Loading...
Attachment I - Design Criteria Package a Attachment 1 DESIGN.'-CRITERIA . PACKAG FOR DESIGN/BUILD SERVICES FOR NEIGHBORHOOD NO. 1 BISCAYNE POINT RIGHT-OF -WAY INFRASTRUCTURE IMPROVEMENT PROJECT Richard W. Saltnck,Pl. P.E. No. 50085 City of Miami Beach 1700 Convention Center Drive Miami Beach, FL 33139 Where Sections 01000 — PROFESSIONAL SERVICES and 01010 — SUMMARY OF WORK conflict with other technical specifications, Sections 01000 — PROFESSIONAL SERVICES and 01010 — SUMMARY OF WORK shall govern. Where technical specifications conflict with plans, technical specifications shall govern. Contract Schedule DESIGN / BUILD FIRM shall be instructed to commence the Work by written instruction in the form of a Purchase Order issued by the City's Procurement Director and Notices to Proceed issued by the CONTRACT ADMINISTRATOR. There will be two Notices to Proceed. DESIGN / BUILD FIRM shall commence design, scheduling activities, permit applications, and other pre-construction work within five (5) calendar days after the First Notice To Proceed. The First Notice To Proceed and Purchase Order will not be issued until DESIGN / BUILD FIRM's submission to CITY of insurance, bonds, and licenses and after execution of the Contract by both parties. The Second Notice To Proceed shall be issued only upon acceptance of the full progress schedule, submittal schedule and schedule of values; acceptance of the 100% contract documents; and receipt of all necessary permits per phase by DESIGN / BUILD FIRM. The Second Notice To Proceed shall authorize the DESIGN / BUILD FIRM to mobilize on the Project site and commence with physical construction work. The CITY may issue phased Notices to Proceed with the construction phase based on the receipt of permits from the respective regulatory agencies. Time is of the essence throughout this Contract. The schedule shall be as directed in the Agreement. Due to the difficulty assessing the costs to the CITY associated with delays in completion of the project by the DESIGN / BUILD FIRM, it shall be agreed that liquidated damages shall be as directed in the Agreement. NEIGHBORHOOD NO.: 1—BISCAYNE POINT March 20, 2012 3 SECTION 01000 - PROFESSIONAL SERVICES PART 1 - GENERAL 1.01 THE REQUIREMENT A. Work to be performed in this Section includes providing professional engineering services to design, permit, and certify the construction of a project meeting the intent of the following items: 1.11 Biscayne Point Basis of Design Report prepared by the Corradino Group, March 2003 (BODR) 2. City of Miami Beach General ROW Design Standards Manual, August 2002, including updates (DSM) 3. City of Miami Beach Public Works Manual, April 2007 (PWM) 4. 100% Biscayne Point Neighborhood Improvement Project Construction Documents, including plans and technical specifications, prepared- EAC Consulting, July 2011 ) and all revisions through March 2012. (Existing Plans B. The work to be performed requires the use of documents and drawings previously created. A successor professional engineer must be able to document and produce upon request evidence that he/she has in fact recreated all the work done by the original professional engineer. The successor professional engineer shall adhere to professional guidelines established in Florida Administrative Code 61 G15-27.001. 1.02 SCOPE OF PROFESSIONAL SERVICES A. The DESIGN / BUILD FIRM shall prepare signed and sealed contract documents for the CITY's review to verify compliance with the Project intent. The DESIGN / BUILD FIRM shall also utilize the DSM and PWM to supplement any details required to complete the Project. B. The following is a list of items that the DESIGN / BUILD FIRM shall incorporate into its Contract Documents: 1. Topographic Survey: DESIGN / BUILD FIRM shall verify / update the information presented as existing conditions in the Existing Plans to the extent necessary to ensure that the proposed improvements do not negatively impact existing / proposed facilities. The.DESIGN / BUILD FIRM shall verify that: • sidewalks have positive slopes from entryways towards the roadway • there is compliance with ADA requirements for access to existing structures • existing edge of pavement elevations match proposed lip of curb elevations where roadways are not being reconstructed • rim / grate elevations match existing surrounding grades • proposed landscaping does not conflict with existing and / or adjacent above ground improvements NEIGHBORHOOD NO.: 1—BISCAYNE POINT March 20,2012 01000-1 • recent improvements are properly identified, protected, and coordinated with proposed Work • proposed improvements are not in conflict with existing conditions / proposed improvements. a. The Existing Plans were developed based on a signed and sealed topographic survey prepared by F.R. Aleman & Associates, Inc. for the Original Design Consultant. The DESIGN / BUILD FIRM shall review and amend the existing topographic survey, as needed, to meet the requirements of the scope of work and the DSM. In particular, the DESIGN / BUILD FIRM shall contact all existing utility owners and request that they verify locations of existing utilities on the survey. The DESIGN / BUILD FIRM shall use this information to design the new water and stormwater infrastructure. b. Identification and Relocation of Existing Underground Utilities: It is the DESIGN / BUILD FIRM's responsibility to identify and coordinate the relocation of any and all existing utilities that may conflict with proposed improvements as depicted in the DESIGN / BUILD FIRM's contract documents. These include but are not necessarily limited to: FPL, BellSouth, Charter Communications, Level 3 Communications, Adelphia Communications, AT&T, Teco-Peoples Gas, NUI- CITY Gas Company, Florida Gas Transmission, MCI WorldCom, M-D WASD, M- D PWD and CITY of Miami Beach, and others as deemed necessary. It is the responsibility of the DESIGN / BUILD FIRM to verify that the final contract documents are free of utility conflicts to a reasonable standard of care. The DESIGN / BUILD FIRM shall be responsible for the coordination of existing utilities that are found to be in conflict with proposed improvements. It is realized that the DESIGN / BUILD FIRM is also the Engineer of Record, hence, the DESIGN / BUILD FIRM has considerable latitude in resolving utility conflicts provided the method meets the applicable codes / standards and approved by the respective utility owner(s). c. Existing Utility Verification: The DESIGN / BUILD FIRM shall utilize whatever means it deems necessary to ensure that the proposed improvements illustrated in its final design drawings are not in conflict with existing underground utilities. The DESIGN / BUILD FIRM shall submit its contract documents to all utility owners and request that they identify / verify the horizontal and vertical location of their utilities. The DESIGN / BUILD FIRM shall forward correspondence and its contract documents to each utility owner with a copy to the CITY. The DESIGN / BUILD FIRM is urged to field verify each proposed utility and / or manhole excavation, utility crossing, utility tie-in, and excavation greater than 12 inches in depth when located close to existing improvements. Methods to be considered by the DESIGN / BUILD FIRM shall include but not be necessarily limited to subsurface utility exploration in accordance with ASCE Standard Guideline for the Collection and Depiction of Existing Subsurface Utility Data (Quality Level A), vacuum extraction, water extraction, ground penetrating radar, magnetic survey, potholing, or other method deemed appropriate by the DESIGN / BUILD FIRM. The CITY reserves the right to request that the DESIGN / BUILD FIRM provide documentation of utility verification requests and subsequent responses from utilities. NEIGHBORHOOD NO.: 1—BISCAYNE POINT March 20,2012 01000-2 2. Stormwater System: The intent of this project is to construct stormwater improvements that provide a 5-year 1-day level of service, stormwater quality treatment and to improve stormwater collection and conveyance within the priority basins and areas of concern listed in article c. below. a. The design parameters of a 5-year 1-day level of service includes: • A storm event with 7.5 inches of rainfall .• A 1.60-foot NGVD tailwater elevation • No flood stages above crown of road or within 15 feet of a building b. No credit will be given for stormwater detention time in piping. All detention time shall be accounted for within structures that are accessible to maintenance personnel. c. The DESIGN / BUILD FIRM shall design a fully functional system that addresses spot flooding and ponding by regrading the streets and adding catch basins and culverts as needed. . In particular, the DESIGN / BUILD FIRM shall prepare a stormwater design for the following areas of concern: • The intersection of Noremac Avenue and Biscayne Point Road • 7955 Biscayne Point Circle . 