Convention Center (Contracts)_October 1973 to April 1974CONVENTION CENTER (Contracts)
Memo 4212 2 changes in wraparound construction:
increase in minimum height of loading deck &
installation of 2 elevators.
25A
Date
10/3/73
Memo #4300, emergency installation of electrical 11/21/73
equipment & transformers for Conv. Hall Wrap-
around vaults - approved, Nat Harrison Assoc.,Inc.,
complete required installations in view of emer-
gency situation existing, on a time and material
basis, estimated cost, approx. $75,000.
Memo 4330, approval of construction, Conv. Hall 12/19/73
Wraparound, BFRTPB-53, addition #2, Change Order
#3, increase by $2,107.49.
CONVENTION CENTER (Contracts) 26
Memo 4330 (continued) increase by $2,107.49. 12/19/73
Memo 4401 Stage intercommunication system for
Conv. Center bids rejected. To be rebid at
Administration's direction.
Discussion of additional cost for construction
of convention hall wraparound due to FPL strike.
Additional expenditure of $150,000 authorized,
to be budgeted in 1974-75 Budget, to be paid to
Gust K. Newberg Construction Co., to assure
(continued p.26)
2/20/74
CONVENTION CENTER (Contracts)
completion of Wraparound by 10/1/74. City Mgr.
to obtain statement in writing, to the effect
that additional payment will not be made if
10/1/74 completion date is not met.
:: Memo #4481, Change Order No. 4, approved for
increase of $20,227.05 for const-ru ti-onof
M.B.tConv#2 Hall Wraparound, BFRTPB-53,
AddMemo 4494 13,900 stacking,ganging chairs for
Convention Center. Bidgs rejected & re -
advertisement authorized.
27
3/20/74
4/3/74
4/17/74
*(Change orders Nos. 2 & 5 - no record - 11/14/74)