L.T.C. No. 198-1999
LETTER TO COMMISSION
--,
October 6, 1999
TO:
The Honorable Mayor Neisen O. Kasdin
and Members :;;JOf the CitY. Commission
Sergio Rodriguez '
City Manager
eeT t I
FROM:
SUBJECT: STATUS OF ADDITIONAL SWIM LANES FOR FLAMINGO POOL
This is in response to the direction given by the City Commission at the September 17, 1999
meeting, concerning the above referenced subject. Specifically, the City Commission directed the
Administration to take the following actions:
· Review the current proposal for Flamingo Park pool to include an additional four swim
lanes.
· Include the cost of this enhancement, approximately $400,000, in the proposed General
Obligation Bond to be presented to the voting residents on November 2, 1999.
· Submit a proposal to the Miami-Dade County Safe Neighborhood Parks Bond Program
requesting an additional $400,000 for the Flamingo Park pool project and develop a third
alternative to finance the cost of the swimming pool expansion.
· Suggested that in the interim time period, the planning and design process for the additional
four lanes be started.
· Proceed with the Normandy Isle Park pool as originally presented.
In response to these directives, the Administration has initiated the following actions:
· Suspended all work on this park bond project until possible alternatives for funding sources
are explored.
. Included the additional $400,000 in the proposed General Obligation Bond to be presented
to the voting residents on November 2, 1999.
. Submitted a request to the Safe Neighborhood Parks Oversight Committee on September 12,
1999 (see attached copy). The Oversight Committee met on September 27,1999 to discuss
the distribution of approximately $3.75 million available in current and future interest
earnings. Included in this discussion was the City's Flamingo Pool request. In addition to
the City's request for $400,000 for the Flamingo Pool, there were requests from Miami-Dade
County presented by County Manager Merrett Stierheim, seeking $3 million for the purchase
of the Miami Circle, the City of Miami seeking $235,000 per year for a three (3) year period
to hire additional professional staff to assist in the implementation of their Safe
Neighborhood Park Bond funded programs, as well as a request from Shake-A-Leg sailing
program for the Disabled asking for $300,000 to complete the construction of their facility
located in the City of Miami's Virrick Gym.
Kevin Smith presented the City's request, explained the need for the additional lanes, as
expressed by citizens of Miami Beach, and showed the Oversight Committee full color
renderings of the Flamingo Pool and another depicting the additional four (4) lanes.
Additionally, Mr. Peter Luria, a resident and swimmer at the Flamingo Pool addressed the
Committee expressing the need for the additional four (4) lanes and the interest of the
community to see this addition take place. When considering the City of Miami Beach's
request, the Chairman stated that the City of Miami Beach had a valid need but also has
resources, so if the Committee supported funding the City, it should be for $200,000 as a
challenge to the City Commission to match the award with the remaining $200,000 needed
to construct the four (4) additional lanes.
Following the presentations, the Oversight Committee deliberated briefly and voted to award
Miami-Dade County $3 million for the Miami Circle and the City of Miami $235,000 to hire
staff for a one year period. The Committee also stated the continuation for year two of the
funding was contingent upon Miami's performance in the first year.
After allocating $3,235,000 of the estimated $3,750,000 available, the Committee
Chairman made a statement that although the Shake-A-Leg and City of Miami Beach projects
were worthwhile, it is very important that the Oversight Committee keep in mind the need
to be fair and equitable to all potential organizations that might also wish to submit an
application for additional funding and to ensure the Committee's process and creditability
is maintained, the remaining two requests should be deferred until a notice is sent out to the
over sixty (60) eligible organizations and municipalities advising them of the available
funding. The Committee voted to support this action.
Accordingly, the Safe Neighborhood Parks Program office will be mailing notices of the
grant application process to all potential applicants on October 8, 1999. The applications
will be due on November 15, 1999, and the allocations deliberations held at the Safe
Neighborhood Parks Oversight Committee meeting of December 6, 1999. It is currently
estimated that there will be a maximum of $750,000 available to fund all the requests for
support. The City of Miami Beach will submit an application seeking $400,000 for the
additional lanes.
. The Administratiun met with representatives of the swimmers group who initiated the
request for additional lanes on October I, 1999. Input for expanding the pool and modifying
the plan to better meet the needs of both competitive and recreational swimmers was the
focus of the discussion. A consensus was reached that if funding is available, an additional
four (4) lanes would be added and will include starter blocks and backstroke flags. It was
also agreed upon that the inclusion of a water cooling system would be studied. It was
clearly understood that no architectural design work will be done until such time as funds are
identified for the additions and a final direction is determined.
