Loading...
2015-29022 Reso RESOLUTION NO. 2015-29022 A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, APPROVING AND AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NO. 2 TO THE CONSTRUCTION CONTRACT, DATED MARCH 13, 2013, BETWEEN THE CITY AND LANZO CONSTRUCTION CO., FLORIDA (THE CONTRACT), FOR THE CONSTRUCTION OF THE CITY OF MIAMI BEACH RIGHT-OF- WAY INFRASTRUCTURE IMPROVEMENT PROGRAM, VENETIAN ISLANDS BID PACKAGE 13C (PROJECT); SUCH CHANGE ORDER, IN THE AMOUNT OF $4,499,103, PROVIDING FOR: 1.) CONSTRUCTION WORK ASSOCIATED WITH A RE- DESIGNED STORMWATER CONVEYANCE SYSTEM FOR SAN MARINO, DILIDO, AND RIVO ALTO ISLANDS THAT WILL MEET THE NEW STORMWATER CRITERIA; 2.) A 422 CALENDAR DAYS CONTRACT TIME EXTENSION REQUIRED TO COMPLETE THIS WORK; AND AN INCREASE IN THE OWNER'S CONTINGENCY, IN THE AMOUNT OF $409,009. WHEREAS, on March 13, 2012, the City Commission approved Resolution No. 2013- 28163, recommending the award and execution of the Contract for the Project with Lanzo Construction Co. Florida, in the amount of $11,373,491 (including 10% owner's contingency of $1,033,954) ; and WHEREAS, on February 12, 2014, the City Commission approved Resolution No. 2014- 28491, recommending Change Order No. 1 to Contract, for the purchase and installation of automatic meter readers, in the amount of $195,532, plus contingency in the amount of $19,553; for a total of$215,085; and WHEREAS, as recommended by the Mayor's Blue Ribbon Panel on Flooding and Sea Level Rise and the Flooding Mitigation Committee, on February 12, 2014 the City Commission approved Resolution No. 2014-28499, amending the City's Storm Water Management Master Plan by modifying the design criteria for the tailwater elevation, and adopted an elevation of 2.7 ft-NAVD for all tidal boundary conditions; and WHEREAS, the Public Works Department (PWD) requested that staff implement the enhanced stormwater system criteria, including increasing from 6-inch to 7.5-inch, 5- day, 24-hour rain event; and WHEREAS, on March 5, 2014, the City Commission adopted Resolution No. 2014- 28528, approving Amendment No. 3 to the contract with Schwebke-Shiskin & Associates (SS&A), the Engineer of Record for the Project, for the re-design and permitting phase services associated with the enhanced stormwater system criteria; and WHEREAS, on August 5, 2014, SS&A completed the design, and submitted it to Miami- Dade County Department of Regulatory and Economic Resources (RER), Environmental Resources Management for approval; and WHEREAS, the City has also retained AECOM to assist in the implementation of a comprehensive flood management plan and to review stormwater improvement plans prepared by the City; and WHEREAS, the Mayor's Blue Ribbon Panel on Sea Level Rise directed PWD to provide the revised stormwater improvement design to AECOM for its review; and WHEREAS, on October 10, 2014, AECOM reviewed and issued comments and, on October 13, 2014, a follow-up meeting took place in the City Engineer's office and additional design modifications were identified; and WHEREAS, on November 19, 2014, the City Commission adopted Resolution No. 2014- 28821, approving Amendment No. 4 to SS&A's agreement to implement additional enhanced stormwater drainage design modifications to existing design, and incorporate AECOM's comments; and WHEREAS, on February 18, 2015, SS&A responded to additional comments issued by AECOM and finalized the enhanced stormwater drainage design modifications and, on February 23, 2015, submitted the 100% documents to PWD for final review; and WHEREAS, subsequently, the Capital Improvement Projects Office (CIP) contacted the twelve (12) property owners that reside adjacent to the six (6) easements where the stormwater pump stations were proposed to be located, for the purpose of discussing the stormwater pump station design and the process of constructing the improvements within the easement; and WHEREAS, the meetings with residents took place between from February to March 2015, resulting in the residents expressing concern on the visual impacts from the proposed structures and equipment components associated with the pump station installations; and WHEREAS, on April 1, 2015, a subsequent meeting was held with concerned residents, where the City stated that it would explore possible design alternatives, in an attempt to minimize the visual impact of the stormwater pump stations and related components; and WHEREAS, in order to maintain the Project on track, and to minimize impacts on the overall schedule, the proposed Change Order will capture all stormwater drainage conveyance components that can be installed