In coordination with the Economic Development Department, the G.O. Bond Program Team has
also been focused on engaging business and property owners of the 41 Street business district, to
inform and educate them on project GO#40: 41 Street Corridor. Letters have been post-mailed and
emailed to every property listed in the area with links to view the proposed AECOM conceptual
streetscape design, and with information on how to submit suggestions and/or join discussions on
the project.
The Program Team continues to work with its G.O. Bond Oversight Committee members, city
departments, and community partners to inform and educate the public. Please see the attached
Exhibit E to view recent outreach materials. The website www.GOMBlnfo.com is where all
construction advisories and blog articles are posted.
For more information, please contact Maria Hernandez at mariahernandez@miamibeachfl.gov or
via cellphone at (786) 371-3168.
DocuSign Envelope ID: 0C1778CC-75A4-4C2C-B90C-8A7498693107
G. O. Bond Program - Project Implementation Update No. 12
December 30, 2020
Page 6 of6
Attachments:
Exhibit A-- GOB Oversight Committee Agenda for October 22, 2020
Exhibit A1- GOB Oversight Committee Agenda for December 17, 2020
Exhibit A2- 2021 GOB Oversight Committee Meeting Calendar
Exhibit B - Subproject and Project List by Phase 12-11-20
Exhibit B1- Savings Breakdown by Project and Category
Exhibit C- Quick Wins Dashboard Sheets
Exhibit D - Tranche 1 Main and Other Projects - Dashboard Sheets
Exhibit E -- Community Outreach Report
RA/MH
F:\cmgr\$ALLIGO Bond Program\Commission\LTCs\202017 October & December 2020\LTC - December 2020 GO Bond Program Implementation Update
No. 12.docx
DocuSign Envelope ID: 0C1778CC-75A EXHIBIT A
YOUR VOICE, IN ACTION!
General Obligation Bond Oversight Committee
City of Miami Beach
Karen Rivo, Chair
Maria Hernandez, Liaison
I.
II.
Roll Call and Introductions
AGENDA - VIRTUAL MEETING
October 22, 2020
All
Committee Business Karen Rivo
4:30pm
4:35pm
• Adoption of Meeting Minutes from 9-24-20
• No Meeting in November- Next Meeting 12-17-20
Ill. Community Outreach Allison Novack 4:40pm
IV. Public Comment Public 4:45pm
V. New Design Review Board Ordinance Nick Kallergis 4:50pm
VI. 41 st Street Corridor Update Presentation AECOM 5:00pm
VII. Major Tranche 1 Projects Update CIP-D. Martinez 5:35pm
• F.S. #1, 72n8 St. Complex, Bayshore Park,
Ped. Bridge, Middle Beach Beachwalk,
North Beach Oceanside Park Beachwalk
VIII. Other Projects Update PWD / Environmental 5:55pm
• Street Tree Master Plan, 41st Street
Lighting Upgrade, Seawalls
IX. Program General Status & Maria Hernandez 6:05pm
Sub-Projects Update, Closed Projects
X. Quick Wins Remaining Police 6:15pm
XI. Public Comment Public 6:25pm
XII. Adjournment 6:30pm
Committee Charge
The purpose of the General Obligation Bond Oversight Committee is to make advisory recommendations to the City Manager and City
Commission from a macro perspective regarding the timely progress, overall goals, costs, including financial efficiencies, and the timely
completion of General Obligation Bond Program projects approved by the voters in the City of Miami Beach Special Election held on
November 6, 2018. The Committee shall have the following powers & duties:
1. Receive input from the public, the City Administration, City consultants, and the City's Inspector General, as needed, to make
recommendations relative to the overall timing, cost efficiencies, and prioritization of the G.O. Bond Program projects.
2. Provide general oversight to ensure that G.O. Bond Program project timelines, budgets (including cost efficiencies) are prioritized and
achieved, and that the projects are completed in accordance with the scope of work approved by the voters.
3. Review City staff and G.O. Bond Program project managers' progress reports and provide monthly reports to the City
Commission.
-' 's)< p] ' XHIBIT A1 0
YOUR VOICE, IN ACTION!
General Obligation Bond Oversight Committee
City of Miami Beach
Karen Rivo, Chair
Maria Hernandez, Liaison
I. Roll Call and Introductions
II. Committee Business
• Adoption of Meeting Minutes from 10-22-20
• 2021 Meeting Calendar Approval
• GO Bond Committee Reappointments
Ill. Public Comment
IV.
AGENDA-VIRTUAL MEETING
December 17, 2020
All
Program General Status, &
Sub-Projects Update, Closed Projects
• Future Revision to Implementation Plan
V. 41 st Street Corridor Final Presentation:
Karen Rivo
Public
Maria Hernandez/
John Woodruff
4:30pm
435pm
4:40pm
4:50pm
AECOM 5:00pm
https://wwwy_miamibeachfl.gov/residents/neighborhood_ associations/neighborhood-_affairs-_diyision/active- projects/other/41-_street- revitalization]
VI. Major Tranche 1 Projects Update
• F.S. #1,72n8 St. Complex, Bayshore Park,
Middle Beach Beachwalk, NBOC Beachwalk
VII. Other Projects Update
• Streets & Sidewalks, Bollards, Nautilus Traffic
Calming, Street Tree Master Plan,
Fairway Park Fence, Palm & Hibiscus
VIII.
IX.
Quick Wins Remaining
• Lummus Cameras, Beachwalk Cameras,
Public Safety Radio System
Public Comment
Adjournment
CIP-D. Martinez
PWD / T & T /ENV/
Parks/ CIP
5:30pm
5:50pm
Police / Fire 6:10pm
Public
X.
6:20pm
6:30pm
Committee Charge
The purpose of the General Obligation Bond Oversight Committee is to make advisory recommendations to the City Manager and City
Commission from a macro perspective regarding the timely progress, overall goals, costs, including financial efficiencies, and the timely
completion of General Obligation Bond Program projects approved by the voters in the City of Miami Beach Special Election held on
November 6, 2018. The Committee shall have the following powers & duties:
l. Receive input from the public, the City Administration, City consultants, and the City's Inspector General, as needed, to make
recommendations relative to the overall timing, cost efficiencies, and prioritization of the G.O. Bond Program projects.
2. Provide general oversight to ensure that G.O. Bond Program project timelines, budgets (including cost efficiencies) are prioritized and
achieved, and that the projects are completed in accordance with the scope of work approved by the voters.
3. Review City staff and G.O. Bond Program project managers' progress reports and provide monthly reports to the City
Commission.
- • - • I 0
YOUR VOICE, IN ACTION!
