Sewage Disposal And Treatment_February 1979 to April 1979SEWAGE DISPOSAL AND TREATMENT 99
Date
Memo #7329, Contract 6A for facilities for trans- 2/7/79
mitting sewage to Va. Key, P-19; Change Order
No. 6A-1, deletion of work, amount: decrease
-$75,572.00, extension of time: none, approved.
(See Sewage Transmission Facilities (Contracts))
Memo #7330, Contract R for facilities for trans- 2/7/79
mitting sewage to Va. Key, P-19; Change Order
No. R-27, additional work, amount: increase
$330.00, extension of time: none, approved.
(See Sewage Transmission Facilities (Contracts))
Memo #7331, Contract R for facilities for trans- 2/7/79
mitting sewage to Va. Key, P-19; Change Order
No. R-28, additional work, amount: increase
SEWAGE DISPOSAL AND TREATMENT 100
(continued) Date
$691.15, extension of time: none, approved.
(See Sewage Transmission Facilities (Contracts) 2/7/79
Memo #7352, Contract 6A for facilities for 2/21/79
transmitting sewage to Va. Key, P-19, Change
Order No. 6A-2, decrease in contract, amount:
decrease -$2,700.00, extension of time: none,
approved. (See Sewage Transmission Facilities
(Contracts))
Memo #7353, Contract 5 for facilities for
transmitting sewage to Va. Key, P-19,Change
Order No. 5-2, additional work, amount: in-
crease $9,931.25, extension of time:
2/21/79
SEWAGE DISPOSAL AND TREATMENT 101
(continued) (See Date
one, approved./ Sewage Transmission Facilities
(Contracts)) 2/21/79
Memo #7376, Contract N for facilities for 3/7/79
transmitting Sewage to Va. Key, P-19, Change
Order No. N-11, additional time and work,
amount: increase $169,443, extension of time:
21 days, Laproved. (See Sewage Transmission
Facilities (Contracts))
Memo #7465, contract for breakwater for M.B. 4/25/79
Marina, MP -36, Change Order No. 3, additional
work, amount: increase $1,000.00, extension of
time: none. Approved, funds to be appropriated
from EDA grant.(See Sewage Trans. Facilities Contracts)