Amendment No. 2 with Atkins North America, Inc. Cell- X76 29
AMENDMENT NO. 2
TO THE PROFESSIONAL SERVICES AGREEMENT
BETWEEN
THE CITY OF MIAMI BEACH, FLORIDA
AND
ATKINS NORTH AMERICA, INC.,
DATED MAY 9, 2011
FOR ADDITIONAL BIDDING AND AWARD SERVICES REQUIRED UNDER A
CONSTRUCTION MANAGEMENT AT RISK METHOD OF PROCUREMENT IN THE NOT-TO-
EXCEED AMOUNT OF $11,974
This Amendment to the Agreement made and entered this 1 st day of July, 2012, by and between
the City of Miami Beach, a Municipal Corporation existing under the laws of the State of Florida
(hereinafter referred to as CITY), having its principal offices at 1700 Convention Center'Drive,Miami
Beach, Florida 33139, and Atkins North America, Inc., a Florida Corporation having its principal
office at 4030 West Boy Scout Boulevard, Suite 700,Tampa, Florida, 33607(hereinafter referred to
as CONSULTANT).
RECITALS
WHEREAS,pursuant to Request for Qualifications(RFQ)No. 04-10/11,the Mayor and City
Commission adopted Resolution No.2011-27628 on April 13, 2011, approving and authorizing the
Mayor and City Clerk to execute a Professional Services Agreement with Atkins North America, Inc.,
(CONSULTANT) for Professional Services for the South Pointe Pier Project(PROJECT); and
WHEREAS, the Agreement provides for the design, bid, award and construction
administration services for the South Pointe Pier Project in the not-to-exceed amount of$369,000;
and
WHEREAS,on February 2012,Amendment No. 1 to the Agreement was executed approving
additional services required pursuant to the USACOE permit RAI process related to a new coral
recipient site in Government Cut, in the not-to-exceed amount of$12,950; and
WHEREAS,this Amendment No.2 to the Agreement shall be executed in the not-to-exceed
amount of$11,974 is to provide additional bidding and award services required under a Construction
Management at Risk method of procurement.
NOW, THEREFORE, the parties hereto, and in consideration of the mutual promises,
covenants, agreements; terms, and conditions herein contained, and other good and valuable
consideration, the respect and adequacy are hereby acknowledged, do agree as follows:
1. ABOVE RECITALS
The above recitals are true and correct and are incorporated as part of this Amendment No.
2
2. MODIFICATIONS
The Agreement is amended to include"Schedule A-2", which is attached and incorporated
herein.
3. OTHER PROVISIONS.
All other provisions of the Agreement, as amended, are unchanged.
4. RATIFICATION.
The CITY and CONSULTANT ratify the terms of the Agreement, as amended by this
Amendment No. 2.
IN WITNESS WHEREOF, the parties hereto have caused this Amendment No. 2 to be
executed in their names by their duly authorized officials as of the date first set forth above.
ATTEST: CITY OF MIAMI BEACH
I'�/ Z By
City Cie r Interim City Manager,
Rafael a� Kathie G. Brooks
� INCO RP ORATED �
:
ATTES CONSULTANT:
�.�•• AT INS NORTH AMERICA, INC.,
B
TITLE: LE:
Print Name Print Name
APPROVED AS TO
FORM &LANGUAGE
&FOR EXECUTION
R
ity Attorn ,, ate
F:\CAPIt5a11\Project FileslSouth Pointe Park Pier\0.0 Conti-acts,RFP's,RLI's,RFQ'st0.2 Contract\P:TKINS\Amendments\AnleridrTleni 2 A-';KINS-
South Pointe Pier.doc
SCHEDULE A-2
1. ADDITIONAL SCOPE OF SERVICES
As per our Professional Services Agreement (PSA), the following post- design services are
already defined under Task 3 -Bidding and Award Services and the associated fees have been
established in the lump sum amount of$ 5,000.00
Task 3-BIDDING AND AWARD SERVICES
• Task 3.1 Construction Contract Document Review:
• Task 3.2 Bid Document Delivery
• Task 3.3 Pre-Bid Conference
• Task 3.4 Addenda Issuance
• Task 3.5 Bid Evaluation and Bid Opening
• Task 3.6 As Bid Contract Documents
Atkins was authorized to commence with the Task 3 services in December 2011 when the City
Commission determined it was in the City's best interest to seek a Construction Manager at Risk
(CM) and Atkins was authorized to assist the CIP office in that regard. For example, on
December 31, 2012 the Atkins project management team met with the City to review the CM
qualification packages.
