Convention Hall Contracts_March to June 1968CONVENTION HALL CONTRACTS
11
BOOK PAGE
to Dade Steel Corp. in excess of original
contract price. City Manager to draft letter
to architect re. justification for payment of
fees at time of final accounting. 3-20-68 53 79
Contract awarded to Maule Industries, pit
rock for parking area adjacent to Expansion
for $9,400. 4-3-68 53 113
Change orders 38-42 approved to Millman
Construction Co. for Addition --increase of
$3,739. 4-3-68 53 113
CONVENTION HALL CONTRACTS
Change orders #43-46 approved to Millman Con-
struction Co. --increase of $4,790.97. 4-17-68 53 148
Change order #47 to Millman Construction Co.
for Expansion approved --increase of $305.90.
5-1-68 53 170
Change orders #48-52 to Millman Construction Co.
for Expansion --increase of $19,343.36 approved.
5-15-68 53 203
Recommendation approved to authorize Millman
Construction Co. to construct additional toilet
facilities at cost of $56,539 ($25,000 pre -
12
BOOK PAGE
CONVENTION HALL CONTRACTS
viously committed by TDA & $31,439 as committed
by Administration). 5-27-68 53 208
Change orders #53 & #54 to Millman Construction
Co. for Expansion approved --decrease of $327.25.
6-5-68 53 234
Bids for construction of storage building for
Convention Hall rejected. Manager advised of plans
for use of pre -fab buildings being supplied at no
cost to City. 6-26-68 53 266
Contract for awning canopy entrance to Hall
awarded to Thomas Awnings for $9,018.86. 6-26-68 53 268