Untitled (3)FIRE STATION #2
Description
Fire Station No. 2 consists of the construction of a new 3-bay Fire Station, with living quarters, and the City Emergency
Operations Center. Full historic restoration of the existing Fire Station Building for use as Fire Department Administrative
Offices is the next phase of this project.
Project Status
Final finishes are underway on all portions of the project. The contractor is working on completing the contractor's punch
list. The landscape contractor has mobilized and final grading of the site has been completed. Irrigation and site lighting
work are being completed. Final inspections are underway for each of the individual trades' work. The inspections are
being coordinated with the contractor and the CIP Office. The project is anticipated to reach Substantial Completion
during mid-First Quarter of 2008 with completion and Fire Department move-in occurring shortly thereafter.
;., x
~ \:
{,_
a°".>i~
e
~~
v.z~°v,
~.
s
~~, ~ , ~•
~ ~ , ~...~.. ~. o•M,„ ~. , .
NAUTILUS NEIGHBORHOOD IMPROVEMENTS
Description
Improvements include streetscape, water, storm water, and lighting upgrades in the area from Surprise Lake south to 41st
Street and from Biscayne Bay east to the Indian Creek waterway.
Project Status
The contractor has completed water main and electrical installation on the entire Orchard Park neighborhood and is
finalizing restoration and testing. Department of Health completed a full clearance for the water line at Orchard Park and
the contractor has started water service connections. The contractor is working on Orchard Park sidewalk and driveway
replacement and sodding. He began street widening for the bike lanes. The contractor is installing water mains on 46th
Street from Alton Road to Meridian Avenue and along 47th Court and 48th Street. The contractor finalized water main
installation on Meridian Avenue from 42nd Street to 47th Streets and is performing bacteriological test on the new lines.
The contractor finalized the water service crossings and wet tap installation for connection points and water main
installation at 47th Court from Alton Road to 48th Street, and 48th Street from Alton Road to 47th Court and Meridian
Avenue from 42nd to 44th Streets.
OCEANFRONT NEIGHBORHOOD IMPROVEMENTS
Description
Improvements to street ends from 23rd Street to 43rd Street including pedestrian facilities, streetscape restorations,
lighting, and signage.
Project Status
The contractor is completing added work and correcting warranty items and is expected to finalize by March, 2008, on
24th, 25th, 26th, 27th, 29th, 31st, 35th, 36th, 42nd and 43rd Streets. Due to existing developer agreements with the
City, improvements to Liberty Avenue, 30th, 32nd, 34th, 37th, 38th, 39th, 40th and 41st Streets were removed from the
scope of the Oceanfront Project and will be completed by the developers.
~.
'~~ - .
SCOTT RAKOW YOUTH CENTER
Description
Replacement of the pool filtration system and miscellaneous minor renovation to the pool equipment room.
Project Status
The overall project is approximately 75% complete and is expected to be completed the first week in March, 2008.
~.
~~
~~
ALTOS DEL MAR PARK
Description
Re-sodding and irrigation improvements as well as completion of a missing sidewalk segment.
Project Status
This project is complete and the contractor is completing the punch list items.
BELLE ISLE PARK AND BELLE ISLE NEIGHBORHOOD IMPROVEMENT
Description
Installation of new water main and storm water pump station, drainage, streetscape improvements on Island Avenue
North, Island Avenue South, Century Lane, Farrey Lane and renovation of Belle Isle Park.
Project Status
Pavement and striping of the off-street parking areas closest to the perimeter of the park is complete. Regulatory signage
and reflectors have been placed. The light poles installed within the Right-of-Way are energized and controlled by an
electrical time clock. Installation of the irrigation lines within the medians and bump outs on Island Avenue North and
South is complete, and landscaping within the Right-of-Way is complete. Pump Station Vault and Treatment Devices 1 and
2 have been installed. The final 36" concrete pipe that will connect the stormwater system on Island Avenue North has
been completed. The 24" stormwater pipe on the Venetian Causeway is being installed (westbound) and is expected to
be completed end of February, 2008. At the February 13th, 2008, City Commission meeting, the Administration
requested an easement in favor of FPL to provide electrical service to the Pump Station. The FPL duct bank has been
placed and FPL will schedule their work for four weeks following the granting of the easement. The new walkways,
enhanced landscaping and relocation of existing trees within the park is ongoing. The project is expected to be completed
by the end June of 2008.
~; .
_~ ,.
.... ,„
~;~
~,: ~:
..
