98-22963 RESO
RESOLUTION NO. 98-22963
A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE
CITY OF MIAMI BEACH, FLORIDA, APPROVING AND AUTHORIZING
THE MAYOR AND CITY CLERK TO EXECUTE A FIRST AMENDMENT
IN THE AMOUNT OF $9,800 TO THE AGREEMENT WITH CARR SMITH
CORRADINO, FOR THE DEVELOPMENT OF A MUNICIPAL MOBILITY
PLAN FOR MIAMI BEACH; SAID AMENDMENT BEING MADE TO
COMPENSATE THE CONSULTANT FOR EIGHTEEN ADDITIONAL
MEETINGS HELD; TO PRINT A GREATER THAN ANTICIPATED
NUMBER OF COPIES OF THE PLAN; AND TO REFLECT AN EXTENDED
PLAN DEVELOPMENT TIMELINE, AS REQUESTED BY THE CITY,
ABOVE AND BEYOND THE ORIGINALLY NEGOTIATED CONTRACT
COST; SAID AMENDMENT FUNDED BY THE PROFESSIONAL
SERVICES CATEGORY OF THE FISCAL YEAR 1998-99 ECONOMIC
DEVELOPMENT BUDGET.
WHEREAS, on April 16, 1997, the Mayor and City Commission approved Resolution No.
97-22354, authorizing the Mayor and City Clerk to execute an Agreement between the City of
Miami Beach and Carr Smith Corradino (Consultant), providing for professional services for the
development of a Municipal Mobility Plan (MMP) for Miami Beach, in the amount of $150,000.00;
and
WHEREAS, the Scope of Services for the MMP required (he Consultant to hold
approximately fifteen (15) meetings and/or workshops throughout a twelve (12)-month plan
development process, from July 1997 through June 1998; and
WHEREAS, due to the number and variety of transportation issues brought up by the
various Miami Beach neighborhoods, and the interest generated by the MMP itself, eighteen (18)
additional meetings were held, the plan development timeline was extended by five (5) months, and
additional copies of the plan had to be printed; and
WHEREAS, the Consultant needs to be compensated for all services performed above and
beyond the originally contracted services; and
WHEREAS, funds are available in the Professional Services category of the 1998-99
Economic Development Budget to cover the $9,800 expense.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND CITY
COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, that the Mayor and City
Commission approve and authorize the Mayor and City Clerk to execute a First Amendment in the
amount of $9,800 to the Agreement with Carr Smith Corradino, for the development of a Municipal
Mobility Plan for Miami Beach; said Amendment being made to compensate the Consultant for
eighteen additional meetings held; to print a greater than anticipated number of copies of the plan;
and to reflect an extended plan development timeline, above and beyond the originally negotiated
contract cost; said amendment funded by the Professional Services category of the 1998-99
Economic Development Budget.
PASSED AND ADOPTED this the 18th day of November
, 1998.
( 'lJ1
MAYOR
ATTEST:
~r p~~
CITY CLERK
aJ
APPROVED AS TO
FORM & LANGUAGE
& FOR EXECUTION
Ail Miuk .IJ/n;4e flf
~ity ~omey r ~
ITV HALL 1700 CONVENTION CENTER DRIVE MIAMI BEACH, FLORIDA 33139
ttp~\\ci,miami-beach. fJ, us
~ITY OF MIAMI BEACH
TO:
FROM:
SUBJECT:
COMMISSION MEMORANDUM No:l(p5-9 <2S
Mayor Neisen O. Kasdin and
Members of the City Co mission
DATE: November 18,1998
~
Sergio Rodriguez
City Manager
A RESOL I N OF THE MAYOR AND CITY COMMISSION OF THE
CITY OF MIAMI BEACH, FLORIDA, APPROVING AND AUTHORIZING
THE MAYOR AND CITY CLERK TO EXECUTE A FIRST AMENDMENT,
TO AN EXISTING AGREEMENT WITH CARR SMITH CORRADINO, FOR
THE DEVELOPMENT OF A MUNICIPAL MOBILITY PLAN FOR MIAMI
BEACH; SAID AMENDMENT BEING MADE TO COMPENSATE THE
CONSUL T ANT FOR EIGHTEEN ADDITIONAL MEETINGS HELD, TO
PRINT A GREATER THAN ANTICIPATED NUMBER OF COPIES OF THE
PLAN, A1~D TO REFLECT AN EXTENDED PLAN DEVELOPMENT
TlMELINE, AS REQUESTED BY THE CITY, ABOVE AND BEYOND THE
ORIGINALLY NEGOTIATED CONTRACT COST; SAID AMENDMENT,
IN THE AMOUNT OF $9,800.00, BEING FUNDED BY THE
PROFESSIONAL SERVICES CATEGORY OF THE lfISCAL YEAR 1998-99
ECONOMIC DEVELOPMENT BUDGET.
