2009-27040 ResoRESOLUTION NO. 2009-27040
A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF
MIAMI BEACH, FLORIDA, APPROVING ON FIRST READING, IN
ACCORDANCE WITH THE REQUIREMENTS OF SECTIONS 163.3220 -
163.3243, FLORIDA STATUTES, ALSO REFERRED TO AS THE "FLORIDA
LOCAL GOVERNMENT DEVELOPMENT ACT", A SECOND ADDENDUM
("SECOND ADDENDUM") TO THE DEVELOPMENT AGREEMENT
BETWEEN THE CITY OF MIAMI BEACH ("CITY") AND THE NEW WORLD
SYMPHONY ("NWS"), DATED JANUARY 5, 2004 (THE DEVELOPMENT
AGREEMENT), AS AMENDED BY THAT CERTAIN FIRST ADDENDUM TO
DEVELOPMENT AGREEMENT, DATED FEBRUARY 20, 2007 (THE FIRST
ADDENDUM) (COLLECTIVELY, THE JANUARY 5, 2004 DEVELOPMENT
AGREEMENT AND THE FIRST ADDENDUM MAYALSO COLLECTIVELY BE
REFERRED TO AS THE "NWS DEVELOPMENT AGREEMENT"); SAID
SECOND ADDENDUM PROVIDING FOR THE FOLLOWING: 1) APPROVAL
OF THE FINAL GARAGE BUDGET, IN THE AMOUNT OF $16,798,000; 2)
AMENDING THE PRELIMINARY PARK PROJECT BUDGET FROM
$14,960,000, TO $13,372,000; 3) DELETING THE REFERENCE IN THE
FIRST ADDENDUM SPECIFYING GEHRY PARTNERS, LLC, AS THE
ARCHITECTURAL CONSULTANT FOR THE PARK PROJECT, AND ALSO
WAIVING THE REQUIREMENT UNDER SECTION 26.20 OF THE
DEVELOPMENT AGREEMENT ("KEY MAN" CLAUSE) AND SECTION 9 OF
THE FIRST ADDENDUM BUT ONLY AS IT PERTAINS TO GEHRY
PARTNERS, LLC'S PARTICIPATION AS THE ARCHITECTURAL
CONSULTANT FOR THE PARK PROJECT; 4) AUTHORIZING NWS TO
PROCEED WITH THE SELECTION OF A NEW ARCHITECTURAL
CONSULTANT AND/OR ARCHITECTURAL ENGINEERING (A/E) FIRM FOR
THE DESIGN OF THE PARK PROJECT, WITH NWS'S SELECTION
PROCESS THEREFORE SUBJECT TO THE PRIOR WRITTEN APPROVAL
OF THE CITY MANAGER (PRIOR TO IMPLEMENTATION BY NWS); 5) IN
CONJUNCTION WITH THE CITY COMMISSION'S FUTURE
CONSIDERATION AND REVIEW OF THE PARK PROJECT CONCEPT PLAN,
DIRECTING NWS TO ALSO, AT THAT TIME, BRING TO THE CITY
COMMISSION, FOR REVIEW AND CONSIDERATION, THE PENDING ISSUE
OF WHETHER TO ADD CERTAIN ARCHITECTURAL TREATMENTS (AS
DISCUSSED AT THE CITY'S FINANCE COMMITTEE MEETING ON MARCH
10, 2009 AND INCLUDING, WITHOUT LIMITATION, THE STAINLESS STEEL
MESH AND LED LIGHTING) FOR THE EAST FACtADE ELEVATION OF THE
NWS GARAGE, WITH THE FINAL DECISION ON WHETHER TO ADD SUCH
TREATMENTS TO BE SUBJECT TO THE APPROVAL OF THE CITY
COMMISSION AT THAT TIME; 6) AMENDING SECTION 23.2.1 OF THE
DEVELOPMENT AGREEMENT ("GARAGE")DELETING THE REFERENCE
THAT THE NWS GARAGE ACCOMMODATE APPROXIMATELY 320 CARS
AND, FURTHER, AMENDING THE DEFINITION OF "GARAGE" IN SECTION
2Q) OF THE FIRST ADDENDUM TO INCLUDE THAT THE GARAGE, AS
CONTEMPLATED BY THE PARTIES, SHALL CONTAIN APPROXIMATELY
535 SPACES (BUT NO LESS THAN 520 SPACES) AND SHALL BE
DESIGNED, DEVELOPED, AND CONSTRUCTED BY DEVELOPER IN
ACCORDANCE AND CONSISTENT WITH THAT CERTAIN ORDER OF THE
CITY'S DESIGN REVIEW BOARD (FILE NO. 22010), APPROVED ON
MARCH 3, 2009; AND 7) THAT THE FINAL GARAGE BUDGET WILL NOT
INCLUDE FUNDING FOR THE TWO (2) ELEVATORS IN THE MIDDLE OF
THE GARAGE (ON THE EAST SIDE), AND HAVING A CONSTRUCTION
VALUE OF $275,000, WHICH HAVE BEEN DESIGNED TO PRIMARILY
ACCESS NWS' BUILDING, HOWEVER, SAID ELEVATORS WILL BE
INCLUDED IN THE GARAGE AND FUNDED AT THE SOLE COST AND
EXPENSE OF NWS; AND FURTHER AUTHORIZING NWS TO PROCEED
WITH DESIGN AND ENGINEERING OF THE GARAGE UPON APPROVAL OF
FIRST READING OF THE SECOND AMENDMENT OF THE DEVELOPMENT
AGREEMENT.
