Convention Center Contracts_September to December 1974CONVENTION CENTER CONTRACTS 33a
119.21L22 _221.2.
Discussion of change order with Gust Newberg 9/4/74
& Co. regarding assured completion date &
substitution of American Air Filter equip-
ment for Cosa/Tron equipment for Conv. Center
Wraparound. Matter continued to 9/11/74
meeting. Admin. requested to ask the architect,
Mr. Mike Deutschman, to be present.
Discussion held of Change Order with Gust
Newberg Co. regarding assured completion date
& substitution of American Air Filter equip-
ment for Cosa/Tron equipment for Conv. Center
Wraparound. Architect Mike Deutschman present.
Admin. requested to submit firm recommendations
9/11/74
CONVENTION CENTER (CONTRACT
estimated expenditure of $100,000.00.
Memo #4775, Change Order No. 12, approved, 10/2/74
Wraparound BFRTPB-53, addition #2, $13,607 41
increased contract to $11,363,885.72. This
covered Bulletins Nos. 81,83,84,87,88,89,
90,91,92,93,and 95.
34
Meeting Date
Memo #4785, 220 Dollies for storage of
folding chairs for Conv. Center, Bid No.
138-74, awarded B. & B. Welding & Machine
Service, Inc., quoting $26,840.00.
10/16/74
CONVENTION CENTER (CONTRACT L 35
Date
Memo #4892, Construction of Garden Center 12/18/74
entrance walk for landscaping of Conv. Hall
Wraparound, MP -71, awarded, C. A. Davis, Inc.,
quoting $7,225.00.
Memo #4905, construct MB Conv. Hall Wrap- 12/18/74
around, BFRTPB-53, Addition #2, Change
Order No. 13, increase of $56,959.55
approved.
Memo #4913, construct MB Conv. Hall Wraparound, 12/18/74
BFRTPB-53, Addition #2, change order #15 to
provide removable gates for crowd control for
North and South lobbies, increase of $33,077.20,
approved. From addendum.