1825 Daytonia Road d. All existing ROW roadway surfaces that are not to be rebuilt shall be milled and resurfaced. All roads shall have a total minimum 2-inch thickness of asphalt upon completion of the project. Up to 1 inch of existing asphalt can be considered to meet the 2-inch minimum thickness, however there shall be no less than 2 inches total thickness at any location. e. The DESIGN / BUILD FIRM shall clean and inspect the entirety of the existing stormwater collection, transmission, and disposal system inclusive of catch basins, manholes, transmission mains, culverts, and outfalls within the project area. f. Redevelopment of "failed" new wells shall remain the responsibility of the DESIGN / BUILD FIRM through the duration of the project and subsequent warranty period, as applicable. 3. Water Distribution System: The DESIGN / BUILD FIRM shall incorporate into its design watermains on Noremac Avenue and Cleveland Road and the Henedon WM plans. a. All proposed open-cut watermains shall be ductile iron, Class 52, fully restrained and wrapped with 36 inches of cover. b. Pipe depth may be reduced at the discretion of the City Public Works Department when using ductile iron pipe, Class 53. c. As a part of the water main design effort, the DESIGN / BUILD FIRM shall include reconnection to existing and installation of new fire hydrant assemblies at spacing required to meet applicable jurisdictional agency permitting requirements. NEIGHBORHOOD NO.: 1—BISCAYNE POINT March 20,2012 01000-3 d. The DESIGN / BUILD FIRM shall install new service connections to replace existing connections. This effort shall include coordination with the City Public Works Department to ensure that any existing meters which are deemed to require replacements (by the CITY) are replaced with new meters. The City Public Works Department shall provide new meters, and the DESIGN / BUILD FIRM shall replace all service connection piping upstream of the meter to the new main with 2-inch diameter lines and install the meter, as required. In all cases, the DESIGN / BUILD FIRM shall provide a replacement water meter box. e. The DESIGN/ BUILD FIRM shall add fittings and valves at all intersections along the route of proposed water mains to result in a fully interconnected system with isolation valves at all crossings. For operational flexibility and ease of maintenance, the DESIGN / BUILD FIRM shall also add fittings and valves at crossings between proposed and existing water mains that are to remain. f. Upon completion of the installation of.the proposed water lines, the existing water lines shall be.cut and capped if they are to be abandoned in place. g. The DESIGN / BUILD FIRM shall provide 8-inch diameter water mains on . Noremac Avenue from and on Cleveland Road from North Biscayne Point Road to Noremac Avenue. 4. Street Lighting System: The DESIGN / BUILD FIRM shall incorporate the Existing plans, the DSM, the PWM, and the BODR to design and construct fully operational lighting improvements on Stillwater Drive. a. The DESIGN / BUILD FIRM shall coordinate its design with Florida Power and Light (FP&L) to ensure coordination of requisite service points and compliance with regulatory requirements. b. The DESIGN / BUILD FIRM shall incorporate the lighting improvements as generally shown on the Existing Plans. c. The added scope of work at Biscayne Beach (new conduit/wire) as well as the light pole base relocations at Biscayne Point Island shall be included in this DCP (design and construction). 5. Streetscape Improvements: The DESIGN / BUILD FIRM shall incorporate the Existing Plans, the DSM, the PW Manual, and the BODR to design and construct the proposed streetscape improvements. The design of proposed hardscape improvements shall be reviewed and conceptually approved by the Miami-Dade Public Works Department Traffic Engineering Division, the CITY of Miami Beach Public Works Department, and other applicable jurisdictional agencies, prior to finalizing construction documents. a. As a minimum, the DESIGN / BUILD FIRM shall incorporate the hardscape and softscape improvements shown on the Existing Plans. b. Existing Damaged Sidewalks, Driveway Ramps, Curbing and Valley Gutter Replacement: The DESIGN / BUILD FIRM shall replace valley gutter and NEIGHBORHOOD NO.: 1—BISCAYNE POINT March 20, 2012 01000-4 I curbing shown to be replaced on the existing plans and shall also replace damaged valley gutter and curbing. The City will evaluate the curbing and provide a list of curbing to be replaced by the DESIGN / BUILD FIRM. All new valley gutter and curbing shall be grey (natural) in color or Miami Beach Red as directed by the City Engineer. All new sidewalks shall be Miami Beach Red in color or as directed by the City Engineer. c. The DESIGN / BUILD FIRM shall provide concrete pavers in lieu of stamped . asphalt at the 77th Street entry. d'. The DESIGN / BUILD FIRM shall provide concrete paver speed tables in lieu. of stamped asphalt at the four locations on Biscayne Point Island. 6. Pavement Marking and Signage: The DESIGN / BUILD FIRM shall develop plans and construct all requisite pavement markings and signage in accordance with Miami-Dade Public Works Department Traffic Engineering Division, the CITY of Miami Beach.Public Works Department, and other applicable jurisdictional agencies, prior to finalizing construction documents. The DESIGN / BUILD FIRM shall also verify that the minimum number of handicapped spaces are provided. The pavement marking and signage at the intersection of Crespi and Hawthorne shall be built to match existing conditions, not built per the existing EAC design. 7. Organic Material: An organic muck layer occurs intermittently throughout the CITY at varying and sometimes shallow depths. a. The CITY is amenable to the DESIGN / BUILD FIRM revising the trench bedding depth within organic layers. In this effort, the DESIGN / BUILD FIRM will work closely with the CITY to minimize any and all impacts that may occur from discovery of organic matter within the project area. b. No additional payment will be made by the CITY for removal of muck. C. Encroachments: The DESIGN / BUILD FIRM shall familiarize itself with the DSM and the BODR to properly address the removal of private encroachments in the right-of-way. It shall be the responsibility of the DESIGN / BUILD FIRM to verify and update the previously prepared encroachment list relative to design revisions and coordinate final classifications with the CITY. D. Permitting: The DESIGN / BUILD FIRM shall prepare applications and such documents and design data as may be required to procure approvals from all governmental authorities that have jurisdiction over the Project as represented in its contract documents. The DESIGN / BUILD FIRM shall be responsible for meetings, submissions, re-submissions, and negotiations with such authorities. The CITY may attend meetings with governmental authorities as deemed necessary by the CITY. It is recognized by the CITY that the time period for obtaining permits is partially beyond the control of the DESIGN / BUILD FIRM except for issues concerning the permitability of the design and the DESIGN / BUILD FIRM's ability to respond to permitting agency requests for information. Nevertheless, the DESIGN / BUILD FIRM shall be responsible for monitoring and tracking progress on the preparation and review of permits and subsequent requests for information. The DESIGN / BUILD FIRM shall correspond with noted jurisdictional authorities to establish permitting requirements, to revise its NEIGHBORHOOD NO.: 1—BISCAYNE POINT March 20,2012 01000-5 documents, and to respond to permitting inquiries as required. The DESIGN / BUILD FIRM shall copy the CITY on all correspondence and also attend meetings with CITY staff to review and discuss permitting status, as may be required. The following governmental authorities that have or may have jurisdiction over Project have been identified: • CITY of Miami Beach Planning Department • CITY of Miami Beach Public Works Department Miami-Dade County Department of Environmental Resource Management • Miami-Dade County Water and Sewer Department • Miami-Dade County Public Works Department—Traffic Engineering Division • Miami-Dade Department of Health and Rehabilitative Services • South Florida Water Management District • Florida Department of Environmental Protection • U.S. Army Corps of Engineers • U.S. Environmental Protection Agency Failure to identify governmental authorities that have jurisdiction over the: Project does .not relieve the DESIGN / BUILD FIRM from responsibility to pursue the permit as described above. Note that this effort includes the procurement of permit extensions, whether existing or new. E. Review of Contract Documents by CITY: The DESIGN / BUILD FIRM shall submit 90% contract documents to the CITY for review and comments. All review comments generated by the CITY shall be addressed with responses included in a subsequent submittal if necessary. It is anticipated that a two (2) week turnaround time for CITY review shall be provided in order for the DESIGN / BUILD FIRM to maintain pre- construction time frame commitments. F. Construction Kick-off Meeting: The DESIGN / BUILD FIRM shall prepare necessary presentation materials and attend / conduct one Construction Kick-off Meeting (CKM) following the acceptance of the 100% contract documents by the CITY. The purpose of the CKM is to advise residents on the schedule and sequencing of upcoming construction activities. The CITY shall schedule, find locations for, and notify residents