WHEREAS, on January 5, 2004, the City of Miami Beach (City) and the New World Symphony
(NWS), entered into a Development Agreement and Ground Lease Agreement (the Agreements),
providing for design, development and construction of an educational performance and Internet
broadcast facility and exterior screen (formally known as "Soundspace„ and now known as the "NWS
Campus Expansion Project") and a public parking garage to`be located on the westernmost portion of
the 17th Street surface parking lots, bounded by 17th StrArrt to the north; North Lincoln Lane to the
south; Drexel Avenue to the east; and Pennsylvania Avenue to the west; and
WHEREAS, pursuant to the direction of the City Commission on September 8, 2004, and
consistent with the Planning Board's August 24, .2004, recommendation, the Project site was
expanded east to Washington Avenue to include both surface lots; and
WHEREAS, on February 20, 2007, the City and NWS executed the First Addendum to the
Development Agreement (First Addendum) wtxich further established the Parties' respective obligations
(including processes, scopes for implemerXEation, and estimated costs and budgets for the NWS
Campus Expansion, the Garage, and also pertaining to certain Additional Improvements, Infrastructure
Improvements, and the design, developrr~nt and construction of a Park); and
WHEREAS, the First Addendum also established the City's Preliminary Budgets forthe Garage
Project at $15,210,135, and the Park project at $14,960,000, and approved a $15 million Grant-in-Aid
for the NWS building; and
WHEREAS, throughout tote course of the Project's development, the City Commission has
consistently taken the position than the Project should not result in a net loss of parking spaces and has
consistently contemplated a Fr;~nk Gehry designed Garage containing 500 to 600 parking spaces; and
WHEREAS, the Firryt Addendum requires that NWS secure the City's approval of the Final
Garage Budget prior to NV10S entering into a Guaranteed Maximum Price ("GMP") contract with a
contractor to construct th6~ Garage; and
WHEREAS, N10VS and Hines (NWS's Project Manager) conducted aproposal/solicitation
process for adesign/build contractor for the Garage, which resulted in the selection of KVC
Construction, Inc., (KVC) as the lowest responsive bidder; and
WHEREAS, KVC's proposal to build the Garage (containing 550-562 parking spaces) came in
at $20,789,459, exceeding the Preliminary Budget set forth in the First Addendum(by $5,579,323); and
WHEREAS, on February 11, 2009, the Finance and Citywide Projects Committee (the
Committee) discussed KVC's proposal in the context of the overall Project; the costs involved; and
the status and design of the Park; and
WHEREAS, the Committee requested that NWS and Hines continue working with KVC to
reduce the proposed cost of the Garage; that NWS contact Gehry Partners, LLC to determine if
Gehry's proposed design fees for the Park could be reduced in order to potentially free up funding for
the difference in the Garage cost; and that NWS proceed to the March 3, 2009, Design Review Board
meeting for approval of the Garage design (with certain design alternatives, including elimination of the
stainless steel mesh and LED lighting on the eastern facade); and
WHEREAS, the Committee also requested that NWS and Hines work with the City to identify
alternative options that would allow for the Park to be designed, permitted and constructed in time for
the grand opening of the NWS Campus Expansion; and
WHEREAS, on March 10, 2009, the Administration reported back to the Committee, indicating
that the proposed cost of the Garage had been reduced to $16,798,000, for a difference of $1,588,000
from the Preliminary Garage Budget allocation; and
WHEREAS, since Gehry Partners would not lower its fees for the design of the Park, NWS and
Hines recommended that the City be considered an altemative design professional for the Park, so that
the projected difference in the Garage costs could be moved from the Preliminary Park Project Budget
without any reduction in scope to the proposed Park; and
WHEREAS, pursuant to the recommendations of the Committee at its March 10th meeting,
the City and the NWS have negotiated a Second Addendum to the Development Agreement, providing
for the following:
1) The definition of the Garage will be modified to specifically state that the Garage will have
approximately 535 parking spaces, but no less than 520 parking spaces; and
2) Approving the Final Garage Budget, in the amount of $16,798,000; and
3) Approving the Design to the Park Budget, in the amount of $13,372,000; and
4) Waiving the "Key Man" requirement for Gehry Partners, LLC., but only as to Gehry Partners
having to be the Architectural Consultant for the Park Project; and
5) Authorizing NWS to proceed in preparing aselection/solicitation for a new architect (A/E
firm) for the Park Project, pursuant to a competitive process to be approved by the City
Manager, and requiring further that the City Commission must approve the new
recommended A/E firm; and
6) The City Commission may, in its sole and absolute discretion, at the time of its
consideration of the Park Project Concept Plan, determine whether or not to include the
certain architectural treatments (i.e., stainless steel mesh and LED lighting) on the east
fagade of the Garage (which approval would be subject to Gehry Partners' concurrence
and, if approved, the treatments would be included at the City's cost); and
7) The Final Garage Budget, as approved by the City, does not contemplate the City funding
the two (2) elevators in the middle of the Garage (on the East side and having a
construction value of $275,000), which have been designed to primarily access NWS'
building; said elevators will be included in the Garage and shall be funded at the sole cost
and expense of NWS.
NOW, THEREFORE, BE IT DULY RESOLVED BY THE MAYOR AND CITY COMMISSION OF
THE CITY OF MIAMI BEACH, FLORIDA, that the Mayor and City Commission hereby approve, on
First Reading, in accordance with Sections 163.3220 -163.3243, Florida Statutes, also referred to as
the "Florida Local Government Development Act", a Second Addendum to the Development
Agreement between the City of Miami Beach and the New Wo~1d Symphony (NWS), dated January 5,
2004, (the Development Agreement), as amended by that certain First Addendum to the Development
Agreement, dated February 20, 2007 (the First Addendum) (collectively, the January 5 2004
Development Agreement and the First Addendum may be referred to as the "NWS Development
Agreement"); said Second Addendum providing for the following 1) approval of the Final Garage
Budget in the amount of $16,798,000; 2) amending the Preliminary Park Project Budget from
$14,960,000 to $13,372,000; 3) deleting the reference in the First Addendum specifying Gehry
Partners, LLC, as the architectural consultant on the Park Project, and also waiving the requirement
under section 26.20 of the Development Agreement ("Key Man" clause) and section 9 of the First
Addendum, but only as it pertains to Gehry Partners, LLC's participation as the architectural consultant
for the Park Project; 4) authorizing NWS to proceed with the selection of a new architectural and/or
architectural engineering (A/E) firm for the design of the Park Project, with NWS' selection process
therefore subject to the prior written approval of the City Manager (prior to implementation by NWS); 5)
in conjunction with the City Commission's future consideration and review of the Park Project Concept
Plan, directing NWS to also, at that time, bring to the City Commission, for review and consideration,
the pending issue of whether to add certain architectural treatments (as discussed at the City's Finance
Committee meeting on March 10, 2009, and including without limitation, the stainless steel mesh and
LED Lighting) for the east fagade elevation of the NWS Garage, with the final decision on whether to
add such treatments to be subject to the approval of the City Commission at that time; 6) amending
Section 23.2.1 of the Development Agreement ("Garage"), deleting the reference that the NWS
Garage accommodate approximately 320 cars and, further amending the definition of "Garage" in
section 2(j) of the First Addendum to include that the Garage, as contemplated by the parties, shall
contain approximately 535 spaces (but not less than 520 spaces) and shall be designed, developed,
and constructed by the Developer in accordance and consistent with that certain order of the City's
Design Review Board (File no. 22010), approved on March 3, 2009; and 7) that the final Garage
Budget will not include funding for the two (2) elevators in the middle of the Garage (on the east side),
and having a construction value of $275,000, which have been designed to primarily access the NWS
building; however said elevators will be included in the Garage and funded at the sole cost and
expense of NWS; and further authorizing NWS to proceed with design and engineering of the Garage
upon approval of First Reading of the Second Addendum to the Development Agreement.
PASSED and ADOPTED this 18th day of March, 2009.
M TI HERRE OWER, MAYO
ATTEST:
RO ERT PARCHER, CITY CLERK
t:\Agenda\2009UAarch 18\Regular\NWS-Second Addendum Reso -First Reading.doc
APPROVED AS TO
FORM & LANGUAGE
ett FOR EXECUTION
;1-- ~ ~~ f. 6~
ity Attom Date
COMMISSION ITEM SUMMARY
Condensed Title:
A resolution approving on 1st Reading a 2" Addendum to the Development Agreement between the City and the New World
Symphony (NWS), approving the final Garage Budget in the amount of $16,798,000, amending the Preliminary Park Budget from
$14,960,000 to $13,372,000 and modifying certain provisions in the Development Agreement and the First Addendum pertaining to the
Garage and the Park as noted in the following summary.
Key Intended Outcome Supported:
Increase community rating of cultural activities and ensure well maintained facilities.
Supporting Data (Surveys, Environmental Scan, etc.): While a majority of residents say that the City has the right amount of
cultural activities, approximately 30% of those surveyed say there are too few cultural activities. The NWS Project will significantly
enhance the City's attraction as a cultural destination.
Issue:
Shall the City Commission approve the proposed 2" Addendum to the Development Agreement between the City of Miami Beach and
the NWS?
