2011-27621 Reso RESOLUTION NO. 2011 -27621
A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF
MIAMI BEACH, FLORIDA, APPROVING A CONTRACT AWARD, PURSUANT
TO INVITATION TO BID NO. 07- 10/11, FOR THE RIGHT -OF -WAY
INFRASTRUCTURE IMPROVEMENT PROGRAM — NEIGHBORHOOD NO. 1 —
BISCAYNE POINT; AUTHORIZING THE MAYOR AND CITY CLERK TO
EXECUTE AN AGREEMENT WITH DAVID MANCINI & SONS, INC., IN THE
NOT -TO- EXCEED AMOUNT OF $10,907,759, FOR THE CONSTRUCTION OF
THE PROJECT, PLUS A 10% PROJECT CONTINGENCY IN THE AMOUNT
OF $1,090,776, FOR A GRAND TOTAL OF $11,998,535; APPROPRIATING
$6,675,401 FROM FUNDS PREVIOUSLY APPROPRIATED IN THE CAPITAL
BUDGET, AND FURTHER APPROPRIATING $5,323,134 FROM FUND 429
STORMWATER PROJECTS LINE OF CREDIT, WITH SUCH FUNDS TO BE
REPAID FROM PROPOSED FUTURE STORM WATER BONDS; FURTHER
AUTHORIZING THE ADMINISTRATION TO ENGAGE IN VALUE
ENGINEERING TO FURTHER REDUCE THE COST AND TIME FOR
COMPLETION OF SAID PROJECT.
WHEREAS, Invitation to Bid (ITB) No. 07 -10/11 was issued on November 30, 2010,
with an opening date of January 27, 2011; and
WHEREAS, Bidsync issued bid notices to 3,761 prospective bidders, which resulted in
the receipt of the following nine (9) bids:
• Central Florida Equipment Rentals, Inc.
• David Mancini & Sons, Inc.
• Foster Marine Contractors, Inc.
• GlobeTec Construction, LLC
• Horizon Contractors, Inc.
• Lanzo Construction Co. Florida
• Ric -Man International, Inc.
• Southeastern Engineering Contractors, Inc.
• Williams Paving Co., Inc.; and
WHEREAS, the City Manager appointed a Technical Review Panel (TRP), which
consisted of the following individuals:
• Humberto Cabanas, Capital Projects Coordinator, CIP Office
• Hermes Diaz, Civil Engineer II, Public Works Department
• Ricardo Guzman, Senior Planner, Planning Department
• Janette Fernandez - Arencibia, Capital Project Coordinator, CIP Office
• Jose Perez, Civil Engineer III, Public Works Department; and
r
WHEREAS, on February 14, 2011, the TRP convened to shortlist bidders based on the
following criteria:
• 50 Points — Base Bid Price
• 10 Points — Risk Assessment PlanNalue Added Submittals
• 10 Points — Past Performance Evaluation Surveys
• —
10 Points Qualifications of Bidder; and
WHEREAS, on February 17, 2011, the TRP reconvened to interview the shortlisted
bidders based on the following criteria:
• 20 Points — Presentation and interview of key personnel; and
WHEREAS, upon completion of the interviews, the TRP discussed their individual
perceptions of each prospective bidder's qualifications, experience, and competence to score
and rank David Mancini & Sons, Inc. as the lowest and best bidder; and
WHEREAS, after considering the review and recommendation of City staff, the City
Manager exercised his due diligence and concurs with the recommendation of the TRP.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND CITY COMMISSION
OF THE CITY OF MIAMI BEACH, FLORIDA, that the Mayor and City Commission hereby
approve a contract award, pursuant to Invitation to Bid (ITB) No. 07- 10/11, for the Right -of -Way
Infrastructure Improvement Program — Neighborhood No. 1 — Biscayne Point; authorize the
Mayor and City Clerk to execute an agreement with David Mancini & Sons, Inc., in the not -to-
exceed amount of $10,907,759, for the construction of the Project, plus a Project contingency,
in the amount of $1,090,776, for a grand total of $11,998,535; appropriating $6,675,401 from
funds previously appropriated in the Capital Budget; and further appropriating $5,323,134 from
Fund 429 Stormwater Projects Line of Credit, with such funds to be repaid from proposed
Future Storm Water Bonds; further authorizing the Administration to engage in value
engineering to further reduce the cost and time for completion of said project.
PASSED AND ADOPTED this c i/Il day of March-, 2011.
ATTEST:
(AAA_ ate- ' ei
CITY CLERK MA OR
T:WGENDA \2011 \March 9 \Regular \ITB 07 -10 -11 - Biscayne Point ROW Improvements - RESO.doc
APPROVED AS TO
FORM & LANGUAGE
4 FOR EXECUTION
0 .. . - ,-,.., (_____
dip PAL. . . a b . . . . i . Ai PA
k ' ;fa . ( As. D ate
1
COMMISSION ITEM SUMMARY
Condensed Title:
A Resolution Of The Mayor And City Commission Of The City Of Miami Beach, Florida, Approving A Contract Award,
Pursuant To Invitation To Bid No. 07- 10/11, For The Right -Of -Way Infrastructure Improvement Program —
Neighborhood No. 1 — Biscayne Point; Authorizing The Mayor And City Clerk To Execute An Agreement With David
Mancini & Sons, Inc. In The Not -to- Exceed Amount of 1 9 For c $ 0,907,75 o The Construction Of The Project, Plus A
10% Project Contingency In The Amount Of $1,090,776, For A Grand Total Of $11,998,535; Appropriating
$6,675,401 From Funds Previously Appropriated In The Capital Budget; And Further Appropriating $5,323,134 From
Fund 429 Stormwater Projects Line of Credit, With Such Funds To Be Repaid From Proposed Future Stormwater
Bonds; Further Authorizing The Administration To Engage In Value Engineering To Further Reduce The Cost And
Time For Completion Of Said Project.
Key Intended Outcome Supported:
Ensure well- maintained infrastructure
Supporting Data (Surveys, Environmental Scan, etc.):
The 2007 Community Satisfaction Survey noted 82% of North Beach residents rated recent capital projects
completed as "excellent" or "good" compared to 89% of residents citywide.
Issue:
1 Shall the City Commission adopt the resolution? I
Item Summary /Recommendation:
The work specified in this bid consists of the construction of the infrastructure and site works for the Biscayne Point
Right -of -Way Improvements Project. The work will include but not be limited to demolition, tree removal/ relocation,
site preparation, earthwork, roadway milling and resurfacing, asphalt pavement installation, curb and gutter installation,
sidewalk restoration, signage and striping installation, water main improvements, storm water improvements, lighting
improvements, irrigation improvements, entry improvements, vegetation and planting within the Biscayne Point,
Stillwater, and Biscayne Beach Neighborhoods.
ITB No. 07 -10/11 was issued on November 30, 2010, with an opening date of January 27, 2011. The pre -bid
conference was held on December 13, 2010. During the pre -bid conference, prospective bidders were instructed on
the procurement process and the information their respective proposals should contain. Bidsync issued bid notices to
3,761 prospective bidders which resulted in the receipt of nine (9) bids.
On February 14 and February 17, 2011, the TRP convened to shortlist and interview bidders. Upon completion of the
interviews, the TRP discussed their individual perceptions of each prospective bidder's qualifications, experience, and
competence to score and rank the firms accordingly. David Mancini & Sons, Inc. received all five first -place votes for
contract award.