of all such meetings. The DESIGN / BUILD FIRM shall prepare all presentation materials as well as draft meeting minutes and forward them to the CITY who shall review, provide comments, and distribute accordingly. G. Record Drawings: At the completion of the Project, the DESIGN / BUILD FIRM shall turn over to the CITY a set of signed and sealed record drawings and a complete set of all drawings in the latest version of AutoCAD on compact disk that accurately reflect the "as built" conditions of the new facility. All changes made to the construction documents, either as clarifications or as changes, shall be reflected in the plans. The changes shall be submitted at least monthly to the CITY. These "as built' drawings and the latest version of the AutoCAD format media must be delivered and found to be acceptable prior to final payment. The DESIGN / BUILD FIRM shall also deliver all technical manuals, operations manuals, maintenance schedules, and other documents necessary for the operation and maintenance of the improvements prior to final payment. NEIGHBORHOOD NO.: 1—BISCAYNE POINT March 20,2012 01000-6 PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION (Not Applicable) - END OF SECTION - NEIGHBORHOOD NO.: 1—BISCAYNE POINT March 20,2012 01000-7 SECTION 01005 - PUBLIC INFORMATION / LIAISON SERVICES PART 1 — GENERAL 1.01 THE REQUIREMENT A. The DESIGN / BUILD FIRM shall procure the services of a Public Relations Firm to provide labor, supplies, and essential communications as may be required for the fulfillment of the intent of the public information / liaison phase of the WORK, in strict accordance with the Contract Documents. B. The goal of these services shall be to allow the DESIGN / BUILD FIRM to maintain stakeholders up to date prior to, during and after the DESIGN / BUILD FIRM's implementation of rear water service relocations as noted in the contract documents. C. Stakeholders as the term is used herein shall include and refer to CITY representatives, property owners and residents affected by the rear easement water service relocation WORK. 1.02 SERVICES TO BE PROVIDED A. The CONTRACTOR shall develop and implement an effective and successful public information / liaison program to perform the following functions: 1. Ensure that, working in concert with CITY representatives, all required authorizations / releases are received from affected property owners. 2. Meet with individual affected stakeholders to review the proposed installation procedures, address stakeholder concerns, and establish a general understanding and level of comfort with stakeholders as to what to expect before, during and after construction..Such efforts shall include a walkthrough of the proposed routing of new water service lines with stakeholders and a DESIGN / BUILD FIRM's representative, to establish agreement as to pre-existing conditions and like and kind return of the finished project, to the satisfaction of the stakeholder. 3. Follow-up with stakeholders on any required warranty work and/or complaint resolution that may result from the WORK until resolved by the DESIGN / BUILD FIRM. PART 2 — PRODUCTS (Not Applicable) PART 3 — EXECUTION (Not Applicable) - END OF SECTION - NEIGHBORHOOD NO.: 1—BISCAME POINT March 20,2012 01005-1 SECTION 01010 - SUMMARY OF WORK PART 1 - GENERAL 1.01 THE REQUIREMENT A. WORK to be performed under this Contract shall consist of furnishing and installing all tools, equipment, materials, supplies, and manufactured articles and furnishing all labor, transportation, and services, including fuel, power, water, and essential communications, and performing all WORK, or other operations required for the fulfillment of the Contract in strict accordance with the Contract Documents. The WORK shall be complete, and all WORK, materials, and services not expressly indicated or called for in the Contract Documents which may be necessary and reasonably expected for the complete and proper construction of the WORK shall be provided by the DESIGN / BUILD FIRM as though originally so indicated, at no increase in cost to the CITY. B. Wherever the term Project is used in these documents, it shall be construed to mean all WORK associate with the BID PACKAGE NO. 1 — BISCAYNE POINT, a portion of the City's Right-Of-Way Improvements Program. C. Wherever the term CONSULTANT is used in these documents, it shall be construed to mean the registered professional engineer, architect, and/or landscape architect who has contracted with or who is employed by the DESIGN / BUILD FIRM to provide professional services for the design and permitting of the Project. The CONSULTANT shall be the Engineer of Record and shall be licensed by the State of Florida to provide said services. D. Wherever the term CONTRACTOR is used in these documents, it shall be construed to mean the DESIGN / BUILD FIRM. E. The Existing Plans included as part of the DESIGN CRITERIA PACKAGE were prepared by EAC Consulting (815 NW 52"d Avenue, Suite.402, Miami, FL 33126), Inc. . for the BP 1 — Biscayne Point ROW Neighborhood Improvements. F. The CITY may elect to provide a full time Resident Project Representative (RPR) throughout the construction Phase of the Project. The RPR shall act as a liaison between the DESIGN / BUILD FIRM and the CITY and shall make necessary observations of materials furnished and the WORK performed by the DESIGN / BUILD FIRM. The RPR shall not perform inspections. Inspections shall only be conducted by representatives of the various regulatory agencies which have jurisdictional authority over the Project. 1.02 SCOPE OF WORK A. The SCOPE OF WORK of this Contract comprises revising the design using the Existing Plans, obtaining the required permits with all applicable regulatory agencies, submittal of proposed construction schedule, and after acceptance, perform the construction of the infrastructure site work in accordance with the approved plans, NEIGHBORHOOD NO.: 1—BISCAYNE POINT March 20,2012 specifications and applicable rules and codes for work activities within the right-of-way in the City of Miami Beach. B. The WORK will include but not be limited to mobilization, staging, site preparation; earthwork, restoration, milling and resurfacing, storm drainage, water distribution, street lighting, streetscaping, and pavement marking and signage improvements as well as related activities that may include existing utilities relocation. C. The DESIGN / BUILD FIRM shall submit revised designs that may be required as part of the permit requirements and/or regulatory agencies comments with their associated cost estimates for acceptance by the DESIGN CRITERIA ENGINEER or his designee prior to proceed in with the final design. D. The general location of the WORK area is Neighborhood No. '1 —Biscayne Point comprising the islands of Biscayne Point, Biscayne Beach, and Stillwater Drive, which are generally north of Normandy Shores and west of Tatum Waterway. 1.03 STANDARD SPECIFICATION A. Except as noted, all materials and workmanship shall meet the requirements of the latest editions of the following publications: 1. Miami-Dade County Public Works Manual 2. The Florida Department of Transportation "Standard Specifications for Road and Bridge Construction", and its supplements; 3. The Florida Department of Transportation 'Roadway and Traffic Design Standards" 4. The Florida Department of Transportation "Structures Standards" 5. Miami-Dade Water and Sewer Department "Design and Construction Standard Specification and Details" 6. City of Miami Beach General ROW Design Standards Manual 7. City of Miami Beach Public Works Manual 1.04 SITE INVESTIGATION A. The DESIGN / BUILD FIRM, by virtue of signing the Agreement, acknowledges that it has satisfied itself to the nature and location of the WORK, the general and local conditions including, but not restricted to: those bearing upon transportation; disposal, handling and storage of materials, availability of water and electric power; access roads to the site; the conformation and conditions of the WORK area; and the character of equipment and facilities needed preliminary to and during the performance of the WORK. Failure on the part of the DESIGN / BUILD FIRM to completely or properly evaluate the site conditions shall not be grounds for additional compensation. Failure by the DESIGN / BUILD FIRM to acquaint itself with all available information shall not relieve it from responsibility for estimating properly the difficulty or cost of successfully NEIGHBORHOOD NO.: 1—BISCAYNE POINT March 20.2012 performing the WORK. The CITY assumes no responsibility for any conclusions or interpretations made by the DESIGN / BUILD FIRM on the basis of the information made available by the CITY. B. Soil boring information has been furnished to the DESIGN / BUILD FIRM for its general information. Such data are not warranted to be correct; the DESIGN / BUILD FIRM, by virtue of signing the Agreement, acknowledges that it has satisfied itself as to the nature and extent of soil and (underground) water conditions on the project site. No additional payment will be made to the DESIGN / BUILD FIRM because of differences between actual conditions and those shown by the boring logs. 1.05 WORK BY OTHERS A. Concurrent work by Other Contractors: The DESIGN / BUILD FIRM'S attention is directed to the fact that work may. be conducted at the site by other Contractors during the performance of the WORK under this Contract. The DESIGN / BUILD FIRM shall conduct its operations so as to cause little or no delay to work of such other Contactors, . and shall cooperate fully with such Contractors to provide continued safe access to their respective portions of,the site, as required to perform work under their respective contracts. B. Interference with WORK on Utilities: The DESIGN / BUILD FIRM shall cooperate fully with all utility forces of the CITY or forces of other public or private agencies engaged in the relocation, altering, or otherwise rearranging of any facilities which interfere with the progress of the WORK, and shall schedule the WORK so as to minimize interference with said relocation, altering, or other rearranging of facilities. 