Attachment SS
CITY OF
MIAMI BEACH
CITY HALL 1700 CONVENTION CENTER DRIVE MIAMI BEACH FLORIDA 33139
-=
OFFICE OF THE CITY MANAGER
LETTER TO COMMISSION
TELEPHONE: (305) 673-7010
FAX: (305) 673-nS2
L.T.C. No. 46-1999
DATE: February 19,1999
TO: Mayor Neisen O. Kasdin
and Members of the Citl: Commission
FROM: Sergio Rodriguez
City Manager
SUBJECT: UPDATE ON THE STATUS OF THE PARK IMPROVEMENT BOND
PROGRAM
The following is an update on the status of the park improvement bond program which is being
implemented with funding from the City of Miami Beach's $15 million General Obligation Bond
and Miami-Dade County's $7.2 million Safe Neighborhood Parks Bond.
STATUS REPORT:
NEIGHBORHOOD PARKS
I. Group" A" Parks: Stillwater, Crespi, LaGorce and Palm Island
(Construction is in progress for this first group of parks.)
B.
.
.
.
.
~
Stillwater Park
City Commission awarded construction contract
for Group "A" Parks to Zurqui Construction
Notice to Proceed issued to contractor
Estimated Substantial Completion
Estimated Project Close-out
Percentage of completion:
30%
.
.
11/04/98
12/21/98
05/05/99
06/04/99
.
.
.
.
Crespi Park
City Commission awarded construction contract
for Group "A" Parks to Zurqui Construction
Notice to Proceed issued to contractor
Estimated Substantial Completion
Estimated Project Close-out
Percentage of completion:
35%
11/04/98
12/21/98
04/14/99
05/13/99
Parks Bond Status Report
February 19, 1999
Page 2
C.
I,aGorce Park
City Commission awarded construction contract
for Group "A" Parks to Zurqui Construction
Notice to Proceed issued to contractor
Estimated Substantial Completion
Estimated Project Close-out
Percentage of completion:
.
.
.
.
.
D.
Palm Island Park
City Commission awarded construction contract
for Group "A" Parks to Zurqui Construction
Notice to Proceed issued to contractor
Estimated Substantial Completion
Estimated Project Close-out
Percentage of completion:
.
.
.
.
.
II. Group "B" Parks: Tatum, Fisher, Island View
A. Tatum Park
. Construction Documents are 100% complete
. Issuance of Construction Bids
. Estimated Substantial Completion
. Estimated Project close-out
B. Fisher Park
. Construction Documents are 100% complete
. Issuance of Construction Bids
. Estimated Substantial Completion
. Estimated Project close-out
C. Island View Park
. Construction Documents are 100% complete
. Issuance of Construction Bids
. Estimated Substantial Completion
. Estimated Project close-out
III. Group "e" Parks: Fairway, Muss, Washington
.
Schematic Design Phase 1 00 % Complete
Construction Documents are 25% complete
and are estimated to be 1 00% complete by
Issuance of Construction Bids
Estimated Substantial Completion of
Group"C" Parks Project Construction
Estimated Project close-out
.
.
.
.
11/04/98
12/21/98
03/22/99
04/21/99
35%
11/04/98
12/21/98
03/22/99
04/21/99
35%
02/26/99
1 0/20/99
11/18//99
02/26/99
07/21/99
08/20/99
02/26/99
07/21/99
08/20/99
04/08/99
04/22/99
12/03/99
01/02/00
Parks Bond Status Report
February 19, 1999
Page 3
IV. Pinetree Park
.
100% Schematic Design Complete.
Construction Drawings 100% complete.
Documents were reviewed by Building Department Inspectors on
Issuance of Construction Bids
Estimated Substantial Completion of Pine tree Park
Estimated Project close-out
.
.
.
.
.
All Neighborhood parks are subject to stafflevel Design Review approval.
DISTRICT PARKS
V. North Shore Park
(Schedule subject to change pending approval of the Design Review Board)
.
Schematic Design 100% Complete.
Architects have completed the revisions to the designs which
were presented to the North Beach Ad Hoc Committee on
Design Review Board Presentation
Complete Construction Drawings
Issuance of Construction Bids
Estimated Substantial Completion of North Shore Park
Estimated Project close-out
.