Item Summa /Recommendation:
Pursuant to the provisions set forth in the Development Agreement between the City and NWS and the 1S Addendum thereto, dated
February 20, 2007, NWS is required to secure the City's approval of the Final Garage Budget prior to NWS entering into a Guaranteed
Maximum Price ("GMP") contract with a contractor to construct the Garage. In accordance with these provisions, NWS and Hines
conducted an RFP process which resulted in the selection of KVC Construction, Inc., (KVC) as the lowest and most responsive bidder.
KVC's proposal to build a garage, containing over 500 parking spaces came in at $20,789,459, exceeding the not-to-exceed
Preliminary Budget set forth in the First Addendum by $5,579,324. Pursuant to direction of the Finance Committee on February 11,
2009, NWS and Hines proceeded to reduce the proposed cost of the Garage to $16,798,000, for a difference of $1,588,000 from the
Preliminary Budget allocation. The revised cost was present to the Finance Committee on March 10, 2009. It was also reported that
since Gehry Partners would not lower their fees for the design of the Park, NWS and Hines recommended that the City consider an
alternative design professional forthe Park. The resulting savings could be moved from the Park Budget to fund the projected difference
in the Final Garage Budget, without any reduction in scope to the proposed Park.
The Administration is recommending a 2"d Addendum to the Development Agreement, generally providing for the following modifications
to the Development Agreement and the 1St Addendum: modifying the definition of "Garage" to state that the Garage will have
approximately 535 parking spaces, but no less than 520 parking spaces; approving the Final Garage Budget in the amount of
$16,798,000; approving the Design-To Park Budget in the amount of $13,372,000; waiving the "Key Man" requirement for Gehry
Partners, LLC., to design the Park component; authorizing NWS to proceed in selecting an Architect and/or Architectural Consultant for
the Park project pursuant to a competitive process approved by the City Manager, and approval by the City Commission of the
recommended Architect and/or Architectural Consultant; providing for the City Commission to determine at the time of the Park Concept
Plan approval, to decide whether or not to place the architectural treatment on the east facade of the Garage; and providing that the
Final Garage Budget will not include funding for the two (2) elevators in the middle of the Garage (on the East side), having a
construction value of $275,000, which shall be funded at the sole cost and expense of NWS. In addition, given the time requirements of
the Project, NWS should be authorized to proceed with design/engineering of the Garage upon approval of the 1St Reading of the Second
Addendum.
Adviso Board Recommendation:
Finance & Citywide Projects Committee, Feb 11, 2009 & Mar 10, 2009: Recommendation in favor of proposed modifications to the
Develo ment A reement and 1st Addendum as noted above.
Financial Information:
Source of Funds: Amount Account Approved
OBPI Total 1,588,000
Financial Impact Summary: The difference between the Preliminary Garage Budget and the Final Garage Budget in the amount of
$1,588,000 is being proposed to be funded from the FY 2009/10 appropriation for the Park, thereby reducing the overall Park Budget
from $14,960,000 to $13,372,000. No new appropriation of funding is required, just a reallocation from planned future capital
a ro riations.
~~~ ~~~~ AGENDA ITEM R~~
~'" DATE 3-I $ _d y
Ci Clerk's Office Le islative Trackin
Kent O. Bonde, Redevelopment Coordinator
m MIAMIBEACH
City of Miami i3sach, 1700 Convention Center Drive, Miami Beach, Florida 33139, www.miamibeachH.gov
COMMISSION MEMORANDUM
TO: Mayor Matti Herrera Bower and Members of the City Commission
FROM: Jorge M. Gonzalez, City Manage FIRST READING
PUBLIC HEARING
DATE: March 18, 2009
SUBJECT: A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF
THE CITY OF MIAMI BEACH, FLORIDA, APPROVING ON FIRST READING, IN
ACCORDANCE WITH THE REQUIREMENTS OF SECTIONS 163.3220 -
163.3243, FLORIDA STATUTES, ALSO REFERRED TO AS THE "FLORIDA
LOCAL GOVERNMENT DEVELOPMENT ACT", A SECOND ADDENDUM
("SECOND ADDENDUM") TO THE DEVELOPMENT AGREEMENT BETWEEN
THE CITY OF MIAMI BEACH ("CITY") AND THE NEW WORLD SYMPHONY
("NWS"), DATED JANUARY 5, 2004 (THE DEVELOPMENT AGREEMENT), AS
AMENDED BY THAT CERTAIN FIRST ADDENDUM TO DEVELOPMENT
AGREEMENT, DATED FEBRUARY 20, 2007 (THE FIRST ADDENDUM)
(COLLECTIVELY, THE JANUARY 5, 2004 DEVELOPMENT AGREEMENT AND
THE FIRST ADDENDUM MAY ALSO COLLECTIVELY BE REFERRED TO AS
THE "NWS DEVELOPMENT AGREEMENT"); SAID SECOND ADDENDUM
PROVIDING FOR THE FOLLOWING: 1) APPROVAL OF THE FINAL GARAGE
BUDGET, IN THE AMOUNT OF $16,798,000; 2) AMENDING THE
PRELIMINARY PARK PROJECT BUDGET FROM $14,960,000, TO $13,372,000;
3) DELETING THE REFERENCE IN THE FIRST ADDENDUM SPECIFYING
GEHRY PARTNERS, LLC, AS THE ARCHITECTURAL CONSULTANT FOR THE
PARK PROJECT, AND ALSO WAIVING THE REQUIREMENT UNDER SECTION
26.20 OF THE DEVELOPMENT AGREEMENT ("KEY MAN" CLAUSE) AND
SECTION 9 OF THE FIRST ADDENDUM BUT ONLY AS IT PERTAINS TO
GEHRY PARTNERS, LLC'S PARTICIPATION AS THE ARCHITECTURAL
CONSULTANT FOR THE PARK PROJECT; 4) AUTHORIZING NWS TO
PROCEED WITH THE SELECTION OF A NEW ARCHITECTURAL
CONSULTANT AND/OR ARCHITECTURAL ENGINEERING (A/E) FIRM FOR
THE DESIGN OF THE PARK PROJECT, WITH NWS'S SELECTION PROCESS
THEREFORE SUBJECT TO THE PRIOR WRITTEN APPROVAL OF THE CITY
MANAGER (PRIOR TO IMPLEMENTATION BY NWS); 5) IN CONJUNCTION
WITH THE CITY COMMISSION'S FUTURE CONSIDERATION AND REVIEW OF
THE PARK PROJECT CONCEPT PLAN, DIRECTING NWS TO ALSO, AT THAT
TIME, BRING TO THE CITY COMMISSION, FOR REVIEW AND
CONSIDERATION, THE PENDING ISSUE OF WHETHER TO ADD CERTAIN
ARCHITECTURAL TREATMENTS (AS DISCUSSED AT THE CITY'S FINANCE
COMMITTEE MEETING ON MARCH 10, 2009 AND INCLUDING, WITHOUT
LIMITATION, THE STAINLESS STEEL MESH AND LED LIGHTING) FOR THE
EAST FACtADE ELEVATION OF THE NWS GARAGE, WITH THE FINAL
DECISION ON WHETHER TO ADD SUCH TREATMENTS TO BE SUBJECT TO
THE APPROVAL OF THE CITY COMMISSION AT THAT TIME; 6) AMENDING
Commission Memorandum -NWS Second Addendum
March 18, 2009
Page 2 of 10
SECTION 23.2.1 OF THE DEVELOPMENT AGREEMENT ("GARAGE")
DELETING THE REFERENCE THAT THE NWS GARAGE ACCOMMODATE
APPROXIMATELY 320 CARS AND, FURTHER, AMENDING THE DEFINITION
OF "GARAGE" IN SECTION 2(j) OF THE FIRST ADDENDUM TO INCLUDE
THAT THE GARAGE, AS CONTEMPLATED BY THE PARTIES, SHALL
CONTAIN APPROXIMATELY 535 SPACES (BUT NO LESS THAN 520 SPACES)
AND SHALL BE DESIGNED, DEVELOPED, AND CONSTRUCTED BY
DEVELOPER IN ACCORDANCE AND CONSISTENT WITH THAT CERTAIN
ORDER OF THE CITY'S DESIGN REVIEW BOARD (FILE NO. 22010),
APPROVED ON MARCH 3, 2009; AND 7) THAT THE FINAL GARAGE BUDGET
WILL NOT INCLUDE FUNDING FOR THE TWO (2) ELEVATORS IN THE
MIDDLE OF THE GARAGE (ON THE EAST SIDE), AND HAVING A
CONSTRUCTION VALUE OF $275,000, WHICH HAVE BEEN DESIGNED TO
PRIMARILY ACCESS NWS' BUILDING, HOWEVER, SAID ELEVATORS WILL
BE INCLUDED IN THE GARAGE AND FUNDED AT THE SOLE COST AND
EXPENSE OF NWS; AND FURTHER AUTHORIZING NWS TO PROCEED WITH
DESIGN AND ENGINEERING OF THE GARAGE UPON APPROVAL OF FIRST
READING OF THE SECOND ADDENDUM OF THE DEVELOPMENT
AGREEMENT.
