South Shore Community Center_September 1969 to June 1970SOUTH SHORE COMMUNITY CENTER 9
Meeting date
Motion passed holding ground-
breaking 9-23-69, inviting HUD and'local
officials, no public funds to be used for
HUD transportation;
Construction to commence by 9-11-69.
Demolition contract to Big Chief
for $3129. (bldgs.on 2 lots)
Liquidated damages clause in contract
for Center, increased from $150 to $400
daily.
9-10-69
9-10-69
10-15-69
12-15-69
SOUTH SHORE COMMUNITY CENTER 10
Meeting date
Demolition contract to Big Chief Inc.,
$2890.
12-17-69
Bids rejected, readvertising authorized;
Lapidus bid letters filed with minutes. 2-4-70
RES. 12942 purchasing Lot 6 from Freida )
DeHaav for $39,500 plus atty's. fee $2000 )
and $830 to S.Z.Bennett. )
RES. 12943 purchasing Lot 10 from M/M )
Esquenazi for $55,000 plus atty.fee $2750 )
and $1155 to Bennett. )
RES. 12944 purchasing Lot 11 from M/M )
Feins for $38,500 plus atty.fee $3400 and )
$838 to Bennett. )
2-4-70
SOUTH SHORE COMMUNITY CENTER
Rebidding for construction to proceed
immediately.
City Atty to render opinion re Avant
Construction Co.
11
Meeting date
Construction bids received, exceed
funds; Adm. to review with architect.
....City Mgr. reported con-
struction not feasible; if plans changed,
Govt. has to reevaluate grant; Messrs.
Toal, Lapidus to go to Atlanta, discuss
with govt.; on their return,spec. meeting
called; discussion re City as genl.contrac-
tor, establishing Contracting Div.,etc.
3-20-70
5-6-70
5-13-70