2011-27735 Reso RESOLUTION NO. 2011 -2773g
A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF MIAMI
BEACH, FLORIDA, ACCEPTING THE RECOMMENDATION OF THE CITY MANAGER,
PURSUANT TO REQUEST FOR QUALIFICATIONS (RFQ) NO. 31- 10/11, FOR
ARCHITECTURAL, ENGINEERING, DESIGN, BID AND AWARD, AND CONSTRUCTION
ADMINISTRATION SERVICES FOR THE COLLINS PARK GARAGE; AND
AUTHORIZING THE ADMINISTRATION TO ENTER INTO NEGOTIATIONS WITH THE
TOP - RANKED FIRM, ZAHA HADID LIMITED T/A ZAHA HADID ARCHITECTS; AND
SHOULD THE ADMINISTRATION NOT BE ABLE TO SUCCESSFULLY NEGOTIATE AN
AGREEMENT WITH THE TOP - RANKED FIRM, AUTHORIZING THE ADMINISTRATION
TO NEGOTIATE WITH THE SECOND - RANKED FIRM, BROOKS + SCARPA
ARCHITECTS, INC.; AND SHOULD THE ADMINISTRATION NOT BE ABLE TO
NEGOTIATE AN AGREEMENT WITH THE SECOND - RANKED FIRM, AUTHORIZING THE
ADMINISTRATION TO NEGOTIATE AN AGREEMENT WITH THE THIRD - RANKED FIRM,
OPPENHEIM ARCHITECTURE + DESIGN LLP.
WHEREAS, on May 11, 2011, the Mayor and City Commission approved the
issuance of Request for Qualifications (RFQ) No. 31- 10/11, for Architectural, Engineering,
Design, Bid and Award, and Construction Administration Services for the Collins Park
Garage; and
WHEREAS, the RFQ was issued on May 26, 2011, with an opening date of July 15,
2011; and
WHEREAS, a pre - qualification meeting to provide information to prospective
proposers was held on June 3, 2011; and
WHEREAS, Bidsync sent notices to 7,772 prospective proposers of which 199
proposers viewed the notice resulting in the receipt of fifteen (15) proposals by Adache
Group Architects, ADD, Inc., AECOM Technical Services, Arquitectonica, BEA Architects,
Inc., Brooks + Scarpa Architects, Inc., Kobi Karp Architecture and Interior Design, Inc.,
Oppenheim Architecture + Design LLP, Perkins + Will ,Robert A.M. Stern Architects, LLP —
Borrelli + Partners, Inc. (JV), Rodriguez and Quiroga Architects Chartered, Studio Daniel
Libeskind, Architect LLC, Wolfberg Alvarez & Partners, Zaha Hadid Limited t/a Zaha Hadid
Architects, Zyscovich, Inc.; and
WHEREAS, the City Manager, via a Letter to Commission (LTC) No. 179 -2011,
appointed the following individuals as Evaluation Committee (the "Committee ") members:
• Ray Breslin, Resident and Collins Park Neighborhood Association Member
• Christina Cuervo, Resident and Capital Improvements Project Oversight Committee
Member
• Grace Escalante, Senior Capital Projects Coordinator, CIP Office
• Saul Frances, Parking Director, Parking Department
• Jason Hagopian, Resident and Design Review Board Member
• Tom Mooney, Preservation and Design Manager, Planning Department
• Corey Narson, Resident and Transportation and Parking Committee Member
with the following individuals also appointed as Committee alternates:
• Silvia Cubina, Director, Bass Museum
• Sherry Roberts, Board of Adjustment Member
• Thais Vieira, Capital Projects Coordinator, CIP Office.
WHEREAS, the Committee convened on August 10, 2011, to discuss their individual
perceptions of each prospective bidder's qualifications, experience, and competence and
shortlisted the following firms:
• ADD, Inc.
• AECOM Technical Services
• Arquitectonica
• Brooks + Scarpa Architects, Inc.
• Oppenheim Architecture + Design LLP
• Perkins + Will
• Wolfberg Alvarez & Partners
• Zaha Hadid Limited t/a Zaha Hadid Architects
• Zyscovich, Inc.