Even though David Mancini & Sons, Inc. (DMSI) was founded in 2010, its project team has extensive experience
working in Miami Beach. Until recently, the project team was part of Ric -Man International, Inc. and oversaw several
major capital projects throughout the City. Some examples include water main and drainage replacements along
Sheridan Avenue and West 41 Street ($27,110,221 total cost), water main installations at 6 Street and Espaniola
Way ($13,107,139 total cost), and installation of sanitary sewer, water mains, and drainage along 5 to 15 Streets
($18,228,903 total cost). In addition, DMSI is also a JOC Horizontal ROW Contractor.
After considering the review and recommendation of City staff, the City Manager exercised his due diligence and
carefully considered the specifics of this ITB process. As a result, the City Manager recommends to the Mayor and
City Commission to award the contract to David Mancini & Sons, Inc.
ADOPT THE RESOLUTION.
Advisory Board Recommendation:
Financial Information:
Source of Amount Account Approved
Funds: 1 $4,839,213 429 - 2321 - 069357 - Fund 429 Stormwater Projects Line of Credit
OBPI 2 $3,163,856 384 - 2321 - 069357 - Fund 384 — 2003 GO Bonds — Neighborhoods
3 $2,904,690 420 - 2321 - 069357 - Fund 420 Water & Sewer GBL Series 2010
$483,921 429 - 2321 - 000356 - Fund 429 Stormwater Projects Line of Credit
4 for Contingency
$316,385 384 - 2321 - 069357 - Fund 384 — 2003 GO Bonds — Neighborhoods
5 for Contingency
$290,469 420 - 2321 - 000356 - Fund 420 Water & Sewer GBL Series 2010 for
6 Contingency
Total $11,998,535
City Clerk's Office Legislative Tracking:
Janette Fernandez - Arencibia, ext. 7170
Sign-0 :
Dep ment Dir • r Assistant City Manager /Chief Financial Officer City Manager
GL , FV JGG PDW JM
T:\AG A\2011\ /oh 9 \Regular \ITB- 07 -10 -11 — Biscayne Point ROW Improvements - Summary.doc
MIAMIBEACH AGENDA ITEM R7
DATA 3 -4 -
'""""
el MIAMI BEACH
City of Miami Beach, 1700 Convention Center Drive, Miami Beach, Florida 33139, www.miamibeachfl.gov
COMMISSION MEMORANDUM
TO: Mayor Matti Herrera Bower and Members of the City Commission
FROM: Jorge M. Gonzalez, City Manager
DATE: March 9, 2011
SUBJECT: A RESOLUTION OF THE MAYOR CITY COMMISSION OF THE CITY OF MIAMI
BEACH, FLORIDA, APPROVING A CONTRACT AWARD, PURSUANT TO
INVITATION TO BID NO. 07- 10/11, FOR THE RIGHT -OF -WAY INFRASTRUCTURE
IMPROVEMENT PROGRAM — NEIGHBORHOOD NO. 1 — BISCAYNE POINT;
AUTHORIZING THE MAYOR AND CITY CLERK TO EXECUTE AN AGREEMENT
WITH DAVID MANCINI & SONS, INC., IN THE NOT -TO- EXCEED AMOUNT OF
$10,907,759, FOR THE CONSTRUCTION OF THE PROJECT, PLUS A 10%
PROJECT CONTINGENCY IN THE AMOUNT OF $1,090,776, FOR A GRAND TOTAL
OF $11,998,535; APPROPRIATING $6,675,401 FROM FUNDS PREVIOUSLY
APPROPRIATED IN THE CAPITAL BUDGET; AND FURTHER APPROPRIATING
$5,323,134 FROM FUND 429 STORMWATER PROJECTS LINE OF CREDIT, WITH
SUCH FUNDS TO BE REPAID FROM PROPOSED FUTURE STORM WATER
BONDS; FURTHER AUTHORIZING THE ADMINISTRATION TO ENGAGE IN VALUE
ENGINEERING TO FURTHER REDUCE THE COST AND TIME FOR COMPLETION
OF SAID PROJECT.
ADMINISTRATION RECOMMENDATION
Approve the award of contract.
KEY INTENDED OUTCOMES SUPPORTED
Ensure well- maintained facilities.
FUNDING
$4,839,213 429 - 2321 - 069357 - Fund 429 Stormwater Projects Line of Credit
$3,163,856 384 - 2321 - 069357 - Fund 384 — 2003 GO Bonds — Neighborhoods
$2,904,690 420 - 2321 - 069357 - Fund 420 Water & Sewer GBL Series 2010
$483,921 429 - 2321 - 000356 - Fund 429 Stormwater Projects Line of Credit for Contingency
$316,385 384- 2321 - 069357 - Fund 384 — 2003 GO Bonds — Neighborhoods for Contingency
$290,469 420 - 2321 - 000356 - Fund 420 Water & Sewer GBL Series 2010 for Contingency
$11,998,535 Total
ANALYSIS
On October 15, 2003, the Mayor and City Commission adopted Resolution No. 2003 - 25376,
approving the Infrastructure Improvement Program Basis of Design Report (BODR) for the
Commission Memorandum — ITB -07 -10/11 — Biscayne Point ROW Improvements
March 9, 2011
Page 2 of 5
Biscayne Point Neighborhood prepared by The Corradino Group, Inc. This BODR was the
culmination of a comprehensive planning effort that included input from and reviews by
residents, various City Departments, and the Design Review Board (DRB). After several
unfruitful attempts to negotiate a reasonable fee for the design, bid and award, and construction
administration of the project, the City terminated its relationship with The Corradino Group Inc.
On October 13, 2004, the City issued a Request for Qualifications (RFQ), to select another
Consultant to complete the Biscayne Point Neighborhood Improvement Project. As a result, on
July 27, 2005, the Mayor and City Commission adopted Resolution No. 2005- 25973, approving
and authorizing the Mayor and City Clerk to execute an agreement with EAC Consulting, Inc. to
provide professional Engineering and Landscape Architecture consulting services for the
Biscayne Point Neighborhood Right -of -Way (ROW) Improvement Project.
In general, the Project limits are bounded by 86 Street to the north, 77 Street to the South,
Crespi Boulevard to the east, and Biscayne Bay to the west. The proposed work activities are
anticipated along all the right -of -ways located within the Biscayne Point, Biscayne Beach, and
Stillwater islands. For a graphical representation of the Project limits, reference Exhibit A.
SCOPE OF SERVICES
The work specified in this bid consists of the construction of the infrastructure and site works for
the Biscayne Point Right -of -Way Improvements Project. The work will include but not be limited
to demolition, tree removal/ relocation, site preparation, earthwork, roadway milling and
resurfacing, asphalt pavement installation, curb and gutter installation, sidewalk restoration,
signage and striping installation, water main improvements, storm water improvements, lighting
improvements, irrigation improvements, entry improvements, vegetation and planting within the
Biscayne Point, Stillwater, and Biscayne Beach Neighborhoods.
BID PROCESS
Invitation to Bid (ITB) No. 07 -10/11 was issued on November 30, 2010, with an opening date of
January 27, 2011. The pre -bid conference was held on December 13, 2010. During the pre -bid
conference, prospective bidders were instructed on the procurement process and the
information their respective proposals should contain.
