2014-28590 Reso RESOLUTION NO. 2014-28590
A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF
MIAMI BEACH, FLORIDA, APPROVING AND AUTHORIZING THE MAYOR
AND CITY CLERK TO EXECUTE CHANGE ORDER NO. 1 TO THE
AGREEMENT BETWEEN THE CITY AND LANZO CONSTRUCTION CO.,
DATED JUNE 19, 2013 (THE AGREEMENT), FOR ADDITIONAL
ENGINEERING SERVICES, DRAINAGE STRUCTURE MODIFICATION,
DRAINAGE PIPE, FENCING AROUND PUMP STATIONS, ELECTRICAL
COMPONENTS, AND PREPARATION OF SITE FOR STOCKPILING OF
MATERIALS FOR THE SUNSET HARBOUR PUMP STATIONS RETROFIT
AND DRAINAGE IMPROVEMENTS PROJECT; SAID CHANGE ORDER, IN
THE AMOUNT OF $315,123, PLUS A PROJECT CONTINGENCY IN THE
AMOUNT OF $231,358, FOR A TOTAL COST OF $546,481.
WHEREAS, Pursuant to Invitation to Bid No. 060-2013TC, and as approved at the May
8, 2013 City Commission meeting, the City entered into an agreement with Lanzo Construction
Co., dated as of June 19, 2013 (Agreement), in connection with the Sunset Harbour Pump
Stations Retrofit and Drainage Improvements Project, in the amount of $1,854,963.40, plus a
10% project contingency, for the total cost of$2,040,459.74; and
WHEREAS, as an initiative to continue infrastructure improvements throughout Sunset
Harbour, the Public Works Department requested an additional scope of work to the existing
Agreement (Change Order No. 1), consisting of the installation of additional drainage pipes for
direct storm water discharge to Biscayne Bay; existing drainage structure modifications; fencing
around Pump Stations No. 1 and No. 2; additional electrical components to raise control panels
to 2-feet above flood elevation at Pump Stations No. 1 and No. 2; preparation of site for
stockpiling of materials at Green Waste Facility; and additional engineering services; and
WHEREAS, the amount requested for Change Order No. 1 is $315,123, plus a total
project contingency in the amount of$231,358; for a total construction cost of$546,481.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND CITY COMMISSION
OF THE CITY OF MIAMI BEACH, FLORIDA, hereby approve and authorize the Mayor and City
Clerk to execute Change Order No. 1 to the Agreement between the City and Lanzo
Construction Co., dated June 19, 2013, for additional engineering services, drainage structure
modification, drainage pipe, fencing around pump stations, electrical components, and
preparation of site for stockpiling of materials for the Sunset Harbour Pump Stations Retrofit and
Drainage Improvements Project,-in the amount of $315,123 plus a total project contingency in
the amount of$231,358; for a total cost of$546,481.
PASSED and ADOPTED this day of Q , 2014.
ATTEST:
PHILIP E AYOR
RALPH GR ADO, CITY LEON l
IN„ORF ORATED: APPROVED AS TO
T:\AGENDA\2014\May\Sunset Harbour Pu Motions 0 AVemenW�-�ange Order No 1 RESO.doc FORM&LANGUAGE
&FOR EXECUTION
5 r k4-
City Attomey Date
COMMISSION ITEM SUMMARY
Condensed Title:
A Resolution Of The Mayor And City Commission Of The City Of Miami Beach, Florida, Approving And
Authorizing The Mayor And City Clerk To Execute Change Order No. 1 To Lanzo Construction Co., For
Additional Engineering Services, Drainage Structure Modification, Drainage Pipe, Fencing Around Pump
Stations, Electrical Components, And Preparation Of Site For Stockpiling Of Material For The Sunset
Harbour Pump Stations Retrofit And Drainage Improvements Project, In The Amount Of$315,123 Plus
A Total Project Contingency In The Amount Of$231,358; For A Total Construction Cost Of$546,481.
Key Intended Outcome Supported:
Ensure value and timely delivery of quality Capital Projects.
