Sewage Disposal And Treatment_January 1980 (3)SEWAGE DISPOSAL AND TREATMENT
Memo #7977, Contract R for facilities for
transmitting sewage to Va. Key, P-19, Change
Order No. R-31, (additional work) amount:
increase $9,735.11, extension of time: None,
approved. (See Sewage Transmission Facilities
(Contracts))
Memo #7978, Contract R for facilities for
transmitting sewage to Va. Key, P-19, Change
Order No. R-32, (additional work), amount:
increase $25,000.00, extension of time: 360
days, approved. (See Sewage Transmission
Facilities (Contracts), ParkView Island
Memo #7989 entry, this date)
SEWAGE DISPOSAL AND TREATMENT
Memo #7979, Contract R for facilities for
transmitting sewage to Va. Key, P-19, Change
Order No. R-33, (additional work) amount:
increase $69,832.88, extension of time: None,
approved. (See Sewage Transmission Facilities
(Contracts))
Memo #7980, Contract S for facilities for
transmitting sewage to Va. Key, P-19, Change
Order No. S-14, (additional work), amount:
increase $6,792.00, extension of time: None,
approved. (See Sewage Transmission Facilities
(Contracts))
SEWAGE DISPOSAL AND TREATMENT
Memo #7981, Contract S for facilities for
transmitting sewage to Va. Key, P-19, Change
Order No. S-15, (decrease in contract) amount:
decrease $4,514.00, extension of time: None,
approved. (See Sewage Transmission Facilities
(Contracts) )
Memo #7982, Contract S for facilities for
transmitting sewage to Va. Key, P-19, Change
Order No. S-16, (additional work), amount:
Increase $928.00, extension of time: None,
a roved. (See Sewage Transmission Facilities
Contracts))