. The Normandy Isle Pool project is progressing as planned and the bids will be issued upon
the completion of the permitting process.
. If the additional funds are not identified via the General Obligation Bond or the Safe
Neighborhood Parks Bond Program by December 6, 1999, the Administration will bring this
item back to the City Commission for further discussion and direction.
We will keep you apprised of progress in this matter and should you have questions or concerns,
please advise.
SRJ~s/eb
c: Janet Gavarrete, Assistant City Manager
Matthew Schwartz, Assistant City Manager
Christina Cuervo, Assistant City Manager
Kevin Smith, Director, Parks and Recreation
Julio Grave de Peralta, Director, Public Works
Odalys Mon, Special Projects Coordinator
Michel Maglorie, Projects Manager
M:\$CMB\TEMP\FLGOPOOL.L TC
CITY OF
MIAMI BEACH
~
CITY HALL 1700 CONVENTION CENTER DRIVE MIAMI BEACH FLORIDA 3313!:i
OFFICE OF THE CITY MANAGER
TELEPHONE: (305) 673-7010
FAX: (305) 67::1-7782
September 10, 1999
Hank Adorno, Esq.
Chairman
Safe Neighborhood Parks Bond Oversight Committee
111 NW 1st Street, Suite #1740
Miami, FL 33128-1974
Dear Mr. Adorno:
The City of Miami Beach was initially awarded $1 Million dollars from the Safe Neighborhoods
Park Bond for pool renovations at various City facilities. The City then requested that the entire $1
Mil be allocated to the Flamingo Pool Facility in order to simplify the accounting process, with the
understanding that the other pools would be done with funds from our City's 0'Wll $15 Mil Parks
General Obligation Bond.
As of August 12, 1999, the new multi-use recreational pool for Flamingo Park is 100% designed and
the project is ready to be bid. In completing this process, the City has received additional input from
the community, requesting that four additional swimming lanes be added to the current pool design.
The Administration requested that the architect for the project (Corradino) provide new cost
estimates, incorporating the request of the citizens. (Please see attached cost estimates.) This
additional work will cost approximately $400,000.
In order to construct the pool facility now being requested by the citizens of Miami Beach, it is .
formally requested that the Safe Neighborhoods Parks Bond Oversight Board allocate an additional
amount of $400,000 to complete this project. To date, the City has only received $100,000 in
interest dollars for playground equipment at several parks. It is requested that you please bring this
matter to the Board's attention at the September 14, 1999 meeting. Please excuse me for not
personally presenting this matter to the Board, but unfortunately, I have a conflict due to the fact that
our City Commission meeting is scheduled for the same day. At the request of the Mayor and
Members of the City Commission, a discussion item related to this issue has been scheduled at this
September 14th meeting.
.. --,-- ....,
Thank you in advance for your attention to this important matter. We look forward to a positive
response from the Board.
Sincerely,
~\\5
gio Rodriguez
City Manager
c: Mayor and Members of the City Commission
Janet Gavarette, Assistant City Manager
JCevin Smith;: Director; Parks'&, Recreation Dept.
Odalys ~1on, Special Projects Coordinator
SRJ&KS:OD:eb
F;IRCP AISAllIOOIFLAMl'OQL.ADR
--....- --.---~- .
. City of Miami Beach
· FLAMINGO POOL
Re: MODlFICATIONS- ADDITIONAL A / E SERVICES
September 3, 1999
Corradino No. 1979
SCOPE OF SERVICES
The scope of services sholl consist of modifying the currently approved design and contrad documents for the
above-referenced projed to include on additional 2 (two) or 4 (four) lanes to the proposed lop pool.
Expansion of the lop pool and pool deck will require substantial modifications to the overall pork site plans and
pool facility plans..as outlined below. The effort associated with the re-submittal of design plans to the Design
Review Board may be required and is included as a separate item.
REQUIRED MODIFICATIONS
1. OVERALL PARK
A. ARCHITECTURAL
1. Overall Pork Site plan
2. New basketball court floor plan
B. CIVIL
1. Demolition plan
2. Site Geometry plan
3. Paving, Grading and Drainage
4. Drainage Calculations
C. LANDSCAPE
1. Planting plans and details
2. Irrigation Plan
2. POOL FACILITY
A. ARCHITECTURAL
1. Pool Facility overall plan
2. Building floor plans
3. Enlarged detailed floor plans
4. Building Elevations'
5. Building Sedions
6. Signage Plan
B. CIVil
1. Pool Deck Drainage
C. STRUCTURAL
1. Pool deck and framing plan
2. Ground floodroming plan
3. Roof framing plan
4. Building Sections
.-..-.....-..