without affecting the exploration of possible alternatives, related to the installation of the aforestated pump stations; and WHEREAS, the scope of the work for this Change Order includes work associated with stormwater drainage structures and all associated pipes and drainage inlets, concrete valley gutter, roadway reconstruction, first and second lift of asphalt and driveway aprons, it does not include work related to the pump stations; and WHEREAS, Change Order No. 2 includes an increase of $4,090,094 plus a 10% Owner's contingency, in the amount of 409,009, for a grand total of$4,499,103; and WHEREAS, Change Order No. 2 also includes a 422 calendar days' Contract time extension to complete this work, and WHEREAS, this Change Order No. 2 will revise the total contract sum to a not-to- exceed amount of$16,087,679. NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND CITY COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, that the Mayor and City Commission of the City of Miami Beach, Florida, approving and authorizing the City Manager to execute Change Order No. 2 to the construction contract, dated March 13, 2013, between the City and Lanzo Construction Co., Florida (the Contract), for the construction of the City of Miami Beach Right- of-Way Infrastructure Improvement Program, Venetian Islands,Bid Package 13c (Project); such Change Order, in the amount of$4,499,103, providing for: 1.) construction work associated with a re-designed stormwater conveyance system for San Marino, Dilido, and Rivo Alto Islands that will meet the new stormwater criteria; 2.) a 422 calendar days contract time extension required to complete this work; and an increase in the owner's contingency, in the amount of$409,009. PASSED AND ADOPTED this day of Ma' , 2015. ATTEST: fif, c //' Raf. -1E. Granado, hilip�'`- f e, City Clerk Mayo` ` ; T:\AGENDA\2015\May\CIP\Lanzo C.0\ITB 49-11-12-Venetian,` la/' -Resolution.doc 01. 1'1 lit ORATED.- • % o.. ';, hr7 26 APPROVED AS TO FORM & LANGUAGE flOR UTION 7" ;211/15 City A m'* Dote I.UIVIIVIIJJIUIN I I tIVI JUIVIIVIHKT Condensed Title: • A Resolution Of The Mayor And City Commission Of The City Of Miami Beach, Florida, Approving And Authorizing The City Manager To Execute Change Order No. 2 To The Construction Contract Between The City Of Miami Beach, Florida,And Lanzo Construction Co., Florida, For The Construction Of The City Of Miami Beach Right-Of-Way Infrastructure Improvement Program, Venetian Islands Bid Package 13c(Project), Dated March 13,2013(The Contract);The Change Order Includes: 1)Construction Work Associated With A Redesigned Stormwater Conveyance System That Will Meet The New Stormwater Criteria In The Not- To-Exceed Amount Of$4,090,094 Plus Time Extension Of 422 Calendar Days Required To Complete This Work Within San Marino, Dilido And Rivo Alto Islands ; And 2) Increasing The Owner's Contingency In The Amount Of$409,009; The Resulting Amount Of$4,499,103 Will Be Added To The Construction Contract;With Previously Appropriated Funding. Key Intended Outcome Supported: Build and maintain priority infrastructure with full accountability. Supporting Data (Surveys, Environmental Scan, etc.): The 2014 Customer Satisfaction Survey indicated that over 77% of residents rated recently completed capital improvement projects as"excellent"or"good". Issue: Shall the Mayor and City Commission Adopt The Resolution? Item Summary/Recommendation: On March 13th,2013,the Commission approved Resolution No.2013-28163, recommending the award of a construction contract to Lanzo Construction Co. Florida, (Lanzo). On February 12, 2014, the City Commission approved Resolution 2014-28491, recommending Change Order No. 1 to the construction contract with Lanzo Construction Co. Florida, for the purchase and installation of automatic meter readers As recommended by the Mayor's Blue Ribbon Panel on Flooding and Sea Level Rise and the Flooding Mitigation Committee,on February 12, 2014 the City Commission approved to amend the City's Storm Water Management Master Plan by modifying the design criteria for the tailwater elevation and adopted an elevation of 2.7 ft-NAVD for all tidal boundary conditions. The Public Works Department(PWD) requested that staff implement the enhanced stormwater system criteria including increasing from 6- inch to 7.5-inch,5-day,24-hour rain event. On March 5, 2014, the City Commission adopted Resolution No. 2014-28528 approving Amendment No. 3 for the re-design and permitting phase services associated with the enhanced stormwater system criteria.SS&A completed their design,and submitted it to Miami-Dade County Department of Regulatory