2013-28119 Resolution RESOLUTION NO. 2013-28119
A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF MIAMI
BEACH, FLORIDA, ACCEPTING THE RECOMMENDATION OF THE HISTORIC
PRESERVATION BOARD (HPB) AND GRANTING A CERTIFICATE OF
APPROPRIATENESS FOR THE TOTAL DEMOLITION OF AN EXISTING SINGLE
STORY BUILDING AND THE CONSTRUCTION OF A NEW 5-STORY PARKING
GARAGE WITH ACCESSORY GROUND LEVEL COMMERCIAL SPACE AT 340 23RD
STREET(COLLINS PARK GARAGE).
WHEREAS, on May 11, 2011, the Mayor and City Commission approved the issuance of
Request for Qualifications No. 31-10/11 (the RFQ) for the Architectural, Engineering, Design, Bid and
Award, and Construction Administration Services for the Collins Park Garage Project(the Project); and
WHEREAS, the RFQ was issued on June 17, 2011, and on September 14, 2011, the City
Commission approved Resolution No. 2011-27735 authorizing the City Manager to negotiate with the top
ranked firm of Zaha Hadid Limited t/a Zaha Hadid Architects; and
WHEREAS, on March 21, 2012, the City Commission adopted Resolution No. 2012-27869,
approving a Professional Services Agreement between the City and a joint venture of Zaha Hadid Limited
t/a Zaha Hadid Architects and Berenblum Busch Architecture, Inc. (the Consultant) for the Planning,
Architectural, Engineering, Design, Bid And Award, And Construction Administration Services; and
WHEREAS, the Agreement was executed on May 3rd, 2012, and on May 24, 2012, the Notice to
Proceed for the Planning Phase was issued; and
WHEREAS, the proposed parking garage will be constructed on the two properties currently
occupied by surface parking lots located on 23rd Street, behind the Miami Beach Regional Library and
the Miami City Ballet building, bridging over Liberty Avenue; and
WHEREAS, the ground level of the proposed structure, between Park and Liberty Avenues, will
provide approximately 17,500 sq. ft. of retail space, while the upper five (5) levels of the parking garage
will accommodate approximately 470 parking spaces; and
WHEREAS, the Project also contemplates a large public plaza at the ground level, just east of
Liberty Avenue, which will merge into the Liberty Avenue right of way, between 22nd and 23rd streets,
encouraging the pedestrian connectivity between the garage, Collins Park, the Miami Beach Regional
Library and the Miami City Ballet; and
WHEREAS, there is currently a vacant, non-contributing, one-story building, located on the lot
behind Miami City Ballet, which must be demolished in order to accommodate the new structure.
WHEREAS, on November 21, 2012, the Historic Preservation Board (HPB) granted approval of
the Certificate of Appropriateness for the total demolition of the existing building, and construction of the
new five-story parking garage with accessory ground level commercial space; and
WHEREAS, pursuant to Miami Beach City Code Section 118-563(i), the actions of the HPB
regarding Certificates of Appropriateness for demolition of any building, structure, improvement, or
landscape feature located within a historic district and located on City-owned property, shall be advisory
with the right of approval or disapproval vested with the City Commission; and
WHEREAS, on December 12, 2012, the City Commission approved Resolution No. 2012-28076,
setting a Public Hearing to consider the issuance of a Certificate of Appropriateness for the total
demolition of an existing single story building and the construction of a new five-story parking garage with
accessory ground level commercial space at 340 23rd Street(Collins Park Garage).
NOW, THEREFORE, BE IT DULY RESOLVED BY THE MAYOR AND THE CITY COMMISSION
OF THE CITY OF MIAMI BEACH, FLORIDA that the Mayor and City Commission accept the
recommendations of the Historic Preservation Board and grant a Certificate of Appropriateness for total
demolition of an existing single story building and the construction of a new 5-story parking garage with
accessory ground level commercial space at 340 23rd Street(Collins Park Garage).
PASSED AND ADOPTED this 16th day of January, 2013.
ATTEST:
Bower, Mayor
Rafael ranad y�.Clerk 0 ��
TANFOR VED AS TO FORM, LANGUAGE ,,,-- •;
E T N
' torn ('� , Date
T:\AGENDA\2013\January 16\Collins Park Garage-Certificate of Appropriateness for Demolition\Collins Park Garage-Certificate
of Appropriateness for Demolition-Reso.doc
I
COMMISSION ITEM SUMMARY
Condensed Title:
A Resolution Of The Mayor And City Commission Of The City Of Miami Beach, Florida, Accepting the
Recommendations Of The Historic Preservation Board(HPB)And Granting A Certificate Of Appropriateness
For The Total Demolition Of An Existing Single Story Building And The Construction Of A New 5-Story Parking
Garage With Accessory Ground Level Commercial Space At 340 23rd Street Collins Park Garage).