.
.
.
.
.
VI. Normandy Isle Park
.
Design Development 100% Complete
Received Design Review approval on
Complete Construction Drawings
Issuance of Construction Bids
Estimated Substantial Completion of Normandy Isle Park
Estimated Project close-out
.
.
.
.
.
VII. Flamingo Park
.
Design Development 100% Complete.
Received Design Review approval on
Complete Construction Drawings
Issuance of Construction Bids
Estimated Substantial Completion of Flamingo Park
Project Construction
Estimated Project close-out
.
.
.
.
.
.
W08/99
03/03/99
09/27/99
10/26/99
01/21/99
04/13/99
07/16/99
07/16/99
09/06/00
10/05/00
09/15/98
05/03/99
05/1 0/99
04/1 0/00
05/19/00
10/13/98
05/03/99
05/1 0/99
04/1 0/00
05/19/00
Parks Bond Status Report
February 19, 1999
Page 4
REGIONAL PARKS
VIII. I,ummus Park
(Schedule pending resolution of reallocation of funds.)
.
Design Development 100% Complete.
Complete Construction Drawings
Issuance of Construction Bids
Estimated Substantial Completion of Lummus Park
Estimated Project close-out
03/03/99
03/03/99
09/27/99
10/26/99
.
.
.
.
IX. North Shore Open Space Park
.
Submitted Grant application requesting funding of $2.1 million
from Miami-Dade County Safe Neighborhood Parks Bond Program
City Commission approved the taking back of Park
City Commission rejected Resolution authorizing an
Amendment to Architects contract to design Park
12/16/98
01120/99
.
.
02/17/99
This project is currently on hold pending the State of Florida's response to the City's request to
return the Park and the approval to initiate a contract amendment for architectural services.
x. South Pointe Park
On September 23, 1998, the Chairman and Members ofthe Miami Beach Redevelopment Agency
adopted a Resolution Authorizing the Administration to Proceed with the Design and
Implementation of Physical Improvements in the South Pointe Redevelopment Area and
Appropriating the Necessary Funds to Accomplish Them From Available Tax Increment Funds.
Included in this approval was $900,659 for South Pointe Park and $291,924 for Washington Avenue
Park that was previously reallocated from the appropriation dedicated to each ofthe parks within the
$15 million General Obligation Parks Bond Program and allocated to the North Shore Park Youth
Center on July 1, 1998, per Agenda Item R7L. At this time South Pointe Park is on hold pending
the identification of additional funding needed to complete the estimated $4.5 million improvement
program.
XI. Scott Rakow V outh Center
(Schedule subject to change pending approval of the Design Review Board)
. Schematic Design 100% Complete.
. Design Review Board Presentation 04/13/99
. Complete Construction Drawings 01114/00
. Issuance of Construction Bids 01/21/00
. Estimated Substantial Completion 12/21/00
. Estimated Project close-out 01/22/01
Parks Bond Status Report
February 19, 1999
Page 5
All District & Regional Parks are subject to Design Review and Historic Preservation Boards
approval.
OTHER FACII,ITIES
XII. Parks Maintenance Yard
(Schedule pending resolution of FEMA issues.)
.
Complete Construction Drawings
Issuance of Construction Bids
Estimated substantial Completion
Estimated Project close-out
01/26/99
03/03/99
11/08/99
12/07/99
.
.
.
XIII. Beaches and Boardwalk
The boardwalk from 21st Street to 44th Street has been resurfaced, the remainder of the structure,
from 44th Street to 47th Street is on hold pending resolution of a legal action against the product
supplier and installation contractor.
The Administration is in the process of developing the Beach Front Master Plan. This plan will
include the installation of additional landscape materials such as Coconut Palms, Sea grapes and Sea
Oats.
The North Beach Recreational Corridor is currently in the schematic development! planning phases
of the project. The cost for these phases is being deducted from the Beaches and Boardwalk
allocation.
The Administration will continue to monitor the progress of these projects and provide quarterly
updates.