General Obligation Bond Oversight Committee
Meeting Calendar 2021
MEETING LOCATION:
VIRTUAL ZOOM MEETINGS UNTIL FURTHER NOTICE
Thursday, January 21, 2021 - 4:30pm
Thursday, February 18, 2021 - 4:30pm
Thursday, March 25, 2021 - 4:30pm
Thursday, April 29, 2021 - 4:30pm
Thursday, May 20, 2021 - 4:30pm
Thursday, June 17, 2021 - 4:30pm
))y l- r
' ·à
) j
. . J L
l'
DocuSign Envelope ID: 0C1778CC-75A4-4C20-B90C-8A7498693107 EXHIBIT B
G.O. BOND PROJECT LIST BY PHASE
Active Phase Project Name Category Department Quick Win Tranche Anticipated End Date T Count % Count $Budget $Encumbered $Spent % Spent $ Available
Closed #53 PORTABLE BOLLARDS Public Safety Police QW I 07-31-2019 600,000 599,915 84
Closed #17 POLO PARK Parks Parks & Recreation Qw I 08-11-2019 499,998 493,673 6,325
Closed #19 S0UNDSCAPE 4K TECHNOLOGY Parks Tourism & Culture 0w I 09-30-2019 3,799,999 3,748,495 51,503
Closed #13 NORTH SHORE LIGHTS & PAINT Parks Property Management Qw I 10-14-2019 130,300 130,210 89
Closed #52 TATUM PARK LED LIGHTING Public Safety Parks & Recreation Qw 1 10-14-2019 151,999 52,758 99,240
Closed #52 CRESPI PARK LED LIGHTING Public Safety Parks & Recreation Qw 1 10-21-2019 86,999 41,780 45,218
Closed #52 STILLWATER PARK LED LIGHTING Public Safety Parks & Recreation Qw 1 10-21-2019 86,999 41,780 45,218
Closed M26 COLONY THEATRE ROOF Parks Property Management aw 1 10-24-2019 300,000 299,650 350
Closed #21 STILLWATER PARK Parks Parks & Recreation 0w 1 11-08-2019 144,999 142,440 2,559
Closed #3 CRESPI PARK Parks Parks & Recreation 0w 1 11-09-2019 210,998 184,919 26,079
Closed #18 SCOTT RAKOW PAINT Parks Property Management 0w I 11-12-2019 130,000 116,776 13,224
Closed #47 MACARTHUR CSWY READERS Public Safety Police 0w 1 11-28-2019 120,000 64,904 55,095
Closed #52 NORMANDY ISLE PARK LED LIGHTING Public Safety Parks & Recreation 0w 1 12-02-2019 715,000 212,593 502,405
Closed #18 SCOTT RAKOW HVAC Parks Property Management 0w I 12-06-2019 150,000 137,302 12,697
Closed #13 NORTH SHORE ROOF Parks Property Management 0w 1 12-16-2019 375,000 374,722 276
Closed #18 SCOTT RAKOW ROOF Parks Property Management 0w 1 01-05-2020 1,124,000 127,217 996,782
Closed #26 MIAMI CITY BALLET ROOE Parks Property Management 0w 1 01-15-2020 760,000 758,824 1,175
Closed #13 NORTH SHORE CAMERAS Parks Property Management 0w 1 02-04-2020 205,699 60,858 144,841
Closed #18 SCOT RAKOW CAMERAS Parks Property Management aw 1 02-05-2020 250,000 110,659 139,340
Closed #32 PALM & HIBISCUS LANDSCAPING Infrastructure Capital Improvement Projects 0w 1 03-25-2020 1,000,000 1,000,000
Closed #18 SCOTT RAKOW WINDOWS Parks Property Management 0W 1 04-16-2020 699,999 194,601 505,396
Closed #26 FILLMORE ROOF Parks Property Management Qw 1 05-15-2020 1,920,000 1,874,154 45,844
Closed #4 FAIRWAY PARK PAVILION Parks Parks & Recreation I 05-15-2020 S0,000 35,044 14,955
Closed #2 COLINS PARK Parks Parks & Recreation aw I 05-28-2020 640,000 557,286 82,713
Closed #13 NORTH SHORE GENERATOR Parks Property Management 0W 1 06-30-2020 524,999 503,861 21,138
Closed #18 SCOTT RAKOW GENERATOR Parks Property Management 0w I 06-30-2020 816,000 729,717 86,281
Closed #47 71ST.ENTRANCE READERS Public Safety Police QW 1 07-12-2020 240,000 31,582 208,417
Closed #47 JULIA TUTTLE CSWY READERS Public Safety Police 0W I 09-21-2020 200,000 89,185 110,814
Closed Sum 15,932,988 12,714,905 38% 3,218,058
Closed Count 28 38%
Complete #18 SCOTT RAKOW POOL Parks Parks & Recreation 0w 1 07-06-2020 977,998 36,936 928,378 12,684
Complete Sum 977,998 36,936 928,378 3% 12,684
Complete Count 1 1%
Construction #57 LUMMUS PARK/OCEAN DRIVE CAMERAS Public Safety Police I 01-22-2021 815,000 124,245 665,155 25,599
Construction #56 CAMERAS- BEACHWALK Public Safety Police 1 01-29-2021 700,000 490,067 192,190 17,742
Construction #49 PUBLIC SAFETY RADIO SYSTEM Public Safety Fire aw 1 02-26-2021 9,700,000 2,038,911 7,595,974 65,114
Construction #4 FAIRWAY PARK FENCE Parks Parks & Recreation 1 02-26-2021 210,000 182,779 27,221
Construction #42 NAUTILUS TRAFFIC CALMING Infrastructure Transportation awa I 04-14-2021 739,499 188,746 536,227 14,526
Construction #24 MIDDLE BEACH BEACHWALK PH3 Parks Capital Improvement Projects 1 06-16-2021 4,500,000 2,698,083 1,448,379 353,535
Construction #33 PART I TREE PLANTING Infrastructure Environmental QWa I 04-01-2022 2,500,000 217,248 641,277 1,641,474
Construction #37 PART I SIDEWALKS Infrastructure Public Works Department QWa I 04-01-2022 3,500,000 1,257,430 1,879,231 363,337
Construction #38 PART I STREETS Infrastructure Public Works Department QWa I 04-01-2022 7,500,000 4,865,159 1,949,739 685,101
Construction Sum $30,164,499 $12,062,668 $14,908,172 45% $3,193,649
Construction Count 9 12%
CITY OF MIAMI BEACH 12/11/2020-10:17 AM
DocuSign Envelope ID: 0C1778CC-7544-4C20-B90C-8A7498693107
G.O. BOND PROJECT LIST BY PHASE
Design #4O 41 STREET LIGHTING UPGRADES Public Safety Public Works Department 1 02-28-2021 85,177 85,177
Design #53 CONVENTION CENTER BOLLARDS Public Safety Public Works Department 1 04-06-2021 b 775,000 45,449 729,551
Design #53 SOUNDSCAPE PARK BOLLARDS Public Safety Public Works Department 1 04-06-2021 b 375,000 45,449 329,551
Design #53 SOUTH POINTE PARK BOLLARDS Public Safety Public Works Department 1 04-06-2021 b 250,000 45,449 204,551
Design #48 PART 1 POUCE HQ Public Safety Property Management 1 06-01-2021 b 4,000,000 707,892 405,370 2,886,737
Design #18 SCOTT RAKOW GYM FLOORS Parks Parks & Recreation 1 06-01-2021 300,000 16,415 283,585
Design #12 N. BEACH OCEANSIDE BEACHWALK Parks Capital Improvement Projects 1 04-04-2022 1,999,999 129,893 70,057 1,800,049
Design #42 8AYSHORE SOUTH TRAFFIC CALMING Infrastructure Transportation 1 04-15-2022 560,148 11,586 34,114 514,447
