Council deferred discussion of placement of
bond issue to afternoon session; however,
matter was not reached. City M rcL to submit
recommendations on 9/23/77.
3
Date
Memo #4833A revised, discussion of bids for 11/20/74
Theatre of the Performing Arts, Res. #74-
14546 adopted, authorizing execution of con-
tract with Edward L. Nezelek, Inc., low bid-
der meeting specifications, in the amount of
$4,795,760.00.
Contract to include provision that architect
shall be final arbiter in all disputes arising
between City and Contractor.
THEATRE OF PERFORMING ARTS Contracts) 4
(cont'd) Date
Funding as recommended by City Mgr. in
Council Memo #4833(B) approved.
City Atty. rendered opinion that trans-
formation of Aud. into Theatre of Per-
forming Arts falls within the intent of
the electorate in approving the $4 mil-
lion, April 23, 1970 Bond Issue. 11/20/74
Memo #5044, Theatre of the Performing Arts,
PB -81, Change Order #1, decreasing contract
$2,500. Deferred to 3/19/75. Architect re-
quested to report on differences between
critical path method schedule and construc-
tion progress schedule and why the former
was required in original specifications.
3/12/75
THEATRE OF PERFORMING ARTS (Contracts) 5
Date
Memo #5044, Theatre of Performing Arts,PB-81,
Change Order ##1, decreasing contract in the
sum of $2,500 (deferred 3/12/75) approved. 3/19/75
Memo #5061, Theatre of Performing Arts,PB-81,
Change Order #2, decreasing contract in the
sum of $28,750 approved. 3/19/75
Additions and alterations to Concession Area 6/4/75
of Theatre of Performing Arts, revision Memo
#3104-C, deferred to June 18, 1975 for full
Council.
Memo #5208, Theatre of Performing Arts, Change 6/18/75
Orders Nos. 4,5, & 6, in the amount of $8,468.00