Supporting Data (Surveys, Environmental Scan, etc.): N/A
Item Summa /Recommendation:
Pursuant to Invitation to Bid (ITB) 060-2013TC for the Sunset Harbour Pump Station Retrofit and
Drainage Improvements Project, on May 8th, 2013, the City Commission authorized an award for
construction contract with Lanzo Construction Co. in the amount of $1,854,963.40. In addition, a base
project contingency in the amount of $185,496.34 totaling a construction cost of $2,040,459.74. The
project's scope of work includes drainage improvements within the Sunset Harbour Neighborhood,
consisting of new retrofit pumps, connections for direct discharge to Biscayne Bay, control panel
modifications at Pump Stations No. 1 and No. 2; and complete reconstruction of Pump Station No. 3,
including associated drainage pipes.
As an initiative to continue the infrastructure improvements throughout Sunset Harbour, the Public
Works Department has requested that Lanzo Construction Co. provide all necessary labor and
equipment for the installation of additional drainage pipes for direct storm water discharge to Biscayne
Bay, existing drainage structure modifications, fencing around Pump Stations No. 1 and No. 2,
additional electrical components to raise control panels to 2-feet above flood elevation at Pump Stations
No. 1 and No. 2, preparation of site for stockpiling of material at Green Waste Facility, as well as
additional engineering services. In addition, an October 1St, 2014 deadline has been added to the
contract, in order to ensure the completion of all pump station-related work by this date, making Lanzo .
Construction Co. liable for damages in the amount of$2,800 per day for non compliance.
THE ADMINISTRATION RECOMMENDS ADOPTING THE RESOLUTION
Advisory Board Recommendation:
N/A
Financial Information:
Source of Amount Account
Funds: 1 $301 431-2730-069357
2 $363,615 429-2730-069357
3 $110,081 431-2738-069357
4 $72,484 435-2473-069357
5
OBPI Total $546,481
Financial Impact Summary:
City Clerk's Office Legislative Tracking:
Eric T. Carpenter,ext.6012
Sign-Offs:
De artme Director Assistan na er City er.
ETC I JL
T:\AGENDA\2014\May\Sunset Harbour Pump Stations Improvements Change Order No 1 SUMMARY.docx
AGENDA ITEM C.7 E
MIAMIBEACH S—oZ/-/
MIAMI BEACH
City of Miami Beath, 1700 Convention Center Drive,Miami Beach, Florida 33139,www.miamibeachfl.gov
COMMISSION MEMORANDUM
TO: Mayor Philip Levine and Members f the City C mmission
FROM: Jimmy L. Morales, City Manager
DATE: May 21, 2014
SUBJECT: A RESOLUTION OF THE MAYO AND CITY COMMISSION OF THE CITY OF
MIAMI BEACH, FLORIDA, APPROVING AND AUTHORIZING THE MAYOR AND
CITY CLERK TO EXECUTE CHANGE ORDER NO. 1 TO LANZO CONSTRUCTION
CO., FOR ADDITIONAL ENGINEERING SERVICES, DRAINAGE STRUCTURE
MODIFICATION, DRAINAGE PIPE, FENCING AROUND PUMP STATIONS,
ELECTRICAL COMPONENTS, AND PREPARATION OF SITE FOR STOCKPILING
OF MATERIAL FOR THE SUNSET HARBOUR PUMP STATIONS RETROFIT AND
DRAINAGE IMPROVEMENTS PROJECT, IN THE AMOUNT OF $315,123 PLUS A
TOTAL PROJECT CONTINGENCY IN THE AMOUNT OF $231,358; FOR A TOTAL
CONSTRUCTION COST OF $5465481.
ADMINISTRATION RECOMMENDATION
The Administration recommends adopting the Resolution
FUNDING
Amount Account Number
$ 301 431-2730-069357
$363,615 429-2730-069357
$110,081 431-2738-069357
72,484 435-2473-069357
$ 546,481 TOTAL
Commission Memorandum—Sunset Harbour Pump Stations Improvements- Change Order No. 1
Page 2 of 2
BACKGROUND
Pursuant to Invitation to Bid (ITB) 060-2013TC for the Sunset Harbour Pump Station Retrofit
and Drainage Improvements Project, on May 8th, 2013, the City Commission authorized an
award for construction contract with Lanzo Construction Co. in the amount of$1,854,963.40. In
addition, a base project contingency in the amount of$185,496.34 totaling a construction cost of
$2,040,459.74. The project's scope of work includes drainage improvements within the Sunset
Harbour Neighborhood, consisting of new retrofit pumps, connections for direct discharge to
Biscayne Bay, control panel modifications at Pump Stations No. 1 and No. 2; and complete
reconstruction of Pump Station No. 3, including associated drainage pipes.