Design #42 NORMANDY ISLE TRAFFIC CALMING Infrastructure Transportation 1 04-15-2022 113,999 13,613 23,720 76,666
Design #42 PALM VIEW TRAFFIC CALMING Infrastructure Transportation 1 04-15-2022 86,349 4,883 81,466
Design #39 PART I SEAWALLS/SHORELINES Infrastructure Public Works Department 1 04-29-2022 7,999,999 652,885 185,493 7,161,619
Design #43 ALTON ROAD SHARED USE PATH Infrastructure Transportation 1 06-29-2022 b 170,000 170,000
Design #9 MARJORY STONEMAN DOUGLAS PARK Parks Parks & Recreation 1 10-27-2022 681,999 850 13,788 667,360
Design #43 23 ST. STREETSCAPE IMPROVEMENTS Infrastructure Capital Improvement Projects 1 12-26-2022 1,500,000 4,990 1,495,010
Design #10 MAURICE GIBB PARK Parks Capital Improvement Projects 1 01-06-2023 3,300,000 37,714 3,262,284
Design #43 CHASE AVE/34 ST SHARED USE PATH Infrastructure Capital Improvement Projects 1 02-02-2023 830,000 830,000
Design #15 PAR 3 / 8AYSHORE PARK Parks Capital Improvement Projects 1 03-08-2023 15,699,999 42,547 672,090 14,985,360
Design #23 PEDESTRIAN BRIDGE Parks Capital Improvement Projects 1 06-28-2023 10,000,000 8,547,268 1,249,043 203,687
Design #4S FIRE STATION i1 Public Safety Capital Improvement Projects 1,2 12-29-2023 7,000,000 1,026,593 126,088 5,847,317
Design Sum $55,727,669 $11,285,889 $2,827,350 9% $41,614,417
Design Count 19 26%
Planning #19 SOUNDSCAPE RESTROOMS/STORAGE Parks Parks & Recreation 1 01-29-2021 b 699,999 699,999
Planning #40 PART 1 REVITALIZE 41 STREET Infrastructure Economic Development 1 01-29-2021 b 1,414,823 221,365 26,300 1,167,158
Planning #55 PART I STREET LIGHTS Public Safety Public Works Department 1 02-26-2021 b 5,000,000 10,108 4,989,892
Planning #50 ALTON RD. CORRIDOR CAMERAS Public Safety Police 1 03-02-2021 b 211,999 15,999 195,999
Planning #SO 41 ST. CORRIDOR CAMERAS Public Safety Police 1 03-31-2021 b 235,324 17,999 217,324
Planning #50 71 STREET CORRIDOR CAMERAS Public Safety Police 1 03-31-2021b 211,999 15,999 195,999
Planning #SO DADE BLVD. CORRIDOR CAMERAS Public Safety Police 1 03-31-2021 b 165,674 165,674
Planning #57 COLLINS AVE/WASH AVE CAMERAS Public Safety Police 1 03-31-2021 b 675,000 10,581 140,410 524,007
Planning #47 OTHER READERS CITYWIDE Public Safety Police 1 04-01-2022 1,390,000 30,547 38,315 1,321,136
Planning #8 LUMMUS PARK Parks Parks & Recreation 1 12-30-2022 b 4,737,000 10,800 4,726,199
Planning 1 72 ST. COMMUNITY COMPLEX Parks Capital Improvement Projects 1,2 12-03-2023 10,800,000 494,467 1,534,592 8,770,940
Planning #30 SKATE PARK Parks Parks & Recreation 1 (blank) 7SO,OOO 7SO,OOO
Planning Sum $26,291,818 $756,960 $1,810,522 5% $23,724,327
Planning Count 12 16%
Pending #54 MARINE PATROL FACILITY Public Safety Capital Improvement Projects 1 (blank) 2,700,000 2,700,000
Pending #5 FLAMINGO YOUTH CENTER FACILITY Parks Capital Improvement Projects 1 (blank) 15,400,000 15,400,000
Pending #29 PART 1 WEST LOTS Parks Economic Development 1 (blank) 1,000,000 1,000,000
Pending #13 NORTH SHORE PATH & FIELDS Parks Parks & Recreation 2 (blank) 2,944,000 2,943,999
Pending Sum $22,044,000 $0 $0 0% $22,043,999
Pending Count 4 5%
73 100% $151,138,972 $24,142,453 $33,189,327 100% $93,807,134
QWa = The quick-win portion of this project is complete.
b = The anticipated end date is of the phase, not of the entire project.
CITY OF MIAMI BEACH 12/11/2020-10:17 AM
DocuSign Envelope ID: 0C1778CC-75A4-4C2C-B90C-8A7498693107 EXHIBIT Bl
G.O. BOND PROJECT LIST - SAVINGS
$
Active Phase Category Project Name Quick Win Tranche Count $ Budget Encumbered $Spent I $ Available - Closed Infrastructure #32 PALM & HIBISCUS LANDSCAPING w 1 1,000,000 1,000,000
, ng oet..
Infrastructure Sum 1 1,000,000 1,000,000 --- .
Closed Parks #17 POLO PARK QW 1 499,998 493,673 6,325
Closed Parks #19 SOUNDSCAPE 4K TECHNOLOGY Qw 1 3,799,999 3,748,495 51,503
Closed Parks #13 NORTH SHORE LIGHTS & PAINT QW 1 130,300 130,210 89
Closed Parks #26 COLONY THEATRE ROOF QW 1 300,000 299,650 350
Closed Parks #21 STILLWATER PARK QW 1 144,999 142,440 2,559
Closed Parks #3 CRESPI PARK QW 1 210,998 184,919 26,079
Closed Parks #18 scoT RAKOW PAINT QW 1 130,000 116,776 13,224
Closed Parks #18 SCOTT RAKOW HVAC QW 1 150,000 137,302 12,697
Closed Parks #13 NORTH SHORE ROOF QW 1 375,000 374,722 276
Closed Parks #18 SCOTT RAKOW ROOF QW 1 1,124,000 127,217 996,782
Closed Parks #13 NORTH SHORE CAMERAS Qw 1 205,699 60,858 144,841
Closed Parks #18 scoTT RAKOW CAMERAS Qw 1 250,000 110,659 139,340
Closed Parks #26 MIAMI CITY BALLET ROOF QW 1 760,000 758,824 1,175
Closed Parks #18 SCOTT RAKOW WINDOWS QW 1 700,000 194,601 505,396
Closed Parks #26 FILLMORE ROOF Qw 1 1,920,000 1,874,154 45,844
Closed Parks #4 FAIRWAY PARK PAVILION 1 50,000 35,044 14,955
Closed Parks #2 COLLINS PARK QW 1 640,000 557,286 82,713
Closed Parks #13 NORTH SHORE GENERATOR QW 1 524,999 503,861 21,138
Closed Parks #18 SCOTT RAKOW GENERATOR QW 1 816,000 729,717 86,281
Complete Parks #18 SCOTT RAKOW POOL QW 1 977,998 36,936 928,378 12,684
et de.
Parks Sum 20 13,709,990 36,936 11,508,786 2,164,251
Closed Public Safety #53 PORTABLE BOLLARDS Qw 1 600,000 599,915 84
Closed Public Safety #52 TATUM PARK LED LIGHTING QW 1 151,999 52,758 99,240
Closed Public Safety #52 CRESPI PARK LED LIGHTING QW 1 86,999 41,780 45,218
Closed Public Safety #52 STILLWATER PARK LED LIGHTING Qw 1 86,999 41,780 45,218
Closed Public Safety #47 MACARTHUR CSWY READERS QW 1 120,000 64,904 55,095
Closed Public Safety #52 NORMANDY ISLE PARK LED LIGHTING QW 1 715,000 212,593 502,405
Closed Public Safety #47 71 ST. ENTRANCE READERS Qw 1 240,000 31,582 208,417
Closed Public Safety #47 JULIA TUTTLE C5WY READERS QW 1 200,000 89,185 110,814 --- --- e
Public Safety Sum 8 2,200,997 1,134,497 1,066,491
Total Sum 29 16,910,987 36,936 13,643,283 3,230,742
Note: Red figures are projected project savings from Completed projects.
