Library (North Shore Branch) Contracts_June 1975 to November 1976LIBRARY (NORTH SHORE BRANCH) CONTRACTS 3
(cont'd) Date
performance bond and had not executed their
contract within the prescribed time, and had
therefore forfeited their rights. 6/18/75
Memo #5225, construction of N. Shore Branch
Library, PB -87, awarded John Demirjan, d/b/a
J. D. Construction Co. quoting $192,000.00.
Appropriation of $250,000 from 11/6/73 Bond
Issue, approved.
Public Works Director put Council on notice
that contract extension may be required in
connection with construction of North Shore
Library in view of delay in delivery of
special glass for this project, and advised
7/16/75
6/16/76
LIBRARY (NORTH SHORE BRANCH) CONTRACTS 4
(continued) Date
that he will be submitting a report to Council. 6/16/76
Memo #5762, purchase of library shelving under 6/16/76
GSA contract for No. Shore Branch Library,
awarded, Newton Seating Co., quoting $13,785.14.
Memo #5797, purchase of library charging desk 7/21/76
under GSA contract for N. Shore Branch Library,
awarded, Brodart, Inc., quoting $4,119.25 to be
paid from Library bond issue.
Memo #5816, change order #1, for N. Shore Branch 7/21/76
Library, PB -87, approved as follows: extension
of contract 79 days from 3/27/76 to 6/14/76.
LIBRARY (NORTH SHORE BRANCH) CONTRACTS 5
Date
Memo #5874, furniture for new library facility 9/15/76
at No. Shore, awarded, Long's, Miami, quoting
$7,188.00, (which includes $116.00 for inside.
delivery), to be funded from No. Shore Library
Project Bond Fund.
Mr. John DeMirjian, contractor for this project, 11/24/76
appeared and advised he was unable to resolve
certain problems because there is a contradic-
tion in his contract with respect to whether the
architect for this project, or the Public Works
Director, is the final authority in settling
disputes concerning his work. City Atty. di-
rected to set up meeting forthwith with the
contractor and appropriate representatives of
Administration, the architect and the Public