ADMINISTRA TION RECOMMENDATION
Adopt the Resolution.
BACKGROUND
On April 16, 1997, the City Commission approved a professional services agreement with Carr
Smith Corradino for the development of a Mtlllicipal Mobility Plan (MMP) for Miami Beach. The
inception date for the original 12-month study was July 1, 1997. The MMP is the City's very first
attempt at dealing with mobility issues on a comprehensive and citywide basis. The Plan was fimded
at $150,000, as follows:
$ 78,500 in Metropolitan Planning Organization grant fimds
$ 36,500 in Miami Beach Parking Enterprise funds, and
$ 35,000 in Miami Beach Redevelopment Agency fimds.
Due to the circumstances explained in the Analysis section of this Agenda item, additional services,
above and beyond those contracted for, were required from the Consultant by the Administration,
the Transportation and Parking Committee, and the Miami Beach community. A larger than
anticipated amount of input has been received and incorporated in the MMP.
AGENDA ITEM ~~;4
DATE 1\-' 8 -9&
ANAL YSIS
The original MMP Agreement was approved last year at $150,000. Its proposed $9,800 amendment
will bring the total contract cost to $159,800. Approximately 95% of the services covered by this
proposed amendment have already been delivered by the Consultants. The reasons for the increased
contract cost follow:
~ Eighteen (18) meetings are being held, above and beyond the contracted fifteen (15):
Contracted Actual
Meetings held every-other month with the Study Steering Committee 7 10
Presentations to Transportation & Parking Committee at project milestones 3 5
Other MMP-related Miami Beach meetings held at City/residents request 0 4
Public Workshops with North, Middle and South Beach communities 2 4
Strategy sessions held with City project manager, Administration and staff 0 5
MMP Workshop with the Planning Board 0 1
MMP Workshop with City Commission 1 1
Final presentation to City Commission for Plan approval 1 1
MMP presentation to MPO technical committees, yet to be made -1.-2.
Total number of meetings held: Approximately 15 33
~ A much larger than predicted number of MMP books and Executive Summary brochures will
have to be printed, both including color graphics and maps. Due to the unprecedented interest
generated by the MMP in the Miami Beach community, requests for copies of the plan are
received daily from individuals, civic groups, and community organizations. The exact number
of additional copies is to be determined by the City's project manager.
~ Reflect a City-requested five-month extension to the plan development schedule, from July
to November, 1998.
The Amended Scope of Services is herein attached as Exhibit "A-I" to the proposed First
Amendment to this Agreement.
Funds to cover the $9,800 expenditure are available in the Professional Services category of the FY
1998-99 Economic Development Budget. A lump-sum payment is recommended at work
completion.
CONCLUSION
Carr Smith Corradino, Consultants, have shown commitment to and enthusiasm for the MMP,
have been attentive to the City's requests, translated the residents' desire for community
sustainability through projects which enhance the character of our unique City, and have not missed
an opportunity to improve, reshape, or clarify the plan further. The Administration is confident that
the Consultants have earned the additional compensation, which is herein recommended for
approval.
a.~c:,
SR/CC/ AJ
(mmpamend)Bj
FIRST AMENDMENT TO PROFESSIONAL SERVICES AGREEMENT
BETWEEN THE CITY OF MIAMI BEACH, FLORIDA (CITY) AND CARR
SMITH CORRADINO (CONSULTANT) TO COMPENSATE CONSULTANT
FOR ADDITIONAL MEETINGS HELD; FOR AN EXTENDED PROJECT
DEVELOPMENT TIMELINE; AND FOR PRINTING ADDITIONAL
COPIES OF THE PLAN, ABOVE AND BEYOND THE ORIGINAL
CONTRACT COST, AT THE CITY'S REQUEST.