Administration Recommendation
Adopt the Resolution.
Funding
Pursuant to the City's Capital Plan, the balance of funding for the Park component, in the
amount of $13,910,000 is anticipated to be appropriated as part of the FY 2009/10 Capital
Budget, to be funded from City Center Redevelopment Agency TIF. The Administration is
recommending to fund the difference between the Preliminary Garage Budget and the Final
Garage Budget in the amount of $1,588,000 from the FY 2009/10 appropriation for the Park,
thereby reducing the overall Park Budget from $14,960,000 to $13,372,000.
Background
On January 5, 2004, the City of Miami Beach (City) and the New World Symphony (NWS),
entered into a Development Agreement and Ground Lease Agreement (the Agreements),
providing for design, development and construction of an educational performance and
intemet broadcast facility and exterior screen (formally known as "Soundspace") and a public
parking garage to be located on the westernmost portion of the 17~' Street surface parking
lots, bounded by 17~' Street to the north; North Lincoln Lane to the south; Drexel Avenue to
the east; and Pennsylvania Avenue to the west. Pursuant to the direction of the City
Commission on September 8, 2004 and consistent with the Planning Board's August 24,
2004 recommendation, the Project site was expanded east to Washington Avenue to
include both surface lots, to be designed as an integrated site, to include the development
of a Park and certain other public improvements.
The Agreements have NWS serving as the Developer of the site and, in this capacity; NWS
enters also into separate agreements with its vendors to plan, design, and construct the
Garage and the Park on the City's behalf. The City is obligated to provide funding for these
improvements upon approval of the scope of work and budgets for each.
Commission Memorandum -NWS Second Addendum
March 18, 2009
Page 3 of 10
On February 20, 2007, the City and NWS executed the First Addendum to the Development
Agreement (First Addendum) that established the City's Preliminary Budgets for the Garage
Project and the Park Project and established a $15 million Grant-in-Aid for the NWS
building. The Preliminary Garage Budget was established as $15,210,135, and the
Preliminary Park Budget was established as $14,960,000.
The First Addendum requires that NWS secure City approval of the Final Garage Budget
prior to NWS entering into a Guaranteed Maximum Price ("GMP") contract with a contractor
to construct the Garage. NWS has advised the City that it is ready to proceed with the
Garage design/build contract.
Architectural Consultant Criteria
The Development Agreement and the First Addendum contain language that names "Gehry
Partners, LLC„, as the Architectural Consultant for the Project (including the Garage and the
Park components). A considerable amount of importance was placed on having the entire
project site developed in accordance with the "single design vision of the Architectural
Consultant...". The City and NWS agreed that a "Gehry' designed Project (including Garage
and Park) was a material and integral part of the development of the site. In deciding that a
"Gehry" design was a material element, the City Commission carefully considered the
potential financial costs attached to making the Architectural Consultant a material
requirement.
The firm "Gehry Partners, LLC" is an architectural company created by Frank O. Gehry. The
services of Mr. Gehry and his firm, Gehry Partners, are in demand throughout the world. Mr.
Gehry is particularly known for the Guggenheim Museum in Bilbao, Spain; the Millennium
Park in Chicago; the Walt Disney Concert Hall in downtown Los Angeles; the Experience
Music Project in Seattle; the Weisman Art Museum in Minneapolis; the Dancing House in
Prague, Czech Republic; and his private residence in Santa Monica, California. His work is
often sought by owners to distinguish themselves from others, as the buildings that he
designs become tourist attractions in and of themselves.
The projects designed by Gehry Partners are considered to be world class facilities. This
type of distinction, which carefully and uniquely combines art with function is, by its nature,
higher in expense than a typical municipal project. The firm is able to command a premium
in fees, and the projects that are designed by them are high end products with a
commensurate premium in the cost of construction. In approving the First Addendum, the
City Commission considered the premium that went with making a Gehry design a material
element, and determined that the distinctive value of the end product, a world class design,
was worth the premium cost of design and construction.
The Garage Project
From the inception of the Project, the Garage has been an integral component. The Project
site, including the Park and the Garage, was previously two (2) City surface parking lots that
contained just over 500 parking spaces. Throughout the course of the Project's
development, the City Commission has taken the position that the Project should not result
in a net loss of parking spaces. For this reason, the Project has consistently contemplated a
Gehry designed Garage containing 500 to 600 parking spaces.
Commission Memorandum -NWS Second Addendum
March 18, 2009
Page 4 of 10
The First Addendum increased the total Preliminary Garage Budget from approximately $7
million, to $15,210,135, for 608 spaces, and including the City Code required retail
component on the ground floor. The Preliminary Garage Budget provided by NWS and
approved by the City Commission in the First Addendum was generally divided as follows:
Total Architectural/En ineerin Cost $1,511,000
Total Construction Cost $12,106,000
Total Site Cost $650,680
Total Tax/Insurance Cost $215,608
Total Owner Ex enses $10,000
Total General/Admin Costs $568,755
Total Contin enc Cost $148,092
Total Pro'ect Cost $15,210,135
The First Addendum anticipated a potential change between the Preliminary Garage Budget
and the Final Garage Budget, and therefore requires NWS to bring back its Final Garage
Budget, for consideration and potential approval by the City Commission. As of March 10,
2009, NWS advised the City that it is prepared to present a Final Garage Budget.