Bidsync issued bid notices to 3,761 prospective bidders which resulted in the receipt of the
following nine (9) bids:
• Central Florida Equipment Rentals, Inc.
• David Mancini & Sons, Inc.
• Foster Marine Contractors, Inc.
• GlobeTec Construction, LLC
• Horizon Contractors, Inc.
• Lanzo Construction Co. Florida
• Ric -Man International, Inc.
• Southeastern Engineering Contractors, Inc.
• Williams Paving Co., Inc.
Through the Procurement Division's review of each bid for responsiveness, Ric -Man
International, Inc. and Foster Marine Contractors, Inc., the third (3 and ninth ( 9 th ) highest
bidders at $13,441,335.47 and $18,664,050.90 respectively, were disqualified for not meeting
Commission Memorandum — I TB -07 -10/11 — Biscayne Point ROW Improvements
March 9, 2011
Page 3 of 5
the ITB's 75% self - performance minimum requirement by noting that 34.05% and 44.89% of the
work respectively was to be subcontracted. Horizon Contractors, Inc., the sixth (6 highest
bidder at $14,762,011.57, was also disqualified for failing to submit omitted information as
requested.
As a result, the following table provides the proposed lump sum bid prices of the six (6)
responsive bids:
inielinempliongosiemeoppoingamonsionntaimmesom
UNIMMIONEMBEIRMipmismoommoommpownommagia
r „ ,FB : Price
David Mancini & Sons, Inc. $10,907,758.61
Globetec Construction, LLC $12,726,986.01
Central Florida Equipment Rentals, Inc. $13,789,750.66
Lanzo Construction Co. Florida $14,223,745.96
Southeastern Engineering Contractors, Inc. $15,842,502.65
Williams Paving Co., Inc. $16,624,499.34
The Technical Review Panel (TRP) consisted of the following individuals:
• Humberto Cabanas, Capital Projects Coordinator, CIP Office
• Hermes Diaz, Civil Engineer II, Public Works Department
• Ricardo Guzman, Senior Planner, Planning Department
• Janette Fernandez - Arencibia, Capital Project Coordinator, CIP Office
• Jose Perez, Civil Engineer III, Public Works Department
On February 14, 2011, the TRP convened to shortlist bidders based on the following criteria:
• 50 Points - Base Bid Price
• 10 Points - Risk Assessment PlanNalue Added Submittals
• 10 Points - Past Performance Evaluation Surveys
• 10 Points — Qualifications of Bidder
As a result of the shortlisting process, the TRP invited the following companies for interviews:
• Southeastern Engineering Contractors, Inc.
• GlobeTec Construction, LLC
• Central Florida Equipment Rentals, Inc.
• David Mancini & Sons, Inc.
On February 17, 2011, the TRP reconvened to interview the shortlisted bidders based on the
following criteria:
• 20 Points - Presentation and interview of key personnel
Commission Memorandum — ITB -07- 10/11— Biscayne Point ROW Improvements
March 9, 2011
Page 4 of 5
Upon completion of the interviews, the TRP discussed their individual perceptions of each
P P p p
prospective bidder's qualifications, experience, and competence to score and rank the firms
accordingly. David Mancini & Sons, Inc. received all five first -place votes for contract award as
noted below:
FINAL RANKING
3
David Mancini & Sons, Inc. 1 (91) 1 (95) 1 (89) 1 (83)) 1 (97) 455
GlobeTec Construction, LLC 2 (84) 2 (84) 2 (79) 2 (70) 2 (83) 400
Lanzo Construction Co. Florida 3 (59) 3(75) 3 (74) 3 (63) 3 (74) 345
David Mancini & Sons, Inc.
Even though David Mancini & Sons, Inc. (DMSI) was founded in 2010, its project team has
extensive experience working in Miami Beach. Until recently, the project team was part of Ric -
Man International, Inc. and oversaw several major capital projects throughout the City. Some
examples include water main and drainage replacements along Sheridan Avenue and West 41
Street ($27,110,221 total cost), water main installations at 6 Street and Espanola Way
($13,107,139 total cost), and installation of sanitary sewer, water mains, and drainage along 5th
to 15 Streets ($18,228,903 total cost). In addition, DMSI is also a JOC Horizontal ROW
Contractor.
CITY MANAGER'S REVIEW
After considering the review and recommendation of City staff, the City Manager exercised his
due diligence and carefully considered the specifics of this ITB process. As a result, the City
Manager recommends to the Mayor and City Commission to award the contract to David
Mancini & Sons, Inc.
It should be noted that the City's regular process of considering the price for projects and its
standard process for bidding construction projects has resulted in a price that is reflective of the
current market. At present, it appears that the market is very competitive and that the City may
continue to receive bids that are lower than those received in the past year or so. The public
procurement process, which is an open and competitive, transparent process, has again served
the City to provide the lowest and best bidder for this project, as it has in the past, with a
proposed proiect cost which is approximately $2,492,241 lower than the construction budget.
CONCLUSION
The Administration recommends that the Mayor and City Commission adopt the attached
resolution, which awards a contract to David Mancini & Sons, Inc. as the lowest and best
responsive bidder, pursuant to Invitation to Bid 07- 10/11, for the right -of -way infrastructure
improvement program — Neighborhood No. 1 — Biscayne Point, based on a total not -to- exceed
lump sum of $10,907,758.61; plus a project contingency in the amount of $1,090,775.86 for a
grand total of $11,998,534.47; appropriating $6,675,401 from funds previously appropriated in
the capital budget; and $5,323,134 to be appropriated from Fund 429 Stormwater Projected
Line of Credit, with such funds to be repaid from proposed future storm water bonds; and further
Commission Memorandum — I TB -07 -10/11 — Biscayne Point ROW Improvements
March 9, 2011
Page 5 of 5
authorize the Administration to engage in value engineering to further reduce the cost and time
for completion of said project.
ATTACHMENTS (3):
1. Unit Price Breakdown Form
2. Representative Projects
3. Project Limits
T:\AGENDA\2011 \March 9 \Regular \ITB 07 -10 -11 - Biscayne Point ROW Improvements - MEMO.docx
.... - .. •.; , ;`!TB 07 -10f 11. UNIT PRICE.BID BREAKDOWN (ADDENDUM 7)
places. Should the Bidder provide more than two decimals on the unit price, the City will round the number to the nearest hundredth, this is two decimal places to
arrive at the total.
The TOTAL BASE BID AMOUNT includes the total cost for the work specified in this bid, consisting of furnishing all materials, labor, equipment, supervision,
mobilization, demobilization, overhead and profit, insurance, permits, and taxes to complete the work to the full intent as shown or indicated in the contract
documents. The administrative evaluation process will allocate a total of sixty (60) points based on the TOTAL BASE BID AMOUNT plus none, any, or all
alternatives which may be selected at the City's sole discretion and based on funding availability. Bidders must fully complete the Schedule of Prices Bid Form to
include unit pricing and totals. The cost of any item(s) of work not covered by a specific contract unit price shall be included in the contract unit price to which the
item(s) is most applicable.
The General Conditions include certain "Allowance" items that have been delineated below. The Contract Unit Price for these allowance items shall be used only
upon the City's discretion, as needed. In the event that the item of work is not conducted or only a portion of the estimated allowance is used, the Bidder
understands that the balance of the cost shall be returned to the City.