WHEREAS, the Committee on August 23 and September 1, 2011, reconvened to
score and rank the shortlisted firms and voted to recommend to the City Manager Zaha
Hadid Limited t/a Zaha Hadid Architects as the top- ranked firm; Brooks + Scarpa Architects,
Inc. as the second - ranked firm; and Oppenheim Architecture + Design LLP as the third -
ranked firm; and
WHEREAS, after considering the review and recommendation of the Evaluation
Committee, the City Manager exercised his due diligence and carefully considered the
specifics of this RFQ process; and
WHEREAS, as a result, the City Manager recommends to the Mayor and City
Commission that the City enter into negotiations with the top- ranked firm of Zaha Hadid
Limited t/a Zaha Hadid Architects; and should the Administration not be able to negotiate
with the top- ranked firm, the Administration should negotiate with the second - ranked firm of
Brooks + Scarpa Architects, Inc.; and should the Administration not be able to negotiate with
the second - ranked firm, the Administration should negotiate with the third - ranked firm of
Oppenheim Architecture + Design LLP.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND CITY
COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, that the Mayor and City
Commission hereby accept the recommendation of the City Manager, pursuant to Request
for Qualifications (RFQ) No. 31- 10/11, for Architectural, Engineering, Design, Bid and
Award, and Construction Administration Services for the Collins Park Garage; authorizing
the Administration to enter into negotiations with the top- ranked firm of Zaha Hadid Limited
t/a Zaha Hadid Architects; and should the Administration not be able to negotiate with the
top- ranked firm, the Administration should negotiate with the second - ranked firm of Brooks +
Scarpa Architects, Inc.; and should the Administration not be able to negotiate with the
second - ranked firm, the Administration should negotiate with the third - ranked firm of
Oppenheim Architecture + Design LLP.
PASSED AND ADOPTED,.,.a.,1%,,,M) DAY OF -3 x
` Q . . - �I APPROVED AS TO
ATTEST: _ �. FORM & LANGUAGE
(AA
a - ' .P• ORATED' � ����� _ /• :�i���,I�
CITY CLERK y . G .. , % MA OR (� t
1 OF/ �' /-! 26 � ' � '�' Attome (1,, Date
COMMISSION ITEM SUMMARY
Condensed Title:
A Resolution of the Mayor and City Commission of the City of Miami Beach, Florida, Accepting the
Recommendation of the City Manager, Pursuant to Request for Qualifications (RFQ) No. 31- 10/11, for Architectural,
Engineering, Design, Bid and Award, and Construction Administration Services for the Collins Park Garage; and
Authorizing the Administration to Enter into Negotiations with the Top- Ranked Firm, Zaha Hadid Limited t/a Zaha
Hadid Architects; and Should the Administration Not Be Able to Successfully Negotiate an Agreement with the Top -
Ranked Firm, Authorizing the Administration to Negotiate with the Second - Ranked Firm, Brooks + Scarpa
Architects, Inc.; and Should the Administration Not Be Able to Negotiate an Agreement with the Second - Ranked
Firm, Authorizing the Administration to Negotiate an Agreement with the Third - Ranked Firm, Oppenheim
Architecture + Design LLP.
Key Intended Outcome Supported:
Ensure well- maintained infrastructure
Supporting Data (Surveys, Environmental Scan, etc.): The 2009 Customer Satisfaction Survey indicated that
79% of businesses rated recentl completed capital improvement pro'ects as "excellent" or ". ood."
Issue:
1 Shall the Mayor and City Commission adopt the Resolution?
Item Summary /Recommendation:
The cultural arts neighborhood district is an area that is in need of parking for the visitors and residents of the City of
Miami Beach. In order to serve this need, the City is proposing to build a five -level parking garage. The site for the
new parking facility is bounded by 23 Street on the north, Park Avenue on the west, the Miami City Ballet on the
south and Liberty Avenue on the east (300 to 342 23 Street). In addition, the City owns a surface lot that serves
the City Library bounded by Liberty Avenue to the west and the City Library to the south (224 23 Street), which the
City is desirous to plan as part of the services contemplated in this Request for Qualifications.
