Theater Of The Performing Arts_August to September 1975THEATRE OF PERFORMING ARTS 24
Date
Discussion held on agreement with Gard Pro- 8/6/75
ductions (Zev Bufmanj for presentations in
The Theatre of Performing Arts. Action de-
ferred to 8/7/75, at 4:00 p.m.
Memo #5284, Res. #75-14809 adopted, awarding 9/3/75
contract for orchestra lift to Flite Line
Equipment Corp., quoting $79,750.00 plus
installation add-on charges, if required, of
up to $1,600.00.
THEATRE OF PERFORMING ARTS 24A
Date
Authorizing execution of agreement with Gard 8/6/76
Productions (Zev Bufman) for presentations in
TOPA. Discussion held on agreement, action
deferred to 8/7/75, at 4:00 p.m.
Revised agreement reviewed. Res. :175-14787 8/7/76
adopted, authorizing execution of agreement.
THEATRE OF PERFORMING ARTS 25
Date
Memo #5285, accousitcal shell award.'ed, Hart 9/3/75
Scenic Studio, Inc., quoting $36,550.00
Memo #5286, memory lighting system. Objections 9/3/75
raised by unsuccessful bidder re: bidding pro-
cedures. City Atty. advised that bidding pro-
cedures were proper and that award, as recom-
mended, was in order. Res. #75-14799 adopted
awarding contract to Strand Century, quoting
$49,800.00.
Memo #5299, estimated expenditure of $50,000 9/3/75
for replacing air cooling system„ approved,
Account W.O. 2610-11, BFPB 81