2012-27957 Reso RESOLUTION NO f 2012 -27957 A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, APPROVING AND AUTHORIZING THE MAYOR AND THE CITY CLERK TO EXECUTE RETROACTIVE AMENDMENT NO. 13 TO THE PROFESSIONAL SERVICES AGREEMENT WITH STA 'ARCHITECTURAL GROUP, INC., DATED JULY 17, 1996, FOR THE FIRE STATION 2 AND HOSE TOWER REFURBISHMENT PROJECTS; SAID AMENDMENT, IN THE NOT TO EXCEED AMOUNT OF $20,747.36, TO PROVIDE PROGRAM REVISIONS AND DESIGN SERVICES FOR CHANGES REQUESTED BY THE FIRE DEPARTMENT, AND EXTENDED CONSTRUCTION ADMINISTRATION SERVICES; WITH FUNDING FROM THE CAPITAL RESERVE FUND 304 APPROPRIATED IN THE CAPITAL BUDGET FISCAL YEAR 2010/2011. RECITALS WHEREAS, pursuant to Request for Letters of Interest No. 133- 94/95, the Mayor and City Commission adopted Resolution No. 96 -22068 on July 17, 1996, approving and authorizing the Mayor and City Clerk to execute a Professional Services Agreement with STA Architectural Group, Inc. (Consultant) for the Renovation and Expansion of Fire Station No. 2, and a Master Plan for the site at 451 Dade Boulevard (the Project); and WHEREAS, the Agreement provided for the detailed planning, design, bidding and construction administration services for the Fire Station No. 2 Project; and WHEREAS, an Agreement for planning services was executed for a not -to- exceed amount of $78,000; and WHEREAS, on June 28, 2000, the Mayor and City Commission adopted Resolution No. 2000- 23975, approving Amendment No. 1 to the Agreement, for schematic design, design development, construction documents, permitting & bidding, and construction administration services for the rehabilitation of the historic structure and the new construction of a dormitory and apparatus structure improvements within the Project, for a not -to- exceed amount of $318,020; and WHEREAS, on October 17, 2001, the Mayor and City Commission adopted Res' esolution No. 2001 - 24624, approving Amendment No. 2 to the Agreement for the design of an Emergency Operations Center, a site drainage system, and a dedicated driveway serving the Public Works Yard, for a not -to- exceed amount of $117,000; and WHEREAS, on December 10, 2003, the Mayor and City Commission adopted Resolution No. 2003 - 25439, approving Amendment No. 3 to the Agreement for construction administration services for the Project, for a not -to- exceed amount of $192,000; and WHEREAS, on March 15, 2007, Amendment No. 4 to the Agreement was executed approving additional construction administration services for the Project, for a not -to- exceed amount of $24,500; and WHEREAS, on October 27, 2007, Amendment No. 5 to the Agreement was executed approving additional construction administration services for the Project, to be rendered on a monthly basis, for a not -to- exceed amount of $24,500; and WHEREAS, on June 20, 2008, Amendment No. 6 to the Agreement was executed approving additional construction administration services for the Project, to be rendered on a monthly basis, for a not -to- exceed amount of $24,447; and WHEREAS, on July 10, 2008, Amendment No. 7 to the Agreement was executed approving additional design and construction administration services for the Project, to be rendered on a monthly basis, for a not -to- exceed amount of $40,000; and WHEREAS, the first phase of the Fire Station No. 2 Project, the construction of Building B and its Emergency Operations Center, is substantially complete, and the Fire Department moved into the building and put if into service; and WHEREAS, Building A has now been more thoroughly inspected and several additional items have been identified that require modifications to the construction documents; and WHEREAS, the hose tower was also evaluated and, despite recent repairs, structural deficiencies were found; and WHEREAS,.as a result, work to the hose tower, which had not been a part of the original scope of work, must now be included in the renovation project; and WHEREAS, on December 9, 2009, Amendment No. 8 to the Agreement was negotiated by staff, for a fee of $183,000, for an in -depth preconstruction review, Historic Preservation Board presentation, re- drawing and development of construction documents (per current codes), and bid and construction administration services for the rehabilitation of the historic building, hose. tower, and new addition two -story connectors; and WHEREAS, on November 12, 2010, Amendment No. 9 to the Agreement was executed approving the additional programming, planning, concept design, meetings and presentations for a two -story Auxiliary Training Structure to be added along the rear side of the Project structure, for a not -to- exceed amount of $11,480; and WHEREAS, on March 25, 2011, Amendment No. 10 to the Agreement was executed approving additional services for the special. structural inspections of all the reinforcing steel, structural steel, wood truss framing, bracing, sheathing, exterior door and wood frame attachments for the construction of the Project, to be performed by a structural engineering sub - consultant, as required by the City's Building Department, to for a not -to- exceed amount of $10,000; and WHEREAS, on May 17, 2011, Amendment No. 11 to the Agreement was executed approving additional services for the architectural and structural design services associated with the re- design of foundations for the two connector buildings due to unforeseen conditions during construction, for a not -to- exceed amount of $2,760; and WHEREAS, on December 8, 2011, Amendment No. 12 to the Agreement was executed approving additional services for remediation special inspection services required for the structural engineer to oversee the structural spalling repairs of the building, for a not -to- exceed amount of $16,600; and WHEREAS, the following Amendment No. 13 to the Agreement approves additional services for program revisions requested by the Fire Department and extended construction administration services, for a not -to- exceed amount of $20,747.36. NOW, THEREFORE, BE IT DULY RESOLVED BY THE MAYOR AND THE CITY COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA that the Mayor and the City Commission hereby approve and authorize the Mayor and the City Clerk to execute retroactive Amendment No. 13 to the Professional services Agreement with STA Architectural Group, Inc., dated July 17,1996, for the Fire Station 2 and the Hose Tower refurbishment Projects; said amendment, in the not to exceed amount of $20,747.36 to provide revisions and Design Services for program changes requested by the Fire Department, and extended Construction Administration services; with funding from the capital reserve fund 304 previously appropriated in the capital budget fiscal year 2010/2011. - 1, B ` ................ C' ATTEST: CITY OF MIAMI BEACH INCORP 0 RA TED � y B Ci y Clerk, � CN 2C�� �� M or Rafael Granado Mattie Herrera Bower PASSED AND ADOPTED this Wh day of J� , 2012. T:\AGENDA \2012 \7 -18 -12 \STA Ammendment No13 - FS2\Reso for STA Amendment No. 13- FS2.doc 3 APPROVED AS TO FORM & LANGUAGE & 4A Fn XECUTION ate COMMISSION ITEM SUMMARY Condensed Title: A Resolution of the Mayor And City Commission Of The City Of Miami Beach, Florida, Approving And Officially Adopting That The Mayor and The City Clerk To Execute Retroactive Amendment No.13 To The Existing Professional Services Agreement With STA Architectural Group, Inc., For The Fire Station 2 And The Hose Tower Refurbishment Projects; To Provide Program Revisions And Design Services For Program.Changes Requested By The Fire Department And Extended Construction Administration Services; For Said Amendment In The Not To Exceed Amount Of $20,747.36 With Funding From The Capital Reserve Fund 304 Previously Appropriated In The Capital Budget Fiscal Year 2010/2011. Key Intended Outcome Supported: Ensure well-Designed, Quality Capital projects Supporting Data (Surveys, Environmental Scan, etc.): Middle Beach lags the rest of the City in quality of City emergency /hurricane preparedness satisfaction: 78% of Middle Beach residents surveyed rated emergency/hurricane preparedness as excellent or good compared to 84% of residents City-wide. Issue: Shall the Mayor and City Commission adopt the Resolution? Item Summa /Recommendation: The Amendment No. 13 is for a not -to- exceed amount of .$20,747.36, to revise the permitted construction set of plans in order to reconfigure the architectural layout during construction, as requested by the Fire Department Administration, since the Fire Prevention Department would remain in its current location. After the project was permitted, and well into construction; a request was made to change the original building layout in a particular section of the building. A detailed and careful evaluation of the changes .took place and STA presented a request for additional services to perform the work required. The additional services proposal was reviewed and negotiated in accordance with the original fees as stipulated in the contract. The additional services negotiated entailed meetings with the Fire Department to discuss program changes; preparing alternate reconfiguration substituting Fire Prevention with other Fire Department Administration uses; preparing Construction Document revisions to the permitted plans; providing MEP services in accordance