IN THE EVENT OF ARITHMETICAL ERRORS, THE BIDDER AGREES THAT THESE ERRORS ARE ERRORS WHICH MAY BE CORRECTED BY THE CITY. GIVE BOTH UNIT PRICE
AND EXTENDED TOTAL. PRICES MUST BE STATED IN UNITS OF QUANTITY SPECIFIED IN THE BIDDING SPECIFICATIONS. BIDDER AGREES THAT ANY UNIT PRICE LISTED
IN THE BID IS TO BE MULTIPLIED BY THE STATED QUANTITY REQUIREMENTS IN ORDER TO ARRIVE AT THE TOTAL. IN CASE OF DISCREPANCY IN COMPUTING THE
AMOUNT OF THE BID, THE UNIT PRICE SHALL GOVERN. THE CITY WILL NOT ACCEPT ANY REVISION TO THIS UNIT PRICE FORM, DIVISIONS, LINE ITEMS, ADD
ALTERNATES, OR GRAND TOTAL BID, AFTER THE DEADLINE FOR RECEIPT OF BIDS. IN ABSENCE OF ANY TOTALS SUBMITTED, THE CITY SHALL INTERPRET AS ZERO.
PROJECT: ITB 07 -10 /11 - RIGHT -OF -WAY IMPROVEMENTS — NEIGHBORHOOD NO. 1 - BISCAYNE POINT
COMPANY NAME:
Summary
rY
1- General Conditions $1,269,125.00
2 - Demolition $385,829.26
3 - Water and Sewer $1,661,833.00
4 - Stormwater $2,417,652.06
5 - Paving and Hardscaping $1,789,132.20
6 - Landscaping /Irrigation and Street Furniture $465,312.70
7 - Lighting $2,506,465.40
w` *'
.. r £ 1 F<u.a..az' 7$ .,.! .' a t4 's, r' s.. -^. ,�' .,,..✓ '.E #..!"", >, x r
;�;'"` •� � ..; � 3 � � � s�; �;.., _-_ ? �,.�, « .�. - >.w �; ��;. � ;� �.,.� ,$��� =.:; � � �„';�k'>kAl SASE BII� AM�I�NI' < .:5w..
...�, �$�Q�4S�$,349.61
8 - ADDITIVE Alternate Bid Items $412,409.00
f e g >.. ;,. , ". ` -t.: M t: ORAM TAL BASCARAMPYRITMAL DIAMOM* ERNATES). -$]:0;90V$8 6
Bidder's Affirmation:
Written Total: Ten million nine hundred seven thousand seven hundred fifty eight dollars and sixty one cent
Company: David Mancini & Sons, Inc.
Address: 1247 Alton Road, Miami Beach, FL 33139
Telephone: 305- 532 -8827
Email: dmancini @dmsi.co
Signature:
Title /Printed Name: President /David Mancini
c 4 .
1- General Conditions
1.01 Bonds and Insurance 1 LS $,:: 58,700.00 $58,700.00
1.02 Mobilization / Demobilization 1 LS $ `110,000.00 $110,000.00
1.03 Survey Layout and As- builts 1 LS $.: 61,000.00 $61,000.00
1.04 Maintenance of Traffic 1 LS $ '. 43,000.00 $43,000.00
1.05 Public Information/ Liaison Services 1 LS $;: 77,400.00 $77,400.00
1.06 Project Office / Staging Area 1 LS $:150,000.00 $150,000.00
1.07 Dewatering 1 LS $-... 53,000.00 $53,000.00
1.08 Other General Requirements 1 LS '$' 380,000.00 $380,000.00
1.09 Allowance: For Consideration for Indemnification 1 LS $ 25.00 $25.00
1.10 Allowance: Permits 1 LS $::', 80,000.00 $80,000.00
1.11 1 $ "200,000.00 $200,000.00
Allowance: Existing Outfall TV Inspection (Pre and Post) and Repair /Replacement LS
1.12 Allowance: TV Inspection (Pre and Post) of Existing Sanitary Sewer 1 LS $,;::.56,000.00 $56,000.00
2 .y.: 3 .. n . _ f r, w
. 11,1<, •, 1.1 y.... ,.s 1 ..1# , taj 0 t 1 ; General Conditions Totat mit $ 269;125.00
2 - Demolition
2.01 Utility pipe, plug and place out of service /abandoned 19,800 LF $ 0.81' $16,038.00
2.02 Remove and dispose utility pipe 2 - 4.9" 50 LF $ 5.40 $270.00
2.03 Remove and dispose utility pipe 8- 19.9" 290 LF $ • 10.75 $3,117.50
2.04 Remove existing fire hydrant 1 EA $ , ,.'269.00 $269.00
2.05 Relocate existing fire hydrant 16 EA $;, .... 375.00 $6,000.00
2.06 Remove existing structure, manhole 3 EA $ 400.00 $1,200.00
2.07 Remove existing structure, inlet 23 EA $ ,:344.00 $7,912.00
2.08 Remove curb and gutter 4,590 SY $ 14.50 $66,559.64
2.09 Remove concrete sidewalk 9,125 SY $ .' 9.40 $85,775.00
2.10 Pavement removal 7,300 SY $ 2.00 $14,600.00
2.11 Clear and grub 6,395 SY $ ; >2.70 $17,266.42
2.12 Remove existing tree 26 EA . :$'.::.. , ...:.•i: , ': , ..160.00 $4,160.00
2.13 Remove existing palm 100 EA $'!. 110.00; $11,000.00
2.14 Mill pavement, 1 inch 100,905 SY , . 1.45; $146,312.70
2.15 Relocate existing wood fence 150 LF $ , '11.00' ` $1,650.00
2.16 Single post sign, remove 137 AS $ 27.00' $3,699.00
g `1° - Ym 4.:t Z ^b# T i" ' ,i ,' !` .a, R a `. R 4 J
., +„ 4 ., r.• :. � i � ,., ... -: a ar._ 'O d§ � ...,>,:n <. .. � .i. ;{ � � Z. tik: �� ...:� k oS ��. �' yl >z ' y "7"', `.` =m �' l,•Q;t {a*NtY# ' Ie7
3 - Water and Sewer
3.01 16 -inch ductile iron i e DfP 1,000 LF
p p ( ) $ :.. :.86.00- $86,000.00
3.02 8-inch ductile iron pipe (DIP) 16,700 LF $ 35.50: $659,650.00