Annurur nrrru rnru urrn DocuSign Envelope ID: 0C1778CC-75A4-4C2C-B90C-8A7498693107
Scope
Replace the city's outdated Motorola analog
radio system with a new Harris Corporation
satellite radio system. giving first responders
access to a state-of-the-art emergency
communications technology network with high
tech functions such as seamless
interoperability and encrypted data.
Phase
EXHIBIT C - Quick Wins Remaining
Contact
Project Details
Construction
G.O. Bond Funding
Budget: $9.700,000
Encumbered. $2.038,911
Spent: $7.595.974
Spent%: 78%
Project Timeline
Department: Fire
Name:
Email:
Phone:
Kevin Pulido
mailtokevinpulido@miamibeachfl_gov
(786) 568-6057
5. Construction l ê
i i i l i l i T l
2019 April luly October 2020 April July October 2021 April
Start Date
d.
Original End Date Actual End Date
01/01/2019 02/28/2020 02/26/2021
Update
Ten sites require installation of microwave dishes and/or radio frequency antennas. Six have
been completed and four are underway Mobile radios are being installed in all 400 PD vehicles.
- For additional project details refer to the PROGRESS REPORT on this website
Miam@Beach
k pi. - [ai@) Tems 3'Ji,rom, 2020 Microsoft Corporation
}tc rAnnrnn rrneurntt
DocuSign Envelope ID: 0C1778CC-75A4-4C2C-B90C-8A7498693107
Scope
Improve public safety for residents and visitors
between 14th Place to 23rd Street by installing
several new security cameras along the
pedestrian beachwalk path.
Phase
Construction
G.O. Bond Funding
Budget: $700.000
Encumbered: $490.067
Spent: $192.190
Sent %: 27%
Project Timeline
Project Details
Contact
Lvepartment Police
Name: Lauren Firtel
Email: mailto;laurenfirtel@miamibeachflgg
Phone: (305) 986-6403
1 Planning b 2. Design
4. Procurement
5. Construction [
I I I I I I I I
April July October 2020 April July October 2021 April
Start Date
d.
Original End Date Actual End Date
04/01/2019 05/29/2020 01/29/2021
Update
Main conduit runs and conduit installation to individual poles have been completed. Field
enclosures and electrical to field enclosures underway. All equipment and fiber have been
ordered. Pending shipment of fiber.
- For additional project details refer to the PROGRESS REPORT on this website
Miami B@ch
e k p;-4I AA, Terms
lb}rom, 2020 Microsoft Corporation
¡ 1Inni_nryr__xi rrr NMERS
DocuSign Envelope ID: 0C1778CC-75A4-4C2C-B90C-8A7498693107
Scope
Install additional security cameras to expand
monitored coverage in Lummus Park and
Ocean Drive.
Phase
Construction
G.O. Bond Funding
Budget: $815.000
Encumbered. $124.245
Spent: $665.15 5
Spent %: 82%
Project Timeline
Project Details
Contact
Deparment. Police
Name: Lauren Firtel
Email: mailto:laurenfirtel@miamibeachfl.gov
Phone: (305) 986-6403
1Planning I 2. Design
4. Procurement
scoveon. I [e
I I I I I I I I I
2019 April July October 2020 April July October 2021 April
Start Date
d.
Original End Date Actual End Date
03/21/2019 02/10/2020 O 1/22/2021
Update
Underground infrastructure work at the Park and between Ocean Rescue and Police
Headquarters is complete. Fiber installation is underway. Cameras installation to follow. COVID-
19 affected production at the Fiber Plant in Mexico. which delayed delivery and final completion
of the project. Pending the scheduling of the contractor to splice the fiber at both PD and Ocean
Rescue.
- For additional project details refer to the PROGRESS REPORT on this website
Miami Beach
co)
] pin Terms & A3jd'1mTom, 2020 Microsoft Corporation
£.-L-
4 "p» T "PAAIIAIIT III I DocuSign Envelope ID: 0C1778CC-75A4-4C2C-B90C-8A7498693107 EXHIBIT O
Scope Phase
Project Details
Contact
Build a new community facility at 72 Street
between Collins Avenue and Harding Avenue
with an Olympic-sized roof-top swimming
competition pool. a warm-up pool. a
library/media center. a community room. an
activated liner. a fitness gym with running
track. green space and a multi-level parking
garage. NOTE: The total G.O. Bond budget for
this project is $53 million. The first issuance of
$10.8 million is to be spent in Tranche 1 and
the remaining $43 million is to be spent in
Tranche 2.
Planning
G.O. Bond Funding
Buaget: $10.800.000
Encumbered. $494467
Spent:
Spent %·
epartme
Name:
Email:
Phone:
Capital Improvement Projects
Kevin Pulido
mailto:keyinpulido@miamibeachfl_gov
(786) 568-6057
$1.534,592
14%
Project Timeline
1 Planning WG l:::J.
[)eS/]Hl I I I I
2019 2020 2021 2022 2023 2024
Start Date
dA.
Original End Date Actual End Date
12/17/2018 12/03/2023
Update
The short list of Design Build Firms was approved by the City Commission in Sept. Technical
Proposals due date was extended to Dec 14th to provide firms additional time. The evaluation
committee meeting is scheduled for January 7th. Commencement date to relocate the
transmission lines by FPL is being targeted for January 2021. The Library lnterlocal Agreement
was adopted by Miami Dade County Board on Nov. 19.
- This project has additional sources of funding
- For additional project details refer to the PROGRESS REPORT on this website
12/03/2023
Indian Creek
Village
Normandy
Isle 6
k pie] Terms l'}#rom, 2020 Microsoft corporation
A EAIDAIA TAADLU EEAIE 'DocuSign Envelope ID: 0C1778CC-75A4-4C2C-B90C-8A7498693107
Scope
Replace the aged perimeter fence with a
higher-quality and higher-security fencing
system.
Phase
Construction
G.O. Bond Funding
Budget: $210,000
Encumbered: $182.779
Spent: $0
Spent %: 0%
Project Timeline
Project Details
Contact
Department: Parks & Recreation
Name: Kevin Pulido
Email: mailtokevinpulido@miamibeachfl_gov
Phone: (786) 568-6057
1. Planning I■■■■■■■I 2. Design
5. Construction lg%eany
F T 77 T T l
December 2021 February November
Start Date
d.
Original End Date Actual End Date
10/14/2020 02/28/2021 02/26/2021
Update
Contractor has been issued a Notice to Proceed and fence fabrication is underway. Permit was
issued on December 3. Installation expected to begin in January.
- For additional project details refer to the PROGRESS REPORT on this website
Indian Creek t
Village
Normana@
Isle (@34)
r"
pg;pal. Terms l@SB''éfaka 2020 Microsoft corporation
t ttt -. -
±ta tit NIN I a.um tiny pop en tam t l
DocuSign Envelope ID: 0C1778CC-75A4-4C2C-B90C-8A7498693107 Project Details
Scope
Construct an on-grade, ADA accessible and
decorative paver pathway from streets 79 to
87, completing the final link of the city's entire
beachwalk system. Redevelop the Beachwalk
to expand path networks and dune systems.
new landscaping and wayfinding signage and
turtle-friendly lighting.
Phase
Design
G.O. Bond Funding
Budget.