City of Miami Beach
FLAMINGO POOL: MODIFICATIONS - COMPARATIYE PROJECT SCHEDULE
September 3, 1999
Corradino No. 1979
PHASE: CURRENT SCHEDULE MODIFIED SCHEDULE
City of Miami Beach (CMB) issue NTP TO CORRADINO for Pool Modifications Sept. 14, 1999
CORRADINO Submit Revised Design Plans for City Staff Review & Approval Sept.28, 1999
100 % Construction Documents Submittal for City Staff and Permit Review Nov. 16, 1999
CMB issue Staff / Permit Review comments Nov. 30, 1999
CORRADINO complelF! incorporating City Staff and Permit Review Comments Dec. 14, 1999
Commence Bidding Sept 19,1999 Dec. 20, 1999
Bids Due Oct 19,1999 Jan.26, 2000
Bids Analysis and recommendation Oct 25,1999 Feb. 2, 2000
Contractor Selection /Commission Approval/Execute Contract Nov 15,1999 Feb. 16, 2000
Construction Start (7 months) Nov 23,1999 Feb. 24, 2000
Construction finish June 23, 2000 Sept. 25, 2000
Project Close-out July 23, 2000 Oct. 25, 2000
Note: The above schedule is based eMB Planning staff granting Administrative Approval for modifications to the
P~oI facility as required for additional lanes in the lap pool. In the event that submission of revised design plans
are required for ORB submittal, we estimate the preparation of the design documents and the submission /
approval process for the ORB to be approximately 10 weeks. This would affect the overall Modified Schedule
and the revised projed close-out date would become December 8, 2000.
,,'
J:\ 1979\Flamingo\Word\CMB FLAMINGOMODIFICATlON SCHEDUlE.doc
City of Miami Beach
. FLAMINGO POOL: MODIFICATIONS COMPARISON
September 3, 1999
Corradino No. .1979
flTEM 4 LANES (PROPOSED) 6 LANES B LAN E
LAP POOL AREA I 2458 S.F. 3058 S.F. /4558 S.F.
LAP POOL VOLUME I 93,600 GAL 138,128 GAL /179,492 GAL
LAP POOL SIZE I 35 FT X 75 FT 49fTX 75 FT I 63 FT X 75FT
POOL DECK AREA 116,000 S.F. /17,792 S.f. /19,548 S.F. I
BATHING LOAD /52 PERSONS /76 PERSONS /99 PERSONS
(LAP POOL ONLY)
COMBINED BATHING lOAD /99 PERSONS 123 PERSONS /146 PERSONS
(ACTIVITY POOL AND LAP)
FILTER RATE I 260 GPM 384 GPM /489 GPM
I
ESTIMATED COST OF ITEMS AFFECTED BY MODIFICATION
LAP POOL & RELATED EQUIP. I $1 72,060.00(PROPOSED) I + 73,500.0 01 + 147,000.00
POOL DECK SLAB + 7,250.00 + 14,500.00
POOL DECK PILES +9,300.00 + 18,600.00
PERIMETER POOL DECK FENCING + 1,900.00 +3,800.00
POOL PUMP ROOM + 15,000.00 + 15,000.00
(ADO APPRDX. 150 SF)
PLUMBING: I + 18,500.00 +2,100.00
ADO POOL DEo( DRAINS AND WATER CLOSET
AT WOMEMS RESTROOM
ELECTRICAL: +3,000.00 +6,000.00
ADD POOL DECK LIGHTING
LANDSCAPE I IRRIGATION + 1 0,000.00 + 1 0,000.00
BASKETBALL COURT DEMOliTION +8,000.00 +8,000.00
NEW BASKETBALL COURT + 19,500.00 + 19,500.00
INClUDES NEW FENCE, POSTS,CONe. &
STRIPPING.
DRAINAGE STRUCTURES +2,500.00 +3,500.00
INClUDES ADDITIONAL FRENCH DRAINS
SUBTOTAL +$168,450.00 +$248,000.00
OVERHEAD I PROFIT (15 %) I +$25,268.00 +$37,200.00
CONTINGENCf (10%) I I +$16,845.00 +$24,800.00
TOTAL ADDITIONAL CONSTRUCTION + $210,563.00 +$310.000.00
CO STS FOR ITEMS AFFECTED BY
MO DIFICATIONS
-r OTAL ADDITIONAL AlE, AQUATIC +$57,160.00 +$57,160.00
SPECIALIST FEES & REIMB. EXPENSES
I
I *TOTAL ADDITIONAL PROJECT COST +$267,723.00 +$367,160.00
. ADD S14, 630.00 FOR ORB PRESENTATION IF REQUIRED
J:\1979\Flom;"go\Wo,cNFltIMINOG COSTANAlYSIIS ADO WlES1 A.cloc
. -- - ..-
D. ELeCTRICAL
1. lighting Plan
2. Power Plan
3. Eledrical Panels
E. PLUMBING
1. Plumbing Plan
2. Plumbing Riser
F. POOL ENGINEERING
1. Pool Location Plan
2. Pool Layout Plan
.3. Pool Piping Plan
4. Pool Piling Plan
5. Swimming Pool Sedions
6. Pool Equipment Plan
Note: Revised calculations will be required and shall be included for all items listed above.