Since execution of the First Addendum on February 20, 2007, NWS has proceeded with
both the construction of the NWS building (now known as the "NWS Campus Expansion")
as well as the conceptual design for the Garage with Gehry Partners. The recommended
and approved process (in large part to help limit the design fees) was to have Gehry
Partners do the conceptual design and obtain Design Review Board approval. Currently, the
conceptual design has been bid todesign/build contractors, and the selected contractor and
its design professional will be responsible for finishing the design and engineering in
accordance with the DRB approved conceptual plans (when that occurs), and then construct
the Garage. The selected design/build contractor is contemplated to be asub-contractor of
the NWS Campus Expansion, general contractor, Facchina McCaughan, LLC.
Schedule
Successful completion of the Garage is on the same Critical Path as for completion of the
NWS Campus Expansion building, for two reasons: (1) The electrical power vaults for both
the Campus Expansion building and the Garage are located within the Garage. At this point,
permanent power cannot be provided to the Campus Expansion building without the Garage
commencing construction. In order to meet the Critical Path for the Campus Expansion
building, final engineering for the Garage would need to commence by the beginning of April
2009 (at the latest); and (2) Pursuant to Resolution No. 2007-26704, the City Commission
approved a temporary license agreement for NWS to count 175 parking spaces within the
proposed Garage to meet its City Code required parking for a period of five (5) years from
the date of Certificate of Occupancy (C.O.) of the Campus Expansion building. This requires
that the Garage be constructed and open in order for a C.O. to be granted on the Campus
Expansion building. After five (5) years, NWS would need to provide for its 175 Code-
required parking spaces at an alternate location.
As soon as approval from the City Commission is obtained, NWS can hire the design/build
contractor (Facchina McCaughan) and finalize the design and initiate the permitting and
construction of the site. If this schedule is met, then completion of the Garage is projected to
be August/September 2010.
Commission Memorandum -NWS Second Addendum
March 18, 2009
Page 5 of 10
Park
The planning effort for the Park has not yet officially commenced. Up until March 1, 2009,
NWS was still in negotiations with Gehry Partners regarding the proposed design services
and fees for this component. The Preliminary Park Budget in the First Addendum is
$14,960,000.
Total Project Funding
The allocated funding for the NWS Project comes from City Center RDA funds. The funding
approved by the City is as follows:
Gara a FY 09 $15,21.0,135
Additional Im rovements FY 08 $6,400,000
Park Desi nFY09/ConstFY2010 $14,960,000
Grant in Aid FY 2010 $15,000,000
Total Fundin Commitment $51,570,135
As noted above, the funding commitments forthe Garage, the Additional Improvements, and
the design for the Park have already been appropriated by the City Commission.
The funding commitment for the construction of the Park and for the Grant-in-Aid will be due
as of October 1, 2009.
Finance and Citywide Projects Committee -February 11, 2009
At the February 11, 2009 FCWPC Meeting, the status of the proposed Garage and of the
Park were discussed. The Committee was generally advised that the Garage budget at that
time was over the allocated amount. NWS also advised that no Agreements had been
executed with Gehry Partners to design the Park and that the negotiations regarding the
Park were ongoing. Based on the information from this meeting, the Committee made the
following requests and recommendations:
1) For NWS/Hines to continue to work with the low bidder(s) for the proposed
Garage and to continue to reduce the proposed cost of the Garage;
2) For NWS, and specifically, Michael Tilson Thomas, to contact Frank Gehry
directly and see if the design fees for the Park portion of the Project can be
brought to within $1.5 million with Gehry Partners remaining as the Architect or
Architectural Consultant;
3) If it is determined that Gehry Partners cannot be retained on the Park Project
within the design fee target identified by the City, then the FCWPC requested
that NWS/Hines work with City staff to determine if a high end urban park can
be designed and built to compliment the Gehry designed Campus Expansion
building for the identified construction budget of $8.5 million with an alternative
designer.
4) For NWS/Hines to proceed to the March 3, 2009 Design Review Board
Meeting with the proposed Gehry designed Garage to see if DRB Approval for
Commission Memorandum -NWS Second Addendum
March 18, 2009
Page 6 of 10
the proposed Garage, with certain design alternatives, such as the elimination
of the stainless steel mesh and LED lighting on the eastern fagade, would be
approved.
5) For NWS/Hines to identify an alternative that would allow for the Park to be
designed, permitted, and constructed in time forthe planned Grand Opening of
the new Campus Expansion building in winter 2010/2011.
Finance and Citywide Projects Committee -March 10, 2009
At the March 10, 2009 FCWPC meeting, the following information was provided:
The NWS/Hines development team has selected a low bidder for the Garage. The low
bidder for the Garage is a local company doing business as KVC Construction (KVC). The
principals of KVC are Miami Beach residents and, although not related, currently have a
contract with the City as the Construction Manager at Risk for the Scott Rakow Youth Center
project.
As of the February 11, 2009 FCWPC Meeting, the cost projected for the proposed Garage
was as follows:
Total Architectural/En ineerin Cost $2,255,612
Total Construction Cost $16,235,372
Total Site Cost Included in Construction Cost
Total Tax/Insurance Cost $331,500
Total Owner Ex enses $0
Total General/Admin Costs $977,000
Total Contin enc Cost $989,974
Total Pro'ect Cost $20,789,458
The current proposed Garage costs as of March 11, 2009 by NWS/Hines are:
Total Architectural/En ineerin Cost $2,155,612
Total Construction Cost $13,132,888
Total Site Cost Included in Construction Cost
Total Tax/Insurance Cost $181,500
Total Owner Ex enses $0
Total General/Admin Costs $578,000
Total Contin enc Cost $750,000
Total Pro'ect Cost $16,798,000
At the current proposed total cost of $16,798,000, the projected amount over the
contractually allocated $15,210,135 is $1,587,865 (for purposes of the 2"d Addendum, this
amount has been rounded up to $1,588,000). KVC's design/build proposal projects
approximately 535+ parking spaces, although the final count will not be known until the full
engineering and permitting effort is completed.
Commission Memorandum -NWS Second Addendum
March 18, 2009
Page 7 of 10
The proposed Garage received approval by the DRB at the March 3, 2009 meeting. The
DRB approval calls for the stainless steel mesh on 3 sides of the structure with the proposed
LED lights. The DRB Order does not include the facade treatment on the eastern elevation,
but does allow for it if funds become available to add the treatment at a future date.
Update on Park Agreement with Gehrv Partners
NWS advised the City that Michael Tilson Thomas discussed the proposed Park fees with
Frank Gehry over the February 28/March 1, 2009 weekend. NWS advised the City that
Gehry Partners will not lower their requested fees.
Proposed Park Status and Potential Alternatives
NWS/Nines is proposing that the City consider an alternative design professional for the
Park, such as a well-known Landscape Architect. NWS/Nines has advised the City that it
has had initial discussions with several firms since the February 11, 2009 FCWPC meeting
and believes that the design costs for the park can be substantially reduced from the Gehry
Partners proposed fee.