3.03 8 -inch DIP horizontal bends 27 EA $ , 140.00 $3,780.00
3.04 8 -inch DIP vertical bends 48 EA $ 154.00 $7,392.00
3.05 8 -inch DIP valves and valve boxes 43 EA $ ' `966.00 $41,538.00
3.06 6 -inch ductile iron pipe (DIP) 1,050 LF $ : $34,650.00
3.07 6 -inch DIP valves and valve boxes 42 EA $ 650.00 $27,300.00
3.08 16" x 8" Tapping sleeve and valve 6 EA $ ;.5,500.00 $33,000.00
3.09 12" x 8" Tapping sleeve and valve 1 EA $ ' 4;300.00 $4,300.00
3.10 8" x 8" Tapping sleeve and valve 8 EA $ 1,100.00 $8,800.00
3.11 6" x 6" Tapping sleeve and valve 3 EA $•:,:::'•.:::::i,: 900.00 $2,700.00
3.12 16" x 8" Tee 3 EA $ ` 900.00 $2,700.00
3.13 16" x 6" Tee 1 EA $ 800.00 $800.00
3.14 8" x 8" Tee 14 EA $ !;_ '500.00 $7,000.00
3.15 8" x 6" Tee 45 EA $ s'_ 400.00 $18,000.00
3.16 Air release valves 35 EA ,$ 650.00 $22,750.00
3.17 Fire hydrant assemblies 22 EA $ `, ::2,000.00 $44,000.00
3.18 2 -inch water service in ROW 10,500 LF
$ -'' <49.00 $514,500.00
3.19 16" x 12" offset bend 1 EA $ :1,500.00 $1,500.00
3.20 8" x 18" offset bend 8 EA $ 360.00 $2,880.00
3.21 8" x 12" offset bend 2 EA $ 310.00 $620.00
3.22 2 -inch cap & plug w/ flushing valve 2 EA $ i 430.00 $860.00
3.23 6 -inch cap & plug w/ flushing valve 13 EA $ 511.00 $6,643.00
3.24 8 -inch cap & plug w/ flushing valve _ 10 EA $ 535.00 $5,350.00
3.25 6" reinforced concrete slab 60 LF $ : 79.00 $4,740.00
3.26 Flexible pavement restoration 13,333 SY $ 9.00 $120,000.00
3.27 8 "x6" Reducer 2 EA $ 190.00 $380.00
=3 = Water and Sewer . $1,661,83300
4 - Stormwater
4.01 Core and Tie to Existing Pipe 4 EA $ 535.00 $2,140.00
4.02 Relocate Exist Inlet 4 EA $`'.`.::2,600.00 $10,400.00
4.03 Curb Inlet Type 4, P Bottom 2 EA $' 3,800.00 $7,600.00
4.04 Curb Inlet Type 5, P Bottom 26 EA $ 2,900.00 $75,400.00
4.05 Curb Inlet Type 5, J Bottom 10 EA $ ;" .3,100.00 $31,000.00
4.06 Curb Inlet Type 6, P Bottom 11 EA $ • 3,200.00 $35,200.00
4.07 Curb Inlet Type 6, J Bottom 12 EA $ ` ?3,400.00 $40,800.00
4.08 Curb Inlet Type 9, P Bottom 10 EA $ '2,300.00 $23,000.00
4.09 Curb Inlet Type 9, J Bottom 18 EA $ 2,550.00 $45,900.00
4.10 Gutter Inlet Type V, J Bottom 1 EA $ 3,100.00 $3,100.00
4.11 Ditch Bottom Inlet Type F, J Bottom 5 EA $ ? .2,450.00 $12,250.00
4.12 Manhole, P7T 14 EA $ '? 2,250.00 $31,500.00
4.13 Manhole, J7T 48 EA $ 2,957.00 $141,936.00
4.14A 12 -inch RCP pipe 73 LF $ •41.00 $2,993.00
4.14B 15 -inch RCP pipe 20 LF $ .:. ... . $860.00
4.15A 18 -inch RCP pipe 1850 LF $ •48.00 $88,800.00
4.15B 14 "x23" - elliptical RCP pipe 135 LF $ :;._ _ ._.':60.00 $8,100.00
4.16A 24 -inch RCP pipe 3750 LF $ -.,., .. ,;'55.00 $206,250.00
4.16B 19 "x30" - elliptical RCP pipe 675 LF $ . 73.00 $49,275.00
4.17 30 -inch RCP pipe 2000 LF •$ ;65.00 $130,000.00
4.18 36 -inch RCP pipe 40 LF $ •:83.00 $3,320.00
4.19 Flexible Pavement Restoration 4746 SY $ ` 9.50 $45,088.06
4.20 24 -inch drainage Well (Hole Boring) (assume 25 feet) 28 EA $ • 1,350.00 $37,800.00
4.21A 24 -inch drainage Well (Casing)(assume 75 feet) 20 EA $ 8,600.00 $172,000.00
4.21B 36 -inch drainage Well (Casing)(assume 75 feet) 8 EA $' ? 9,000.00 $72,000.00
4.22 Special Structures for Drainage Wells 28 EA $ ;4,550.00 $127,400.00
4.23 Special Grates for Disconnected Bulb outs 2000 LF $-: ; 108.00 $216,000.00
4.24 Special Outlet Structures w /Red Valve 2 EA $.;..:21,000.00 $42,000.00
4.25 Special Control Structures 5 EA $ : :6,234.00 $31,170.00
4.26 HydroDynamic Separation Structures 1 EA $ 50,000.00 $50,000.00
4.27 Stormwater Pumping Station (incl structural) 4 EA $ "'.126,000.00 $504,000.00
4.28 16 -inch DIP Ductile Iron Pipe 675 LF .S.:::. ; $41,850.00
4.29 12 -inch DIP Ductile Iron Pipe 150 LF $ ;:39.00` $5,850.00
4.30 16 "x16" Tee 12 EA $ ,` $28,200.00
4.31 16 "x24" Tee to Well Head Connector 8 EA $ : _;2,800.00 $22,400.00
4.32 16" Horiz. Bend 15 EA $'? 720.00 $10,800.00
4.33 16" Vertical Bend 21 EA .$-.-r...7'.'...:720.00 $15,120.00
4.34 12" Horiz. Bend 3 EA $.:-:::.,:::.:.-: 410.00 $1,230.00
4.35 16 "x12" Reducer 4 EA $ .730.00 $2,920.00
4.36 Desilting Pipe 4200 LF $ 3.25' $13,650.00
4.37 Desalting Structure 105 EA $ 270.00' $28,350.00
" t � M3y .x..,,� x `+'s ... - '7. ��.,. � '.T�' w.b :..:µ G,�- ,er>.. __."` krc X �.'�/ .`�u �f �. ...::, .. .