Encumbere
Spent:
Spent %:
Contact
Department: Capital Improvement Projects
$1,999.999
$129.893
$70.057
4%
Name:
Email:
Phone:
Kevin Pulido
mailto:keyinpulido@miamibeachfLgoy
(786) 568-6057
Project Timeline
1 Planning
2. Design
3. Contractor Selection
{_nTf{[THQll
2016 2018 2020
I
2022
Start Date
A.
Original End Date Actual End Date
08/13/2015 04/28/2021 04/04/2022
Update
Invitation to Bid ITB) for the beachwalk construction was issued on Oct 2. The due date for
proposals has been extended to December 16th to provide bidders additional time. The removal
and relocation of existing trees. which will be completed with a different contractor. is scheduled
to start January 2021.
- This project has additional sources of funding
- For additional project details refer to the PROGRESS REPORT on this website
Surfside
Indian Creek
Village O
Normandy T k. pi] a.» Terms l!BB3,#tan, e 2ottcroson corporation
+1rpD 2 trncLDr DDI
DocuSign Envelope ID: 0C1778CC-75A4-4C2C-B90C-8A7498693107
Scope
Develop a brand new 19 acre park space with
environmental remediation and resiliency
components; construct an outdoor
amphitheater. walking trail with lake overlooks.
tennis courts and restroom facility. a pavilion
shade structure. dog park. vita course.
playground. and butterfly garden.
Phase
Design
G.O. Bond Funding
+age: $15.699,999
Encumberec' $42,547
Spent: $672.090
Spent %: 4%
Project Timeline
Project Details
Contact
neartment: Capital Improvement Projects
Name: Vanessa Vazquez
Email: mailto_Vanessa/azquez@miamibeachfL,goy
Phone: (786) 599-6543
1. Planning trwl3I -.-----------~ 2.Desio ZEE3
3. Contractor Selection cm"
sconstution• l • I I I I I I
2016 2018 2020 2022 2024
Start Date
d.
Original End Date Actual End Date
08/12/2015 07/28/2021 03/08/2023
Update
Project was approved by ORB on 9/1/20. Plans have been submitted to Building Dept for
permitting. DERM Environmental Division provided comments on 12/4/20, which included a
request for the installation of additional monitoring wells. Comments must be addressed by Feb
2. 2021. Consultant submitted a cost estimate which exceeds the project budget. and has been
directed to make adjustments and value engineering to bring the project within budget.
- This project has additional sources of funding
- For additional project details refer to the PROGRESS REPORT on this website
Fa ~-
NAUTILUS Four Points
] pin Miami Beach Terms ¿'d'1mTi, ¢'2d20'Micro5ht corporation
±/A MmmrrrnrLu prnrLuAn Lu DLI2 DocuSign Envelope ID: 0C1778CC-75A4-4C2C-B90C-8A7498693107
Scope
Replace the current wooden boardwalk
structure that exists between 23 Street and 45
Street with an on-grade pedestrian pathway
that connects Mid Beach with South Beach and
North Beach Beachwalk portions - providing
one seamless oceanside pathway that
stretches from 1st Street to 87th Street.
Phase
Construction
G.O. Bond Funding
udget: $4,500,000
Encumbered: $2.698,083
Spent: $1448.379
Spent %: 32%
Project Timeline
Project Details
Contact
vepartment: Capital Improvement Projects
Name: Vanessa Vazquez
Email: mailto_Vanessa/azquez@miamibeachfl.goy
Phone: (786) 599-6543
1. Planning mnŒim••······ b 2. Design EE:
3.contractor selection EI_.
s.cooto. EE3
I I I I
2016 2018 2020 2022
Start Date
A
Original End Date Actual End Date
10/22/2015 02/13/2021 06/16/2021
Update
Project is on track for completion by June 2021. and efforts are being made to open sections of
the beachwalk in the Spring. as they are completed. Shower & wall foundation. electrical. water
& drainage underground work continues at street ends. Concrete paver installation has
advanced to the northern portion. The wiring tor the light bollards has advanced to 42nd St and
security camera poles have been installed up to 32nd St.
- This project has additional sources of funding
- For additional project details refer to the PROGRESS REPORT on this website
NAUTILUS
•
Hot Tub at
Four Points
k pi„] Terms
lWdnrm, g,2020_ Microsoft corporaíon ami Deacn
LL PAA I d NIN Pt N ltit
DocuSign Envelope ID: 0C1778CC-75A4-4C20-B90C-8A7498693107 Project Details
Scope
Plant the first $2.5 million worth of trees to
under-shaded parks and neighborhoods
citywide.
Phase
Construction
G.O. Bond Funding
Budget:
Contact
Department: Environmental
$2,500.000
Encumbered: $217,248
Spent: $641.277
Spent %: 26%
Name:
Email:
Phone:
Kevin Pulido
mailto:keyinpulido@miamibeachfLgoy
(786) 568-6057
Project Timeline
1. Planning I I
2 Design
5. Construction ,.I--------------,--------------,,
I I I I l
2020
Start Date
A.
Original End Date
2021
T
2022
Actual End Date
04/22/2019 04/01/2022 04/01/2022
Update
759 Florida friendly & native trees have been planted Citywide. The Lake Pancoast neighborhood
will receive 114 trees commencing in January which will bring the total to 873 trees. There are
other upcoming projects under design & coordination for various locations throughout the City.
Learn more about where trees have been planted & the benefits of the species planted at
www.opentreemap.org/miamibeachtrees/map.
- This project has additional sources of funding
- For additional project details refer to the PROGRESS REPORT on this website
Norn"Y,,a) Isle 9
$%2° • · erms ; krom, e 2020 Microsot corporáí6
au toe t .77-7iaa 2ctu hod
GO BOND Reforestation Projects
Neighborhood Trees Planted Total Project Cost
5" street Corridor so $51,876
Normandy Isles 75 $54,196
Brittany Bay Park 26 $30,000
4 Muss Park 39 $40,730
hl» a0" street 65 $75,355 ra a) - 20" street Pocket 60 $87,825 Park
Stillwater 20 $23,640
Biscayne Point 122 $182,123
YEAR1 TOTAL 457 $545,745
James Avenue 36 $10,840
South Beach $62,715 Reforestation 62
Normandy
Isles/Normandy 85 $39,348
N Shores hl
0 a» - Normandy Shores 119 $97,674
Lake Pancoast
(Project to begin 114 $121,155
January 2021)
YEAR2TOTAL 416 $331,732
I s73] I $877,476.08
I j P j i
\ Brittany Park
,, or. g , r ., ., .. •· / ,.,,..,
+ ·,,
" ' i41
1 1, :1
ti ±;i
r
touth Beach Reterestatie"
H ! ' t,
t i i
Legend
Go Bond Reforestation
Parcel
Street
/27 DADT A cIrrA u
DocuSign Envelope ID: 0C1778CC-75A4-4C2C-B90C-8A7498693107
Scope
Renovate part 1 of deteriorated sidewalks. as
per the city's pavement condition index
assessment.
Phase
Construction
G.O. Bond Funding
Budget. $3.500.000
Encumbered: $1.257.430
Spent: $1.879.231
Spent %: 54%
Project Timeline
Project Details
Contact
epartment. Public Works Department
Name: Kevin Pulido
Email: mailto:keyinpulido@miamibeachfL_gov
Phone: (786) 568-6057
1. Planning ■I
2. Design ■
5. Construction ... [--------------~ ------------,
I I 1
2019 2020 2021 2022
Start Date
d.