with the changes, extended coordination meetings, additional site visits, inspections, and evaluation of the potential impact to the construction schedule, allowance for reimbursable, and it was also determined that the above mentioned items would in -fact impact the original schedule by approximately two months. This Amendment also consists of additional services for the Consultant to provide extended construction administration services from January thru March 2012. In accordance with City of Miami Beach procurement policies, change orders up to $25,000 can be processed administratively, Although this Amendment is less than the threshold ($20,747.30) there have already been previous Amendments administratively approved this fiscal year for STA on this project. The cumulative total would exceed the $25,000 threshold, therefore warranting Commission approval. Advisory Board Recommendation: N/A Financial Information: Source of a > Amount �� ' ¢ k: E ;ACCOUtIt:'':, F LV1,d s: $20,747.36 304- 2146- 061357 g OB7 �LL� =Total `: $20,747.36 in an I act Summary: N/A City Clerk' ffice Le islative Tracking: Fernando Vazquez ext. 6135 Sign-Offs: ::De artm t' ector :,.'Assistant Cit er s w r, ..'.:Cit . Mana er° FV JGG /DB KGB T:\AGENDA\2012\7-18-A\STAAmmendment No13 - FS2 \Summary for STAAlffiTi5endment No13.docx M IA M IBEACH AGENDA ITEM DATE —/ — 2- m MIAMI BEACH City of Miami Beach, 1700 Convention Center Drive, Miami Beach, Florida 33139, www.miamibeachfl.gov COMMISSION MEMORANDUM TO: Mayor Matti Herrera Bower and Members of the City Commission FROM: Kathie G. Brooks, Interim City Manager DATE: July 18, 2012 SUBJECT: A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, APPROVING AND AUTHORIZING THE MAYOR AND THE CITY CLERK TO EXECUTE RETROACTIVE AMENDMENT NO. 13, TO THE EXISTING PROFESSIONAL SERVICES AGREEMENT WITH STA ARCHITECTURAL GROUP, INC., FOR THE FIRE STATION 2 AND HOSE TOWER REFURBISHMENT PROJECTS; TO PROVIDE PROGRAM REVISIONS AND DESIGN SERVICES FOR PROGRAM CHANGES REQUESTED BY THE FIRE DEPARTMENT AND EXTENDED CONSTRUCTION ADMINISTRATION SERVICES; SAID AMENDMENT IN THE NOT - TO- EXCEED AMOUNT OF $20,747.36 WITH FUNDING FROM THE CAPITAL RESERVE FUND 304 APPROPRIATED IN THE CAPITAL BUDGET FISCAL YEAR 2010/2011. ADMINISTRATION RECOMMENDATION Adopt the Resolution. FUNDING Previously appropriated Fire Station No. 2 Project funds: $20,747.36 Capital Reserve fund account 304 - 2146 - 000346 for Contingency to be transferred into Design account 302- 2146 - 061357. ANALYSIS On June 7, 2012, Miami Beach officials celebrated the grand re-opening of the historically- designated Fire Station No. 2. The historic building, at 2300 Pine Tree Drive, serves as the City Fire Department's administrative headquarters. The firehouse's estimated cost of $2 million renovation and reconstruction had the approval of Miami Beach's historic preservation and planning boards. The plans for the reconstruction of the Historical Fire Station were developed by STA Architectural Group. On July 17, 1996, the Mayor and City Commission adopted Resolution No. 96 -22068 authorizing an Agreement with STA Architectural Group (Consultant) for Professional Services for the Renovation and Expansion of Fire Station No. 2 building A and B as well as a Master Plan for the Site. The Agreement provided for the detailed planning, design, bidding and construction administration services. After many years of planning and development, the Historical Fire Station 2 project commenced. After the project was "permitted, and well into construction; the Fire Department requested changes be made to the original building layout. The changes were required since the Fire Prevention Division would no longer move into the Fire Station 2 building. Fire Station No. 2 - STA Amendment #13 July18, 2012 Page 2 of 2 STA was directed to perform a detailed evaluation of the changes and they in turn presented a request for additional services. The additional services proposal was reviewed and negotiated in accordance STA's original fees as stipulated in the contract (Exhibit B -1 and B -2). The negotiated additional service was for a not -to- exceed amount of $20,747.36 presented as Amendment No. 13 (Exhibit A) as identified in the scope of services, for the permitted construction set of plans. The additional services negotiated entailed meetings with the Fire Department to discuss program changes; preparing alternate reconfiguration substituting Fire Prevention with other Fire Department Administration uses; preparing Construction Document revisions to the permitted plans; providing MEP services in accordance with the changes, extended coordination