1.06 WORK SEQUENCE A. The DESIGN / BUILD FIRM shall schedule and perform the WORK in such a manner as to result in the least possible disruption to the public's use of roadways, driveways, and utilities. Utilities shall include but not be limited to water, sewerage, drainage structures, ditches and canals, gas, electric, internet, television, and telephone. Prior to commencing with the WORK, the DESIGN / BUILD FIRM shall perform a location investigation of existing underground utilities and facilities in accordance with the Sections entitled "Professional Services" and "Protection of Existing Facilities" and shall have obtained all required permits and permissions. The DESIGN / BUILD FIRM shall also deliver written notice to the CITY and property occupants (private and public) of all planned disruption to roadway, sidewalks, driveways, and utilities 72 hours in advance of disruption. In addition, all notifications of planned disruptions shall be coordinated with the CITY's Capital Improvement Project Office (CIP). B. If other projects will be connected to portions of WORK constructed as part of this project, it may be necessary to sequence portions of this project. The DESIGN / BUILD FIRM shall be responsible for coordinating construction activities and tie-ins with Contractor's of adjacent phases and sections as required. C. In addition to the above, the following restrictions shall be maintained: NEIGHBORHOOD NO.: 1—BISCAYNE POINT March 20,2012 1. WORK shall be allowed in two non-adjacent streets or avenues, subject to CITY approval. 2. The DESIGN / BUILD FIRM shall provide detailed phasing and maintenance of traffic plans for review and acceptance by the CITY prior to the commencement of,any construction activities within a Phase. 3. The DESIGN / BUILD FIRM'S phasing plans shall clearly illustrate :the DESIGN / BUILD FIRM's WORK intent. Each work area shall be broken down into sub-phases that allow work by up to two separate crews within each Phase simultaneously. 4. In no case shall more than one block of roadway on each street or avenue (two blocks total) be under construction at one time. 5. In no case shall more than 300 feet of trench be open at one time unless approved. by the Public Works Department. 6. All roadways surfaces within the Project area shall be milled and resurfaced if not rebuilt. Asphalt transitions between new and existing pavement at the limit of work shall be placed at a maximum slope of five (5%) percent. 7. The DESIGN / BUILD FIRM shall promptly provide temporary asphalt surfacing for any pavement disturbed during the installation of proposed water main, stormwater, and/or hardscape improvements. 8. Temporary asphalt patching will only be allowed for thirty (30) calendar days. Permanent restoration must be provided within thirty (30) days of disturbing any particular section of road. 9. The DESIGN / BUILD FIRM shall make necessary provisions to provide access to all driveways at the end of the working day. 10. All corrective work on private property necessitated by damage that may have occurred during construction activities, including but not limited to the restoration of landscaping, driveways, sidewalks, and utility connection must be complete before the work area is considered substantially complete. 11. Construction within the right of way of affected roads shall be scheduled so that all improvements are completed at once, and residents are only disrupted for one time period. This excludes water service plumbing work which may be required on private property - which shall be scheduled after mains are tested and accepted for connection by individual services. 12. Access for emergency vehicles shall be maintained at all times to all residences and businesses. 13. Excavations must be back-filled or barricaded at the end of each workday to prevent hazardous conditions. If a trench, excavation or structure is to be left open, it must be covered with a steel plate and made accessible to residents at the end of each workday or when work will be suspended for more than eight (8) hours. NEIGHBORHOOD NO.: 1—BISCAME POINT March 20.2012 14. The DESIGN / BUILD FIRM shall coordinate with the appropriate local agencies and private companies, which may provide services to the residents, as required to provide uninterrupted bus, school bus, garbage collection, mail delivery and other service during the WORK period. A traffic maintenance plan indicating proposed street closings, schedules, and alternate routes, which have been approved by the applicable jurisdictional agency, should be submitted to all affected agencies and companies for coordination and routing purposes. 15. Transportation provisions for handicapped or disabled residents shall be made by. the DESIGN / BUILD FIRM if construction prevents access to homes. D. The DESIGN / BUILD FIRM shall be. responsible for coordinating all water service interruptions within the project area. 1. All affected residents shall be notified by the Public Works Department a minimum of seventy-two (72) hours prior to a shut off of water supply. Any water supply interruptions shall be scheduled to be as short as possible and not exceed four (4) hours in duration. For multi-family apartments or condominium complexes, written notice of planned disruptions may be directed to Condominium Association's Management Companies, Condominium Association's Board of Directors, Apartment Property Managers or other property managing companies or individuals via certified mail; for single family residences written notices shall be directed to the residents via door hangers. All notifications of planned disruptions shall be coordinated with the CITY CIP Office and the City of Miami Beach Public Works Department. 2. The DESIGN / BUILD FIRM shall submit a written request to the City of Miami Beach CIP Office for forwarding to the Fire Department and Public Works Department for shut-off of potable water or fire main supply, a minimum of one week prior to the scheduled shut-off. The DESIGN / BUILD FIRM shall obtain confirmation from the City of Miami Beach Public Works Department. Note that ONLY the City of Miami Beach Public Works Department is authorized to shut-off any potable water or fire main supply lines. E. The DESIGN / BUILD FIRM shall store materials and equipment in a fenced or otherwise enclosed area during non-working hours. 1. Pipe and material shall not be strung out along installation routes, for more than one workday. DESIGN / BUILD FIRM shall store minimal amount of material on site within designated areas, which shall be shown on the Construction Documents. 2. The City will provide the DESIGN / BUILD FIRM with staging area. 3. The DESIGN / BUILD FIRM shall develop a staging plan for review and acceptance by the CITY. 4. The DESIGN / BUILD FIRM shall restrict parking for its employees and sub- contractors within the staging areas and/or swales adjacent to the work area. If necessary, the DESIGN / BUILD FIRM shall provide additional off-site storage, staging, and parking as necessary at no additional cost to the contract. DESIGN / BUILD FIRM shall maintain all staging areas until the project is completed. NEIGHBORHOOD NO.. 1—BISCAYNE POINT March 20,2012 F. The DESIGN / BUILD FIRM shall maintain existing infrastructure in working condition. 1. As stormwater management system improvements are comprised of system wide requirements, the DESIGN / BUILD FIRM shall plan, design, and construct stormwater improvements in a manner that results in minimal impact to existing stormwater system performance. 2. Existing lighting levels shall be maintained in operation at all times during construction. In this effort, the DESIGN / BUILD FIRM shall provide temporary power supply and/or temporary lighting when necessary to maintain lighting conditions that meet a minimum of pre-existing conditions. However the DESIGN / BUILD FIRM. shall not be responsible for lighting failures that are not the result of its work activities. 3. DESIGN /. BUILD FIRM shall schedule and coordinate all parking related signage and street markings demolition and installation with the City of Miami Beach Parking Department through the CIP Office. 