Presently, NWS/Nines is proposing to the City that if the design professional is changed,
then the projected shortage to the Garage can be moved from the Park project without any
reduction in scope to the proposed Park. NWS/Nines has advised the City that the can-ent
Park construction budget can be increased under the NWS proposal described above. The
previous Park budget, as of February 11, 2009 was:
Total Architectural/En ineerin Cost $4,662,800
Total Construction Cost $8,628,600
Total Tax/Insurance Cost $300,000
Total Owner Ex enses $300,000
Total General/Admin Costs $878,600
Total Contin enc Cost $190,000
Total Project Cost $14,960,000
The proposed Park Budget byNWS/Nines is summarized belowfor a 535+ space Garage, if
the Park design professional is changed:
Total Architectural/En ineerin Cost $1,500,000
Total Construction Cost $10,344,000
Total Tax/Insurance Cost $300,000
Total Owner Ex enses 0
Total General/Admin Costs $578,000
Total Contin enc Cost $650,000
Total Project Cost $13,372,000
Under this proposal from NWS/Nines, the NWS would meet its commitments to provide a
500 to 600 space parking garage and a high end urban park to compliment the total campus
site and remain within the overall contractual amounts for the Project. It does require the City
Commission Memorandum -NWS Second Addendum
March 18, 2009
Page 8 of 1 D
Commission to approve the transfer of dollars between budgets ($1,588,000) within the
current NWS Development Agreement, as well as removing the Gehry "key man"
requirement for the Park design. This proposal would also increase the construction budget
for the Park by approximately $1.7 million above the current allocation.
Park Schedule
The schedule for the Park is largely dependent upon how the City elects to proceed at this
point. If Gehry Partners is maintained as the Park Project consultant, then the current
Development Agreement allows for a Planning and Design phase of 18 months, followed by
a construction period of 12 months. If this schedule is met, then the opening of the Park
would be 30 months from the time that Park notice to proceed is issued to Gehry Partners. If
this were to be done on May 1, 2009, then the proposed opening date would be around
November 2011.
If the decision is made to proceed with an alternative design professional to Gehry Partners,
then the timeline would be directly affected by the selection process required by the City. A
full City procurement process for an altemative design professional would take at least 4
months. The projected Planning and Design period is 12 months, followed by a 12 month
construction period. Under this scenario, assuming authorization to proceed is granted by
May 1 ~ 2009, the projected opening date for the Park would be September 2011.
Alternatively, if the City authorized NWS/Hines to select an alternative design professional,
then this timeline may be reduced by as much as 60 to 120 days.
In any event, depending upon the quality of the design professional, it may be possible to
shorten both the design and construction timelines; however, staff is not prepared to adjust
these timelines until a design professional is selected.
Proposed Second Addendum to the Development Agreement
Based on the above, and pursuant to the recommendation of the FCWPC, the City
Administration is recommending that the City Commission consider a Second Addendum to
the Development Agreement to memorialize the changes to the Development Agreement
and the First Addendum requested by New World Symphony. Although more specifically
delineated above, NWS is requesting the following changes be considered by the City
Commission:
1) The definition of Garage will be modified to specifically state that the Garage will
have approximately 535 parking spaces, but no less than 520 parking spaces;
and
2) Approving the Final Garage Budget in the amount of $16,798,000; and
3) Approving the Design To Park Budget in the amount of $13,372,000; and
4) Waiving the "Key Man" requirement for Gehry Partners, LLC., to design the Park
component under the Development Agreement; and
5) Authorizing NWS to proceed in selecting an Architect and/or Architectural
Consultant, or both, for the Park project, pursuant to a competitive process
approved by the City Manager, and with a reservation that the City Commission
Commission Memorandum -NWS Second Addendum
March 18, 2009
Page 9 of 10
must approve the recommended Architect and/or Architectural Consultant; and
6) The City Commission, may, in its sole and absolute discretion, determine at the
time of Concept Plan approval for the Park, whether or not to place the
architectural treatment (i.e., stainless steel mesh and LED lighting) on the east
fagade of the building; and
7) The Final Garage Budget will not include funding for the two (2) elevators in the
middle of the Garage (on the East side), and having a construction value of
$275,000, which have been designed to primarily access NWS' Building;
however, said elevators will be included in the Garage and funded at the sole
cost and expense of NWS.
The proposed Second Addendum has the same force and effect of the original Development
Agreement and the First Addendum. The purpose of the proposed Addendum is to formalize
the agreement of the parties of the above noted items, as well as to clarify the intent of the
parties in some areas of the previous Agreements.
Disputed Items
The Second Addendum to the Development Agreement is essentially agreed to by staff and
New World Symphony with one exception.
At the March 10, 2009 FCW PC Meeting, the recommendation of the Committee was for the
Garage to have four (4) elevators. Two (2) of the elevators are to be paid by the City and two
by NWS. The two NWS elevators are located in the middle of the Garage on the East
elevation and serve primarily NWS patrons. The value of these two elevators is $275,000.
The elevators are appropriate to address the rush of attendees as functions in the facility
begin or end.
The value of $275,000, has been removed from the City's portion of the Final Garage
Budget and the City's expectation is the NWS will separately fund these two elevators.
Subsequent to the March 10~' meeting, NWS has advised the City that it will not fund these
two elevators. NWS is recommending that these two elevators be removed from the Garage.
If this is done, this would result in only two elevators for the Garage, one (1) in the Southwest
corner, and the other in the Northeast comer.
Design for Garage
Due to the timing of the Project, NWS would like to proceed with the design and engineering
of the Garage as approved at the March 3, 2009 DRB Hearing. If the Second Addendum is
approved by the City Commission on First Reading, I recommend that NWS be authorized to
proceed with the design and engineering for the Garage.
The proposed Addendum is attached.
Conclusion
As noted the Garage component is a critical piece of the overall development of the NWS
campus. At the present time, it is appropriate to move forward with the Garage as
Commission Memorandum -NWS Second Addendum
March 18, 2009
Page 10 of 10
recommended by the FCWPC. The overall cost for the Garage is competitive for a Frank
Gehry designed building and will provide an appropriate architectural companion to the
Symphony Campus Expansion Building. The proposed transfer of funds from the Park
Budget, combined with the waiver of the "Key Man" clause will result in a higher Park
construction budget. It is possible to construct awell-designed and high end Urban Park for
the $10 million proposed.
The issue of the elevators for the NWS building is the only remaining issue in dispute
between staff and NWS. The elevators will serve a necessary purpose during periods of
entry or exit from events within the Symphony building and are appropriate given how the
Garage is likely to be used. Since the elevators would serve primarily the NWS building, it is
appropriate for NWS to fund same.
I recommend that the Commission approve on First Reading the Second Addendum as
recommended by the FCWPC.