Since December 2011, the CM procurement process has progressed and Atkins performed the
following services as defined under Task 3 -BIDDING AND AWARD SERVICES:
• Task 3.1 Construction Contract Document Review:
This task has been completed. Atkins has provided the City with electronic copy of
all project deliverables and has participated in construction contract meetings with
the City and has responded to City agency comments. No further services are
anticipated under this task.
• Task 3.2 Bid Document Delivery:
This task has been completed. Atkins has provided the City with the necessary sets
of contract documents as requested. No further services are anticipated under this
task.
• Task 3.3 Pre-Bid Conference(s):
This task has been completed. The Atkins project management team participated in
the review of CM proposals and participated in a full day CM interview process in
which Atkins provided technical information to the CM Selection Committee. No
further services are anticipated under this task.
• Task 3.4 Addenda Issuance:
This task has been completed. Most recently Atkins at the direction of the City met
with the selected CM and his designated marine contractor to discuss technical
merits of potential design modifications under consideration by the CM.
Additionally, Atkins participated in two (2) teleconferences with the CM to further
discuss and review potential design modifications. While no formal "addenda"were
issued, the services performed by Atkins constitute a response to numerous
inquiries received from the CM. In this case, the CM and his designated marine
contractor have inquired about possible design modifications. Atkins has reviewed
these inquiries and has provided the City and CM with opinions and technical
responses. No further services are anticipated under this task.
• Task 3.5 Bid Evaluation and Bid Opening:
This task is about to commence and Atkins will be providing the following services under
this task as related to the IGMP and GMP process:
o Attend the IGMP presentation ( held on 04.23.12)
o Evaluate the IGMP submittal and provide written comments
o Evaluate the GMP and provide written comments
o Provide formal GMP award recommendation to the City
Additional Services: Based on our meetings to date with the City and CM, Atkins
understands that the CM will present a number of Value Engineering (VE) design
modifications and/or VE related material substitutions for consideration,as potential project
cost savings and these will likely include:
o Design Modification - Concrete Pile Lengths
o Design Modification - Concrete Pile Sizes
o Design Modification - Precast Concrete Pile Caps
o Design Modification- Post Tensioned Concrete Beams
o Design Modification - Deck Grating - Material Change
o Design Modification - Hand Railing and Guard Railing - Material Change
o Design Modification - Entrance Gate - Material Change
o Design Modification - Directional Bore for Underground Utilities
o Design Modification — Concrete Mix Design — Admixture Changes
It is our understanding that as the A/E of Record, Atkins would be expected to perform a
review of the CM's proposed design modifications and/or material substitutions and offer a
qualified opinion as to their adaptability, quality, aesthetics, contract amount change, life
cycle functions and other considerations deemed in the best interest of the City.This effort
would likely require a review of the structural design computations, plans and technical
specifications including the research of the various products and materials proposed for
modification. A review of"samples" of the proposed materials (ie: aluminum v. stainless
steel)would also be required of Atkins.Ultimately,the City would rely on Atkins for any and
all technical reviews and material acceptance recommendations.
Additional Services: While services related to "alternative prices and unit prices" is
included in Task 3.5 design modification reviews of the type noted above were not
contemplated.These services would be considered Additional Services as defined by Article
5 of the Professional Services Agreement.