4. The DESIGN/ BUILD FIRM shall coordinate with the Parking Department through the CIP Office to ensure timely implementation of the following tasks. The DESIGN / BUILD FIRM shall adjust its schedule to comply with Parking Department timelines, accordingly. • Removal of parking meter heads (Posts to be removed by DESIGN / BUILD FIRM). • Removal of parking signs (Post to be removed by DESIGN / BUILD FIRM). • Reinstallation of parking meter post and heads (Heads to be provided by the CITY). • Reinstallation of parking related signs and posts (Signs to be provided by the CITY). 1.07 TRAFFIC CONTROL A. The DESIGN / BUILD FIRM shall submit a conceptual Traffic Control Plan at the Pre- Construction Conference. This preliminary plan shall identify the phases of construction that the DESIGN / BUILD FIRM plans to proceed with and identify traffic flows during each Phase. The DESIGN / BUILD FIRM will be required to submit a detailed plan showing each Phase's Maintenance and Protection Plan prior to starting construction of any Phase. B. The DESIGN / BUILD FIRM shall submit a weekly Traffic Impact Plan to the CITY by Wednesday of each week to allow for notification of anticipated road closures to public entities located in and doing business in the project area. The Traffic Impact Plan shall identify streets that are under construction and construction activities that may impact vehicular and pedestrian traffic. C. The Maintenance of Traffic Plans shall be prepared in accordance the Current Edition of the Florida Department of Transportation Standard Specification for Road and Bridge Construction, Florida Department of Transportation Design Standard for Road and NEIGHBORHOOD NO.: 1—BISCAYNE POINT March 20, 2012 Bridge Construction, and the Miami-Dade County Public Works Department Manual for Design and Construction. D. The Maintenance of Traffic plan shall address pedestrian traffic as well as vehicular traffic. E. The DESIGN / BUILD FIRM, at all times, shall conduct the WORK in such a manner as to insure the least obstruction to traffic as is _practical. Convenience of the general public and of the residents.adjacent to the work shall be provided for in a satisfactory manner, as determined by the CITY. F. Fire hydrants on or adjacent to the WORK.shall be kept accessible to fire apparatus at all times, and no material or obstruction shall be placed within twenty (20) feet of any such hydrant. G. All existing stop signs and traffic signalization shall be maintained in operating conditions at all times during construction. H. When permission has been granted by the City of Miami Beach Public Works Department to close an existing roadway, the DESIGN / BUILD FIRM shall furnish and erect signs, barricades, lights, flags and other protective devices, which shall conform to the requirements, and be subject to the approval of the jurisdictional agency. The DESIGN / BUILD FIRM shall furnish and maintain proper protective devices at such location for the entire time of closure as the jurisdictional agency may direct. Signage shall be affected one week before closure. I. The DESIGN / BUILD FIRM shall furnish a sufficient number of protective devices to protect and divert the vehicular and pedestrian traffic from working areas closed to traffic, or to protect any new work. Failure to comply with this requirement will result in the shut down of the work until the DESIGN / BUILD FIRM provides the necessary protection. J. In areas.where there are existing pavement markings, the DESIGN / BUILD FIRM shall install temporary pavement markings any time traffic is diverted for a period of time that will exceed one work day or as allowed by the City of Miami Beach Public Works Department. 1.08 WORK SCHEDULE A. Time is of the essence in completing this project. Because time is of the essence, the DESIGN / BUILD FIRM shall commit the necessary resources to this project to complete it in a timely manner. Note that a typical workday will be based on the hours established in the CITY Noise Ordinance, for the specific zoned area. If the DESIGN / BUILD FIRM wishes to work longer hours than those specified herein, it shall request so, in writing, by Wednesday of the previous week for which the request is made. Due to the residential nature of project area, the DESIGN / BUILD FIRM shall coordinate its construction activities with the Miami-Dade County Public Schools and other private and/or religious academic institutions to minimize disruptions to the flow of traffic during drop-off and pick-up hours. WORK completed at other than regular working hours should be easily observable by CITY staff on the subsequent day. If the DESIGN / NEIGHBORHOOD NO.: 1—BISCAYNE POINT March 20,2012 BUILD FIRM proposes to complete work that will be "covered up" after normal working hours, it shall reimburse CITY for costs associated with the observation of such work. . B. The Construction progress will be measured with the construction schedule submitted by the DESIGN / BUILD FIRM as specified in Section 01311. If the CITY determines that the DESIGN / BUILD FIRM does not meet the Critical Path Method (CPM) schedule, the DESIGN / BUILD FIRM shall be required to commit those resources necessary to ensure the completion of the project in a timely manner. All costs incurred to implement measures to complete the WORK in timely manner shall be borne by the . DESIGN / BUILD FIRM. C. Whenever a reference to number of days is noted, it shall be construed to mean calendar days. 1.09 COMPUTATION OF CONTRACT TIME A. It is the DESIGN / BUILD FIRM's responsibility to provide clear and convincing . documentation to the CITY as to the effect additional WORK will have with respect to additional contract time extension requirements. If additional quantities of .WORK can be carried out concurrent with other existing construction activities without disrupting the critical path of the project then no contract time extension will be granted. B. The DESIGN / BUILD FIRM is obligated to provide documentation to the CITY if additional elements of WORK affects the critical path of the project. If WORK set forth in the original scope of the project is deleted, the contract time may be reduced. This contract is a calendar day contract. While the DESIGN / BUILD FIRM may be granted time to suspend WORK operations for vacations or holidays, contract time will not be suspended. During suspensions, the DESIGN / BUILD FIRM shall be responsible for all maintenance of traffic and liability without additional compensation from the CITY. In addition, DESIGN / BUILD FIRM shall comply with timely notice requirements as specified in the General Conditions. 1.10 PRE-CONSTRUCTION CONFERENCE Prior to the start of construction activities, a Pre-Construction Conference will be held between the DESIGN / BUILD FIRM, CITY, other interested agencies, representatives of utility companies and others affected by the WORK. The time and place of this conference will be set by the CITY. The DESIGN / BUILD FIRM shall take to the conference a copy of its preliminary WORK schedule for review and comment by the CITY. The schedule shall include sequences of operation and time schedule. 1.11 UTILITY LOCATIONS A. To the extent possible, some existing utility lines in the project area have been shown on the conceptual plans. However, neither the Original Design Consultant or the CITY guarantee that all lines are shown, or that said lines are shown in their true location. It shall be the DESIGN / BUILD FIRM's responsibility to identify and locate and relocate / design around all underground and/or overhead utility lines or equipment affected by the project. No additional payment will be made to the DESIGN / BUILD FIRM because NEIGHBORHOOD NO.: 1—BISCAYNE POINT March 20,2012 01010-8 of discrepancies in actual and plan shown / not shown location of utilities and damages suffered as a result thereof of lines shown on the plans. B. The DESIGN / BUILD FIRM shall notify each .utility company with known / suspected utilities in the Project area at least thirty.(30) days prior to the start of construction to arrange for positive underground location, relocation or support of its utility where that utility may be in conflict with or endangered by the proposed construction. Relocation of water mains or other utilities for the convenience of the DESIGN / BUILD FIRM shall be paid for by the DESIGN / BUILD FIRM. All charges by utility companies for temporary support of their utilities and permanent utility relocations to avoid conflict shall be the responsibility of the DESIGN / BUILD FIRM and the utility company involved. C. The DESIGN./ BUILD FIRM shall schedule and coordinate its WORK in such a manner that it is not delayed by the utility companies relocating or supporting their utilities. No compensation will be paid to the DESIGN./ BUILD FIRM for any loss of time or delay. D. All overhead, surface or underground structures and/or utilities encountered are to be carefully protected from damage or displacement. All damage to said structures and/or utilities is to be completely repaired within a reasonable time- needless delay will not be tolerated. The CITY reserves the right to remedy any damage by ordering outside parties to make repairs at the expense of the DESIGN / BUILD FIRM. All repairs made by the DESIGN / BUILD FIRM are to be made to the satisfaction of the Utility Owner and shall be inspected by a representative of the Utility Owner and the CITY. E. A minimum of forty-eight (48) hours before excavating, the DESIGN / BUILD FIRM should call Sunshine State One Call of Florida Inc., and a locator will be dispatched to the WORK location. The DESIGN / BUILD FIRM shall coordinate with the utility companies not included in the Sunshine State One Call of Florida, Inc. location service. 