LTC 362-2009 Update on MDC WASD plans to replace sanitary sewerm MIAMIBEACH
OFFICE OF THE CITY MANAGER
NO. LTC # 362-2009
,;
2009 DEC 29 P~1 t2= 38
LETTER TO COMIs/titS~~~ F ~~: ~- ~~
TO: Mayor Matti Herrera Bower and Members of the City Commission
FROM: Jorge M. Gonzalez, City Manager
DATE: December 23, 2009
suB~ECT: Update on Miami Dade County Water and Sewer Department (WASD) plans to
replace an existing 54-inch sanitary sewer line running from Miami Beach to
Virginia Key
On Friday, December 18, 2009, representatives of the City met with WASD officials to discuss the
WASD plan to replace an existing 54-inch sanitary sewer line running from Miami Beach to Virginia
Key. The purpose of the meeting was to obtain information on a recently announced change in the
project scope, and to better understand the impacts such a change of scope would have on the City.
The original plan to build a Utility Tunnel containing three pipes dedicated to sewer flow was
changed to a project with a single new 54-inch sewer line in a deeper location.
At the December 18, 2009 meeting, WASD explained that they were concerned that the planned
Utility Tunnel Project (a twelve-foot diameter tunnel bored under Government Cut with three pipes
dedicated to sewer flow, and a reclaimed water pipe) was too complex to be constructed in time for
the anticipated start of the Port of Miami dredging project. In order to meet the Port of Miami
dredging project time line, WASD changed the project to be a single 54-inch sanitary sewer line
constructed in a deeper location. WASD believes that the changed scope would allow them to
complete the pipe relocation project and also to accommodate the dredging project timeline.
WASD described the new project as a micro tunnel (a smaller version of the original Utility Tunnel
Project) that would be bored from Fisher Island, starting on land, go under Government Cut and
surface on the Miami Beach side of the Cut. The new line would then be connected to the existing
54-inch sewer line that serves Miami Beach. The construction involves boring a small tunnel under
Government Cut with a smaller tunnel boring machine, and placing pipe sections behind the
machine as the machine advances. The connection point would be in Government Cut and the
boring machine would be retrieved from a marine access shaft that would be built in the Cut. The
construction would not involve blasting and would need to be supported by barges operating in
Government Cut. The number of barges to be used and the duration of use is not known at this
time. At this point, WASD does not believe that the capacity of the new sewer line would change
from what is currently available to the City. The cost of the new 54-inch sanitary sewer line is
estimated to be 45 million dollars.
The impact of WASD's change in project design is that the original Utility Tunnel project would be
delayed at least until 2014. WASD indicated that it was still their intent to build the larger Utility
Tunnel Project to provide for added capacity and sewer system redundancy; however, it would now
be a part of the regular County Capital Improvement Project process. As the new 54-inch sewer line
is not intended to be temporary, the future Utility Tunnel design would likely provide fewer pipes
dedicated to sewer flow than the original design. The current design for the future Utility Tunnel,
subject to change, is for a twelve foot tunnel with a single 54-inch sewer line and a reclaimed water
line.
Page 2 of 3
WASD LTC
With the priority for the original Utility Tunnel Project no longer being driven by the Port of Miami
dredging project, it was clear to the Miami Beach representatives that WASD was not certain that
the future Utility Tunnel Project would be built as anticipated. The future or second Utility Tunnel
Project would now have to compete with other Capital Improvement Projects at the County for
resources and priority.
The uncertainty on the part of WASD as to when or if the second Utility Tunnel Project would be built
creates a dilemma for the City, which was expressed to WASD, as to how the City is to deal with the
City Coast Guard Booster Pump Station (CGBPS). In the original Utility Tunnel design, there was
sufficient sewer pipe capacity that it did not seem to be necessary to proceed with the CGBPS. In
the new approach to replace the existing 54-inch sewer line, the project only replaces current
capacity. As such, there is an operating problem that at some point in the future the City would have
to address. The same conditions that existed and were the reason for the City to pursue the
CGBPS would be present if WASD delayed or did not build the future Utility Tunnel Project. If
WASD proceeds with the second Utility Tunnel Project as planned (by 2014), the City believes that
the CGBPS would not be necessary and, as the final solution (the second Utility Tunnel) is near
term if built by 2014, there is only limited and acceptable risk on the part of the City not to proceed
with the CGBPS.
The dilemma of course, is that the City must rely on WASD to proceed with a second Utility Tunnel
Project as planned. In order to address this issue, Miami Beach representatives suggested to
WASD that the City enter into an agreement with the County to provide for the second Utility Tunnel
within an agreed upon time frame and, in the event that WASD did not pursue the second Utility
Tunnel, WASD would then assume the responsibility and cost of building a booster pump station to
address the City`s needs.
Not having to build the CGBPS as a result of having the; larger Utility Tunnel that was originally
planned by WASD, or the timely construction of the second Utility Tunnel Project, is the best option
for the City. In the event that the Utility Tunnel project does not get built as indicated by WASD, one
of the next preferable options would be for WASD to assume the responsibility and expense for the
project.
In order to help WASD assess what risk they might be assuming by virtue of an agreement as
outlined, the City agreed to develop and to provide operating capacity calculations on the City sewer
system. The operational information will help assure WASD that the City system could operate
safely for a short period of time without the need for a booster pump station.
WASD indicated that they would consider the City's suggested agreement. While WASD has
indicated they would consider an agreement, it is very likely that the assistance of our Elected
Officials and citizens will be needed to help WASD move.affirmatively.
This meeting was also the first time the City was able to discuss with WASD the reclaimed water
element of the Utility Tunnel Project. WASD indicated that a plan was not yet fully developed for the
reclaimed water that was included in the Utility Tunnel Project. Current thinking by WASD is that the
water might be used to provide less expensive waterfor the larger Condominium buildings in South
Pointe for use in cooling systems in lieu of potable water. WASD recognized that the City has no
infrastructure in place to use reclaimed water at this time. The reclaimed water element may
change in the future design, as WASD will need to develop a plan for reused water that can be
applied to the entire WASD system, and this specific pipe may not fit in those plans.
The City will be developing the required operating: information to provide to WASD as soon as
possible. Shortly after that data is provided to WASD, the City will again meet with WASD to
continue discussion of an agreement that would provide for a commitment on the part of WASD to
pursue a second Utility Tunnel and, in the event they do not proceed with that second Utility Tunnel
Page 3 of 3
WASD LTC
Project, for WASD to assume responsibility for the construction of a Booster Pump Station to
address the City's sewer system operational needs. It is anticipated that discussions will proceed
quickly enough that the City Commission can take action,Iif needed, at the January 13, 2010 City
Commission meeting.
i
As more information becomes available, it will be forwarded to the City Commission. If you have
questions, please feel free to call me or Assistant City Managers Robert Middaugh or Jorge Gomez.
JMG:RCM
F:\cmgr\$ALL\BOB\LTC-WASD Utility Tunnel Update