LUMMUS STREET IMPROVEMENTS
Description
Additional drainage and streetscape improvements on bth, 9th, 10th, 1 1 th, 12th, 13th, and 14th street between
Washington Avenue and Ocean Drive, 14th lane between Collins Avenue and Ocean Drive and Espanola Way between
Washington Avenue and Collins Avenue
Project Status
The Contractor is now installing light poles, sidewalk, curb and gutter at 13th Street and is waiting on FPL connection to
energize the lighting on 6th Street. Milling and Re-surfacing is ongoing at 10th Street. The contractor also completed
City's punch list items for 7th, 8th and 9th Streets and obtained approval from MDC Traffic Signal Department on 7th and
9th Streets and is waiting on written approval from FDOT and MDC Traffic signals approval for 8th Street. Substantial
walk thru was performed at 6th, and 1 1 th Streets and Espanola Way and will be addressing punch list items. On January
7, 2008, the contractor received a Notice To Proceed (NTP) on 14th Lane but was later directed to stop due to an
injunction from the Carlton Hotel.
NORMANDY ISLE & NORMANDYE SUD NEIGHBORHOOD IMPROVEMENTS
Description
Water system improvements including relocation of water meters to the fronts of homes, enhanced landscaping, street
lighting, repair and extension of existing sidewalks, and street resurfacing/pavement markings.
Project Status
Placement of the new 8" water main is now complete between Rue Versailles and Trouville Esplanade. First lift of asphalt
is also complete along Bay Drive between Trouville and Rue Versailles. Contractor has mobilized onto Biarritz Drive and is
currently installing the new water main from Rue Versailles westward. Royal Palms located in the median along Trouville
esplanade have been root-pruned and will be relocated to accommodate the new median width. New drainage structures
have been installed at the Trouville street-end and at Biarritz Drive. Contractor will be adding additional parking spaces
along Rue Versailles to ease the current parking crisis.
NORMANDY SHORES NEIGHBORHOOD IMPROVEMENTS
Description
Stormwater system improvements; enhanced landscaping and street lighting; repair, extension and widening of existing
sidewalks; and street resurfacing/pavement markings.
Project Status
The previous contractor met with the administration on 9/27/2007 to discuss a reasonable exit strategy and completion
of critical activities on South Shore Drive. On January 4, 2008, the CIP Office issued a Notice to Proceed to Unitech
Builders. The drainage well on Hagan Street is now complete, and crews have mobilized to the western end of South
Shore Drive and the northern end of Sarazen Street to develop these wells. The developed wells will be used primarily for
dewatering, when placing the drainage structures and piping across the island. Unitech is currently milling the asphalt
surface on Shore Lane, and preparing the edge of pavement for placement of new valley gutter and pavement. Residents
have been notified of pending encroachment removal, necessary to realize the proposed street improvements.
.:~ _a-,
~,% ., ~,-
~a
:.%-'•°
NORMANDY SHORES GOLF COURSE
Description
The Renovation of the golf course including the tees, greens and bunkers, new drainage and irrigation system with new
Irrigation Pump House.
Project Status
The irrigation is approximately 85% complete, and the pump house is now approximately 90% complete. The Basamid
herbicide application has been rescheduled to the middle of February, 2008, due to water restrictions from South Florida
Water Management district. This process will take approximately 3 to 4 weeks to complete. Notices will be sent to all
residents with new schedule.
,~
~n
SOUTH POINTE PARK
Description
Improvements to the regional park as mentioned in the 1996 City of Miami Beach Parks Master Plan. Proposed elements
includes a redesigned park entrance, new pavilion and maintenance buildings, new restroom, pedestrian walks, site
lighting, playground, and more.
Project Status
Work is progressing at the Central and West Lawn areas as follows: installation of drainage structures at existing parking
lot, lay out of foundation for Cut-walk, lay out of concrete walkway at Central Lawn -South side of parking lot, and
preparation work for Washington Avenue Fountain pump room. Work is progressing at the East Lawn area as follows:
structural formwork for new maintenance and pavilion buildings; importing, placing fill, and compacting lime rock at
serpentine landform continues; lay out of mid walk on serpentine landform; lay out of bleachers at serpentine landform;
lay out of ramps at Cut-Walk; installation of keystone border at Cut-Walk; forming for pylon light foundations and
proceeded with the forming of sand dunes. Work progress is currently at 42% complete.
,.v, ~
~r
..~
~~: ,
,, r
r~ ~ v st*