Sewage Transmission Facilities (Contracts)_June to September 1979SEWAGE TRANSMISSION FACILITIES (Contracts) 33
Date
Memo #7558, Contract R for facilities for trans- 6/20/79
mitting sewage to Va. Key, P-19, Change order
No. R-30, extension of time: 126 days, amount:
none, approved. (See Sewage Disposal and Treat-
ment)
Memo #7684, Contract 3 for facilities for 9/5/79
transmitting sewage to Va. Key, P-19; Change
Order No. 3-10 (additional work); amount:
increase $753.95 approved.
Memo #7685, Contract 3 for facilities for 9/5/79
transmitting sewage to Va. Key, P-19; Change
Order No. 3-11, (additional work); amount:
increase $26,000.00
approved.
SEWAGE TRANSMISSION FACILITIES (Contracts) 34
Date
Memo #7686, Contract 3 for facilities for 9/5/79
transmitting sewage to Va. Key, P-19; Change
Order No. 3-12, (additional work) amount:
increase $2,365.20 approved.
Memo #7687, Contract 3 for facilities for 9/5/79
transmitting sewage to Va. Key, P-19; Change
Order No. 3-13; (additional work and time)
amount: increase $16,343.84; extension of
time: 59 days, approved.
Memo #7688, Contract 3 for facilities for 9/5/79
transmitting sewage to Va. Key, P-19; Change
Order No. 3-14; (decrease in contract) amount:
SEWAGE TRANSMISSION FACILITIES (Contracts) 35
(continued) Date
decrease ($60,693.50); extension of time:
none, approved. 9/5/79
Memo #7689, Contract 3 for facilities for 9/5/79
transmitting sewage to Va. Key, P-19; Change
Order No. 3-15; (additional work and time)
amount: increase $20,850.00p extension of
time: 590 days, approved.
Memo #7690, Contract 4 for facilities for 9/5/79
transmitting sewage to Va. Key, P-19; Change
Order No. 4-16, (additional work), amount:
increase $10,568.03; extension of time: none,
approved.