meetings, additional site visits, inspections, and evaluation of the potential impact to the construction schedule, allowance for reimbursable, and it was also determined that the above mentioned items would in -fact impact the original schedule by approximately two months. This Amendment also consists of additional services for the Consultant to provide extended construction administration services from January thru March 2012. In accordance with City of Miami Beach procurement policies, change orders up to $25,000 can be processed administratively. Although this Amendment is less than the threshold ($20,747.30) there have already been previous Amendments administratively approved this fiscal year for STA on this project. The cumulative total would exceed the $25;000 threshold, therefore warranting Commission approval. CONCLUSION The Administration recommends that the City approve retroactive Amendment No.13 to the STA Architectural Group, Inc., Agreement, to provide program revisions as requested by the Fire Department and the required extended construction administration services, for a not -to- exceed amount of $20,747.36. KGB /JGG /FV /DM /HC Attachment T:\AGENDA\2012 \7 -18 -12 \STA Ammendment No13 - FS2 \FS2 - STA Amend 13 - Memo.doc EXHIBIT A AMENDMENT NO. 13 TO THE PROFESSIONAL SERVICES AGREEMENT BETWEEN THE CITY OF MIAMI BEACH, FLORIDA AND STA ARCHITECTURAL GROUP, DATED JULY 21, 1996 FOR PROGRAM REVISIONS REQUESTED BY THE FIRE DEPARTMENT AND'EXTENDED CONSTRUCTION ADMINISTRATION SERVICES IN THE NOT -TO- EXCEED AMOUNT OF $20,747.36. This Amendment No. 13 to the Agreement made and entered this day of , 2012, by and between the City of Miami Beach, a Municipal Corporation existing under the laws of the State of Florida (hereinafter referred to as CITY), having its principal offices at 1700 Convention Center Drive, Miami Beach, Florida 33139, and STA Architectural Group, Inc., a Florida Corporation, having its offices at 3526 North Miami Avenue, Miami, Florida, 33127 (hereinafter referred to as CONSULTANT). RECITALS WHEREAS, pursuant to Request for Letters of Interest No. 133- 94/95, the Mayor and City Commission adopted Resolution No. 96 -22068 on July 17, 1996, approving and authorizing the Mayor and City Clerk to execute a Professional Services Agreement with STA Architectural Group, Inc. (CONSULTANT) for the Renovation and Expansion of Fire Station:No. 2, and a Master Plan for the site at 451 Dade Boulevard (PROJECT); and WHEREAS, the Agreement provided for the detailed planning, design, bidding and construction administration services for the Fire Station No. 2 Project; and WHEREAS, an Agreement for planning services was executed for a. not -to- exceed amount of $78,,000; and WHEREAS, on June 28, 2000, the Mayor and City Commission adopted Resolution No. 2000- 23975, approving Amendment No. 1 to the Agreement, for schematic design, design development, construction documents, permitting & bidding; and construction administration services for the rehabilitation of the historic structure and the new construction of a dormitory and apparatus structure improvements within the PROJECT, for a not -to- exceed amount of $318,020; and WHEREAS, on October 17, 2001, the Mayor and City Commission adopted Resolution No. 2001- 24624, approving Amendment No. 2 to the Agreement for the design of an Emergency Operations Center, a site drainage system, and 'a dedicated driveway serving the Public Works Yard, for a not -to- exceed amount of $117,000; and WHEREAS, on December 10, 2003, the Mayor and City Commission adopted Resolution No. 2003- 25439, approving Amendment No. 3 to the Agreement for construction administration services for the PROJECT, for a not -to- exceed amount of $.192,000; and WHEREAS, on March 15, 2007, Amendment No. 4 to the Agreement was executed approving additional construction administration services for the PROJECT, fora not -to- exceed amount of $24,500; and i WHEREAS, on October 27, 2007, Amendment No. 5 to the Agreement was executed approving additional construction administration services for the PROJECT, to be rendered on a monthly basis, for a not -to- exceed amount of $24,500; and WHEREAS, on June 20,"2008, Amendment No 6 to the Agreement was executed approving additional construction administration services for the PROJECT, to be rendered on aponthly basis, for a not -to- exceed amount of $24,447; and WHEREAS, on July 10, 2008, Amendment No. 7 to the Agreement was executed approving additional design and construction administration services for the PROJECT, to be rendered on a monthly basis, for a not -to- exceed amount of $40,000; and WHEREAS, the first