and Economic Resources(RER), Environmental Resources Management for approval. On July 22, 2014, RER issued approval for the revised design. On August 5, 2014,the revised design was submitted to PWD and concurrently,change order negotiations were taking place with Lanzo Construction. The City retained AECOM to assist in the implementation of a citywide comprehensive flood management plan and to review stormwater improvement plans prepared by City's Consultants. On October 13, 2014 a follow up meeting took place in the City Engineer's office and additional design modifications were identified and added to the scope. Based on the comments issued by the City Engineer,SS&A had to revise stormwater drainage plans to meet the new criteria implemented by the City Engineer. On November 19, 2014, the City Commission adopted Resolution No. 2014-28821 approving Amendment No. 4 to SS&A Agreement to implement additional enhanced stormwater drainage design modifications to existing design and incorporate AECOM's review comments issued on October 10,2014 plus other comments issued on October 13,2014 by the City Engineer. On February 18, 2015, SS&A responded to additional comments issued by AECOM and finalized the enhanced stormwater drainage design modifications and on February 23,2015,submitted the 100%documents to PWD for final review. Once the design was completed, the Capital Improvement Projects Office(CIP)contacted the twelve (12) property owners that reside adjacent to the six(6)easements where the stormwater pump stations were proposed to be located.The purpose of the meeting was to discuss the stormwater pump station design and the process of constructing the improvements within the easement. The meetings with residents took place from February to March 2015. The residents expressed great concern on the visual impacts from the proposed structures and equipment components associated with the pump station installations.As a result, on April 1, 2015, a meeting was held with concerned residents,their legal counsel, and staff from CIP, PWD, the City Attorney's Office and the City Manager's Office. It was determined that the City would explore alternatives attempting to minimize the visual impact of the stormwater pump stations and related components. In order to maintain the project on track, and to minimize impacts on the overall schedule, this change order will capture all stormwater drainage conveyance components that can be installed without affecting the exploration of possible alternatives related to the installation of pump stations.The work related to the pump stations is not included in the scope of this change order. The scope of work, for this change order, will include; stormwater drainage structures with all associated pipes and drainage inlets,concrete valley gutter,roadway reconstruction,first and second lift of asphalt and driveway aprons. Based on the supporting documentation presented by Lanzo, the project Engineer of Record (EOR) / Schwebke-Shiskin & Associates, Inc. has found the proposal acceptable and is recommending approval of the change order and a project time extension of 422 calendar days to complete the work associated with stormwater conveyance work(Attachment B). The Administration recommends approval of the Resolution. Advisory Board Recommendation: N/A Financial Information: Source oft_ Amount Account Funds:$V 1 $4,499,103 429-2127-069357 Stormwater LOC Reso No.2009-27076 OBPI Total $4,499,103 Financial Impact Summary:N/A City Clerk's Office Legislative Tracking: David Martinez ext.6972 Sign-Offs: law Departm:;;x t Director Assistan 00 !er City M=l';'. DM 'CA $'p(Z o MT • JLM At T:WGENDA\2015\May\CIP\L. ,•.O\ITB 49-11-12-Venetian Islands ROW-Summary.docx l I ITEM MIAMI BEACH DATE 7-6--1 INN o 1915 •2015 M(AMIBEAC City of Miami Beach, 1700 Convention Center Drive,Miami Beach, Florida 33139,www.miamibeachfl.gov COMMISSION MEMORANDUM TO: Mayor Philip Levine and Members of t !e City Com ssion FROM: Jimmy L. Morales, City Manager I DATE: May 6, 2015 SUBJECT: A RESOLUTION OF THE MAYO AND CITY COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, APPROVING AND AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NO. 2 TO THE CONSTRUCTION CONTRACT BETWEEN THE CITY OF MIAMI BEACH, FLORIDA, AND LANZO CONSTRUCTION CO., FLORIDA, FOR THE CONSTRUCTION OF THE CITY OF MIAMI BEACH RIGHT- OF-WAY INFRASTRUCTURE IMPROVEMENT PROGRAM, VENETIAN ISLANDS BID PACKAGE 13C (PROJECT), DATED MARCH 13, 2013 (THE CONTRACT); THE CHANGE ORDER INCLUDES: 1) CONSTRUCTION WORK ASSOCIATED WITH A REDESIGNED STORMWATER CONVEYANCE SYSTEM THAT WILL MEET THE NEW STORMWATER CRITERIA