:.r.� .-a£,..,,..„� -. t_.g a ..:..£ . �..... �Xi '.. - s & ; �`S. .. c x , '°`e t •. y tata. -S ;3 _ �'<' 3i p`
. � .: .��� _ . 3 . N,.��� .� � .... ...�: -� �,. .���< �;,� � fi < � :�,- �Stormwat erTotal V;41Z652:06
5 - Paving and Hardscaping
5.01 Road base 8 -inch thickness 4,530 SY . .S . ...'::'.. , ..:. , :....:12.50 $56,625.00
5.02 Road base 12 -inch thickness (type B stabilization) 4,530 SY $ 1.90 $8,607.00
5.03 Superpave Asphaltic Concrete Pavement 1 -inch lift, Type SP -9.5 76,330 SY $.> 15.35 $408,365.50
5.04 Superpave Asphaltic Concrete Pavement 1.5 -inch lift, Type SP -9.5 24,580 SY $ 8.00 $196,643.20
5.05 Superpave Asphaltic Concrete Pavement 2 -inch lift, Type SP -9.5 2,490 SY $ 10.60 $26,394.00
5.06A Stamped asphalt (Patterned /Textured) 1,250 SY $ X20.00 $25,000.00
5.07 pavers, crosswalk 1,825 SY •$ 38.00 $69,350.00
5.08 Sidewalk, 4 -inch thickness (red) 8,400 SY $ '_,...., 133.00 $277,200.00
5.09 Sidewalk, 6 -inch thickness (red) 1,275 SY $ 40.00 $51,000.00
5.10 24 -inch valley gutter 640 LF $ (. 13.25 $8,480.00
5.11 Drop curb 4,200 LF $ :' 13.25 $55,650.00
5.12 Concrete curb, type D 14,800 LF $ __ _ 11.50 $170,200.00
5.13 Concrete curb and gutter, special (2.5' gutter) 5,500 LF $- 17.00 $93,500.00
5.14 Concrete curb and gutter, type F 9,700 LF $ is .14.00 $135,800.00
5.15 Detectable warning on walking surface 101 EA $ 190.00 $19,190.00
5.16 Single post sign, f &I, less than 12 SF 132 AS $ 160.00 $21,120.00
5.17 Double post sign, f &I, less than 12 SF 98 AS $ 250.00 $24,500.00
5.18 Retro - Reflective Pavement Markers 600 EA $:. 2.65 $1,590.00
5.19 Thermoplastic, std, white, solid, 6" 33,250 LF I $ 0.65 $21,612.50
5.20 Thermoplastic, std, white, solid, 12" 4,150 LF $ 1.60 $6,640.00
5.21 Thermoplastic, std, white, solid, 18" 4,600 LF $ 2.10 $9,660.00
5.22 Thermoplastic, std, white, solid, 24" 1,150 LF $ 2.85 $3,277.50
5.23 Thermoplastic, std, yellow, skip, 6" 8,300 LF $ 0.65 $5,395.00
5.24 Thermoplastic, std, white, message 8 EA $ 86.00 $688.00
5.25 Thermoplastic, std, white, arrow 19 EA $ 43.00 $817.00
5.26 Thermoplastic, std, yellow, solid, 6" 12,850 LF $ 0.65 $8,352.50
5.27 Thermoplastic, std, yellow, solid, 18" 195 LF $ 2.10 $409.50
5.28 Thermoplastic, std, white, 2 " -4" skip 490 LF $ 0.65 $318.50
5.29 Auger Cast Piles (Biscayne Point Entry Feature) 300 LF $ 54.00 $16,200.00
5.30 Cast in Place Concrete - Pile Cap Foundations (Biscayne Point Entry Feature) 65 CY $ 215.00 $13,975.00
5.31 Cast in Place Concrete - Vertical Pillars (Biscayne Point Entry Feature) 48 CY - $:;,;:. 270.00 $12,960.00
5.32 Concrete Forms and Accessories (Biscayne Point Entry Feature) 12 EA $ ` 270.00 $3,240.00
5.33 Concrete Reinforcement, for Concrete Work (Biscayne Point Entry Feature) 12 EA $ : ..270.00 $3,240.00
5.34 Grouts, for Concrete Work (Biscayne Point Entry Feature) 12 EA $ 54.00 $648.00
5.35 Masonry Units - Brick Veneer (Biscayne Point Entry Feature) 480 SF $ 21.50 $10,320.00
5.36 Stone Veneer (Biscayne Point Entry Feature) 192 SF $ 54.00 $10,368.00
5.37 Glass Block (Biscayne Point Entry Feature) 6 EA $ 1,000.00 $6,000.00
5.38 Concrete Reinforcement, for Masonry Work (Biscayne Point Entry Feature) 12 EA $ 161.00 $1,932.00
5.39 Grouts, for Masonry Work (Biscayne Point Entry Feature) 12 EA $ 161.00 $1,932.00
5.40 Smoot Coat plaster finishes - banding (Biscayne Point Entry Feature) 12 EA $ " °.`161.00 $1,932.00
6 - Landscaping /Irrigation and Street Furniture
6.01 St. Augustine Sod 15,800 SF $ .0.35 $5,530.00
6.02 Groundcover 6,890 EA .$ 3.20 $22,048.00
6.03 Shrub 3,711 EA $ 7.65 $28,389.15
6.04 Tree, Medium -Large 439 EA $' 204.00 $89,556.00
6.05 Tree, Small 117 EA $ ': 125.00 $14,625.00
6.06 Palm, Large 100 EA $`'., 700.00 $70,000.00
6.07 Palm, Small 45 EA $ •470.00 $21,150.00
6.08 Install Rain Bird Bubblers 577 EA $ ;.. .- 23.00 $13,271.00
6.09 Install Rain Bird Shrub Spray Sprinklers 14 EA $ •27.00 $378.00
6.10 Install Rain Bird 6" Pop -up Spray Sprinklers 464 EA $'' .33.70 $15,636.80
6.11 Install Rain Bird 12" Pop -up Spray Sprinklers 727 EA $38 $27,807.75
6.12 Install Rain Bird Pop -up Rotors 10 EA $45 $450.00
6.13 Install Rain Bird 1" Solenoid Valve 12 EA $110 $1,320.00
6.14 Install Rain Bird 1 1/2" Solenoid Vaive 14 EA $130 $1,820.00
6.15 Install Rain Bird 2" Solenoid Valve 6 EA $156 . $936.00
6.16 Install Rain Bird Quick Coupler Valve 36 EA $121 $4,356.00
6.17 Install Motorola Expansion Controller 1 EA $4,650 $4,650.00
6.18 Install Leit 4 Station Ambient Light Controller 2 EA $1,200 $2,400.00
6.19 Install Rain Bird rain Sensor 5 EA $89 . $445.00
6.20 Install Pressure Vacuum Breaker Backflow Preventer 5 EA $454 $2,270.00
6.21 Install 2" Ball Vaive 32 EA $71 $2,272.00
6.22 Tie -in to existing system 4 EA $403 .. , . $1,612.00
6.23 Install #12 AWG THHN Control Wire 10,000 LF $0.15 $1,500.00
6.24 Install #14 AWG THHN Control Wire _ 43,000 LF $0.12 $5,160.00
6.25 Install SCH 40 PVC Gray Wire Conduit 10,000 LF $1.25 $12,500.00
6.26 Install 3" SCH 40 PVC Main Line 1,500 LF $3.25 $4,875.00
6.27 Install 2 1/2" SCH 40 PVC Main Line 5,700 LF $2.75 $15,675.00
6.28 Install 6" SCH 40 PVC Sleeve Under Pavement 400 LF $10 33 $4,132.00
6.29 Install 4" SCH 40 PVC Sleeve Under Pavement 4,100 LF $6.37:: $26,117.00
6.30 Install 3" SCH 40 PVC Sleeve Under Pavement 1,500 LF $5.42 $8,130.00
6.31 Install 2" SCH 40 PVC Sleeve Under Pavement 13,000 LF $4.05‘.;:, $52,650.00
6.32 Install an Arad Flow Meter 1 EA $1;400.00 $1,400.00
6.33 Install DC latching adapters on solenoid valves 8 EA $147.00: $1,176.00
6.34 Restore existing irrigation r ble condition 1 LS 1,07 .00? 1
6.3 Re g to ope a o $ , 5 $ , 075.00
,,.b .,, 1"vit " , r &: Ak" x^ $ .L � `L �6 S' y '' '``ii d . i.,z �:: �yw,y,,� { r� r sr 5 r //��
4 a::: t ..1 Y ,. k` .,.^Y" � mod. i ,� ., . . N F �.:M04000 i**StoOtsiokoloto ASxxa' eyl. 7 070
7 - Lighting
2" PVC Schedule 80 conduit installed in earth /existing pavement /existing sidewalk.
Includes hand excavation, saw- cutting, labor, conduits, connectors, warning tape,
7.01 37,050 LF $ 2.60 $96,330.00
pull string, sod restoration, concrete /pavement repair, and backfill complete in
place.