SRJ~IKS/MMJrar
F:\WORKISALLIMAGMlC\PARKSIL TCUPDA T. WPD
c: Janet Gavarrete, Assistant City Manager
Mayra Diaz-Buttacavoli, Assistant City Manager
Christina M. Cuervo, Assistant City Manager
Kevin Smith, Parks and Recreation Director
Julio Grave de Peralta, Public Works Director
Jorge Chartrand, Capital Projects Coordinator
Michel Magloire, Construction Manager
,..,.... ~~~
,~<
hi I-
I~ ]
...... I-
~.".... ~
-- ~~
~ I
....... I-
~i -
~
-4
1> ~
I-
.... ~ ~ ii
:> ~ ;:\ ~
;; ~
f-
~ ii ~ ~ !i ~ I'lh:: ~ :;: !!
~ a; 0 ~
gl ~ ,; ~ ; ~ ~ ~ s ~ :<I ~
iii Il ~ Ii; Ii M ~
:t~ I:l I;i
~. ;i ~ ~ ~ t-;;;~I-;: s ~ R !!
~'I ill ~ a; ~
III ~ ~ ~ III m -. ~ ~ i
I:l c: II ;; ~ Ii; ~ a ~ ~
;:1 I:l c:
~ ~ ~
.c
s~ f-
"'*' Iii ! 2 !i ~ ~ s ~ m !! ~
~> ~ - N
~ m ; ~ ~ i ~ ~ ~ 1\
~:.:~ iii Il m ~
Q';::~ ci M I:l
ii~
t44 ~ ! ~ !l ! ~ f-;:;I-;; ~ 8 ~ !!
.,it; ~ ~
MI ~ ; !ii ~ !i ~ i a; ;t
~. c: ~ M I:l ;; I:l
+i'- f-r- 1-1-
If!; I ~ tl tl ~ I I ~ I I I ~ ~ tl
...~
~...~ ~ ~ ~ ~ ~
'Z7; l-
I ~ ~ ~ i tl tl ! ~ ~ I ~ ~ ~
1+; ~ " ~ ~ ~ ~ ~
.;: I;
....
i2 ~ ~ ~ ~ ~ ~ ~ ~ ! ! $ $ ~ ~
v:'. ~ ~ ~ ~ ~ ~ ~ ~ ~
~ I-
:1 n H j ~ j i i i tl I I $
! ~ ~ ~
~ '-
~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
<(:~ I-
~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
';;1 ~ ~ ~ 1\ ~ I I $ $ $ $ $ $
;:M 0 0 0 ~ ~ ~ ~ ~ ~ ~
H;
I~ ~ ~ I tl tl i $ ~ ~
~ i I I
~ ~ ~ ~ I 9 ~ ~
iif i ~ ~
jl ~ ~ ~ ~ ~ ~ ~
~ ~ ~ ~ I i I i i i ~ i ~ ~
!! !! ~ ~ ~ ~ 0
~ I-
o .r # ~ # ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
~ ~i 8 8
~ ~ ~ ~ ~ g ~ g ~ ~ ~ ~ ~ ~
..'U'" l- I-
j::'z ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
-Co
it;;;
~....~ !! ~ !! !! ~ !! ~ !! !! !! !! ~ !!
<<
it>>
:
'.~ .~....~
:;:1
~-
>
lr
c(
::E
::E
;:)
rn
rn
rn
w
lr
Cl
0
lr
0.
I-
0
w
..,
0
lr
0.
C
Z
0
f ID
0 rn
:0:
N lr
c(
0.
a-
ll:.
a-
"-
N
~ ~ Ii!
,.. ~ ::!
_ _ e
tl tl c:
nli!~
:: " Iii ~
Ii Ii Il l::
1\;; ~
lH!~
~! iH
~ ~ 5i ~
~ t: ~ ~
~ ~ ~
~~~ ~?$
l:: Il Il
~ ~ ~
~ ~ ~
. . .
p~
;; ~ ~
i ~ ~
i
... l ~
I
i ~ ~
~ S $
fH
~!l!i
s ;; ;;
~ ~ ~
~ ~ iii
" - -
~ ~ 2
~ ~ ~
~ ~ ~
n~
!l !l 0
n~
- - l::
~ ~ -
~p
I; I; ~
tl Ii l!
n~
~ l ~
~ 2 ~
~n
n~
- - l::
n~
~ ~ 0
n~
n~
n~
H~
n~
; ~ ~ ~ ~ ~ ~ e ~
N
~
~
I'l " f:j ~