IN THE NOT-TO- EXCEED AMOUNT OF $4,090,094 PLUS TIME EXTENSION OF 422 CALENDAR DAYS REQUIRED TO COMPLETE THIS WORK WITHIN SAN MARINO, DILIDO AND RIVO ALTO ISLANDS ; AND 2) INCREASING THE OWNER'S CONTINGENCY IN THE AMOUNT OF $409,009; THE RESULTING AMOUNT OF $4,499,103 WILL BE ADDED TO THE CONSTRUCTION CONTRACT; WITH PREVIOUSLY APPROPRIATED FUNDING. ADMINISTRATION RECOMMENDATION Adopt the Resolution. KEY INTENDED OUTCOME Build and maintain priority infrastructure with full accountability. FUNDING $4,499,103 429-2127-069357 Stormwater LOC Reso No. 2009-27076 Change Order No. 2 to Lanzo Construction Co.,for Venetian Islands project-Memorandum May 6, 2015 Page 2 of 4 BACKGROUND Pursuant to Invitation to Bid (ITB) No. 49-11/12, for the Right-of-Way Infrastructure Improvement Program — Venetian Islands Bid Package 13C, on March 13th, 2013, the Commission approved Resolution No. 2013-28163, recommending the award of a construction contract to Lanzo Construction Co. Florida, (Lanzo) in the amount of $9,699,509 base bid plus $640,028 for selected alternates (sanitary sewer lining and road reconstruction) and a project contingency in the amount of $1,033,954; for a total construction cost of$11,373,491. On February 12, 2014, the City Commission approved Resolution 2014-28491, recommending Change Order No. 1 to the construction contract with Lanzo Construction Co. Florida, for the purchase and installation of automatic meter readers in the amount of$195,532, plus contingency in the amount of$19,553, for a total of$215,085. As recommended by the Mayor's Blue Ribbon Panel on Flooding and Sea Level Rise and the Flooding Mitigation Committee, on February 12, 2014 the City Commission approved to amend the City's Storm Water Management Master Plan by modifying the design criteria for the tailwater elevation and adopted an elevation of 2.7 ft-NAVD for all tidal boundary conditions. The Public Works Department (PWD) requested that staff implement the enhanced stormwater system criteria including increasing from 6-inch to 7.5-inch, 5-day, 24-hour rain event. The new criteria required the Engineer of Record, Schwebke-Shiskin & Associates (SS&A) to revise the design included in the contract documents for this project. On March 5, 2014, the City Commission adopted Resolution No. 2014-28528 approving Amendment No. 3 for the re-design and permitting phase services associated with the enhanced stormwater system criteria. SS&A completed their design, and submitted it to Miami-Dade County Department of Regulatory and Economic Resources (RER), Environmental Resources Management for approval. On July 22, 2014, RER issued approval for the revised design. On August 5, 2014, the revised design was submitted to PWD and concurrently, change order negotiations were taking place with Lanzo. Occurring on a parallel path with the change order negotiation, the City's Public Works Department (PWD) was in the process of completing their final review of the revised stormwater improvement plan when, the Mayor's Blue Ribbon Panel on Sea Level Rise directed PWD to provide the revised stormwater improvement design to AECOM for their review. The City retained AECOM to assist in the implementation of a citywide comprehensive flood management plan and to review stormwater improvement plans prepared by City's Consultants. On October 10, 2014, AECOM reviewed and issued comments. On October 13, 2014 a follow up meeting took place in the City Engineer's office and additional design modifications were identified and added to the scope. Based on the comments issued by the City Engineer, SS&A had to revise stormwater drainage plans to meet the new criteria implemented by the City Engineer. On November 19, 2014, the City Commission adopted Resolution No. 2014-28821 approving Amendment No. 4 to SS&A Agreement to implement additional enhanced stormwater drainage design modifications to existing design and incorporate AECOM's F:\T_Drive\AGENDA\2015\May\CIP\Lanzo C.O\ITB 49-11-12-Venetian Islands ROW-Memo-C.O.2-FINAL STEPHANIE .docx Change Order No. 2 to Lanzo Construction Co.,for Venetian Islands project-Memorandum May 6, 2015 Page 3 of 4 review comments issued on October 10, 2014 plus other comments issued on October 13, 2014 by the City Engineer. On February 18, 2015, SS&A responded to additional comments issued by AECOM and finalized the enhanced stormwater drainage design modifications and on February 23, 2015, submitted the 100% documents to PWD for final review. Once the design was completed, the Capital Improvement Projects Office (CIP) contacted the twelve (12) property owners that reside adjacent to the six (6) easements