Original End Date Actual End Date
03/01/2019 04/01/2022 04/01/2022
Update
299.210 sq ft. of sidewalk have been repaved across the city. The quick-win portion of the
project was completed ahead of schedule. Public Works has completed a revised schedule for
completion of Tranche 1.in coordination with Jacob's Stormwater Projects Prioritization Plan
recently approved by City Commission and other upcoming capital improvement projects.
- For additional project details refer to the PROGRESS REPORT on this website
Miami_Beach
Li (@@) terms lWdnrom, 2O20 Microsoft Corporaüon -
DocuSign Envelope ID: 0C1778CC-75A44-4C2C-B890C-8A7498693107
-)
TREASURE
IS LAND
North Beach
8 i $
Mid Beach
WVAT SON
1LAND South Beach
DODGE ISL NE
LUMMUS
1SL4ND
Part 1- Sidewalk Work Plan
Tranche 1
GOB_Status
- 3 Month Work Ahead
- Part 1 Completed
- Part 1 Scheduled
Esn, HERE, Garmin, (c) OpenStreetMap contributors, and the GIS user community
O ars 12082020
4 WORKHerS
Net To Scale 8'14 - Ry Cely
#.at Man.a ae MG.S
Miami Beach Gls t7a0 Convention Center Drive • Miami Beach, FL 33139+ 305,673.7000 • gis@miamibeach f.gov • www,miamlbeachf\. go¢ ORK$Auvemet Mago«to»ates s Year wok Pao uawrd»'sdewa»_TRANOE_V10_5_20201201.m œ' Sidewalk Work Plan w.E Miami Beach State & County EEJ» Progress By C.I.P
- ; ,_M_i_a_m_;._o_a_d_e_c_o_u_n_ty_,_F_L.J ,. _,
±22 DAT A cTDEETc
DocuSign Envelope ID: 0C1778CC-75A4-4C2C-B90C-8A7498693107 Project Details
Scope
Repave and restore part 1 of deteriorated
streets. as per the city's pavement condition
index assessment.
Phase
Construction
G.O. Bond Funding
Budget: $7.500.000
Encumbered: $4,865.159
Spent: $1,949.739
Spent %: 26%
Project Timeline
Contact
Department: Public Works Department
Name:
Email:
Phone:
Kevin Pulido
mailto:keyinpulido@miamibeachfLgoy
(786) 568-6057
1 Planning
2. Design
5 Construction FF
2019
■■I
I ~
2020 2021 2022
Start Date
d.
Original End Date Actual End Date
03/01/2019 04/01/2022 04/0 l /2022
Update
19.9 miles of roadway have already been repaved across the city. The quick-win portion of the
project was completed ahead of schedule. Public Works has completed a revised schedule tor
completion of Tranche 1. in coordination with Jacob's Stormwater Projects Prioritization Plan
recently approved by City Commission. and other upcoming capital improvement projects.
- For additional project details refer to the PROGRESS REPORT on this website
MiamiBeach
l p¡· (AA) Terms ld¿&ldmrom, e 2020 Microsoft corporation
DocuSign Envelope ID: 0C1778CC-7544-4C2C-B890C-8A7498693107
TREASURE
IS LANI
North Beach
Mid Beach
WATS ON
1SL AtD South Beach
€e DODGE 1SLANE
LUM!MUS
ISLAND
Part 1 - Streets Work Plan
GOB Status
- Part 1 Scheduled
- Part 1 Completed
Esn, HERE Garmin, (c) OpenStreetMap contributors, and the GIS user community
Miami Beach Gis • 1700 convention Center Drive • Miami Beach, FL33139· 305,673.7000 • gist@miamibeach ft.gov • www.mlamibeachf\.go¥.OR»sAu Pae«t Moog«wtowotea s Yau wens Pia+Go Mus 4rM»\trot_0w_10_511x171_20.20 1209_1 mt œ. Street Work Plan w$, Miami Beach
T Miami-Dade County, FL AK ar 12/102020 - WORK+rS
Net Te Seale 8+ Rey Cely
M.in8eae. hGus
sa» s cuy Rosas [Z U]«ores yvc1
+30 DADT 4 CEAAIAIIILIDII IAIr DocuSign Envelope ID: 0C1778CC-75A44-4C2C-B90C-8A7498693107
Project Details
Scope
Implement part 1 of public seawall and
shoreline resilient infrastructure.
Phase
Design
G.O. Bond Funding
Budget:
Encumbered. $305,300
Spent: $60.800
Spent % 1%
Project Timeline
Contact
Department: Public Works Department
$8.000.000
Name:
Email:
Phone:
Kevin Pulido
mailto:kevinpulido@miamibeachfLgoy
(786) 568-6057
2. Desi _-F,
2020 2021 2022
Start Date
d.
Original End Date Actual End Date
01/10/2020 04/29/2022 04/29/2022
Update
8100 Hawthorne Ave construction to begin in November. and Maurice Gibb and Britanny Bay to
begin in early 2021. Design underway for Jefferson avenue. Lenox Court. Garden Avenue. Bonita
Avenue. Rue Notre Dame. Trouville Esplanade. and 71 50 Indian Creek. Additional locations to be
determined upon completion of prioritization matrix.
- This project has additional sources of funding
- For additional project details refer to the PROGRESS REPORT on this website
Venetian Miami Beach
Islands
Terms b Bine92020 Tomtom 2020 HERE. 2@20
ii ¿hk1sLAND Microsoft Corporation
a o o
#gr Morta Dang
tat cot tat4043 E±:
feule Eplanage £at eat $72¢2¢ 1i.
noray lay Psi Llinten«tina c tete»t tu7t, .1"-o«or
±attrar a tat oat 47040 :%:
Lanen .t ft Coar $too@ z:
Legend
Private Seawall (48.85 miles)
Public Seawalls (4.15 miles)
------· Seawall To Be Constructed '0.31 miles
Noto. Total Length of Seawall within tho City (63 miles) Seawalls within City ROW(1.82 Milos) Seawalls within City proportios (2.33 Milos)
Mi dian teak DO
Est or 421$.0o z
acing.o beth fmet val attingentien
Citywide Seawall Survey Identifying Funding
Citywide Master Plan and Prioritization to
Follow After Seawall Survey
+AO AIAITII II TD»AAEEI "AI AIAI 'DocuSign Envelope ID: 0C1778CC-75A4-4C2C-B90C-8A7498693107 Project Details
Scope
Implement traffic calming measures in the
Nautilus neighborhood.
Phase
Construction
G.O. Bond Funding
Contact
Department: Transportation
Budget:
Encumbered:
Spent:
$739.499
$188.746
$536.227
Name:
Email:
Phone:
Vanessa Vazquez
mailto;Vanessa/azquez@miamibeachflgo
(786) 599-6543
Spent %: 73%
Project Timeline
1. Planning ■I
2. Design
5. Construction ]
I I I I
2019 2020 2021
Start Date
d.
Original End Date Actual End Date
03/01/2019 02/05/2020 04/14/2021
Update
The quick win portion of this project (which includes bike lanes and speed tables) is complete.
The contractor has suffered some delays in submitting the shop drawings due to COVID. CMBPW
issued comments on drainage. which are being corrected for permit submission. Work is
expected to begin two weeks after securing of permit.