The project consists of a five (5) level parking garage with a maximum height of fifty (50) feet or as required by City
Ordinance, which accommodates approximately 400 parking spaces and houses retail establishments on the
ground floor. The parking garage will be located on 300 -342 23 Street. The City is contemplating enhancing or
closing a portion of Liberty Avenue from 23 Street to 22 Street in order to create a pedestrian plaza that will
provide a strong connection from the parking structure to Collins Park, Miami Beach Ballet, and the Public Library.
In addition, the City is requesting that the Consultant study the best use of the parcel located on 224 23 Street and
propose various concepts to the City which may include a commercial building with retail on the ground floor and
commercial and retail on the floors above with the possibility of being connected directly by an extension of the
parking levels or via a bridge to the new parking garage as described above.
On August 10, 2011, the Committee convened to shortlist the proposals. It reconvened on August 23 and
September 1, 2011, to score and rank the shortlisted firms. Upon completion of the presentations and interviews,
the Committee discussed their individual perceptions of each prospective firm's qualifications, experience, and
competence in order to score and rank each accordingly to develop its recommendation to the City Manager based
on their scores and ranking. As a result, Zaha Hadid Limited t/a Zaha Hadid Architects received four of seven first -
place votes.
Zaha Hadid Limited t/a Zaha Hadid Architects
Zaha Hadid is an award - winning architect whose drawings, designs, and architectural vision has earned her notable
recognition as one of the top architects in the world. She was the recipient of the Pritzker Prize, considered by
many as the Nobel Prize of architecture. Her architectural practice, established in 1980, has acquired over 30 years
of experience building some of the most acclaimed architecture in the world. The practice currently has more than
400 staff from over 40 nationalities based in their London offices with additional staff in their site offices in Rome.
Guangzhou, Beijing and Hamburg. Notable projects include the Guangzhou Opera House in China and the London
Aquatic Center being finalized for the 2012 Summer Olympics.
Advisory Board Recommendation:
N/A
Financial Information:
Source of Amount Account
Funds: 1 N/A
OBPI Total
Financial Impact Summary: N/A
City Clerk's Office Legislative Tracking:
Gus Lopez ext. • .41
Sign -Offs:
Depa ° nt ID • r Assistan Manager City Ma er
GL FV DB JM
T:\AGENDA\201 P 14 -11 \ -.ular \RFQ 31 -10 -11 - Collins Park Garage - Summary .doc
..
AGENDA ITEM
7 E
DATE 9"lY -1/
al MIAM
City of Miami Beach, 1700 Convention Center Drive, Miami Beach, Florida 33139, www.miamibeachfl.gov
COMMISSION MEMORANDUM
TO: Mayor Matti Herrera Bower and Members of t - ity Commission
FROM: Jorge M. Gonzalez, City Manager
DATE: September 14, 2011
SUBJECT: A RESOLUTION OF THE MAYO' AND CITY COMMISSION OF THE CITY OF
MIAMI BEACH, FLORIDA, ACCEPTING THE RECOMMENDATION OF THE CITY
MANAGER, PURSUANT TO REQUEST FOR QUALIFICATIONS (RFQ) NO. 31-
10/11, FOR ARCHITECTURAL, ENGINEERING, DESIGN, BID AND AWARD, AND
CONSTRUCTION ADMINISTRATION SERVICES FOR THE COLLINS PARK
GARAGE; AND AUTHORIZING THE ADMINISTRATION TO ENTER INTO
NEGOTIATIONS WITH THE TOP - RANKED FIRM, ZAHA HADID LIMITED T/A ZAHA
HADID ARCHITECTS; AND SHOULD THE ADMINISTRATION NOT BE ABLE TO
SUCCESSFULLY NEGOTIATE AN AGREEMENT WITH THE TOP - RANKED FIRM,
AUTHORIZING THE ADMINISTRATION TO NEGOTIATE WITH THE SECOND -
RANKED FIRM, BROOKS + SCARPA ARCHITECTS, INC.; AND SHOULD THE
ADMINISTRATION NOT BE ABLE TO NEGOTIATE AN AGREEMENT WITH THE
SECOND - RANKED FIRM, AUTHORIZING THE ADMINISTRATION TO NEGOTIATE
AN AGREEMENT WITH THE THIRD - RANKED FIRM, OPPENHEIM
ARCHITECTURE + DESIGN LLP.