As an initiative to continue the infrastructure improvements throughout Sunset Harbour, the
Public Works Department has requested that Lanzo Construction Co. provide all necessary
labor and equipment for the installation of additional drainage pipes for direct storm water
discharge to Biscayne Bay, existing drainage structure modifications, fencing around Pump
Stations No. 1 and No. 2, additional electrical components to raise control panels to 2-feet
above flood elevation at Pump Stations No. 1 and No. 2, preparation of site for stockpiling of
material at Green Waste Facility, as well as additional engineering services. In addition, an
October 1St, 2014 deadline has been added to the contract, in order to ensure the completion of
all pump station-related work by this date, making Lanzo Construction Co. liable for damages in
the amount of$2,800 per day for non compliance.
COST ANALYSIS
Lanzo Construction Co. has submitted a cost proposal in the amount of $315,123 (Attachment)
for additional drainage pipes for direct storm water discharge to Biscayne Bay, existing drainage
structure modifications, additional electrical components to raise control panels to 2-feet above
flood elevation at Pump Stations No. 1 and No. 2, preparation of site for stockpiling of material
at Green Waste Facility, as well as additional engineering services.
This cost proposal has been submitted to the City's Public Works Department for further review
and recommendation. City staff reviewed the proposal and found that the amount was fair and
reasonable.
CONCLUSION
The Administration recommends adopting the Resolution
Attachment— Lanzo Construction Co. Cost Proposal dated 5/6/2014
J LM/MT/ /BAM/EA
T:\AGENDA\2014\May\Sunset Harbour Pump Stations Improvements Change Order No 1 Memo.doc
ATTACHMENT A
LANZO
CONSTRUCTION COMPANY
Delivering sustainable infrastructure solutions
for tomormw's communities
May 6, 2014
City of Miami Beach,Florida
Public Works Department-Engineering Division
1700 Convention Center Drive
Miami Beach,FL 33139
Attention: Eric Arencibia,Civil Engineer I
Reference: Sunset Harbour Pump Station Retrofit—ITB No. 60-2013TC
Sunset Harbour Re-Design Proposal—Revised Outfalls and Scope Changes
Below is a summary of the work included in the attached Sunset Harbour Re-Design Proposal:
Additional Scope of Work:
1) S-16, S-17, S-18,Positive Buoyancy Compensation Redesign and Construction
2) Existing Valve Vault Modification
3) Design Changes for 20"existing water main
4) Soil Boring
5) Fencing Pump Stations 1 and 2
6) Video existing PS 2 outfall
7) Not Used
8) Electrical Components for Raising Control Panels
9) Additional Structures Positive Buoyancy Compensation and Construction
10)Change Tide-Flex Valves from Duckbill to Inline
11)Other Engineering Costs
12)Pump Station 3 Outfall Redesign and Construction
13)Pump Station 2 Outfall Redesign and Construction
14)Clear, Grub and Reconstruct Berms at Golf Course
15)Additional Brick Pavers
16)Lengthened Pump Power Cables
17)Pump Station Gravity Bypass with Aluminum Slide Gate
18)Cost of Acceleration
Deleted Scope of Work /
1)Bid Item(34) 16"PVC Force Main S l F r
2)Bid Item(59) 18"Tide Flex S
3)Bid Item(New)Dissipater Box
4)Bid Item(New)Pump Station 2 Tie-In
Sunset Harbour Re-Design Addition $3159123.00
Additional work items are lump sum,with the exception of(15),which is unit price and items(12 and 17),which
will utilize restoration and civil quantities as in the existing contract.