where the stormwater pump stations were proposed to be located. The purpose of the meeting was to discuss the stormwater pump station design and the process of constructing the improvements within the easement. The meetings with residents took place from February to March 2015. The residents expressed great concern on the visual impacts from the proposed structures and equipment components associated with the pump station installations. As a result, on April 1, 2015, a meeting was held with concerned residents, their legal counsel, and staff from CIP, PWD, the City Attorney's Office and the City Manager's Office. It was determined that the City would explore alternatives attempting to minimize the visual impact of the stormwater pump stations and related components. On April 15, 2015, the City Commission adopted Resolution No. 2015-28993 approving Amendment No. 5 to SS&A Agreement for additional Construction Administration and RPR services due to the increased construction schedule plus design modification services required to minimize the impact of the proposed structures and components. The design modifications will include conceptual design, meetings with City staff, electrical and structural revisions and permit submittals. ANALYSIS In order to maintain the project on track, and to minimize impacts on the overall schedule, this change order will capture all stormwater drainage conveyance components that can be installed without affecting the exploration of possible alternatives related to the installation of pump stations. The work related to the pump stations is not included in the scope of this change order. The scope of work, for this change order, will include; stormwater drainage structures with all associated pipes and drainage inlets, concrete valley gutter, roadway reconstruction, first and second lift of asphalt and driveway aprons. Lanzo has presented a change order proposal, (Attachment A) that address the following: • Additional scope relating to stormwater drainage conveyance improvements designed to comply with the City's new stormwater. • Exercising the provision of Article 38.1.1 of their contract with the City of Miami Beach that allows for the adjustment of unit prices from the original contract wherever the unit quantities are adjusted in excess of 20% of the original amount. • Effects of recently imposed weight restrictions on the Venetian Causeway bridges. F:\T_Drive\AGENDA\2015\May\CIP\Lanzo C.O\ITB 49-11-12-Venetian Islands ROW-Memo-C.O.2-FINAL STEPHANIE .docx Change Order No. 2 to Lanzo Construction Co.,for Venetian Islands project-Memorandum May 6 2015 Page 4 of 4 • Implementing an alternative trench restoration detail, utilizing woven filter fabric and the use of Geosynthetic (GEOGRID) under lime rock to reduce the quantity of removal of unsuitable fill. The resulting costs are as follows: • Stormwater improvements $ 2,834,683 • Bridge Weight Restriction Cost Impact $ 1,200,461 • Unit quantity greater than 20% $ 54,950 Sub-Total $ 4,090,094 • Contingency at 10% $ 409,009 Grand Total $ 4,499,103 Based on the supporting documentation presented by Lanzo, the project Engineer of Record (EOR)/ Schwebke-Shiskin &Associates, Inc. has found the proposal acceptable and is recommending approval of the change order and a project time extension of 422 calendar days to complete the work associated with stormwater conveyance work (Attachment B). A subsequent change order to Lanzo will be presented to the Mayor and City Commission once all the available options for proposed enhanced pump station design have been explored and a consensus is achieved with the residents. CONCLUSION The Administration recommends approval of the Resolution. ATTACHMENTS: Attachment A- Lanzo Construction change order proposal Attachment B - SS&A— Letter of recommendation JLM\MT\DM F:\T_Drive\AGENDA\2015\May\CIP\Lanzo C.O\ITB 49-11-12-Venetian Islands ROW-Memo-C.O.2-FINAL STEPHANIE .docx ATTACHEMENT "A" 71LANZD TA CONSTRUCTION COMPANY Delivering sustainable infrastructure solutions for tomorrow's communities April 27, 2015 Luis Leon, P.E. Schwebke-Shiskin&Associates, Inc. 3240 Corporate Way Miramar, Florida 33025 Re: Venetian Islands Bid Package 13C—ITB No. 49-11/12—Price for Drainage System Redesign&Backup information Dear Mr. Leon, As requested,please find below the pricing breakdown for the Stormwater System Redesign, provided to us on the plans dated February 2015, and which, as directed by your office, exclude pump stations, grate boxes, water quality unit(WQ's) structures,piping between WQ's and Pump Stations, 2-IN Water Services&wet taps, Dissipater Boxes, Tide Flex Valves, Turf Blocks, Restoration of Outfall R/W's, Core Drilling of existing sea walls, Manatee Grates, Plug Existing Outfalls, ALL RCP Outfall Pipe,ALL 20"and 24"DIP Pressure Pipe, and Associated Bridge Loading Costs for these items. • Stormwater Redesign improvements $ 2,834,683.00 • Bridge Weight Restriction Cost Impact $ 1,200,461.00 • Unit quantity greater than 20% $ 54,950.00 Total Increase $ 4,090,094.00 Please, refer to the attached table for reference. 