phase of the Fire Station No. 2.Project, the construction of Building B and its Emergency Operations Center, is 'substantially complete, and the Fire Department moved into the building and put it into service; and WHEREAS, Building A has now been more thoroughly inspected and several additional items have been identified that require modifications to the construction documents; and WHEREAS, the hose tower was also, evaluated and, despite recent repairs, structural deficiencies were found; and WHEREAS,' as a result, the hose tower, work*to which had not been a part of the original scope of work,. must now be included; and WHEREAS, on December 9, 2009, Amendment No. 8 to the Agreement was negotiated by staff, for a fee of $183,000, for an in- depth preconstruction review, Historic Preservation Board presentation, re- drawing and development of construction documents (per current codes), and bid and construction administration services for the rehabilitation of the historic building, hose tower, and new addition two =story connectors; and WHEREAS, on November, 12, 2010, Amendment No. 9 to the Agreement was executed approving the additional programming, planning, concept design, meetings and presentations for a two -.story Auxiliary Training Structure to be added along the rear side of the PROJECT structure, for a not -to- exceed amount of $11,480; and WHEREAS, on March 25, 2011, Amendment No. 10 to the Agreement -was executed approving additional services for the .special structural inspections of all the reinforcing steel, structural steel, wood truss framing, bracing, sheathing, exterior door and wood frame attachments for the construction of the PROJECT, to be performed by a structural engineering sub = consultant, as required by the City's Building Department, for a not -to- exceed amount of $10,000; and WHEREAS, on May 17,'2011, Amendment No. 11 to the Agreement .was executed approving additional services for the architectural and structural design services associated with the re- design of foundations for the two connector buildings due to unforeseen conditions during construction, for a not -to- exceed amount of $2,760; and WHEREAS, on December 8, 2011, Amendment No. 12 to the Agreement was executed approving additional services for rernediation special inspection services required for the structural engineer to oversee the structural spalling repairs of the building, for a not -to- exceed amount of $16,600; and WHEREAS, the following Amendment No. 13 to the Agreement approves additional services for program revisions requested by the Fire Department and extended construction administration services, for a not -to- exceed amount of $20,747.36. NOW, THEREFORE, the .parties hereto, and in consideration of the mutual promises, covenants, agreements, terms, and conditions herein contained, and other good and valuable consideration, the respect and adequacy are hereby acknowledged, do agree as follows: 1. ABOVE, RECITALS The above recitals are true and correct and are incorporated as a part of this Amendment No. 13: 2. MODIFICATIONS The Agreement is amended to include "Schedule A -13 ", which is attached and incorporated. herein. 3. OTHER PROVISIONS. All other provisions of the Agreement, as amended, are unchanged. 4. RATIFICATION. The CITY and CONSULTANT ratify the terms of the Agreement, as amended by this Amendment No. 13. IN WITNESS WHEREOF, the parties hereto have caused this Amendment No. 13 to be executed in their names by their duly authorized officials as of the date first set forth above. ATTEST: CITY OF MIAMI BEACH By City Clerk, Interim City Manager, Rafael Granado Kathy G. Brooks ATTEST: CONSULTANT: STA ARCHITECTURAL GROUP, INC. By TITLE: TITLE: Print Name Print Name APPROVED AS TO FORM & LANGUAGE & FOR rCUTION y orney e F; \CAPI \$all\Employee Files \JANETTE \Fire Station No. 2\ Contract \STA\Amendment #13\2012- 1 -27 2 -STA . mend'ment # d SCHEDULE A -13 1. SCOPE OF WORK AND SERVICES REQUIRED .Exhibit "A" of the Agreement, entitled "Scope of Services ", is amended as follows and attached as Schedule A -13: Fire Department Requested Program Changes: This Amendment consists of additional services to revise the construction document set of plans to accommodate a reconfiguration of the architectural layout impacted by the City Manager's approval to maintain Fire Prevention at it's current location, as requested by the Fire Department. Revisions to the plans generally entail the relocation of the employee lounge, relocation of the division chief's office, reconfiguration of the second floor main building bathroom/ janitor's closet, and the deletion of work stations in