Loading...
Library (North Shore Branch) Contracts_November 1976 to April 1977LIBRARY (NORTH SHORE BRANCH) CONTRACTS 6 (continued) Date Works Director, to resolve the situation. 11/24/76 North Shore Branch Library, MP-87 4/6/77 2.a. Memo #6272, (additional charges and con- tract summary); amount: increase contract with architect by $5,063.60, approved. Administration's recommendations approved, and 1) City Atty. authorized to notify the contractor's bonding company to either take over and complete the project, or the City will complete it and assess damages at a later time; 2) $5,063.60 in- crease in contract with Architect for extra services, to be considered as damages against the contractor together with any liquidated damages incurred for failure to complete the