1.12 LINE AND GRADE The DESIGN / BUILD FIRM shall provide vertical and horizontal control for layout of the WORK in the form of bench marks and reference points located adjacent to the WORK. From these controls provided, the DESIGN / BUILD FIRM shall develop and make all detailed surveys needed for construction and shall establish all working points, lines and elevations necessary to perform the WORK. This surveying WORK shall be supervised by a Professional Land Surveyor registered in the State of Florida. 1.13 PROTECTION AND RESTORATION OF SURVEY MONUMENTS The DESIGN / BUILD FIRM shall carefully protect from disturbance all survey monuments, stakes and bench marks, whether or not established by it, and shall not remove or destroy any surveying point until it has been properly witnessed by a representative of the CITY. All major survey monuments that have been damaged by the DESIGN / BUILD FIRM such as section corners, 1/4 section corners, property corners or block control points, shall be replaced at the DESIGN / BUILD. FIRM's expense with markers of a size and type approved by the CITY. All replacements shall be under the supervision of a Florida Registered Land Surveyor. The DESIGN / BUILD NEIGHBORHOOD NO.: 1—BISCAYNE POINT March 20,2012 01010-9 FIRM shall document survey monuments prior-to construction and submit the location and type of all markers to the CITY. 1.14 EQUIPMENT All equipment necessary and required for the proper construction of all work shall be on the construction site, in first-class working condition. 1.15 OWNERSHIP OF EXISTING MATERIALS All materials removed or excavated from the job site shall remain the property of the CITY until released by the DESIGN CRITERIA ENGINEER / PROGRAM MANAGER,.at which time -.it shall become the property of the DESIGN / BUILD FIRM, who shall dispose of it in a manner, complying with all applicable jurisdictional requirements. 1.16 EXCESS MATERIAL All vegetation, debris, concrete or other unsuitable materials shall be disposed of off- site in approved areas provided by the DESIGN / BUILD FIRM. Storage of unsuitable materials on site shall not-be allowed. All unsuitable materials are to be removed from work site as they are generated. Any excess material desired to be retained by the CITY shall be delivered by the DESIGN / BUILD FIRM to a designated area within a 5 mile radius of the project, at no extra cost to the CITY. 1.17 AUDIO-VISUAL PRECONSTRUCTION RECORD A. General: 1. The DESIGN / BUILD FIRM shall engage the services of a professional electrographer. The color audio-video documents shall be prepared by a responsible commercial firm known to be skilled and regularly engaged in the business of preconstruction color audio video documentation. The electrographer shall furnish to the CITY a list of all equipment to be used for the audio-video taping i.e., manufacturer's name, model number, specifications and other pertinent information. Additional information to be furnished by the electrographer are the names and addresses of two references that the electrographer has performed color audio-video recording for on projects of a similar nature within the last 12 months. 2. Prior to beginning the WORK, the DESIGN / BUILD FIRM shall have a continuous color audio-video recording taken along the entire length of the project to serve as a record of preconstruction conditions. No construction shall begin prior to review and approval of the tapes covering the construction area by the CITY. The CITY shall have the authority to reject any and/or all portions of the video tape not conforming to the specifications and order that it be redone at no additional cost to the Project. The DESIGN / BUILD FIRM shall reschedule unacceptable coverage within five days after being notified. The CITY shall designate those areas, if any, to be omitted from or added to the audio-video coverage. B. Equipment: NEIGHBORHOOD NO.: 1—BISCAYNE POINT March 20,2012 01010-10 1. All equipment, accessories, materials and labor to perform this service shall be furnished by the DESIGN / BUILD FIRM. 2. The total audio-video system shall reproduce bright, sharp, clear pictures with accurate colors and shall be free from distortion, tearing, rolls or any other form of imperfection. The audio portion of the recording shall reproduce the commentary of the camera operator with proper volume and clarity and be free from distortion and interruptions. 3. When conventional wheeled vehicles are used, the distance from the camera lens to the ground shall not be less than twelve feet. In some instances audio-video tape coverage may be required in areas not accessible by conventional wheeled vehicles. Such coverage shall be obtained by walking or special conveyance approved by the CITY and DESIGN CRITERIA ENGINEER / PROGRAM MANAGER. 4. The color video camera used in the recording system shall have a horizontal resolution of 300 lines at center, a luminance signal to noise ratio of 45 dB and a minimum illumination requirement of 25 foot-candles. C. Recorded Information -Audio: Each CD shall begin with the current date, project name and municipality and be followed by the general location, i.e., name of street, house address, viewing side and direction of progress. The audio track shall consist of an original live recording. The recording shall contain the narrative commentary of the electrographer, recorded simultaneously with his fixed elevation video record of the zone of influence of construction. D. Recorded Information -Video 1. All video recordings must, by electronic means, display continuously and simultaneously generated with the actual transparent digital information to include the date and time of recording, and station numbers as shown on the drawings. The date information shall contain the month, day and year. The time information shall contain the hour, minutes and seconds. Additional information shall be displayed periodically. Such information shall include, but not be limited to, project name, contract number, name of street, house address, direction of travel and the viewing side. This transparent information shall appear on the extreme upper left hand third of the screen. 2. All recording shall be made during times of good visibility. No recording shall be made during precipitation, mist or fog. The recording shall only be done when sufficient sunlight is present to properly illuminate the subjects of recording and to produce bright, sharp video recordings of those subjects. 3. The rate of speed of the vehicle used during taping shall not exceed 10 miles per hour. Panning, zoom-in and zoom-out rates shall be sufficiently controlled to maintain a clear view of the object. NEIGHBORHOOD NO.: 1—BISCAYNE POINT March 20,2012 01010-11 4. Record coverage shall include all surface features located within the zone influence of construction supported by appropriate audio coverage. Such coverage shall include, but not be limited to, existing driveways, sidewalks, curbs, pavements, ditches, mailboxes, landscaping, culverts, fences, signs and headwalls within the area covered. Particular attention should be paid to those items outside or adjacent to the work limits that may become damaged during construction. 1.18 ADJUSTING EXISTING VALVES, METERS, CATCH BASINS, AND MAINTENANCE ACCESS STRUCTURES (i.e. MANHOLES) It shall be the DESIGN / BUILD FIRM's responsibility to coordinate and have all adjustments made to existing water meters, valves, and structures encountered during construction, to meet all final grades, unless otherwise instructed by the respective utility owner. All valves and maintenance access structures shall be accessible during all phases of the WORK for emergency access. Omission of such structures from the conceptual plans does not relieve the DESIGN / BUILD FIRM from making such adjustments as may be deemed necessary. 1.19 CONFLICT STRUCTURES: The DESIGN / BUILD FIRM shall abide by the following criteria concerning conflicts between new drainage, water, or sewer construction and existing utilities. A. The DESIGN / BUILD FIRM shall verify the location of all utilities suspected of being potential conflicts prior to ordering materials for these locations. B. Where an existing utility is to pass through a conflict structure, the DESIGN / BUILD FIRM shall protect the utility from damage by whatever means the utility owner deems necessary. C. In no case shall there be less than 0.3 feet between any two (2) pipe lines within the structure or between pipe lines and the structure. 