125 SE 5TH Court Deerfield Beach FL 33441-4749 Phone(954)979-0802 Fax(954)979-9897
www.lanzo.net
Eric Arencibia,Civil Engineer I
May 1,2014
Page Two
With this proposal we request a thirty(30)day contract acceleration cost and extension in the amount of$ 1,400.00
per day for a total of$42,000.00, as seen on item(18)of the attached schedule of values. This item is to be paid in
five equal amounts of$8,400.00 from May to September 2014.
Lanzo understands that the Pumps, outfalls and Tide Flex Valves for Pump Stations 1, 2 & 3 must be functional as
well as the Tide Flex valves on Dade Blvd by October 15`, 2014 or there will be Liquidated Damages in the amount of
$2,800.00 per day until these items are substantially completed.
These thirty days contract extension will extend the contract Substantial Completion date to October 31", 2014 and
the Final Completion date to November 30th, 2014, while having a Milestone completion for Pump Stations 1, 2 & 3
items for October 151, 2014, as stipulated above. For concurrent delay for the Milestone and the Substantial
Completion, the greater amount of the applicable Liquidated Damages will apply. Nothing contained here allows for
additive Liquidated Damages.
Please review the attached cost spreadsheet and attachments. Lanzo Construction is also available to meet with you to
discuss any specific questions that you may have.
Feel free to contact me at your convenience.
Sincerely,
Daniel Mesquita
Project Manager
Lanzo Construction Company
Attachment(s)
CC: LCC
File
125 SE 5TH Court Deerfield Beach FL 33441-4749 Phone(954)979-0802 Fax(954)979-9897
www.lanzo.net
"r
5/6/2014
CONSTRUCTION COST ADDITION AND DELETIONS
Pump Station #3 and Alternate Pump Station #1, #2
City of Miami Beach Sunset Harbor
Revised Quantities
DESCRIPTION
ITEM BID ITEM UNITS Quan UNIT PRICE COST
ADDITIONS
1 NEW S-16,S-17,S-18 Buoyancy Redesign LS 1 $ 49,322.00 $ 49,322.00
2 NEW Exiling Valve Vault Modification LS $ - $ -
3 NEW Redesign Changes for existing 20"WM Conflict LS 1 $ 7,200.00 $ 7,200.00
4 NEW Reimbersible Expense for Soil Boring LS 1 $ 1,950.00 $ 1,950.00
5 NEW Fcncing Around PSI and PS2 LS 1 $ 25,430.00 $ 25,430.00
6 NEW TV PS2 Outfall LS 1 $ 1,560.00 $ 1,560.00
7 NEW Not Used $ - $ -
8 NEW Electrical Components Regarding Raising the Control LS 1 $ 48,425.00 $ 48,425.00
Panels
9 NEW Other Structue Modifications For Buoyancy LS $ - $ -
10 NEW Price Change For lnhne Check Valves Vs.Duckbill LS 1 $ 13,941.00 $ 13,941.00
11 NEW Other Enginneering Costs LS 1 $ 5,174.00 $ 5,174.00
12 1 NEW PS3 Discharge LS 1 $ 162 239.00 $ 162 239.00
13 NEW Increase PS2 Outfall LS 1 $ 102,925.00 $ 102 925.00
14 NEW Clear,Grub and Reconstruct Berms LS 1 $ 52 484.00 $ 52 484.00
15 NEW Additional Brick Pavers SF 1,850 $ 16.00 $ 29,600.00
16 NEW Lengthened Pump cables LS 1 $ 2,985.00 $ 2,985.00
17 NEW Pump Station Gravity By-Pass with Gate LS 1 $ 47,170.00 $ 47,170.00
18 NEW Cost of Acceleration DAY 30 $ 1,400.00 $ 42 000.00
DELETIONS
1 34 16"PVC Forcemein LF -354 $ 350.00 $ (123,900.00)
2 59 F&118"Tide Flex Valve at Existing Outfall EA. -1 $ 11,500.00 1 $ 11 500.00
3 NEW Dissapater Box EA. -1 $ 58,000.00 $ (58,000.00)
4 NEW Tie PS 2 Into Existing 30"With Tide Flex EA. -1 $ 56,000.00 $ (56,000.00)
IGR'AND-TOTAL 315,123.00