FEE ESTIMATE
The fee break-down for the scope of additional work as outlined above for either an additional 2(two) or
4 (four) lanes to the lap pool is os follows:
A. BASIC ADDITIONAL SERVICES:
Construdion Documents through re-permitting:
1. . ARCHITECTURE... .............. ..... ..... ... ......... ............... .......... ..... ..... ................$ 19,800.00
2. CIVIL ENGINEERING.................................................................... ........ ..... ...$ 4,860.00
3. STRUCTURAL ENGINEERING........................................ ................................. $ 3,500.00
4. MECHANICA.l & ElECTRICA.l ENG/NEER/N/G..................................................... $ 3,800.00
5. lANDSCA.PE... .................... .... ... ... ... ..... ... ............. .., ............... .......... .........$ 3.400.00
SUBTOTAL....... $ 35,360.00
B. SPECIALIST ADDITIONAL SERVICES (Aquatic Pool Consultant):
Construdion Documents through re permitting including HRS.
1. AQUATIC SPECIALIST ENGINEERING............................................................ . $ 130400.00
C. COST ESTIMATING
........................................................................................
$ 2.000.00
D. COMPARATIVE ANALYSIS (COMPLETED).............. ~............................................. $ 10400.00
TOTAL............... $ 52,160.00
E. REIMBURSABLES.. ..................... ...... ................... ....... ......... ............... ........................ . $5,000.00
Reimbursable expenses sholl include those items required to produce the scope of work above:
Pg2
_r___._<rt,
F. PRESENTATilON TO THEDESIGN REVIEW BOARD (IF REQUJREO).............................$74,630.00
Oe/iverables
Corradino will provide 0 submittal package to the City of Miami Beach, composed of 15 copies of the following:
COMPLETED APPLICATION
SURVEY
DESIGN DOCUMENTS
Site Plan
Floor Plans
Elevations
Sedion
Contextual Elevation
Landscape Plan
Eledrical Site Plan
CONCEPTUAL PERSPECTIVE
COLOR PHOTOS OF SURROUNDING AREA
TABUlATION OF ZONING DATA
BUILDING DEPARTMENT RElATED INFORNiATION
MAILING lABELS / INFORNiATION
The total fee for the scope of work described above is 0 lump sum of $14,630.00. The following is a breakdown of
this estimate which is based on 1 (one) presentation to the City of Miami Beach Design Review Boord: .
I. ... MEETINGS (3 total @ $240.00)................................................................. .............. .........$ 720.00
In on effort t9 gain consensus with the City of Miami Beach, Carr Smith sholl condud a minimum 3
meetings with various entities, including the City of Miami Beach Planning Deportment staff.
II. PRODUCTION OF THE SUBMITT At PACKAGE....................... ............................................$8,2 70. 00
The produdion of the material listed above in 'de/iverables'" which included redesign of the pool deck and
affeded strudures includin. typical building sedions and building elevations if requested by the Tom
Mooney of the City of Miami. This includes the effort of architeds, designers, landscape archited, civil
engineer, strudural engineer and eledrical engineer.
w
. _ _ __-r'-
. .
III. PRESENTA TJON TO THE SOARD................ ................................... .....................................$5, 140.00
A PRODUCTION OF GRAPHIC PRESENTATION MATERIAL..........................................$3,600.00
Special presentation material will need to be produced for presentation to the board: This i~cludes
but is not limited to color boards, perspectives, and rendered plans and elevations.
B. REPRESENTATION BEFORE THE CITY OF MIAMI BEACH...,............._~.......................$l ,540.00
A total of 1 visit before the board by 2 representatives from CORRADINO, (5.5 man-hours each)
is expected to be provided in order to gain approval from the City of Miami Beach.
rY. REIMBURSABLES........................................ ................................... .......................................$500.00
Reimbursable expenses shall include those items required to produce the scope of work above:
photographic material, presentation boards as well as reproduction of said items, and couriers.
J;\ 1979\Flamingo\WordVFlAMINOGOPOOLMODIFICATJONS ADDSVCS.docM