Youth Center_Contracts_November 1974 to July 1976YOU-wv Ce M-er
YOUTH CENTER (Contracts) 1
Date
Memo #4809, construction of Youth Center, 176774
PB -74, Bid No. 136-74, awarded Seldin
Construction Co., Inc., quoting $2,240,000.00.
Memo #5237, MB Youth Center, PB -74, Change 7/16/75
Orders #1,#2, & #3 totaling $6,765.73 providing
for increase in contract from $2,240,000.00 to
$2,246,765.73 approved.
Memo #5263, M.B. Youth Center, PB -74, Change 8/6/75
Orders Nos. 4 & 5, totaling $33,815.76 pro-
viding for increase in contract from
$2,246,765.73 to $2,280,581.49 approved.
YOUTH CENTER (Contracts) 2
Date
Memo #5264, M.B. Youth Center, PB -74, Change 8/6/75
Order #6, in amount of $4,114.00 providing for
increase in contract from $2,280,581.49 to
$2,284,695.49 approved.
Memo #5296, M.B. Youth Center, PB -74, Change 9/3/75
Orders #7 for $9,584.40 and #8 for $335.60,
approved, increasing contract from
$2,284,695.49 to $2,294,615.49.
Memo #5500, Youth Center equipment and furni- 1/21/76
ture, awarded, Central Office Products, Items
1,9,14, $3,631.71; Long's, Items 2,4,5,6,10,
$15,226.00; Contract 39, Inc., Items 3,7,12,
$10,251.00; Schnupp Mfg.Co.Item 8,$140.70;
YOUTH CENTER (Contracts)
(continued)
John Martin Co., Item 11, $3,672.68.
Memo #5568, Youth Center Change Orders No.
9 and 10, approved.
Memo #5684, Youth Center change order #11,
deferred to 5/19/76, per request of City Mgr.
Memo #5685, Youth Center change orders Nos.
12 and 13, deferred to 5/19/76, per request
of City Mgr.
Memo #5684, Youth Center, Change Order #11,
(deferred from 5/5/76), in amount of $7,061.00
a roved, (to provide additional bracing and
3
Date
1/21/76
3/3/76
5/5/76
5/5/76
5/19/76
YOUTH CENTER (Contracts)
(continued)
supports for 6 new ceiling -suspended basket-
ball backstops) increasing contract from
$2,297,144.15 to $2,304,205.15
4
Date
5/19/76
Memo #5733, Youth Center Change Order No 12, 6/2/76
in amount of $779.00 approved, increasing
contract from $2,304,205.15 to $2,304,984.15.
Memo #5734, Youth Center Change Order No. 13, 6/2/76
extending contract for 60 days from 4/27/76
to 6/26/76, approved.
Memo #5788, change order #14 for Youth Center, 7/7/76
PB -74, Credit of $800.00 approved. Extension