Attachment
T:\AGENDA\2009\March 18\RegularWew World Symphony 2nd Addendum MEMO2.doc
p~ FRIQAY, MARCH 15, 2009 I 5B
m A/11AM1 ~A~I~
CITY OF MIAMI BEACH
NOTICE OF PUBLIC HEARING
NOTICE IS HEREBY given that a public hearing will be held by the Mayor and City Commission of the
City of Miami Beach, Florida, in the City Commission Chambers, 3rd floor, City Hall, 1700 Convention
Center Drive, Miarni Beach, Florida, on Wednesday, March 18, 2009, at 11:00 a.m., to consider approval,
on First Reading, of a Second Addendum to the Development Agreement between the City of Miarnl
Beach and the New World Symphony (NWS), dated January 5, 2004, (the Development Agreement), as
amended by that certain First Addendum to the Development Agreement, dated February 20, 2007 (the
.First Addendum) (collectively, the January 5, 2004 Development Agreement and the First Addendum
may be referred to as the "NWS Development Agreement"); said Second Addendum providing for
the following 1) approval of the Final Garage Budget in the amount of $17,033,120; 2) amending the
Preliminary Park Project Budget from $14,960,000 to $13,137,015; 3) deleting the reference in the First
Addendum specifying Gehry Partners, LLC, as the architectural consultant on the Park Project, end
also waiving the requirement under section 26.20 of the Development Agreement ("Key Man" clause)
and section 9 of the First Addendum, but only as it pertains to Gehry Partners, L_LC's participation as
the architectural consultant for the Park Project; 4) authorizing NWS to proceed with the selection of
anew architectural andlor architectural engineering (A/E) firm for the design of the Park Project, with
NWS' selection process therefore subject to the prior written approval of the City Manager (prior to
implementation by NWS); 5) in conjunction with the City Commission's future consideration and review
of the Park Project Concept Plan, directing NWS to also, at that time, bring to the City Commission,
for review and consideration, the pending issue. of whether to add certain architectural treatments (as
discussed at the City's Finance Committee meeting on March 10, 2009, and including without limitation,
the stainless steel mesh and LED Lighting) for the east fagade elevation of the NWS Garage, with the
final decision on whether to add such treatments to be subject to the approval of the City Commission at
that time; 6) amending Section 23.2.1 of the Development Agreement ("Garage"); deleting-the reference
that the NWS Garage accommodate approximately 320 cars and, further amending the definition of
"Garage" in section 2Q) of the First Addendum to include that the Garage, as contemplated by the
parties, shall contain approximately 540 spaces (but not less than 525 spaces) and shall be designed,
developed, and constructed by the Developer in accordance and consistent with that certain order
of the City's Design Review Board (File no. 22010), approved on March 3, 2009; and 7) that the final.
Garage Budget will not include funding for the two (2) elevators in the middle of the Garage (on the east
side), and having a construction value of $300,000, which have keen designed to primarily access the
NWS building; however said elevators will be included in the Garage and funded at the sole cost and
expense of NWS.
Inquiries may be directed to the Miami Beach Redevelopment Agency at (305) G73-7295.
INTERESTED PARTIES are invited to appear at this meeting or be represented by an agent or to express
their views in writing addressed to the City Commission c/o the .City Clerk, 1700 Convention Center
Drive, 1st Floor, City Hall, Miami Beach, Florida 33139. This meeting may be opened and continued and
under such circumstances additional legal notice would not be provided.
Robert E. Percher, City Clerk
City of Miami Beach
Pursuant to Section 286.0105, FL Statutes, the City hereby advises the public that: if a person decides
to appeal any decision made by the City Commission with' respect to any matter considered at its
meeting or its hearing, such person must ensure that a verbatim record of the proceedings is made,
which record includes the testimony and evidence upon which the appeal. is tq be based. This notice
does not constitute consent by the City 'for the introduction or adrnissi~n of otherwise inadmissible or
irrelevant evidence, nor does it authorize challenges or appeals not otherwise allowed by law.
To request this material in accessible format, sign language interpreters information on access for
persons with disabilities, and/or any accommodation to review any. document or participate in any
City-sponsored proceeding, please contact (305) 604-2489 (voice), (305) 673-7218(TTY) five days in
advance tp initiate your request. TTY users may also call 711 (Florida Relay Service).
Ad #528
SECOND ADDENDUM TO DEVELOPMENT AGREEMENT
THIS SECOND ADDENDUM TO DEVELOPMENT AGREEMENT is made as of
this day of , 2009 (this "Second Addendum") by and between the
CITY OF MIAMI BEACH, FLORIDA ("Owner" or "City"), a municipal corporation duly
organized and existing under the laws of the State of Florida, and NEW WORLD SYMPHONY,
a not-for-profit Florida corporation ("Developer") (the Owner and Developer, each a "Party" and
collectively, the "Parties").
RECITALS
A. Owner and Developer entered into an Agreement of Lease ("Lease") dated as of
January 5, 2004, pursuant to which Owner leased to Developer certain real property described in
Exhibit "A" to said Lease (the "Land").
B. Concurrently therewith, Owner and Developer also entered into a Development
Agreement ("Development Agreement") dated as of January 5, 2004, setting forth, among other
things, the Owner's and Developer's respective responsibilities and agreement to coordinate and
cooperate in the planning, scheduling and approval of the development, design and construction
of an automobile parking garage (the "Garage") to be located on land adjacent to the Land, and a
performance, educational and Internet broadcast facility, together with certain related amenities,
facilities and other infrastructure improvements on the Land ("Developer's Improvements"), as
set forth in the Development Agreement.
C. On February 20, 2007, Owner and Developer entered into a First Addendum to
Development Agreement ("First Addendum"), further clarifying the parties' respective
obligations (including processes, scopes for implementation, and estimated costs and budgets)
for the Garage and Developer's Improvements, and also pertaining to certain Additional
Improvements and Infrastructure Improvements, and the design, development, and construction
of the Park (collectively, for purposes of these Recitals, the "Project").
D. On January 23, 2008, Developer commenced construction of Developer's
Improvements. Notwithstanding the preceding, subsequent to the execution of the Lease,
Development Agreement and First Addendum, and commencement of construction, and given
the current fiscal/financial realities affecting the U.S. and global economies, the Parties now wish
to enter into this Second Addendum, further clarifying and memorializing their agreements
regarding the ongoing development of the Project (including, without limitation, the Garage and
Park components).
NOW THEREFORE, it is hereby mutually covenanted and agreed by and between the
Parties hereto that this Second Addendum is made in consideration of the terms, covenants and
conditions hereinafter set forth.
1. Capitalized Terms; Recitals. All capitalized terms not defined herein shall have
the meanings given to them in the Development Agreement, as amended by the First Addendum.
Hereafter, all references to the Development Agreement shall mean the Development
1
Agreement, as modified and augmented by the First Addendum and this Second Addendum,
unless the context indicates otherwise. The Recitals are incorporated herein by reference.
2. Additional and Revised Definitions. The following definitions, as initially set
forth in the Development Agreement or as may have been subsequently added or amended
pursuant to the First Addendum are amended as follows:
(a) "Design-to Park Project Budget" means the preliminary total costs
budgeted by the City for the Park Project, which is the preliminary estimate of costs, including
estimated hard and soft construction costs, anticipated as of the date hereof, to be incurred in
connection with the design, development and construction of the Park Project. As of the date
hereof, the parties acknowledge and agree that the City has budgeted an amount not to exceed
$AA9 $13,372,000 for Zones 3.1, 3.2 and 3.3, ,
for a total of ~#,~,589 $13.372.000, for the entire Park Project.
(b) "Garage" means the public municipal parking garage comprising Zone 1.1
to be designed, developed and constructed by Developer for Owner and funded as set forth in
Section 13 of the First Addendum (as amended hereto), and operated by Owner at its sole cost
and expense on City-owned property adjacent to the Land, legally described in Exhibit "C." It
is anticipated that the Garage will maximize public parking and minimize any net loss of public
parking within Zone 1.1 and will have approximately 535 (but no less than 520 spaces; have six
(6) stories, including five (5) stories of covered parking plus open rooftop parking; two (2) FPL
vaults; four (4) elevators [NOTE: DISPUTED ITEM]; a pedestrian bridge to Developer's
Project; and ground-floor retail space along 17th Street and Pennsylvania Avenue. Owner shall
be responsible for operation and management of the Garage, including the leasing and
management operations of the retail portion of the Garage.