ADMINISTRATION RECOMMENDATION
Adopt the Resolution.
BACKGROUND
The cultural arts neighborhood district is an area that is in need of parking for the visitors and
residents of the City of Miami Beach. In order to serve this need, the City is proposing to build a
five -level parking garage. The site for the new parking facility is bounded by 23 Street on the
north, Park Avenue on the west, the Miami City Ballet on the south and Liberty Avenue on the
east (300 to 342 23 Street). In addition, the City owns a surface lot that serves the City Library
bounded by Liberty Avenue to the west and the City Library to the south (224 23 Street), which
the City is desirous to plan as part of the services contemplated in this Request for
Qualifications. This project once built will generate jobs as well as provide a source of revenue
for the City.
SCOPE OF SERVICES
The City is requesting qualification statements from Design Firms that meet the minimum
qualifications described in this document. The Consultant shall provide Architectural, Structural
Engineering, MEP Engineering, Civil Engineering, Landscape Architecture, Parking and
Commission Memorandum — RFQ -31 -10/11 — Architectural, Engineering, Design, Bid and
Award, and Construction Administration Services for the Collins Park Garage
September 14, 2011
Page 2of11
Transportation Consultant, Traffic Impact Study within the parameters required by the City's
Public Works and Planning Departments, Environmental Assessments, Threshold Inspection,
Special Inspection as required by the Building Department, Construction Cost Estimating,
Surveying, Geotechnical, Asbestos survey and material testing services for the Project. The
work shall include, but not be limited to planning, design development, estimate(s) of probable
construction cost, construction documents, ermittin bidding / award, LEED
p g� 9 process support
pp ort
and documentation and construction a r
e a d administration services for the Project.
The project consists of a five (5) level parking garage with a maximum height of fifty (50) feet or
as required by City Ordinance, which accommodates approximately 400 parking spaces and
houses retail establishments on the ground floor. The parking garage will be located on 300 -342
23 Street. The City is contemplating enhancing or closing a portion of Liberty Avenue from 23
Street to 22 Street in order to create a pedestrian plaza that will provide a strong connection
from the parking structure to Collins Park, Miami Beach Ballet, and the Public Library. In
addition, the City is requesting that the Consultant study the best use of the parcel located on
224 23 Street and propose various concepts to the City which may include a commercial
building with retail on the ground floor and commercial and retail on the floors above with the
possibility of being connected directly by an extension of the parking levels or via a bridge to the
new parking garage as described above.
The Consultant's services shall also include LEED process support and documentation
pursuant to US Green Building Counsel LEED Standard and/ or City of Miami Beach Ordinance
Section 100 whichever is most stringent and include but not be limited to the following:
• LEED documentation, application and all required submittals q s to achieve a USGBC LEED
SILVER certification for new construction;
• Providing the project specifications that clearly delineate all LEED - related Contractor
responsibilities and procedures, provide the LEED required documentation of all
materials, technologies, and procedures upon which the achievement of design intent
and LEED Silver certification depend;
• Coordinating with and assisting the City's Building Commissioning Agent / Contractor in
its implementation of the Building Commissioning Plan. That plan shall result in full
compliance with the LEED standard for full documentation of building commissioning. In
particular it will structure and document the full initiation, testing, operational instruction,
and record documentation of all building systems.
• The Project Team will conduct meetings that will result in a list of clearly defined and
clearly assigned actions and responsibilities for moving towards the achievement of
LEED Silver certification and related project goals.
The total allocated Construction Cost Budget earmark for the project is approximately
$12,500,000.
The successful firm will be tasked with the following duties and responsibilities at a minimum:
• Planning Services: The purpose of this Task is to develop a concept plan that meets the
City's functional requirements and stays within established schedule and cost
parameters.