- For additional project details refer to the PROGRESS REPORT on this website
Hot Tub at
Four Points - r ~~---
k pf„ Terms l'}nrom, 2020 Microsoft corporation
AE III£ rNrtl 44
' DocuSign Envelope ID: 0C1778CC-75A4-4C2C-B90C-8A7498693107
Scope
Replace the deteriorated Fire Station #1 facility
with a new and larger building in a location that
expands emergency coverage in South Beach:
include space tor a911call center. NOTE: The
total G.O. Bond budget tor this project is $10
million. The first issuance of $7 million is to be
spent in Tranche 1 and the remaining $3
million is to be spent in Tranche 2.
Phase
Design
G.O. Bond Funding
Budget: $7.000.000
Encumbered $1,026.593
Spent: $126.088
Spent %: 2%
Project Timeline
Project Details
Contact
Department: Capital Improvement Projects
Name: Lauren Firtel
Email: mailto;laurenfirtel@miamibeachfl_goy
Phone: (305) 986-6403
1. Planning
[)es4an d
5. Construction .-------.-------.------11------
2018 2019
IEE
E3 ' I
II
I " 2020 2021 2022 2023 2024
Start Date
d.
Original End Date Actual End Date
11/06/2018 03/30/2023 12/29/2023
Update
Revised Schematic Design documents removing the 911 Call Center and reducing the size of the
building to bring project within budget was submitted by the Consultant on November 24. 2020.
Documents are under review by various City Departments. Once the design is updated with
comments from all. contractor will update the estimate of construction cost.
- For additional project details refer to the PROGRESS REPORT on this website
Miami Beach
k pi„] Terms
Rh}nrom.e,2020 Microsoft Corporation Etcher
}+r2 AIVEAITIAL rrAITrD r2Il_ADnc DocuSign Envelope ID: 0C1778CC-75A4-4C2C-B90C-8A7498693107
Scope
Install decorative concrete bollards in the
Convention Center corridor.
Phase
Design
G.O. Bond Funding
Budget. $775.000
Encumbered: $45.449
Spent: $0
Spent%· 0%
Project Timeline
Project Details
Contact
Department: Public Works Department
Name: Kevin Pulido
Email: mailtokevinpulido@miamibeachfl,gov
Phone: (786) 568-6057
1. Planning ■■■■■■■■■■■■■■■■■■■■~---------- 2.Design l
I I I I I I I
April July October 2021 April
Start Date
A.
Original End Date Actual End Date
02/28/2020 04/06/2021
Update
Consultant has been selected and purchase order has been issued. Site assessments and
analysis will follow.
- For additional project details refer to the PROGRESS REPORT on this website
04/06/2021
7A tr' '
Mían%ah
] Rinl Jax Terms
dB'd'mrom, o 2020 fl#sot corporation
+r3 IIAIrrADr DAD III nDr DocuSign Envelope ID: 0C1778CC-75A4-4C2C-B90C-8A7498693107 Project Details
Scope
Install decorative concrete bollards in
SoundScape Park.
Phase
Design
G.O. Bond Funding
Contact
Department: Public Works Department
Budget:
Encumbered:
Spent:
$375,000
$45.449
$0
Name:
Email:
Phone:
Lauren Firtel
mailto_laurenfirtel@miamibeachfLgoy
(305) 986-6403
Spent %: 0%
Project Timeline
1. Planning 1------- 20ess E l
I i I I I I I
July pil
Start Date
d.
Original End Date
Octote 2021 Ail
Actual End Date
02/28/2020 04/06/2021 04/06/2021
Update
Consultant has been selected and purchase order has been issued. Site assessments and
analysis will follow.
- For additional project details refer to the PROGRESS REPORT on this website
Miam@Beach
n;+ (@@) 1ems
l3}#rom, 2020 Microsoft Corporation
l .gag t a,tit.gee u. t tr • t t I.
DocuSign Envelope ID: 0C1778CC-75A4-4C2C-B90C-8A7498693107
Scope
Install decorative concrete bollards in South
Pointe Park.
Phase
Design
G.O. Bond Funding
Budget: $250.000
Encumbered $45.449
Spent: $0
Spent %: 0%
Project Timeline
Project Details
Contact
Depa ment Public Works Department
Name: Lauren Firtel
Email: mailto:laurenfirtel@miamibeachfl.gov
Phone: (305) 986-6403
1. Plan11111g ■■■■■■■■■■■■■■■■■■■■d
2. Design l
I I I I I I
April July October 2021 April
Start Date
d.
Original End Date Actual End Date
02/28/2020 05/28/2021 04/06/2021
Update
Consultant has been selected and purchase order has been issued. Site assessments and
analysis will follow.
- For additional project details refer to the PROGRESS REPORT on this website
Fisher •
Island
k pi„ Terms
lB3}rom, e 2020 Microsoft corporation
': ( '-'[s's } i4
EXHIBIT E
BLOG
Growing Greener with Shade
Trees
The City of Miami Beach continues to plant new shade trees by
the hundreds as it works to expand the shady tree canopy from
17% to 22% by 2040. Of the more than 1,000 new shade trees
planted throughout the city over the past two years, 759 were
funded by the 2018 voter-approved General Obligation (G.0.)
Bond! $5 million of the total $439 million program budget is
dedicated to the...
Your Voice, Your Vote: A Two
Year Overview
/'/IL' 'BE Wv .ACH
Go
MIAMI(BEACH
gor0.o
Two years ago on Nov. 6, 2018- an overwhelming 70% of
Miami Beach voters approved the $439 million G.O. Bond
Program. Following that mandate a G.O. Bond Program team
was formed. A citizen-led G.O. Bond Oversight Committee was
established. A final project list was approved. The first tranche of
bonds got issued and the bonds sold quickly on Wall...
'! il '-si'°' } i
SOCIAL
#MaskUpMiamiBeach " 9 @MiamiBeachNews · Dec 17
We continue to plant new shade trees by the hundreds as we work to
expand the shady tree canopy from 17% to 22% by 2040. Of the more
than 1,000 new shade trees planted throughout the city, 759 were funded
by the #G0MB2018 program -- learn more:
gombinfo.com/growinggreener/
£,hh, city ot Miami each Government o o os«mr¢ e
On November 6, 2018, an overwhelming 70% ot Miami Beach voters approved
the $439 million #G0MB2018 .- now 2 years later the G.O. Bond Program has
completed a number of quality-of-life improvements throughout the city.
Learn more: https //www gombinto.corr/your-voice-your-vote-a-two-yeat
. ·~
. . -
s , a ....s z, le fmhg #MaskupMiamieach " o @MamiBeachNews 4m
miii-iseee s lt/ Construction set to egin on Final segment ot Beachwak - Once
completed in spring of 2022, residents and visitors will be able to travel
from South Beach to North Beach along a spectacular oceanfront
promenade!
1• 8EACH
Go
4.A2.AO
GOMF O COM
Your Voice, Your Vote: A Two Year
Overview - G.O. Miami Beach
Two years ago- on Nov.6, 2018 an
overwhelming 70% 0f Mam Beach
voters approved the $439 million G.O
Bond Program. Following that mandate
a G.0. Bond Program team was torme.
W,AN BEACH
o+. # au+ ts4ow.r.A,trgi tu M9'1730
Ta.wale oa.
ta. leo tait a a o
PRESS RELEASE
F OR WE DATE RELEASE Dec 21,2020
Construction Set to Begin on Final Segment of Beschwalk
- One cooplot et an pg t 222 residents ad wtons wot be able to tree tom Soath Bech to Nionth bleach along a spectacular oceanbront promende
lamie Beh, Ft- Controacton ns setto begin n eey 221on te fnal' segrret ot te Be.twai. a rone tan 7-ride oanhronet proen.de that wel pan te entre ienrgth ot the aty
hrom South Boch through North Beach
Many ot us n ts oty Marve had a Mekong dream ot berg able to envoy sweeoeg vows ot te
YOUR VOICE. IN ACTION! YOUR VOICE, IN ACTION!