1.20 ENVIRONMENTAL PROTECTION A. The DESIGN / BUILD FIRM shall furnish all labor and equipment and perform all WORK required for the prevention of environmental pollution during and as a result of the WORK under this contract. For the purpose of this contract, environmental pollution is defined as the presence of chemical, physical, or biological elements or agents which adversely affect human health or welfare; unfavorably alter ecological balances of importance to human life, affect other species of importance to man, or degrade the utility of the environment for aesthetic and recreational purposes. The control of environmental pollution requires consideration of air, water, land and involves noise, solid waste management and management of radiant energy and radioactive materials, as well as other pollutants. B. The DESIGN / BUILD FIRM shall take all steps necessary to protect water quality in the connected waters around the project. Silt screens shall not be removed until the turbidity of the affected waters is equal to or lower than the ambient turbidity of undisturbed segments of adjacent surface waters. NEIGHBORHOOD NO.: 1—BISCAYNE POINT March 20,2012 01010-12 C. The DESIGN / BUILD FIRM shall implement a Stormwater Pollution Prevention Plan in accordance with the Florida Department of Environmental Protection minimum requirements. The DESIGN / BUILD FIRM shall obtain and prepare all documents necessary to obtain a Florida Department of Environmental Protection National Pollution Discharge Elimination System Permit for Construction Activities. All cost associated with this activity shall be included in the Lump Sum Bid Price. D. All protection requirements covered by this subsection shall be in compliance with all applicable jurisdictional agency requirements. 1.21 VIBRATORY COMPACTION A. The use of vibratory compaction equipment shall be limited to a total gross weight of three (3) tons. The use of vibratory equipment shall be limited to compacting backfill of utility trenches and subgrade of roadways only. If approved in writing by the CITY, larger vibratory compaction equipment may be allowed if operated in a static mode only. The DESIGN / BUILD FIRM shall be responsible for addressing and settling all damages / claims that may result from its compaction activities on the surrounding neighborhood and its residents. 1.22 REPORTING OF DAMAGE CLAIMS The DESIGN / BUILD FIRM shall keep the CITY informed of any damage claims made against the DESIGN / BUILD FIRM during the construction period. All claims for automobile damage, property damage and/or bodily injury will be reported to the CITY within 24 hours of receipt of notice. DESIGN / BUILD FIRM will conduct a timely investigation of the claim and determine if they will honor claim and/or report to their insurance carrier and provide periodic updates, each quarter, until final disposition of claims. The DESIGN / BUILD FIRM will advise the CITY in writing of its decision/referral to carrier. 1.23 PERMITS A. It shall be the DESIGN / BUILD FIRM's responsibility to secure all permits of every description required to initiate and complete the work under this Contract, except for permits obtained by the CITY. B. The DESIGN / BUILD FIRM shall furnish signed and sealed sets of Contract Documents for permit use as required. C. The DESIGN / BUILD FIRM shall furnish to the CITY copies of all permits prior to commencement of work requiring permits. D. The DESIGN / BUILD FIRM shall be responsible for procuring extension permits as required throughout the duration of the project. E. The cost for Permit Fees shall be included in the guaranteed maximum price. NEIGHBORHOOD NO.: 1—BISCAYNE POINT March 20,2012 01010-13 1.24 DIMENSIONS OF EXISTING FACILITIES Where the dimensions and locations of existing improvements are of critical importance in the installation or connection of new work, the DESIGN / BUILD FIRM shall verify such dimensions and locations in the field prior to the fabrication and/or installation of materials or equipment which are dependent on the correctness of such information. PART 2 - PRODUCTS (Not Applicable) PART 3 - EXECUTION (Not Applicable) - END OF SECTION NEIGHBORHOOD NO.: 1—BISCAYNE POINT March 20,2012 01010-14 Attachment 2 ° SETTLEMENT AGREEMENT AND MUTUAL RELEASE BETWEEN DAVID MANCINI & SONS, INC. AND THE CITY OF MIAMI BEACH, FLORIDA This Settlement Agreement and Mutual Release ("Agreement') is made and entered into this day of March, 2012 ("Effective Date"), by and between DAVID MANCINI & SONS, INC., a Florida corporation, (hereinafter "DMSI") and the CITY OF MIAMI BEACH, FLORIDA, a municipal corporation (hereinafter, the "City"). DMSI and the City may also be referred to individually as a"Party", and collectively as the"Parties." RECITALS WHEREAS, DMSI and the City are parties to a construction contract, dated April 4`h, 2011 (the "Contract'), for Construction Services for the water main, storm water collection/disposal, irrigation, electrical, lighting, curb/gutter, sidewalk, road reconstruction and asphalt milling/resurfacing improvements of Biscayne Point — Neighborhood No. 1 Right-of- Way Improvements Project, consisting of the Biscayne Point Island, Biscayne Beach, and Stillwater Drive sub-neighborhoods, Miami Beach, Florida, and entered into pursuant to Invitation to Bid No. 07-10/11 (hereinafter, the"Project'); and WHEREAS, the Parties have agreed to a termination for convenience of the Contract, due, in part, to construction design deficiencies and associated delays, as of the Effective Date of this Agreement; and WHEREAS, the Parties desire to settle all claims, disputes, past or present, regarding the Project, regardless of responsibility, based upon the uncertainties of potential litigation and that settlement is in the best interest of the City and its residents; WHEREAS, the Parties further agree to waive any and all past and present claims against the other, as it relates to this Project including, but not limited to, change order requests, Page 1 of 8 delay claims, liquidated damages, back charges, requests for time extensions, as it relates to this Project. WHEREAS, the Parties agree to bear their own respective costs and attorney's fees as it relates to this Settlement Agreement. NOW THEREFORE, in consideration for the exchange of promises contained herein, and for good and valuable consideration acknowledged herein, the Parties agree as follows: 1. The above Recitals are true and correct and are incorporated herein. 2. The Parties agree and acknowledge that the Contract amount was $10,907,758.61. Five (5) change orders, totaling $561,744.43, were added to the Contract amount, for a revised Contract amount of$11,469,503.04. 3. The Parties hereby agree to remove scope of work, in the amount of $7,533,778.41, from the Contract amount. The remaining balance of$3,935,724.64 includes a previous paid amount of $3,510,403.53, and an unpaid amount of $425,321.11. This unpaid amount shall be used to fund the remaining scope in the Contract. Final completion of the Contract is anticipated by June 29th, 2012. Retainage shall be held and released as per the Contract terms and conditions for the remaining scope of work. Of the funding removed from the Contract ($7,533,778.41), a credit of $825,177.00 shall be removed from the remaining balance, leaving $6,708,601.00. Pursuant to Article 33 of the Contract, regarding value engineering, the credit of $825,177.00 includes a $515,523.00 credit for the two (2) pump stations and a $309,654.00 credit for the grates at the bulb-outs and the stamped asphalt, which were deleted scopes of work. 4. In addition to the Contract amount listed above, the City has agreed to pay DMSI the sum of $1,500,000.00, in consideration for settlement of all claims, whether expressly or Page 2 of 8 implicitly raised by claimant DMSI, related to the Contract, as well as compensation in the amount of$515,523.00, for DMSI's portion of the shared savings for the value engineering of two (2) pump stations. These amounts, totaling $2,015,523.00 (also referred to herein as the "Settlement Payment"), will be billable on the Effective Date of this Agreement. Payment will be made within three (3) weeks of the Effective Date of this Agreement. 5. The Parties agree and acknowledge the remaining scope of work pending completion under the Contract, which DMSI has agreed to complete is as follows: a. All water improvements, excluding irrigation improvements; b. All landscape removal within Biscayne Point Island; C. All lighting improvements within Biscayne Point Island and Biscayne Beach, excluding the Biscayne Point Island paver entrance, Stillwater Drive lighting and the undergrounding of the Biscayne Beach Lighting System; d. Demolition work associated with the above referenced improvements; and e. General Conditions to complete the above-referenced improvements. Attached hereto and incorporated herein as Exhibit "A" is the Total Project Summary Spreadsheet. 6. The Parties agree and acknowledge that the following outstanding change order will be executed by the Parties as part of the Contract as follows: a. Change Order#5: Line item overruns for$54,014.26. 