(c) "Preliminary Park Project Budget" means the total cost budgeted by the
City for the Park Project, as mutually agreed to by the Parties and as shall be approved by the
City Commission concurrently with the approval of the Park Project Concept Plan (pursuant to
the provisions of Section 10 and Exhibit "D" of the First Addendum, as amended hereto), which
is the preliminary estimate of costs, including estimated hard and soft construction costs,
anticipated as of the date thereof to be incurred in connection with the design, development and
construction of the Park Project, including the sound system. The Parties acknowledge and agree
that the Preliminary Park Project Budget shall be established in accordance with the dollar
amounts set forth in the "Design to" Park Project Budget, in the amount of
$~4;96A;A88 $13,372,000.
(d) All reference (s) in the Agreement to "Zone 3.4" (as said term is defined
in the First Addendum) is hereby deleted. Accordingly, the area encompassing Zone 3.4, and any
improvements to be designed, developed and constructed thereon, shall not be part of the Park
Project or Park Project Zone, and the budgeted amount allocated to Zone 3.4 in the Design-to
Park Project Budget (or $1,150,000), as defined in the First Addendum, has been allocated to the
Park Project Budget for Zones 3.1, 3.2 and 3.3 (which shall hereafter consist of the Park Project
Zone).
2
3. Amendment or Replacement of Certain Sections of Development Agreement.
The following section or subsections in the Development Agreement or the First Addendum, as
noted respectively below, are amended as follows:
(a) Section 23.2.1 of the Development Agreement is deleted in its entirety and
replaced with the following:
Developer shall design and construct the Garage (as set forth in the
Development Agreement), at Owner's cost and expense, and as
further set forth and subject to the provisions of the Development
Agreement. The Parties acknowledge that the timing of
construction and completion of the Garage is critical; therefore,
Developer agrees to, and shall, as expeditiously as reasonably
possible, obtain Substantial Completion of the Garage prior to
completion of Developer's Improvements.
(b) Section 26.20 of the Development Agreement ("Key Man" Clause), shall
not be deemed to include Gehry Partners, LLC as the Architectural Consultant (as said term is
defined in the Development Agreement) for the Park Project. Accordingly, to the extent that
there is any other reference in the Development Agreement, or any exhibits thereto, to the
Architectural Consultant in relation to the design, development, and construction of the Park
Project (but only as to the Park Project), then such reference shall not be interpreted as referring
to Gehry Partners, LLC but, rather, shall refer to the successor architect/engineering (A/E) firm
selected by NWS, and approved by the City, for the Park Project.
(c) (i) In accordance with Section 3(b) above, Section 9 of the First
Addendum ("Park Project Design") shall also be amended to delete
the reference to Gehry Partners, LLC, as the architectural
consultant for the Park Project, and the use of the defined term
"Architectural Consultant" in Section 9 (as well as in any other
section of the First Addendum, and/or exhibits thereto) referring
to, or intending to refer to, the Architectural Consultant, in relation
to the Park Project only, shall be deemed to refer to the successor
A/E firm selected by Developer, and approved by the City, for the
Park Project.
(ii) The first sentence of Section 9(b) of the First Addendum is
deleted.
4. Gara ems.
(a) The amount for the Garage Costs, as set forth in Section 5(a)(i) of the First
Addendum, is hereby amended from $15,210,135, to $16,798,000
(b) The City and Developer hereby mutually agree upon, and the City
Commission hereby approves, the Final Garage Budget, in the amount of $16,798,000; such
approval by the City is further subject to, and contingent upon, the following conditions:
3
(i) The approval of the Final Garage Budget contemplates the design,
development, and construction of the Garage, as said term is
defined in this Second Addendum;
(ii) At the City's sole cost, and subject to the approval of Gehry
Partners, LLC, the City Commission shall retain authority and final
approval over whether to add certain proposed "architectural
treatments", to the east facade of the Garage including, without
limitation, the stainless steel mesh and LED lighting. The City
Commission shall review, consider, and approve or disapprove, the
inclusion of aforestated treatments concurrent with its review of
the Park Project Concept Plan; and
(iii) [NOTE: DISPUTED ITEM] The approved Final Garage Budget,
as set forth in this Second Addendum, shall not include the cost for
the two (2) elevators in the middle of the Garage (on the east side)
which will primarily service NWS's patrons and guests. These
elevators shall be designed, developed and constructed at NWS's
sole cost and expense.
(iv) Section 13 (c) (iii) of the First Addendum shall remain in full force
and effect and Developer shall not obligate any amount in excess
of $15,210,135 for the design, development and construction of the
Garage, prior to October 1, 2009, with the balance of the funding
in the amount of $1,588,000, available after October 1, 2009..
5. Miscellaneous.
(a) Counterparts. To facilitate execution, the Parties hereto agree that this
Second Addendum may be executed in counterparts as may be required and it shall not be
necessary that the signature of, or on behalf of, each Party, or that the signatures of all persons
required to bind any Party, appear on each counterpart; it shall be sufficient that the signature of,
or on behalf of, each Party, or that the signatures of the persons required to bind any Party,
appear on one or more of such counterparts. All counterparts shall collectively constitute a
single Second Addendum.
(b) References. All references in the Development Agreement (or the First
Addendum) to the "Agreement" shall hereafter mean and refer to the Development Agreement,
as amended by the First Addendum and this Second Addendum. If there is a contradiction
between the terms of the Development Agreement, the First Addendum, and this Second
Addendum, then the terms of this Second Addendum shall control. Facsimile signatures
appearing hereon shall be deemed an original.
(c) Effect of Second Addendum. Except as modified herein, the Development
Agreement remains in full force and effect. In the event of any conflict or ambiguity between
the Development Agreement, the First Addendum, and this Second Addendum, this Second
Addendum shall control.
4
EXECUTION BY OWNER
IN WITNESS WHEREOF, Owner and Developer intending to be legally bound have
executed this Second Addendum to Development Agreement as of the day and year first above
written.
WITNESSES: CITY OF MIAMI BEACH, FLORIDA, a
municipal corporation of the State of Florida
Print Name: BY~
Print Name:
STATE OF FLORIDA )
)ss:
COUNTY OF MIAMI-DADE )
ATTEST:
By: [SEAL]
The foregoing instrument was acknowledged before me this day of
by , as Mayor, and , as
City Clerk of the CITY OF MIAMI BEACH, FLORIDA, a municipal corporation of the State
of Florida, on behalf of such municipal corporation. They are personally known to me or
produced valid Florida driver's licenses as identification
My commission expires:
Notary Public, State of Florida
Print Name:
APPROVED AS TO
FORM & LANGUAGE
~ FOR EXECUTION
5 ~ ~ ~~~~; ~l~ z~ 4a
m Date
EXECUTION BY DEVELOPER
WITNESSES:
Print Name:
THE NEW WORLD SYMPHONY, snot-for-
profit Florida corporation
By:
Howard Herring, President and CEO
Print Name:
ATTEST:
By:
Secretary
[CORPORATE SEAL]
STATE OF FLORIDA )
)ss:
COUNTY OF MIAMI-DADE )
The foregoing instrument was acknowledged before me this day of ,
by Howard Herring, as President and CEO, and , as Secretary,
of THE NEW WORLD SYMPHONY, anot-for-profit Florida corporation, on behalf of such
corporation. They are personally known to me or produced valid Florida driver's licenses as
identification.
My commission expires:
Notary Public, State of Florida
Print Name:
6