O o 0
YOUR VOICE, IN ACTION!
G0#24: Middle Beach Beachwalk
Project date • December 12, 2020
Drexel Avenue Paving- 12 to 13 Street
Notice Date: November 5, 2020
Meridian Avenue Restriping Starts 11/30
Project benefits TM« bes@side corrrunty amenity is port ot the Gneater tanti Greenway Network (MGM}, which
aimns to support the use ot aterrat/ve modes ot
transport@ton along the easter seaboard. The project watt nerve the existing rad wooden boardwalk and replace wth an approaomat'eMy1$- tot wide, on-grade, Aerans wth Dsabtoties At (AD4)-acesobe paver pathway that supports the use otbwyins, pee strans and other non-
rotor.gd neons. f transportation
what's Happening The tyot Miami eh continues work on the eactalk prot between 2pee 4$ streets, irctudong II street tends. The preexistrg wooden boardwalk has been
tornpletel derrol shed and work is taking pie along the entire project tort. Pease rote that due to the nature o the projt, ore areas ray not see work taking ple tor a few weeks ata time. Ongoing work is a rolling operation and is talking pace i a
th to north dnton,
Project Overview ad ere+ta The Coty ot Morr each wet start sod weak, urt and gutter restoration ori no Dr»t tenue ben 12Street and 13s4net to prove onet 9rd asphalt surface tor0tons.. Dor@ged sodewalk, urps ad gutters along ths section of roadway wit be renewed toe better and sates mobwdty
what' Mew The oty's ontrator, Metro Espress, wot tart on the wet htt et tt road niating draged ode wat, rurt and gutter area and tten mono an0 resurfacong the eavrrnt t Draei Ana, That hot ot the rod folio to merit the job Sae rage hgght for work ara. During woe# hours, re,dents and guest« wadi have res to theer proper tea,, tooter, work ray tnrparty bi ne rtr ance, ad ot« and parking $potes i the voity
Projet Oerview and enefit he Coty t Mari beach wit ontine G0. Bond rot +3, which irkdes concrete curb adments and restrerg work n Meridian were between I6 Street ad17 Street. Thia wt wt make t easier to identity roadway secties and improve the saety ard oran«aaton et mobetty on
the rod.
what Mew feotys ontractor, Metro Express, wt taet restripng from 16 Street heading north At the ere time tenet be ongoing. concrete d,streets starting at 12 Sueet wor iurn south, Pease note hotted work zone on the repo. teses to popertes nd hopes wet nerain open t
put tan; however, parking is in the area wet be restricted during onstructon wk Test
roboty ire oererti wtetiriate pub street par king going toewad an Merdian #ere between !2"::"%%.::re
DocuSign Envelope ID: 0C1778CC-75A4-4C2C-B90C-8A7498693107
NEWS ANNOUNCEMENTS
Press Release: Construction Set to
Begin on Final Segment of
Beachwalk
Dec 21, 2020
Construction is set to begin in early 2021 on
the final segment of the Beachwalk, a more
than 7-mile oceanfront promenade that will
span the entire length of the city from South
Beach through North Beach ...
Read More
Construction Advisory! Meridian
Avenue Pavement Striping
Nov 30, 2020
Work on Meridian Avenue starts Monday
November 30, and is expected to last one
week. The city's contractor, Metro Express,
will start re-striping from 16 Street heading
north ...
Read More
AECOM Releases Survey Results for
the 41 Street Corridor Streetscape
Project!
Oct 22, 2020
After a public meeting that was held on 10/1
and a one-week-long open feedback session
that followed, AECOM has presented final
survey results for streetscape preferences ...
Construction Update! Middle Beach
Beachwalk
Dec 17, 2020
The City of Miami Beach continues work on
the Beachwalk project between 24 and 45
streets, including 11 street ends...
Read More
Construction Advisory! Drexel Ave.
Street Pavement!
Nov 5, 2020
Work on Drexel Avenue starts Monday,
November 9 and is expected to last
approximately two weeks, one for each side.
The city's contractor, Metro Express, will start
on the West halt of...
Commission Memo: GO#40: 41
Street Corridor Conceptual
Streetscape Design
Dec 7, 2020
AECOM and city staff will be requesting
approval from the Mayor and City
Commission on December 9 2020, for the
41 st Street Corridor conceptual streetscape
design ...
Read More +
Construction Advisory! 12 Street
Pavement
Nov 5, 2020
The City of Miami Beach will start asphalt
restoration work on 12 Street between
Michigan Avenue and Alton Road. The road
will be milled and resurfaced for better and
safer mobility, creating a smooth new ...
Read More -+ Read More +
Program Team to Present to MB
Chamber of Commerce
Construction Council
Oct 19, 2020
The Miami Beach Chamber of Commerce
Construction & Development Council will
hear a presentation, followed by discussion,
with the Program Team...
Read More Read More +
OocuSign Envelope ID: 0C17780C-75A4-4C2C-B90C-8A7498693107
MEETINGS
YOUR VOICE, IN ACTION!
e # October 2020
COUNCIL MEETING
GO BOND PROGRAM
UPDATE & DISCUSSION
3 7qEz2Ag ass2-.sis.3a3
Tuesday, October 20, 2020
8:00 AM - 9:00 AM
[3 a or or cenarono « oc«on coi
] eolr Mark Gerignani (Dominion Builders) and Vice Chair
Jeovan Tllit (East of Collins Expediters), we inte you to join
us for our monthly council meeting to learn more about
the updates happening with the GO Bond Program
Overview ot the $439 rtt+on Genera! Obligation
Status update on Tranche 1Program
-Projects What is coming down the pipeline?
SPEAKERS
MARIA HERNANDEZ ALLISON NOVACK
G.O. BOND DOCRAM DICTO GO. RONDO QOCRAM
CITY OF MIAMI BEACH INFORMATION MANAGE
CITY OF MIAMI BEACH
MIAMI BEACH
MEETING ID: 838 8649 6532
Register in Advance tor this Zoom Meeting
tter tegistoting,you ti noise an rat with more information n how
to join the rating
Virtual Public Meeting: 41 Street Corridor Revitalization Project
October 1 @5:00 pm-6:30 pm
This is a public meeting that AECOM is co-hosting with the City of Miami Beach to present
potential schematic design options for GO#40: 41 Street Corridor. See HERE for more
information on the city's main website. Zoom Webinar Link: https://miamibeachf\-
gov.zoom.us/j/81283775765 Telephone: US: 877 853 5257 (Toll Free) Webmnar ID: 812 8377
5765
Find out more »
~ G.O. Bond Presentation: Miami Beach Chamber of Commerce
Construction & Development Council Meeting
October 20 @8:00 am -9:00 am
find out more »
G.O. Bond Oversight Committee Meeting
October 22 @ 4:30 pm - 6:30 pm
SEE AGENDA htpp://zoom _us/i/91749157894 Access ID 91749157894# 1.929.205.6099 or
1.301. 715.8592 Access ID 91749157894#
Find out more »
December 2020
G.O. Bond Oversight Committee Meeting
December 17 @4:30 pm- 6:30 pm
To join the meeting: https://us02web.zoom.us /j/94174823571 1.301.715.8592 Access ID:
94174823571# SEE AGENDA
Find out more »