Sewage Transmission Facilities (Contracts)_November 1978SEWAGE TRANSMISSION FACILITIES (Contracts) 24
Date
Memo #7171, Contract N for facilities for 11/1/78
facilities for transmitting sewage to Va. Key,
P-19, Change Order No. N-12 (additional work),
amount: increase: $6,888.25, extension of time:
none, approved.
Memo #7172, Contract 4 for facilities for trans- 11/1/78
mitting sewage to Va. Key, P-19, Change Order
No. 4-10 (additional work), amount: increase
$27,002.90, extension of time: none, approved.
Memo #7173, Contract 4 for facilities for 11/1/78
transmitting sewage to Va. Key, P-19, Change
Order No. 4-11 (additional work) amount:
increase $11,546.41, extension of time:
SEWAGE TRANSMISSION FACILITIES (Contracts) 25
(continued) Date
none, approved. 11/1/78
Memo ##7174, Contract 4 for facilities for 11/1/78
transmitting sewage to Va. Key, P-19, Change
Order No. 4-14, (additional work) amount:
increase $6,290.84, extension of time: none,
approved.
Memo #7199, Contract S for facilities for trans- 11/15/78
mitting sewage to Va. Key, P-19: Change Order
No. S-12, (additional work), amount: increase
$640.75, extension of time: none, approved.
Memo #7200, contract N for facilities for 11/15/78
SEWAGE TRANSMISSION FACILITIES (Contracts) 26
(continued) Date
transmitting sewage to Va. Key, P-19: Change
Order No. N-14, (additional time and work),
amount: increase $679.73, extension of time:
2 days, approved. 11/15/78
Memo #7201, contract R for facilities for 11/15/78
transmitting sewage to Va. Key, P-19: Change
Order No. R-26, (additional work), amount:
increase $2,630.22, extension of time: none,
approved.
Memo #7202, contract N for facilities for
transmitting sewage to Va. Key, P-19: Change
Order No. N-13, (additional time and work),
amount: increase $2,805.00, extension of
11/15/78