This First Amendment to Agreement made this lilt day of Nuvl.>>t(~t::'fL,.. , 1998 by
and between the CITY OF MIAMI BEACH, FLORIDA, hereinafter called the "City," which term
shall include its officials, successors, legal representatives, and assigns, and CARR SMITH
CORRADINO, hereinafter called the "Consultant."
WITNESSETH:
WHEREAS, on April 16, 1997, the Mayor and City Commission approved Resolution No.
97-22354, authorizing the Mayor and City Clerk to execute a Professional Services Agreement
between the City and Consultant to develop a Municipal Mobility Plan (MMP) for Miami Beach
(Agreement); and
WHEREAS, pursuant to the Agreement, the Consultant was paid a fixed fee of$150,000 for
the Scope of Work and Services required pursuant to Exhibit "A" of the Agreement; and
WHEREAS, the parties now wish to amend the Agreement, specifically with regard to the
Scope of Work and Services in Exhibit "A," to reflect an increased number of required meetings
and workshops (33 instead of the 15 agreed upon), the printing of a larger than expected number
of plan copies, which include expensive color graphics, and an extended plan development timeline;
and
WHEREAS, the Amendment would increase the fixed fee paid to Consultant under the
Agreement by $9,800.00.
NOW THEREFORE, the Agreement is hereby amended as follows:
1. Exhibit "A", entitled "Scope of Services," is amended to include the additional Scope of
Work required by the City from Consultant regarding the MMP and attached hereto as
Exhibit "A-I."
2. Schedule "A" of the Agreement, entitled "Professional Services Fees and Reimbursable
Allowance," shall be amended to include the additional fee payable to Consultant, in the
amount of $9,800.00, as required for completion of the additional work set forth in Exhibit
"A-I."
3. The professional services contracted by this Amendment, and set forth in Exhibit "A-I,"
shall be completed by November, 1998.
4. All other terms and conditions of the Agreement between the City and Consultant shall
remain the same in full force and effect.
IN WITNESS WHEREOF, the parties hereto have caused this First Amendment to the
Agreement to be executed by their duly authorized officials on the day first above indicated.
ATTEST:
CITY OF MIAMI BEACH, FLORIDA
~o-- P Mdv---
City Clerk
~~,
Mayor
Secretary
Corporate Seal:
APPROVED AS TO
FORM & LANGUAGE
& FOR EXECUTION
1Jt~
Ci Attomey
~
(mmpamend) aj
EXHIBIT "A-I"
AMENDED SCOPE OF SERVICES
MUNICIPAL MOBILITY PLAN
The proposed $9,800 addition to the original $150,000 contract with Carr Smith Corradino
retroactively covers the following additional services rendered, above and beyond the Scope of
Services, Exhibit "A" to the original contract:
<> Approximately eighteen (18) additional meetin~s already held or to be held, as follows:
3 Study Steering Committee meetings - already held
2 MMP Presentations/Workshop with the Transportation & Parking Committee - held
4 Other MMP-related Miami Beach meetings held at City and residents request -held
4 Strategy sessions held with City project manager and/or Administration and staff-held
2 MMP Community Workshops - already held
1 MMP Presentation to the Planning Board - already held
1 Final presentation to City Commission for MMP approval - being held
1 Presentation to the MPO technical committees - upcoming.
<> The printing of a much larger number of MMP books/Executive Summary brochures,
both including color graphics and maps. The exact number of additional copies is to be
decided by the City's project manager.
<> A five-month extension (from July to November 1998) to the plan development schedule,
due to additional City requirements,.
(mmpamend)aj