#6, 600V, XHHW Conductor installed in new conduits. Includes installation,
7 02 conductors, testing, connectors, waterproof splice kits, terminations, 74,800 LF $
identification, pulling compound, pull string, labor and etc. for a complete working ` 1.20 $89,760.00
system in place.
#4, 600V, XHHW Conductor installed in new conduits. Includes installation,
7.03 conductors, testing, connectors, waterproof splice kits, terminations, 36,350 LF
identification, pulling compound, pull string, labor and etc. for a complete working $ 1.35 $49,072.50
system in place.
#1, 600V, XHHW Conductor installed in new conduits. Includes installation,
7.04 conductors, testing, connectors, waterproof splice kits, terminations, 2,350 LF
identification, pulling compound, pull string, labor and etc. for a complete working $ 2.90 $6,815.00
system in place.
New pull box installed in earth complete in place. Includes hand excavation, pull
7.05 box, grounding, rock, waterproof splice kits, identification, labor, sod restoration, 17 EA $ 364.00 $6,188.00
backfill, and etc. complete in place.
New FP &L splice box installed in earth, provided by FP &L and installed by the
7.06 Contractor, complete in place. Includes hand excavation, labor, restoration, 11 EA $ 26.90 $295.90
backfill, coordination, and etc. complete in place.
Provide and install new electrical service point, complete. Includes stainless steel
enclosure, meter & meter can, panel, circuit breakers, lighting contactor,
7 07 wireways, photocell, surge protective devices (SPDs), conduits, conductors, 6 EA
testwells, grounding, rebar, concrete, connections, testing, identification, splice $ ! 6,000.00 $36,000.00
kits, mounting hardware, hand excavation, labor, coordination, and etc., complete
in place.
Provide and install new electrical service point "D" on new concrete pole,
complete. Includes concrete pole, hand excavation, meter & meter can,
7 08 combination panel - lighting contactor, circuit breakers, wireways, photocell, surge 1 EA
$ - 6,000 00. $6,000.00
protective devices (SPDs), conduits, conductors, testwells, grounding, concrete,
connections, testing, identification, splice kits, mounting hardware, labor,
coordination. and etc.. comnlete in mace.
New 100W MH acorn street light luminare, fiberglass pole, and pullbox installed in
earth /existing sidewalk, complete in place. Includes hand excavation, saw- cutting,
7.09 fixture, pole, concrete base, pullbox, fuses, fuse kits, splice kits, grounding, 177 EA $ 3,700.00 $654,900.00
conduits, conductors, testing, lamps, labor, photocell, sod restoration,
concrete /pavement repair, and backfill complete in place.
New 100W MH acorn street light luminare, mounted on existing concrete pole,
7.10 complete in place. Includes removal of existing fixture, delivery of existing fixture, 137 EA
new fixture, fuses, fuse kits, splice kits, conductors, testing, photocell, lamps, and $ 1,200.00 $164,400.00
labor complete in place.
New 100W MH acorn street light luminare, concrete pole, and pullbox installed in
earth /existing sidewalk, complete in place. Includes hand excavation, saw - cutting,
removal of existing fixture and pole, delivery of existing fixture to owner, disposal
7.11 of existing pole, new fixture, new pole, pullbox, fuses, fuse kits, splice kits, 5 EA
g p p p $ ; 1,700.00 $8,500.00
grounding, conduits, conductors, interception of existing circuit conductor and
conduit systems, testing, lamps, labor, photocell, sod restoration,
concrete /pavement repair, and backfill complete in place.
New 100W PSMH post top street light luminare, fiberglass pole, and pullbox
installed in earth /existing sidewalk, complete in place. Includes hand excavation,
7.12 saw- cutting, fixture, pole, concrete base, pullbox, fuses, fuse kits, splice kits, 4 EA $ 3,450.00 $13,800.00
grounding, conduits, conductors, testing, lamps, labor, photocell, sod restoration,
concrete /pavement repair, and backfill complete in place.
New 70W PSMH post top street light luminare installed on new pillars, complete in
7.13 place. Includes fixture, fuses, fuse kits, splice kits, grounding, pullbox, conduits, 12 EA
$ . 1,722.00 $20,664.00
conductors, testing, lamps, labor, photocell, and pillar mounting brackets
complete in place.
New pump station electrical and control system, complete in place. Includes
control panel, pump control system, motor controllers, terminal strips, float
switches, rain sensor, contacts, motor starters, generator receptacle, receptacles,
7.14 lighting, switches, UL lableing, conduits, conductors, flow meter, circuit breakers, 4 EA $ 338,435.00 $1,353,740.00
grounding, ground rods, meter can, pedestal, channel, transformer, mounting
hardware, test well, conduit seal, alarm light, testing, wireways, surge protective
devices (SPDs), lightning arrestor, concrete, identification, splice kits, mounting
hardware, labor, coordination, and etc., complete in place.
7 - `Lighting Total ` . ' $2,506,465.40
8 - ADDITIVE Alternate Bid Items
8.01 Water Meter - Residential 585 EA
$ 537.00 $314,145.00
8.02 Stamped Asphalt (Patterned /Textured) (2 ft Strip at Stillwater Sub Neighborhood) 692 SY $ 92.00 $63,664.00
8.03 Pavers, Alternate 2 ft Strip (Stillwater Sub Neighborhood) 692 SY $ ` 50.00 $34,600.00
. $ - ADDITIVE Alternate Bid itemS $412,409.00
Neighborhood No. 7 Nautilus ROW Infrastructure improvement
Project
Miami Beach, Florida
Project Location:
Sheridan Ave. & W. 41 Street
Description of Work Performed:
Watermain & Drainage Replacement, 6 New Pump Station and Wells
8" WM, 18" to 42" HDPE /RCP
Name, Address, Phone, & Fax # of Owner or Agency:
City of Miami Beach
1700 Convention Center Dr.
Miami Beach, FL 33139
Contact Name:
Aurelio Carmenates
Phone: (305) 673 -7000
Fax: (305) 673 -7073
Architect or Landscape Architect, or Engineering Consultant:
APCTE & Ric -Man International
General Contractor (if work performed as sub):
Ric -Man International, Inc.
Name of General Contractor's Project Manager and Field Superintendent:
Albert Dominguez, Project Manager
Remo lafrate, General Superintendant
Nelson Liberti, Superintendent
Awarded and Final Contract Amount:
$27,110,221.00
Project Status:
In Progress
Lummus Neighborhood improvements
Miami Beach, Florida
Project Location:
6 Street to Espanola Way
Description of Work Performed:
Installation of 8" DIP Watermain, 4" PVC Forcemain and 18 " -36" RCP Drainage
Name, Address, Phone, & Fax # of Owner or Agency:
City of Miami Beach
1700 Convention Center Dr.
Miami Beach, FL 33139
Contact Name:
Carlos Gil
Phone: (305) 592 -7283
Fax: (305) 593 -1594
Architect or Landscape Architect, or Engineering Consultant:
APCTE
General Contractor (if work performed as sub):
Ric -Man International, Inc.