Task 3.6 As-Bid Contract Documents:
This task will be completed once the GMP has been accepted. This task as defined in the
PSA would include the incorporation of all changes to the contract made via contract
addenda. In this case, these changes would be made as a result of the IGMP and GMP
process.
Additional Services: Based on our understanding of this requirement, Atkins would be
expected to formally incorporate any and all approved design modifications and approved
material substitutions into the conformed Contract Documents (plans and specifications).
Additionally,most if not all of the approved design modifications would require approval by
the City of Miami Beach Building Department, other Departments and the DRB, as they
would constitute a material change to the approved plans. Atkins would be required to
resubmit plans and calculations for BD review as well as, other City Departments and
possibly DRB.
These services would be considered Additional Services as defined by Article 5 of the PSA.
to the extent that incorporation of multiple design modifications into the Contract Documents
and resubmitted to the BD is beyond the current scope. Based on recent proposals offered by
the CM,the following design modifications may have to be incorporated into the confirmed
Contract Documents.
o Design Modification - Concrete Pile Lengths
o Design Modification -Concrete Pile Sizes
o Design Modification - Precast Concrete Pile Caps
o Design Modification - Post Tensioned Concrete Beams
o Design Modification -Deck Grating -Material Change
o Design Modification - Wood Decking- Material Change
o Design Modification - Hand Railing and Guard Railing- Material Change
o Design Modification - Entrance Gate - Material Change
o Design Modification - Directional Bore for Underground Utilities
o Design Modification—Concrete Mix Design—Admix Changes
o Design Modification—Alternative to Concrete Penetrate Sealers
o City of Miami Beach Departments/DRB—Plans Resubmittal
Summary: As outlined above, in conformance with Article 5 - Additional Services of the
Professional Services Agreement,Atkins herein requests the City's approval and authorization to
perform Additional Services under Task 3 - Bidding and Award Services.
Not- to-Exceed Fee
Based on the anticipated number of design modifications and material substitutions currently
proposed by the CM, we estimate a level of effort not to exceed 80.0 manhours may be
required to: l.) evaluate the technical issues associated with each.proposal, 2.) render written
comments and recommendations to the City, 3.) incorporate the approved design modifications
into the conformed Contract Documents and 4.) submit any design changes to the City
Departments/DRB for review.
This estimated level of effort would translate to additional fees not to exceed $11,974.00
which Atkins would perform on a certified time and material basis per the provisions of
Article 5 of the PSA. A manhour breakdown and fee analysis has been prepared in conformance
with the Hourly Billing Rates as stipulated in Schedule C of the PSA and is attached hereto as
Exhibit 1.
Closing
Thank you for the opportunity to be of service to the City of Miami Beach. We trust the City will
recognize that additional effort is required to review and address the numerous CM proposals
and that this effort is beyond the scope of services as defined in the PSA and as contemplated by
parties at the time of execution of the PSA.
We also trust that the City will find the proposed manhours and not to exceed fee limitation to
be fair and reasonable and can issue an Amendment (No. 2) to the PSA for the additional
services described herein. Please do not hesitate to contact the undersigned with any questions or
concerns. Your prompt reply will be appreciated.
2. PAYMENT AND COMPENSATION
The scope of services described in this amendment shall be performed for a not-to-exceed
amount of$11,974. Invoicing shall be as referenced in the original agreement.
Consultant's request for additional services is attached for reference purposes.
