Sewage Transmission Facilities (Contracts)_March to June 1979SEWAGE TRANSMISSION FACILITIES (Contracts) 30
Date
Memo #7376, Contract N for facilities for 3/7/79
transmitting sewage to Va. Key, P-19, Change
Order No. N-11, additional time and work
amount: increase $169,443, extension of time:
21 days, approved.
Memo #7465, contract for breakwater for M.B. 4/25/79
Marina, MP -36, Change Order No. 3, additional
work, amount: increase $1,000.00, extension of
time: none. A roved, funds to be appropriated
from EDA grant. See Sewage Disposal and Treat-
ment)
SEGfACE TRANSMISSION FACILITIES (Contracts) 31
Date
Memo #7503, Contract 6A for facilities for 5/16/79
transmitting sewage to Va. Key, P-19, Change
Order No. 6A-3, (decrease in contract), amount:
$1,387.50, extension of time: none. Approved.
(See Dewage Disposal and Treatment)
Memo #7554, Contract 1 for facilities for trans- 6/20/79
mitting sewage to Va. Key, P-19, Change order
No. 1-3, increase in contract, amount: increase
$1,492.21, extension of time: none, final change
order, approved.
Memo #7555, Contract 2 for facilities for 6/20/79
transmitting sewage to Va. Key, P-19, Change
SEWAGE TRANSMISSION FACILITIES (Contracts) 32
(continued) Date
order No. 2-2, decrease in contract, amount:
decrease $28,772.00, extension of time: none,
approved. 6/20/79
Memo #7556, Contract 2 for facilities for
transmitting sewage to Va. Key, P-19, Change
order No. 2-3, amount: none, extension of time:
110 days, final change order, approved.
Memo #7557, Contract R for facilities for
transmitting sewage to Va. Key, P-19, Change
order No. R-29, additional work, amount; in-
crease $50,535.46, extension of time: 308
days, approved.
6/20/79
6/20/79