• Design Services: The purpose of this Task is to establish the requirements for the
Commission Memorandum — RFQ -31 -10/11 — Architectural, Engineering, Design, Bid and
Award, and Construction Administration Services for the Collins Park Garage
September 14, 2011
Page 3 of 11
preparation of Contract Documents for the Project. The selected firm will be required to
perform a variety of forensic tasks to verify, to the extent practicable, existing conditions,
and the accuracy of base maps and as -built drawings to be used in the development of
Construction Documents. These tasks include, but may not be limited to, demolition
drawing preparation, surveying, utility verification, environmental site assessments,
geotechnical explorations, traffic impact studies, hazardous material testing and
coordination with proposed design improvements.
• In addition, the selected firm will follow the City Standards for the preparation of Contract
Documents, inclusive of Drawings, Specifications and Front -End Documents, Cost
Estimates, and a Risk Assessment Plan (RAP). Review submittals will be prepared at
the completion of the Design Development Phase and at the 30 %, 60 %, 90% and 100%
completion stages of the construction documents.
• Contract Documents will be subject to Constructability and Value Engineering reviews.
The selected firm will attend and participate in design review meetings to present and
discuss the design progress and concept at different stages during the design and will
work with City staff to adjust and revise Project scope as may be deemed necessary to
meet established budgets and the established phasing plan. The selected firm will also
be responsible for reviewing and receiving approvals for the Contract Documents from
all jurisdictional permitting Agencies and Boards prior to finalization of each phase of the
Project. To facilitate the implementation of a Public Information Program, the selected
firm will provide electronic files of all project documents, as directed by the City. City
departments shall be required to respond, in writing, to all review comments.
Presentation formats will be as directed by the City.
• The selected firm shall establish and maintain an in -house Quality Assurance / Quality
Control (QA/QC) program designed to verify and ensure the quality, clarity,
completeness, and constructability of its Contract Documents.
• Bid and Award Services: The selected firm shall assist the City in the bidding and award
phases of each portion of the Project scope. Such assistance shall include facilitating
reviews of Contract Documents with applicable Procurement, Risk Management and
City Attorney's Office representatives. In addition, the selected firm shall furnish camera -
ready Contract Documents for reproduction and distribution by the City, attend pre -bid
conferences, assist with the preparation of necessary contract addenda, attend bid
openings where applicable, assist with bid evaluations, and prepare a recommendation
to award letter for the City's consideration. The selected firm shall provide "As -Bid"
documents for use during construction.
• Construction Administration Services: The selected firm shall perform a variety of tasks
associated with the administration of the construction of the project. These shall include
attendance at the pre - construction conferences, attendance at weekly construction
meetings, responding to contractor Requests for Information (RFI), clarification,
responding to and evaluating contractor requests for change orders, contract
amendments, review of shop drawings, review of record drawings, review and
recommendation of contractor applications for payment, specialty site visits, project
closeout reviews, including substantial completion, final punch list development and
Project certification of final completion and acceptance of each phase, and warranty
administration of each phase.
• Additional Services: If required during the performance of the work, they will be
requested by the City and negotiated in accordance with the Contract requirements.
• Reimbursable Services: The City may reimburse additional expenses such as
Commission Memorandum — RFQ -31 -10/11 — Architectural, Engineering, Design, Bid and
Award, and Construction Administration Services for the Collins Park Garage
September 14, 2011
Page 4 of 11
reproduction costs, underground utility verification costs material testing / abatement
and /or any other service as required for successful project completion.
RFQ PROCESS
On May 26, 2011, the RFQ was issued with an opening date of July 15, 2011. A Pre - proposal
meeting to provide information to prospective proposers was held on June 3, 2011. Bidsync
issued bid notices to 7,772 prospective bidders with 199 having viewed the notice of which
resulted in the receipt of the following fifteen (15) bids:
• Adache Group Architects
• ADD, Inc.
• AECOM Technical Services
• Arquitectonica
• BEA Architects, Inc.
• Brooks + Scarpa Architects, Inc.
• Kobi Karp Architecture and Interior Design, Inc.
• Oppenheim Architecture + Design LLP
• Perkins + Will
• Robert A.M. Stern Architects, LLP — Borrelli + Partners, Inc. (JV)
• Rodriguez and Quiroga Architects Chartered
• Studio Daniel Libeskind, Architect LLC
• Wolfberg Alvarez & Partners
• Zaha Hadid Limited t/a Zaha Hadid Architects
• Zyscovich, Inc.