407 Lincoln Road Miami Beach FL 33139 Phone(954)979-0802 Fax(786)476-0368 www.lanzo.net Page 2 of 2 All the prices here presented relate to the information currently available. Also,based on the information presented, it is expected for the project duration not to exceed 12 months from the date of Notice to Proceed, for construction of the re-designed collection system. As such, the total project duration shall be 422 pays from last day of the original contract date (2/2/2015). Based on this duration, the Final Completion date of the project should be March 31, 2016. If you have any questions, comments or concerns, please do not hesitate to contact us. Sincerely, Pablo C.Riano Project Manager CC: Mark Tomczyk,P.E.,City of Miami Beach CIP(via e-mail) Roberto Rodriguez,City of Miami Beach CIP(via e-mail) James C.Tello,Schwebke-Shiskin&Associates,Inc(via e-mail) 407 Lincoln Road Miami Beach FL 33139 Phone(954)979-0802 Fax(786)476-0368 www.lanzo.net �f gg . . � Q8�88;8�88_8s 2i8gA8°8°88,. 38x282 8.°888 Ar°r8 ;l oRr A o :?g;li2 m RN E§ § , 8 §§§§§g m e„ � s - g, F,§ , 1 8'68A818=88-=!8 P888888.; a8<482 68.6.'', gRm^ r - gg"o!8 2A l agm - - i §e § °2§ §' , 2§§ 8 7.� $ i g s 2s'M22aTAooAa82.FA gicgP 2 g.A g 8 se8%' • a Pxr P$Ngg=14aa-_ rq 8 g gogg 2g,gg PsgA22 - f', N • =2M a.14 a2 $AM $AMA'ig 1 AgA282° .2-i -mg° m2m ; MB222n m aia,'2a ,amagi=2%laae; ,s8� aTs5, 5 i - - .,,a a ;ate.,, ., aaLlama g 8 Ba ' ' N 1 8 8 8 8 8 88 8 8 888 8 8 88 88 8 8 8 88 8 8 8 8 8 888 88 88 8 8 8 88888 8 88 it § § § § 61 § s 3r§ § § 28 38 g a s 88 s § 8 s M8, a8 88 s § § 88888 §§ 0 141 2 o2 ?. 8 Mg-g". 8 8 8: ti 8. 5' o8n°%Z - _egA gage - - o u c EZ= .ig 8= e8 - 8 = a s e 7, � °5 g g.:gr ��m=8o g$$3 ry �g o.�� 8,--48g2 - n v��o m "°m ?gn v�m�m�am a� a�u�v! s s a , Mar , 'R- „ - , ^$_ a ,.a, ;a=le ac;a-sum „ , Ra_ 8 88 8 8 8 888 8 8 88 88 8 8 8 88 8 8 8 8 8 888 88 88 8 8 8 88888 8 88 1 § § § § 6§ § ^ s 121 8 E 2s 3I s a 8 8s 8 8 8 8 E 888 s8 E8 s E E 88588 E EE 4 s 8 0 3 8 8 88 8 888888088 88 88 8 83 888888883838 8888858838888x888888888888888 § § § § 68 § ati „ x88 �3 N FIE, 888888882.888 8888§38888858.588888§88899§�88 3 1 1.. n n n, .h i l,,i tl 6 ;-,,,,,t,-L 6 C, J n- 55' 3 3 5 3 5 S 5 5 5 5 5 5 5 3 5 5 5 5 5 5":5 5 5 5 3 g - W � 1 j -.--_.-...------..._ 3 $$a N a a --' m ,. 8 ,, it N_ - c b m m m N e£ o § sa g E; d 28 2 Li 5 Ai o 3 g = g 8 3' A.,, o S_ �W uu c 5 3 3 2 68.E -- _: 3 3 8 :A 41 S _s t H y l, = r.. z e<m _ 6 z o a w, - s a = o a °a W r W W d c a 8 __ `-.G G G g K a o$c -"'L'-'W� 63 N' a 2,- G 6 G 3 G a 1`_ $� r o 3 n 5,f,,a&a a 8 9 r a'P. 3`3`a 8 3 x 3 , z z N W -g o>> W LL 5 5 5 5 G a - - - -- ,?,,,"8,98:',.,1 _ a�� im�$ e� m o$���88 g, -°-off -°_gU 3 Wifil __ e - sca` a ° L` l,l,- 3 Flip _3 -°35 W�' i „°o - _ o° °sor 8 5!t,4Lt,L1,LLi.Li,V'.,1,I,t,LVLLt,t,5'e_ 5oa a a ° 9 $° y a Z z.z 33 8.:; 33 i z i£< z - `+ ;:J.K!u.�.EE °z S" `�=�� �': <<�_° <<<a<`a`-.� G- x`W F��"�� � ��°�k�z�����'"��� �����c��� �.'°°i z°° wf 3 i °o ,2 E E6_E Et5' 5' EE.L_EE 4F 9 9z8 2P $ ����:��� wg• 8c bb¢ �r -��bEbd �c�tcwttccattitttcctW :r �:�: 8 ��€ ., o m?8 2 J' w 6 f 3 F y,r f 3 P 4 f f s, z z z z z z z z z ; s° =f= �����.. ., ����a�<�s�82 :z::�:z:�:� =��`��i$�gifiii'ee4:, II g § 5m .Cm ° s o J °a R R R8Rmm88R188 8888 -S N xS'88888888888888888888883mra8gA - 8SS88 88888888888888 1 ZW88� 8 = 0.,E_8 ee sAmm88r8 8§8PF.s _ ;9,,g21?, Vi- =888eg8^74 § H - -�- - - - - a s=� a`aa;� a= =-=- - „ -„ n ...-a ,-a ,-H Ra �a i R „8a 8888 8888888888888888888?88R 88m 8mP88 88"888888888888 S. 8Pe38748R7 AgN - _ N N 3" m it _ , 3 Ag 8l v N la 1 s .. b f e r 2 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 8 88 88 8 8 88 88888 88 88 88888888 1 3 8 8 8 8 8 8 8 § § 8 8 8g §E 8 E5 q P1R888 8a 888s888R r, a a a. a. 14 3m m a 2 a o= $ �S8ma88N 88 8 Ar '•.a? �$ 8 8 a 8 8 8 g 8 8� a BNAg 8 8 LL8a S" 8 e -3m sZ a g 8 a r s gEF. ;x ,.. -o 8 8 ` s ggggggg 2 8 8 3 Z @ a sz §- - - " . - , - n o 5Z;, g >8 6 c R 18 88g 83 8888 3�4-3 - 888888888888.8888888�?88°'^�85 8<°88 88888888888888 i m,gsd ;,88 age :.3 a8 x78 2§ §8 HHg9�° °§ m88 § "8§8 88; 08 8888S88d8o3Aa 88a888ga 88g88C8m 43 2 8 8 g= 8.88888888888.88 8883888'.89 8 885 888888 3 $ s 9FsN 85P .ws� °"s es 2 s <s° 588 m§ rs s s s sos§ss g s�• Nas_ �e �aasas� xss"a - as a ggg g a aN aR aaaa 6,� a. NssN 8888s88a8sm 88"'88 58888 aes ss�sss 8sssm�8 -�s: :;s,ss �•s:sF ssasss € 33§s3§ as s.