Name of General Contractor's Project Manager and Field Superintendent:
Albert Dominguez, Project Manager
Remo lafrate, General Superintendant
Nelson Liberti, Superintendent
Awarded and Final Contract Amount:
$13,107,139.00
Project Status:
Completed
I `
Washington Avenue improvement Program
Miami Beach, Florida
Project Location:
5 to 15 Street
Description of Work Performed:
Installation of 8" Sanitary, 12" Watermain, 4" to 42" Drainage
Name, Address, Phone, & Fax # of Owner or Agency:
City of Miami Beach
1700 Convention Center Dr.
Miami Beach, FL 33139
Contact Name:
Aurelio Carmenates
Phone: (305) 673 -4363
Fax: (305) 673 -7073
Architect or Landscape Architect, or Engineering Consultant:
APCTE
General Contractor (if work performed as sub):
Ric -Man International, Inc.
Name of General Contractor's Project Manager and Field Superintendent:
Albert Dominguez, Project Manager
Remo lafrate, General Superintendant
Nelson Liberti, Superintendent
Awarded and Final Contract Amount:
$18,228,903.00
Project Status:
Completed
ROW improvement Program Neighborhood No. 6. Oceanfront
Miami Beach, Florida
Project Location:
Collins Ave. Between 27 St & 43 St.
Description of Work Performed:
Streetscape: Water, Stormwater, Sidewalk, Curb & Gutter, Street lighting, Landscape, Irrigation, Asphalt,
Roadwork.
Name, Address, Phone, & Fax # of Owner or Agency:
City of Miami Beach
1700 Convention Center Dr.
Miami Beach, FL 33139
Contact Name:
Aurelio Carmenates
Phone: (305) 673 -7000
Fax: (305) 673 -7073
Architect or Landscape Architect, or Engineering Consultant:
Albert Dominguez, Milian, Swaing & Associates.
General Contractor (if work performed as sub):
Ric -Man International, Inc.
Name of General Contractor's Project Manager and Field Superintendent:
Albert Dominguez, Project Manager
Remo Iafrate, General Superintendant
Nelson Liberti, Superintendent
Awarded and Final Contract Amount:
$1,911,570.72
Project Status:
Completed
South 26 Street Area Improvements
Fort Pierce, Florida
Project Location:
26 Street
Description of Work Performed:
Installation of 15 ", 18" and 24" Pipe Culvert
Name, Address, Phone, & Fax # of Owner or Agency:
St. Lucie County
2300 Virginia Ave
Fort Pierce, FL 33139
Contact Name:
Kyle Croce
Phone: (772) 462 -2153
Fax: (772) 462 -2362
Architect or Landscape Architect, or Engineering Consultant:
LBFH, INC
General Contractor (if work performed as sub):
Ric -Man International, Inc.
Name of General Contractor's Project Manager and Field Superintendent:
Rene Castillo, Project Manager
Remo lafrate, General Superintendant
Larry Smith, Superintendent
Awarded and Final Contract Amount:
$2,234,040.00
Project Status:
Completed
La Mancha Avenue Pipeline Extension Project
West Palm Beach, Florida
Project Location:
LaMancha Avenue
Description of Work Performed:
Installation of 30" Forcemain, 36" Watermain, 4 Aqueous Crossings and 2 36" Directional Drills
Name, Address, Phone, & Fax # of Owner or Agency:
Palm Beach County WUD
8100 Forest Hill Blvd.
West Palm Beach, FL 33413
Contact Name:
Joseph Tanacredi
Phone: (561) 493 -6088
Fax: (561) 493 -6085
Architect or Landscape Architect, or Engineering Consultant:
Mathews Consulting
General Contractor (if work performed as sub):
Ric -Man International, Inc.
Name of General Contractor's Project Manager and Field Superintendent:
Rene Castillo, Project Manager
Remo lafrate, General Superintendant
Luis Hernandez, Superintendent
Awarded and Final Contract Amount:
$4,959,963.00
Project Status:
Completed
Design/Build for Replacement of 48" Force Main
Oakland Park, Florida
Project Location:
Sunrise Avenue & Turnpike
Description of Work Performed:
48" Forcemain
Name, Address, Phone, & Fax # of Owner or Agency:
Broward County WWS
2555 West Copans Rd
Pompano Beach, FL 33069
Contact Name:
Alan Garcia
Phone: (954) 831 -0704
Fax: (954) 831 -0798
Architect or Landscape Architect, or Engineering Consultant:
Ric -Man International and Chen & Associates
General Contractor (if work performed as sub):
Ric -Man International, Inc.
Name of General Contractor's Project Manager and Field Superintendent:
Juan Barreneche, Project Manager
Remo lafrate, General Superintendant
Luis Hernandez, Superintendent
Awarded and Final Contract Amount:
$4,418,669.00
Project Status:
Completed
NE 6 Avenue Drainage improvements
Oakland Park, Florida
Project Location:
NE 6 Ave and Oakland Park Blvd
Description of Work Performed:
4' x 7' Box Culvert and 15 " -30" RCP
Name, Address, Phone, & Fax # of Owner or Agency:
City of Oakland Park
3650 NE 12 Avenue
Oakland Park, FL 33334
Contact Name:
John Perez
Phone: (954) 630 -4475
Fax: (954) 561 -6296
Architect or Landscape Architect, or Engineering Consultant:
LBFH, INC
General Contractor (if work performed as sub):
Ric -Man International, Inc.
Name of General Contractor's Project Manager and Field Superintendent:
Juan Barreneche, Project Manager
Remo lafrate, General Superintendant
Luis Hernandez, Superintendent
Awarded and Final Contract Amount:
$3,899,416.00
Project Status:
Completed
CCNIP St, George
Watermain, Force Main Sanitary and Drainage
Broward County, Florida
Project Location:
Sunrise Boulevard and State Road 7, Broward County, Florida
Description of Work Performed:
Replacement of 15 " -36" RCP and 29,000' of 8" WM
26,000' 8" of 16" SS
Name, Address, Phone & Fax # of Owner or Agency:
Broward County BOCC
115 S. Andrews Ave.
Ft. Lauderdale, FL 33301
Contact Name:
Pat MacGregor- Project Manager
Phone: (954) 831 -0904
Phone: (954) 831 -0798
Architect or Landscape Architect, or Engineering Consultant:
Chen & Associates Consulting Engineers, Inc
General Contractor (if work performed as sub):
Ric -Man International
Name of General Contractor's Project Manager and Field Superintendent:
Rene Castillo, Project Manager
Remo lafrate, Superintendant
Awarded and Final Contract Amount:
$7,980,000/ $ 8, 306, 789.06
Project Completion Date:
Completed in 2005
Watermain and Forcemain Relocation
Miami, Florida
Project Location:
SW 8 Street and 132 Avenue, Miami -Dade County, Florida
Description of Work Performed:
Installation of 30 -inch DI and Steel Casing
Name, Address, Phone & Fax # of Owner or Agency:
Miami -Dade Water & Sewer Department
3071 SW 38 Avenue
Room 534
Miami, Fl 33146
Contact Name:
Mr. Armando Rubio - Project Manager
Phone: (786) 552 -8146
Fax: (786) 552 -8641
Architect or Landscape Architect, or Engineering Consultant:
Miami Dade Water & Sewer Department
General Contractor (if work performed as sub):
Ric -Man International
Name of General Contractor's Project Manager and Field Superintendent:
Ron Bell, Project Manager
Larry Smith, Superintendent
Awarded and Final Contract Amount:
$1,027,199
$1,027,199
Project Status:
Completed