The City Manager, via a Letter to Commission (LTC) No. 179 -2011, appointed an Evaluation
Committee (Committee) consisting of the following individuals:
• Ray Breslin, resident and Collins Park Neighborhood Association member
• Saul Frances, Parking Director, Parking Department
• Grace Escalante, Senior Capital Projects Coordinator, CIP Office
• Jason Hagopian, resident and Design Review Board member
• Tom Mooney, Preservation and Design Manager, Planning Department
• Corey Narson, resident and Transportation and Parking Committee member
• Sherry Roberts, Board of Adjustment member
EVALUATION PROCESS
On August 10, 2011, the Committee convened to shortlist the proposals and unanimously
nominated Sherry Roberts as Committee Chair. In determining the most qualified firms, the
Committee discussed each firm's proposal based on the criteria noted in the RFQ below.
Commission Memorandum — RFQ -31 -10/11 — Architectural, Engineering, Design, Bid and
Award, and Construction Administration Services for the Collins Park Garage
September 14, 2011
Page 5 of 11
Total Point Criteria
20 The experience, qualifications and portfolio of the Principal Firm
20 The experience and qualifications of the professional personnel assigned to the
Project Team as well as their familiarity with this project and a thorough
understanding of the methodology and design approach to be used in this
assignment.
20 The experience, qualifications and portfolio of the Project Manager, as well as
his /her familiarity with this project and a thorough understanding of the
methodology and design approach to be used in this assignment.
10 Past performance based on quality of the Performance Evaluation Surveys and
the Administration's due dilligence based upon reference checks performed of
the Firm(s) clients.
5 Willingness to meet time and budget requirements as demonstrated by past
rf r
pe o mance, methodology and approach
5 Risk Assessment Plan that reflects a clear understanding of project objectives;
a thorough review of existing conditions; familiarity with the project site; a
thorough understanding of all permitting and regulatory requirements and
impacts; and other considerations that may impact the design and construction
of the proposed improvements.
5 Certified minority business enterprise participation. Either the Prime Consultant
or the sub - Consultant team may qualify for proof of certification for minority
business enterprise participation. Accepted minority business enterprise
certifications include the Small Business Administration (SBA), State of Florida,
or Miami -Dade County.
5 Location
5 Recent, current and projected workloads of the firms
5 The volume of work previously awarded to each firm by the City, with the object
of effecting an equitable distribution of contracts among qualified firms,
provided such distribution does not violate the principle of selection of the most
highly qualified firm.
The Committee discussed their individual perceptions of each prospective bidder's
qualifications, experience, and competence to shortlist the following firms:
• ADD, Inc.
• AECOM Technical Services
• Arquitectonica
• Brooks + Scarpa Architects, Inc.
• Oppenheim Architecture + Design LLP
• Perkins + Will
• Wolfberg Alvarez & Partners
• Zaha Hadid Limited t/a Zaha Hadid Architects
• Zyscovich, Inc.