^" - a.�V.a �^ V. 5 .as N ! '"' ~. ssaJ . ,, ��°s . 5881 s s- g lzV a,,,, -5.6a - sN F, N s � aa ~ sass Ra . i N EE i g a�_ sf A g P gg g 8888 88 8 885 88888888 888 8� 88 8 888 8 8888888 8888888 8 8 8 8 888888 11 $m88 �8 858888 88F „ mP § a§8 SFina F, §m88:e8 8 6 8 8 § 888888 o e gaszs. a 80°5 8848 8 e& 2 82 3 e. 8 x 8 sr g e s vs a m $ _ Egg 2 h!a= _ s 8 L5 8 i _ - 5N =� ii V Q • 8888888g88„7 a 88T890A2 887.88Sm 43 2 8�8 '" 88888888888898 8°8,:888888 e'"88-s1 888888 $m§8U2§N N ei g5ag=mi� °sa N e"a ^l§ F $° mgggm§: 2-AL P§ s^2§,m asg$ag ' s . ---"8' a° �� 6 "� " . 555 5 a� �..,aa ,9z v.a : Eiae i 8888 88 8 8833 888E8888 888 8 P 88 8 8E8 8 3888888 88!!8888 8 8 8 8 8 8 8 888888 5 3 n9 --" - =8 U_ 5 P31 - 3°nP.s. 3 on 5n - a 3 § 838388 e a.w. a. w ..w. .ww..w.. ww. .. N .N » .aw w . .w»Mww .......w . . . a a a a . .ww.w. 98883888 8888 88'c -88 88888838 8885 88°° 88Fzn 383 338 8388e?828 NSts ° 8888 g -asg< • - -- 3,----n--� .° _ ° ° - ,s°- as-°-^ a 8 RR..§ - -g,„8„4 °a 3 sy 9 ;; 5 9 3 W W a_ N a h 5 N„5 N 5 5 V6 6 6 3 _ 5 5., ,5..W n_9,N h 1 5 W 5_5_,3 n 5 5 h H t t n s s W g 8e0Amss o.323= as ms$ sT PAN ; g $-.-e 4 g W _d I E 85 T. is=_ 6 s> <; i ":<< x Wo E a 5 Wgaz g 8 °�_ _ z gf W u 9 F 5, m ° z o o W a` 2. z g W i o ° 9 ASS Wo Vi 's.,.;.8 ,z� L2 N ,, gi ��' a °; 6 5.E1 m a m x o 8 o'a - _ $$ F a ¢ `2 o m• ” 3 o = ESE 3 • LLs's g o i_Iak 86565555., 5e _ ga eW- �'8 2'2' 3- 5z9 s t s m o D g V l L 8 i o t W 5.5 m S W W W W �0 84 6'i; - i 0 3 _ W ° F-. s . ,� 2 f t a G . 3 J 5 F :g§8 0' a m 0656,°°"'" 0; Y 5 G o- *E F`MW‘g W W.:3 � __ g^ 8 t , 255:318 om9 8 58`,4888 Wk11 32 Pi 33 uWW88° .20000 i9LL5".�.'595??'- I5 Pg 30=`0 $ X85„5.0?s-3 W aW8s 588 F18 888E258 -- 5g;223 3�855iE' -- ---- � �yy >;$°s,, ° �H m N < m g i < a R a �� m 1!!f:' m a 5 s s z a I i G G_ 5 !Op!S >, _ 8 c 8 E m o..8 8 F g 8 8 5 8 5 8 o 8'x 3 o = _r 2 z a a3 8 5 8 n f 9 9'o u Ib>2 6 3 W W E O S 8 5 w -8 w v y E 8 9 C m E m m m. s s W 9 f s f a $F 3 3 w 8 �� r e 686 1 2 2 2 6 6 . .d: ..... . -....z 2 "0-.-m- 5 5 5 9 9 9 t 8 8 0 0 8 8 8 5 El s a - __ _ _ _9 3 5 2 5 9 a ,.9,.5 9 :_-_- - R y, c o-- 3 o n s e 3 e \k 8 8 8 8 - ` ! ,;28.8.8 R } :, , , . . . %z,a; 8 8 8 8 ! \ 5 8 | 7n& z ; : . t '4'▪ \ a ` ...7; - P,I e 1 IT 8 |, m §. , 2 |k ■ ! E■ I- I 8 8 8 8 g f, ; ! k n . , , .!! j }|! \ _ , . , lwa,z, 8 @; . \_ , 8 ■ /kk ! - \kid 4 ! k§� '^:,:' . . . _!■ k h ! •E' 22C | - —a ;|§ ! 8 8 2 8 - 5 8 j - . . _ ,= 8 , a;;,7»8 8 ® !!%= ,;;88888888898 ; A8 ,8 - ; 88 =88= . § n;'. _)(; '/!;W ii7#[!!a(;;la; ¥ ` \\\& % ; 7`<��G .� -,,, -.!; m- , )§ - -; _- _ _ _ a -- - --- ------------------------- - -- -- ---- -- ---. !l, a 44Pr ,!!;% ,! !78,!27! 58 m 8 8 8 - ,7= § 5558 »!;§ § 55 88§§/ f* \ 8 \k)m [ (f ----. --.---®---- -------- -- - - ---- - !§ ! | `§ ; |>■K | , a,,,_1) 2 !„:! 88555333588 66555553 „ ! : / §| 8888 ,2 E|§, | . \..1p _ |k - _}—)1 } § ` | | R�__ .] ----- -- ----- -- - - ( §! - . §§B 5 i • . — — i i § ! . ! 3 I § § ! 4 8' \ _!| !\ - i f . : = 8 835 )B ! £ ) )|| _ § § - | 1 � _ - \i.i!! Ff!! ! _ §/}j ` - § . E k) \ . ,_ ( . � �\\ 7777 \\(8 /\ } § . B k) : 22!§! :.:! , !!§.3.4 § ;EIEM. : '- , | / .0 3,'.=.'z' \ k k i'§§!!i||;1!| (|[§S :_ z\ - 4)))|k} - . !2)!;c°---rg- "-za.:;| !} - § .|.- ■; «.��;;;l, l�= ..., _ £r|of 0,'' : ! § k |;);,--4000!!)!§§)a fi.W gS - § fi.'0F § z ; « ;.-_, "� "�� ��� ` -; k\) 121 ! :§! ,.l.!«,=|;;li;!555 | zo,...| ;_ ,�g «-2 � i}{\) - _ §-4474)!{|!!»ff! =!s!/!!!!l-77] 7447 _ |)\7§)5 ) 2:!@4474!|§))§�;|�\|I||| \;!! !_ - : : EM.-a s .:__. a N,-7, .2_;8„�.M VR=.,..:==aa, ,_�. s , _ _ 2 7 - / 4 434\ k §2E f !! ! ! , 8 ! §mE 9 \ _ _ ATTACHMENT "B" �gUTEt kE-cgid in 4-1-- 6- c loaiatEd.,ine. Principals Civil Engineers-Land Planners-Surveyors Luls F.Leon,P.E. Hernando J.Navas,P.E. Alberto A.Mora,P.E. Mark S.Johnson,P.S.M. 3240 Corporate Way•Miramar, Florida 33025 John C.Tello,P.E. Phone:(954)435-7010•Fax:(954)438-3288 Michael D.Gonzalez,P.E. of Council Ronald A.Fritz,P.S.M. Alfonso C.Tello,P.E.,P.S.M. Jose G.Hernandez,P.S.M. Michael J.Alley,P.S.M. • Emilio E.Llufrlo,P.S.M. April 28,2015 Mr. David Martinez, P.B.,Director of CIP City of Miami Beach Capital Improvement Projects Office 1701 Meridian Avenue, Suite 300 Miami Beach, Florida 33139 Re: Venetian Island iVeighborhood 13 BID Package "C"—Drainage Redesign Proposal Analysis(Drainage Collection System Only) Dear David, As requested, we have completed our review of the Change Order proposal provided by Lanzo Construction Company for a portion of the drainage