7. Prior to final payment, DMSI shall submit all required deliverables, warranties, and guarantees for the Work performed as part of the Contract, which shall comply with the terms and conditions of such Contract and associated technical specifications. Said deliverables shall include, but not limited to: Page 3 of 8 a. Four (4) full-size (24" x 36") hard copy sets and two (2) CDs (CAD files or .dwg files) of the final as-builts, approved by the City's Public Works Department and other regulatory agencies, as required. The hard copy sets shall be signed and sealed by a registered Land Surveyor in the State of Florida; b. Close-out of Final Punch List items; C. Final Releases of liens arising out of the Work performed as part of the original Contract; d. Affidavit certifying that all suppliers, subcontractors and that all indebtedness connected with the Work performed as part of the Contract have been paid in full and/or satisfied; e. Final consent of surety to final payment; f. Proof that all permits, licenses and impact fees necessary for the prosecution of the work undertaken as part of the Contract have been closed-out and paid in full; g. Certification that all insurance duration requirements shall be maintained in force through the durations specified in the Contract; h. Contractor's continual acceptance of the indemnification clause outlined in Section 00800 "General Conditions", Article 6, as it relates to the Work performed as part of the Contract; i. Contractor's certification that Payment and Performance Bonds provisions of the Contract, Section 008000, "General Conditions", Article 4, will be adhered to as it relates to the work performed under the Contract. Page 4 of 8 8. DMSI agrees that it remains responsible for any defects on the Project and all applicable warranties pursuant to the terms of the Contract. 9. The Parties agree to cooperate fully and execute any and all supplementary documents and to take all additional actions which may be reasonably necessary or appropriate to give full force and effect to the basis and intent of this Agreement. 10. Upon payment of the Settlement Payment, DMSI releases, acquits and forever discharges the CITY, including its affiliates and insurers, directors, officers, employees, agents and attorneys, together with its heirs, executors, administrators, associates, representatives, successors and assigns, from any and all past and present claims, demands, obligations, damages, costs, expenses, actions and causes of action whether for compensatory, punitive, or other damages, arising from or relating to the Contract and the Project, whether presently known or unknown. 11. Except as provided in Paragraph 8 hereof, the City releases, acquits and forever discharges DMSI, including its affiliates and insurers, directors, officers, employees, agents, subcontractors, sureties, and attorneys, together with its heirs, executors, administrators, associates, representatives, successors and assigns, from any and all past, present and future claims, demands, obligations, damages, costs, expenses, actions and causes of actions, whether for compensatory, punitive, liquidated or other damages, arising from or relating to the Contract . and the Project, whether presently known or unknown. --# 12. This Agreement contains the entire agreement between the Parties as related to the Contract and the Project. This Agreement replaces any prior or contemporaneous written or oral representation or understanding about the terms of this Agreement. This Agreement may- not be changed except in writing signed by the Parties or their respective attorneys. This Page 5 of 8 Agreement shall be binding on and shall inure to the benefit of the respective successors and assigns, if any, of each party. 13. This Agreement is being consummated in the State of Florida, and the performance by the Parties hereto is in the State of Florida. This Agreement shall be governed by and construed in accordance with the laws of the State of Florida. The venue for any legal proceeding of any nature brought by either party against the other to enforce any right or obligation under this Agreement, or arising out of any matter pertaining to this Agreement, shall be in Miami-Dade County, Florida. The Parties expressly agree to waive a trial by jury in any action to enforce this Agreement and that the Prevailing Party will be awarded reasonable attorney fees and costs. 14. The Parties warrant to each other that they have read this Agreement and that they understand this Agreement and that each have been represented by counsel before signing this Agreement. 15. This settlement is further subject to and contingent upon the successful execution by the City and DMSI of the negotiated Design/Build Contract, as stipulated in the City of Miami Beach Resolution No. 2011-27809. Page 6 of 8 IN WITNESS WHEREOF, the Parties have set their hands and seals on the day and date first written above. DAVID MANCINI & SONS, INC. Attest: Title:a �/ L I//G( 1&Ar,;A t Secretary Print Name OMB Nid�Z Print Name STATE OF FLORIDA COUNTY OF MIAMI-DARE The foregoing instrument was acknowledged before me this !�e day of>Z-4. -e-6 2012, by as of David Mancini & Sons, Inc., who is personally known to me or who has produced (type of identification). Name: 616-t) (Prin ame) .•a�P OLGA SANCHEZ Notary Public.Slate of Florida My Comm.Expires Jan 31,2015 Notary Public-State of Florida Commission s EE 56701 My Commission Expires: 1)11-111--20 .� •��••4:•�t.•`�` Bonded Through National Notary Assn. TY OF MIAMI PEACH, FLORIDA , Attest: * INCORP ORATED: '9� H 26 �01 ��,• ��-�r��e r o, �o i✓�r City Clerk Print Name APPROVED AS TO 0 FORM & LANGUAGE Print Name & FOR EXECUTION Page 7 of 8 3' City Atto Date STATE OF FLORIDA COUNTY OF MIAMI-DADE The foregoing instrument was acknowledged before me this day of , 2012, by as of the City of Miami Beach, who is personally known to me or who has produced (type of identification). Name: (Print Name) Notary Public—State of Florida My Commission Expires s Page 8 of 8 EXHIBIT "All Total Project Summary 597,512 Previously Executed JOC Contracts 5,951,247 Settlement : 11,1511-240 Design Build/GMP 17,700,000 1 Total Project Cost Previously Executed JOC Contracts 250,197 84th Street Water Main 205,914 85th Street Water Services 141,401 Redesign of Stillwater Water Main-2nd 1,000 LF 597,512 Total JOC Settlement 3,93S,72S Final Revised Contract Amount 825,177 Funding Allocation for scope credited 1,500,000 DMSI Settlement of Claims and Delays (515,523) Credit for the Value Engineering of two Pump Stations 515,523 DMSI Portion for the Value Engineering of the two Pump Stations Credit for the deletion of grates at bulb outs and Credit for Stamped (309,654) Asphalt 5,951,247 Total Settlement Amount Design Build / GMP 6,193,078 Remaining Balance from Original Contract 1,325,000 2.0 PWD Requests less JOC's issued 451,404 3.0 Misc.Owner Added Items less JOC's issued 124,000 5.0 Henedon Rd.Water line Replacement 1,330,100 6.0 New DCP Impacts 593,825 DB Risk&Construction Manager 870,400 A/E Design 263,433 Double Chamber Well Structures 11,151,240 Total Design Build Amount Page 1 of 1 W O O O O O O O O O O O O O O O O O O O C Ur O O O O O O O O O O O O O O O O O O O Q O O O O O O O O O O O O O O O O O O O C; 2' Efi 69 60 Vi 09 64 69 W. 64 U) H9 60 E9 E9 69 Vi W. b9 64 p o - a W CL O oU� v 0 0 O o O 0 O O v -n w (D 0 0 W) M O Lq u7 O) . 6l n O O O O v (n r r O O O ci W S O 0 v m w N M G (t) C C 7 M Qi (C G G O U H N O CO M M (n O O N O O N It O O _O (O v (O r. O) r� M v C O O O ul N O O = Z M O M t- M u7 CO O M O N O Cl (O M It N O N m LL GO r M W M M co O O) u7 r N �_ 69 N_ o O -n Go M Cl) t• v a0 tT In t` Cn M 69 O vi m F N9 fA 69 EA N fA fA fA fA fA fl9 E!9 E9 t9 1A n a o 0 0 o O o 0 0 0 0 0 0 o O o 0 0 0 o e N n U d O °o e 0 r�� O ooN U O O o O O O O O O O O O O O O O O O F�O ° w O O O O O O O O O O O O O O O O O O O Z a a Z F O O O O O O O O O O O O O O O O O O O Q Z g~ Q M f19 f9 W. 69 69 EA V9 fA fA f9 E9 E9 69 69 H 69 69 W. W y w p 7 a a O O CL a a o 0 0 0 0 0 0 o O 0 o O O O 0 0 0 0 o c a a Q y p 0 0 0 0 0 0 0 0 0 0 O O O O O O O O O p W 69 69 69 69 69 69 fA to 69 Vf 69 69 69 69 69 69 u► fA 69 u O FO. ZO p0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 F 0 0 0 CD CD 0 CD 0 0 cm 0 0 0 0 C> 0 CD C> 0 ci 69 69 69 69 669 69 69 69 69 69 69 69 C9 6/9 69 69 69 69 69 w C W N W N O � � y 0 0 0 o O o 0 0 0 0 0 0 0 o O O O o 0 0 Z 0 0 0 0 0 0 0 0 0 0 0 o 0 0 0 O 0 O o H O 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 CD OF 69 69 (9 69 69 69 69 69 6) 69 69 69 69 69 09 K1 69 (9 W. C a � W E O p Ca 0 w u »JJ u O W_Q N Q U rn °o Z Z w W W u Z ' F OOHO U Q O O u9 v .0 0 0 0 0 O 0 O IT N C° 0 0 0 N p M O u'? Iq rn r n o 0 0 0 v, U rn 0 0 0 o W O O V m O N M G Ln G 0 v Mi M 0 0 0 O O J W N O w M M LO CO O N O O N O O _O N > > (O v (O Il W n M v O GO O O O) 6• N O O u p J M O u1 M n M (n (D O M O (n O O (O M v N O W Q ap t` M O M M 6O o O u7 t` N H N_ x > 0 0 M M � r v Go v (n n (n (n 69 rn 69 („) 69 to 69 f9 N 69 fA 69 to 69 69 69 H 69 69 N 69 ea N •O C N tll � a c c 06 A a° d a`r � W Z A c o O Y c O Cl Z_ u N c d O a F C m V » N O " 1- a a 0 p d « 9 H o m m 3 c c a va $ a N LL o U-) N Q W ° y d •A ; v _� O y Y r C Y y O r U W i• J M 0 W « (O Z O ¢ a. d 01 W t « C F m O• t 7 U W cwi d s d � a N y = 0 a A C o « N> O K » y V W F- o m 6n r 9 V O at O 0 No m V d � A 'c° cc I u Gd CU/l m m A c («o e a c mm a V d - A ; w e (ca H G c. r `0rn c roi Z n w d e o �, E e y - ; 2 o e d o 06 m c u"i is m y o Q N v e° m C7 w C 3 % d J J Q C Q Ld m 3 d Q m Q F ` N of v N w (. co 06 o CO M 0 N M a W 6o Z i� 6� c W O r F Z Z a 0 ate =