the first floor main building. Relocation of the employee lounge will impact changes to the mechanical, electrical, and plumbing plans as well. This scope of work include the necessary architectural, mechanical, electrical, and plumbing services required to address these revisions and any associated coordination with the City. Scope of work not -to- exceed fee includes reimbursable expenses. Extended Construction Administration Services: This Amendment consists of additional services for the Consultant to provide extended construction administration services from Januarythru February 2012. These additional services are necessary for the Consultant to address the ongoing construction issues' of the project including, but not limited to: coordination with the City and Contractor; conducting site visits, as necessary, to inspect and document the progress of construction; attend meetings with the City and Contractor to resolve ongoing concerns; addressing Contractor Requests for Information (RFI); review and approval of change orders and Contractor payment applications; etc. 2. TIME OF COMPLETION Services. authorized by this Amendment shall be completed by February 29, 2012. 3. PAYMENT AND COMPENSATION The scope of services described in this Amendment No. 13 shall be performed for a not -to- exceed amount of $20,747.36. Invoicing shall be as referenced in the original agreement. Compensation: Original Agreement $78,000.00 Amendment No. 1 $318,020.00 Amendment No. 2 $117,000.00 Amendment No. 3 $192,000.00 Amendment No. 4 $24,500.00 Amendment No. 5 $24,500.00 Amendment No. 6 $24,446.70 Amendment No. 7 $40,000.00 Amendment No. 8 $183,000.00 Amendment No. 9 $11,480.00 Amendment No. 10 $10,000.00 Amendment No. 11 $2,760.00 Amendment No. 12 $16,600.00 Amendment No. 13 $20,747.36 Total Revised Agreement $1,063,054.06 EXHIBIT B -1 Title: Amendment - Extended Construction Administration ADDITIONAL WORK AUTHORIZATION Date: June 24, 2011 Fire Station No. 2 - Miami Beach No, AWA 9607.012 Scope of Services Projected Fee months rate fee �a °+t'3'f; ;;;�`� r � +p �F�*m {sc�-- s-y .7^�: '��caT� � ^r*�iFr" r-� -*,� at,••, sY - :..at�'a,s..^S.uvw' c 'S t 's�,.f Architectural - Exten ed Construction Administration Sery es - JanuarY /March 2012 Extended coordination / site visits with Contractor + City for the final inspections and documentation for Certificate of Occupanc Estimated at three -(3) additional months based on 25 days alreadyapproved..35 days pe din2 approval, and 30 projected additional days Note: Rate is based on current monthly billing amount.for CA Services in Amendment #8 .3 $6,863.68 $20;591.04- #� Total M $20,5940 -- '7i� '`ei'w7s�+x'°` sa -' f� s &E � 3,' $"+;c."✓ f tt€sbitlFVf Reimbursabie Expense Estimate Pdntina /copyingtTransmihinglDelivering Plans, Sketches, RFIs, Applications for Payment, Change Orders, Shop Drawings & Materials Submitting, and other project- related reproductions; Messenger Services, Parking & Mileage, Consultant Reimbursable Expenses, etc. Estimated @ $200.00 per month -} A $200.00 - $60"o , F .a �r Notes: 1. No work shall begin customer authorization " Total Amount, Authorization I Approval Date STA Architectural Group EXHIBIT B -2 Title: Amendment - Program Revisions per attached plan diagrams ADDITIONAL WORK AUTHORIZATION Date: ,tune 30, 201.1 Fire Station No, 2 - Miami Beach No. AWA 9607.014 Scope of Services Proiected Fee hours rate fee =archilecturaf m.., >• Iyi + 1 personnel to,discuss program changes. Prepare alternate reconfiguration substituting prevention with other.fire dept administration,uses. coordinate with fire dept, cip, consulting engineers, and contractor. Prepare construction document revisions for permit admendment submission. Principal 4 $ 150 $ 600 Project Manager 18 $ 120 $ 2,160 Technical Staff 12 $ 75 $ 900 Total Hours , 34 $ 3,660 * r ! �' a� a }mac � 12" '�rtBa i ��f�? r ev ,. i� r '' xa" ���wr. -r ` 'vu ��.reu..s�"�s. zz�`:�`''h�TM -:�� ;rasccxttm'. co Provide mechanical, electrical and plumbing services in accordance to fire department mQuesled programatinc revisions. Principal 6 $ 150 $ 900 Project Manager 8 $ 120 $ 960 Technical Staff 8 $ 75 $ 600 Total Hours 22 $ 2,460 structural scope - '.,R � struct anticibated, i -e. none included Principal 0 $ 150 $ Project. Manager 0 $ 120 $ Technical Staff 0 $ 75 $ _ Total Hours 0 $ - .� � cs.a M R WM3iX,.aY'Bw�. r usable expense estimate $ 500 °� .t�.. tir� .a.X1A15 ..3 _Yt. �- .''kg.:C.SCry =1iv� "C...K -. YFz 't ;` .��a .r =Y2 M1at Notes: 1. No work shall begin without customer authorization Total Amounts 56 $6,620 �.. fir v mw Authorization 1 Approval Date STA Architectural Group