Compensation
Original Agreement $369,000
Amendment No. 1 $ 12,950
Amendment No. 2 11,974
Total Revised Agreement $393,924
j
N
01 to �
-� � nCCCCC7CCCCCC y � CCCCCCCCCCC
a� a CD CD CD CD CD (D CD CD CD n CD a s CD n a a d d a 0 d a a
p N O
CD .+ .: p p p .•r p p p p p w OQ
0 0 0 0 0 0 0 0 0 0 0 c o 0 0 0 0 0 0 0 0 0 a�
`�i '� i y "i E "t'i ^h ""i Ci l ?� `i '� C
� r+ A7 w W w w Z)A7 A� C1 Sy w A7 C .+ t� f.1 n7 r.7 A7 fy W fy Al G Al y y
AT
►- IrD
ro
x B CD A
0 0 °_ ° o °_ ft
0 fo
CD
CD
CO 5' �c0' o 0 b 0 �, �' pr c' o 0 _v
x °
CD CD x -s CD
5 ry CD 0. ' CD N CD G ' 0. CD N N
O n ►0 CD =
CD CD C , , f1 p N Er CD .+ n '. n C4 N S
'z W CD CD
n N a =
Q- .+ A7 .» ^ a- .+ w ...
'C'' n ° N v CD n X
• :r w 00 aq o 00
CND p
C = CD D
:» = ': ,� a
CD n
as a0o c
M* p•
O O O O O O O O O O O O
d
� � n
fD (D S
� � to — ►- J N N — � N N � '�'' � O
O 0 0 O O O O O O O O O C O O O O O O O o� N
�3
tJQ
O O O 0 0 0 0 O O O O O O o
� Q
o ,
t-4 --• w w — — — N LA w w
O O D O C O O O O C C O 0 0
69-
"" b09 bA b9 4Ep9 b9 b9 b9 b9 iA b9 b5 b-9 b4 b'3 b9 b9 b9 be b5
j to O� W V' C (--, w w VA \J .o ( ut c Vr V' J Q) lh
\i 00 00 00 00 O 00 00 00 00 00 � 00 00 00 00 00 00 00 00 00 00
O O O O O C O O 0 C) 0 0 0 0 0 0 0 0 0 0 0
DC O O O O O O O O O 0 0 0 0 0 0 0 0 0 0 0
d
LA -G
S X
m V =
N p7
O
MIAMI BEACH
CAPITAL IMPROVEMENT PROJECTS OFFICE MEMORANDUM
TO: Kathie G. Brooks, Interim City Manager
FROM: Fernando Vazquez, CIP Director
VIA: Jorge Gomez, Assistant City Manager
DATE: September 12, 2012
SUBJECT: Amendment No. 2 to the Professional Services Agreement for the South Pointe Pier
Project
Pursuant to RFQ No. 04-10/11,the Mayor and City Commission authorized the execution of the
Professional Services Agreement with Atkins North America, Inc. (Atkins)on April 2011. Since
April 2011,Atkins has provided services in accordance with their Agreement with the City,which
included services for design, permitting, bidding and construction administration for the South
Pointe Park Pier.
Subsequent to the execution of the agreement with Atkins, on February 8, 2012, the City
awarded the Pre-construction Service agreement to the Construction Management at Risk(CM)
firm, the Weitz Company for the provision of pre-construction services during the design and
permitting phase of the project. The City anticipated a conventional bid process but elected to
proceed with a CM bid process thus impacting Atkins' bid phase services. The selection of a
CM was initiated to procure a firm that could assist in constructability and value engineering
reviews during the design phase with a resultant Guaranteed Maximum Price(GMP)that would
offset any future change orders.
Atkins is expected to perform a review of the CM's value engineering (VE)and constructability
review recommendations. Theywill provide VE design modifications(including Structural design
and calculations) and the implementation of material substitutions to address the selected
alternates during the negotiation of the GMP.They will also provide their qualified opinion as to
the adaptability, quality, aesthetics, contract price changes and life cycle impacts to determine
the best value for the City. The additional services includes several meetings to define the final
design modifications, open the sub-contract bids and negotiate the final GMP.
If you require er larification, please do not hesitate to call me.
Sin ely,
Fer ndo Vazquez, PE, CIP Director
C pital Improvements Office
FV/mer