Key Intended Outcome Supported:
Ensure value and timely delivery of quality capital projects; improve parking availability.
Supporting Data(Surveys, Environmental Scan, etc.):
The Cultural Campus is currently serviced by 55 parking spaces on two surface parking lots,these will be
replaced with a parking structure of over 400 parking spaces.
Item Summa /Recommendation:
On March 21, 2012, the City Commission adopted Resolution No. 2012-27869, approving a Professional
Services Agreement between the City and a joint venture of Zaha Hadid Limited t/a Zaha Hadid Architects and
Berenblum Busch Architecture, Inc.(the Consultant)for the Planning,Architectural, Engineering, Design, Bid
And Award, And Construction Administration Services for the Collins Park Garage Project(the Project).
The Agreement was executed on May 3rd,2012,and on May 24,2012,the Notice to Proceed for the Planning
Phase was issued.
The proposed parking garage will be constructed on the two properties currently occupied by surface parking
lots located on 23rd Street, behind the Miami Beach Regional Library and the Miami City Ballet building,
bridging over Liberty Avenue.The ground level of the proposed structure, between Park and Liberty Avenues,
will provide approximately 17,500 sq.ft.of retail space,while the upper five(5)levels of the parking garage will
accommodate approximately 470 parking spaces.
There is currently a vacant, non-contributing, one-story building, located on the lot behind Miami City Ballet,
which must be demolished in order to accommodate for the new structure.On November 21,2012,the Historic
Preservation Board(HPB)granted approval of the Certificate of Appropriateness for the total demolition of the
existing building,and construction of the new five-story parking garage with accessory ground level commercial
space.
Pursuant to Miami Beach City Code Section 118-563(i), the actions of the HPB regarding Certificates of
Appropriateness for demolition of any building, structure, improvement,or landscape feature located within a
historic district and located on City-owned property, shall be advisory with the right of approval or disapproval
vested with the City Commission.
On December 12,2012,the City Commission approved Resolution No.2012-28076,setting a Public Hearing to
consider the issuance of a Certificate of Appropriateness for the total demolition of an existing single story
building and the construction of a new five-story parking garage with accessory ground level commercial space
at 340 23rd Street(Collins Park Garage).
The Administration recommends approval of the Resolution.
Advisory Board Recommendation:
Historic Preservation Board
Financial Information:
Source of Amount Account
Funds: 1
2
OBPI Total
Financial Impact Summary:
City Clerk's Office Legislative Tracking:
Fernando Vazquez, ext. 6135
Sign-Offs:
Departme D' ector Assistant City Manager City Ma er
FV JGG KB
AAGENDA ITEM
MIMIBEACH DATE �
MIAMI BEACH
City of Miami Beath, 1700 Convention Center Drive,Miami Beach,Florida 33139,www.miamibeachfl.gov
COMMISSION MEMORANDUM
TO: Mayor Matti Herrera Bower and Members of the City ommission
FROM: Kathie G. Brooks, Interim City Manager
DATE: January 16, 2013
SUBJECT: A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF MIAMI
BEACH, FLORIDA, ACCEPTING THE RECOMMENDATIONS OF THE HISTORIC
PRESERVATION BOARD,AND GRANTING A CERTIFICATE OF APPROPRIATENESS
FOR THE TOTAL DEMOLITION OF AN EXISTING SINGLE STORY BUILDING AND
THE CONSTRUCTION OF A NEW 5-STORY PARKING GARAGE WITH ACCESSORY
GROUND LEVEL COMMERCIAL SPACE AT 340 23RD STREET (COLLINS PARK
GARAGE).
ADMINISTRATION RECOMMENDATION
Adopt the Resolution.
KEY INTENDED OUTCOME
Ensure value and the timely delivery of a quality capital project.
Improve parking availability.
ADMINISTRATION RECOMMENDATION
Adopt the Resolution.
ANALYSIS
On May 11, 2011, the Mayor and City Commission approved the issuance of Request for
Qualifications No. 31-10/11 (the RFQ)for the Architectural, Engineering, Design, Bid and Award,
and Construction Administration Services for the Collins Park Garage Project(the Project).
The RFQ was issued on June 17, 2011, and on September 14, 2011, the City Commission
approved Resolution No. 2011-27735 authorizing the City Manager to negotiate with the top ranked
firm of Zaha Hadid Limited t/a Zaha Hadid Architects.
On March 21, 2012, the City Commission adopted Resolution No. 2012-27869, approving a
Professional Services Agreement between the City and a joint venture of Zaha Hadid Limited t/a
Zaha Hadid Architects and Berenblum Busch Architecture, Inc. (the Consultant)for the Planning,
Architectural, Engineering, Design, Bid And Award, And Construction Administration Services.