improvements designed to comply with the City's recent sea level rise criteria. The portion of the drainage improvements in Lanzo's proposal includes all drainage construction upstream of the designed water quality units for each respective island. Note that • the proposal includes full road reconstruction of all roadways as mentioned in more detail in this letter. Based on the most recent information provided to us in a proposal by Lanzo Construction Company dated April 27,2015 and in summary of our review of the project costs: Total Stormwater Redesign Improvements(Excluding Pump Stations&•Outfalls)_ $2,834,683.00 Bridge Weight Restriction Cost Impact= $1,200,461.00 Unit quantity increases/decreases greater than 20%= $54,950.00 u Original Contract Amount, including change orders= $11,588,575.13 . Total Project Cost= $15,678,669.13 • The change order proposal submitted by Lanzo Construction Company included a combination of Unit Price and Lump Sum values for change order work. - Pursuant to Article 38.1.1 of the contract between the City of Miami Beach and Lanzo Construction Company(ITB 49-11/12)we found that unit prices from the original contract were used wherever the unit quantities did not exceed 20%of the original amount. However due to recently imposed weight restrictions on the Venetian Causeway,Lanzo Construction Company provided supporting documentation used to determine the additional cost of construction to comply with the regulated bridge weight restrictions. Based on the documentation provided,the weight restrictions on the Venetian Causeway require that the number of trips needed to import and export materials to and from the project be increased to transport the mentioned materials in lighter loads. We find that the documentation provided clearly defines the impacts of the bridge loading restrictions,however,please note that the change order proposal and supporting • Mr.David Martinez,P.E. April 28, 2015 Page 2 of 2 documentation provided by Lanzo Construction Company was not independently verified by this firm and that our firm does not have information available on the pricing structure and comparison of Lanzo's truck capacities used in the original contract. As such,for our review of the supporting documentation,we could only assume that the truck capacities used to bid the project were based on full truck loads as shown in the supporting documentation. - Pursuant to Article 38.7 of the contract between the City of Miami Beach and Lanzo Construction Company(ITB 49-11/12),where unit quantities increased or decreased more than 20%of the contracted quantities,we found that Lanzo Construction Company adjusted unit prices based on negotiated values. It is our opinion,to the best of our knowledge,that the negotiated values of these items are within an acceptable value.. - Pursuant to Article 38.1.2 of the contract between the City of Miami Beach and Lanzo Construction Company(ITB 49-11/12),a change order for individual items proposed for construction that were not included in the original bid documents was provided. The proposal provided by Lanzo Construction Company included a redesigned drainage collection system, furnishing and installing FPL conduits and pullboxes for anticipated electrical systems,and fitrnishing and installing a geosynthetic grid below the proposed roadway limerock base. Based on our review of the change order proposal for these items it is our understanding that a component for overhead and profit is included and to the best of our knowledge it is our opinion that the unit prices for these items are within an acceptable value for the work proposed. • Our review consisted of an independent cost analysis while also taking into consideration the unique circumstances regarding the bridge loading restrictions of the Venetian Causeway. Using these factors we determined that the cost proposed by Lanzo Construction Company an acceptable value for the proposed work. 1 It is our understanding that the project duration is anticipated not to exceed 12 months from the date of Notice to Proceed for construction of the re-designed collection system. As such,it is our understanding that the total project duration shall be 422 days from last day of the original contract date(2/2/2015). Based on this duration,we find that the Final Completion date of the project shall be March 31,2016. As always,if you have any questions please contact me. Respectfully submitted, • daizan.ACE-eSgatn c ssoelat&S,_Una. Lui F. Leon,P E. Assistant Vice President • cS�uuE�,�E-eS�ils�ln fs o¢110e1.atES,g . k:132$342\vi-sm-di-ra\documents\outgoing\david martinei-cmbcipO3.doc