The Committee reconvened on August 23 and September 1, 2011, to score and rank the
shortlisted firms. Upon completion of the presentations and interviews, the Committee
discussed their individual perceptions of each prospective firm's qualifications, experience, and
competence in order to score and rank each accordingly to develop its recommendation to the
Commission Memorandum — RFQ -31 -10/11 — Architectural, Engineering, Design, Bid and
Award, and Construction Administration Services for the Collins Park Garage
September 14, 2011
Page 6 of 11
City Manager based on their scores and ranking. As a result, Zaha Hadid Limited t/a Zaha
Hadid Architects received four of seven first -place votes as noted below:
RFQ 31 -10/11 Final Ranking (Scoring)
Breslin Escalante Frances Hagopian Mooney Narson Roberts Total
Zaha Hadid 2 (90) 5 (84.) 1 (93) 1 (94) 1 (100) 4 (90) ;1 (99,99) 15 (650.99)
Brooks + Scarpa 3 (89) 4 (87) 2 (92) 2 (86) 2 (94) 3 (93) 3 (97) 19 (638)
Oppenheim 5 (87) 1 (91) 9 (74) 4 (84) 4 (88) 1 (98) 2 (98) 26 (620)
Wolfberg Alvarez ' (93) 2 (89) 7 (79) 5 (82) 9 (64) 2 (94) 4 (97) 30 (598)
Zyscovich 6 (86) 7 (79.5) 4 (89) 3 (85) 6 (85) 6 (89) 7 (94) 39 (607.5)
Perkins + Will 4 (88) 3 (89) 5 (88) 9 (65) 5 (85) 5 (90) 8 (89.25) 39 (594.25)
Arquitectonica 7 (81) 9 (73) 3 (91) 8 (67) 3 (90) 8 (88) 9 (54) 47 (544)
AECOM 9 (80) 8 (74) 6 (82) 6 (72) 7 (70) 7 (89) 5 (96) 48 (563)
ADD 8 (80) 6 (83) 8 (77) 7 (70) 8 (67) 9 (66) 6 (95) 52 (538)
Zaha Hadid Limited t/a Zaha Hadid Architects
Zaha Hadid is an award - winning architect whose drawings, designs, and architectural vision has
earned her notable recognition as one of the top architects in the world. In fact, she was the
recipient of the Pritzker Prize, considered the Nobel Prize of architecture. Her architectural
practice, established in 1980, has acquired over 30 years of experience building some of the
most acclaimed architecture in the world. The practice currently has more than 400 staff from
over 40 nationalities based in their London offices with additional staff in their site offices in
Rome, Guangzhou, Beijing and Hamburg. Notable projects include the Guangzhou Opera
House in China and the London Aquatic Center being finalized for the 2012 Summer Olympics.
CONCLUSION
The Administration recommends that the Mayor and City Commission adopt the attached
Resolution accepting the recommendation of the City Manager pursuant to Request for
Qualifications (RFQ) No. 31- 10/11, for architectural, engineering, design, bid and award, and
construction administration services for the Collins Park Garage; and authorizing the
Administration to enter into negotiations with the top- ranked firm, Zaha Hadid Limited t/a Zaha
Hadid Architects; and should the Administration not be able to successfully negotiate an
agreement with the top- ranked firm, authorizing the Administration to negotiate with the
second - ranked firm, Brooks + Scarpa Architects, Inc.; and should the Administration not be
able to negotiate an agreement with the second - ranked firm, authorizing the Administration to
negotiate an agreement with the third - ranked firm, Oppenheim Architecture + Design LLP.
ATTACHMENTS
• Attachment A - Zaha Hadid Limited t/a Zaha Hadid Architects Executive Summary
• Attachment B — Collins Park Garage Conceptual Drawings
Commission Memorandum — RFQ -31 -10/11 — Architectural, Engineering, Design, Bid and
Award, and Construction Administration Services for the Collins Park Garage
September 14, 2011
Page 7 of 11
Attachment A — Zaha Hadid Limited tla Zaha Hadid Architects Executive Summary
[PAGE INTENTIONALLY LEFT BLANK]
Commission Memorandum — RFQ-31 -10/11 — Architectural, Engineering, Design, Bid and
Award, and Construction Administration Services for the Collins Park Garage
September 14, 2011
Page 9 of 11
.. - - ¢" 3 fi m S 3'�xX
,.Y Y '�,rsY Y� j Y f '�/'�
2`".
its °'`
c✓
xfi s Via/
S 2' 3 k
� „�ia £fib .g . i, � L>w � a�� � th
. `spa < '4 �[ � s ' �. , " F Y'
F
su/
r - .
r
F
. y M'
�
T Vass, x t �'�
,
s —
- — —
7'J/ ' 2 A.. ,',/
Commission Memorandum — 1 — Architectural, Engi
September 14, 2011
Page 10 o
Design #2
Aar m � a =w a X :
9 h '
r
d F '
Xpf n �F
f � r
a C
■
x \
F
2 Y
{ � i
, %s ue '/ � ., � � � •' � y :c
Commission Memorandum — RFQ -31 -10/11 — Architectural, Engineering, Design, Bid and
Award, and Construction Administration Services for the Collins Park Garage
September 14, 2011
Page 11 of 11
,,,,- has v
<: ,F
t / @5
9 ,
n G
b �.