The Agreement was executed on May 3rd, 2012,and on May 24, 2012,the Notice to Proceed for the
Planning Phase was issued.
Commission Memorandum—Collins Park Garage—Setting Public Hearing for Certificate of Appropriateness
January 16,2013
Page 2 of 2
The proposed parking garage will be constructed on the two properties currently occupied by
surface parking lots located on 23rd Street, behind the Miami Beach Regional Library, and behind
the Miami City Ballet building, bridging over Liberty Avenue. The ground level of the proposed
structure, between Park and Liberty Avenues, will provide approximately 17,500 sq. ft. of retail
space, while the upper five (5) levels of the parking garage will accommodate approximately 470
parking spaces. The Project also contemplates a large public plaza at the ground level,just east of
Liberty Avenue, which will merge into the Liberty Avenue right of way, between 22nd and 23rd
streets, encouraging the pedestrian connectivity between the garage, Collins Park,the Miami Beach
Regional Library and the Miami City Ballet.
The design concept for the Project was presented to the Community on September 5, 2012. The
meeting was well attended and the Project was very well received.
There is currently a vacant, non-contributing,one-story building, located on the lot behind Miami City
Ballet, which must be demolished in order to accommodate the new structure. On November 21,
2012,the Historic Preservation Board(HPB)granted approval of the Certificate of Appropriateness
for the total demolition of the existing building,and construction of the new five-story parking garage
with accessory ground level commercial space.
Pursuant to Miami Beach City Code Section 118-563(i), the actions of the HPB regarding
Certificates of Appropriateness for demolition of any building,structure, improvement,or landscape
feature located within a historic district and located on City-owned property, shall be advisory with
the right of approval or disapproval vested with the City Commission.
On December 12, 2012,the City Commission approved Resolution No.2012-28076,setting a Public
Hearing to consider the issuance of a Certificate of Appropriateness for the total demolition of an
existing single story building and the construction of a new five-story parking garage with accessory
ground level commercial space at 340 23rd Street(Collins Park Garage).
CONCLUSION
The Administration recommends that the City Commission accept the recommendations of the
Historic Preservation Board, and grant a Certificate of Appropriateness for the total demolition of an
existing single story building and the construction of a new five-story parking garage with accessory
ground level commercial space at 340 23rd Street(Collins Park Garage).
KB/JGG /DM
T:IAGENDA120131January 161Collins Park Garage-Certificate of Appropriateness for Demolition\Collins Park Garage-Certificate of
Appropriateness for Demolition-Memo.doc
2NE►THURSDAY,DECEMBER 13,2012 NE MiamiHeraldmm I THE MIAMI HERALD
MIAMI BEACH
CITY OF MIAMI BEACH
NOTICE OF PUBLIC HEARINGS
NOTICE IS HEREBY given that a public hearing will be held by the Mayor and City Commission of the City of Miami Beach,Florida,in the
Commission Chambers,3rd Floor,City Hall,1700 Convention Center Drive,Miami Beach,Florida,on Wednesday,January 16,2013,to
consider the following:
10:50.a.m.
A Resolution Pursuant To Miami Beach City Code Section 118.563,To Consider Granting A Certificate Of Appropriateness For The Total
Demolition Of An Existing Single Story Building And The Construction Of A New 5-Story Parking Garage With Accessory Ground Level
Commercial Space At 340 23rd Street(Collins Park Garage).
Inquiries may be directed to the'Capital Improvements Office(305)673-7071.
INTERESTED PARTIES are invited to appear at this meeting,or be represented by an agent,or to express their views in writing addressed to
the City Commission,c/o the City Clerk,1700 Convention Center Drive 1 st Floor,City Hall,Miami Beach,Florida 33139.Copies of these items
are`available for public inspection during normal business hours in the City Clerk's Office,1700 Convention Center Drive,1st Floor,City Hall,
Miami Beach,Florida 33139.This meeting may be continued,and under such circumstances additional legal notice will not be provided.
(Due to The Miami Herald's deadline,ordinances and/or resolutions that are tabled,denies or withdrawn will appear in this advertisement).
Rafael E.Granado,City Clerk
City of Miami Beach
Pursuant to Section 286.0105,Fla.Stat.,the City hereby advises the public that:if a person decides to appeal any decision made by the
City Commission with respect to any matter considered at its meeting or its hearing,such person must ensure that a verbatim record of
the proceedings is made,which record includes the testimony and evidence upon which the appeal is to be based.This notice does not
constitute consent by the City for the introduction or admission of otherwise inadmissible or irrelevant evidence,nor does it authorize
challenges or appeals not otherwise allowed by law.
To request this material in accessible format,sign language interpreters,information on access for persons with disabilities,and/or any
accommodation to review any document or participate in any City-sponsored proceeding,please contact us five days in advance at
(305)673-7411(voice)or TTY users may also call the Florida Relay Service at 711.