Loading...
2016-29264 Reso RESOLUTION NO. 2016-29264 A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, APPROVING "ALTERNATIVE NO. 1" AND AUTHORIZING THE MAYOR AND CITY CLERK TO EXECUTE CHANGE ORDER NO. 3 TO THE MARCH 13, 2013 CONSTRUCTION CONTRACT BETWEEN THE CITY OF MIAMI BEACH, FLORIDA, AND LANZO CONSTRUCTION CO., FLORIDA, FOR RIGHT-OF-WAY INFRASTRUCTURE IMPROVEMENTS UNDER • THE VENETIAN ISLANDS BID PACKAGE 13C (THE CONTRACT); WHICH CHANGE ORDER INCLUDES: 1) CONSTRUCTION WORK ASSOCIATED WITH SIX (6) NEW STORMWATER PUMP STATIONS THAT MEET THE CITY'S ENHANCED STORMWATER CRITERIA, IN THE NOT-TO-EXCEED AMOUNT OF $12,257,864, 2) A TIME EXTENSION OF 365 CALENDAR DAYS REQUIRED TO COMPLETE THE SCOPE OF WORK WITHIN SAN MARINO, DILIDO AND RIVO ALTO ISLANDS; AND 3) AN INCREASE TO THE OWNER'S CONTINGENCY OF $1,225,787; ALL FOR A TOTAL CHANGE ORDER OF $13,483,651. WHEREAS, on March 13, 2012, the City Commission approved Resolution No. 2013- 28163, recommending the award and execution of a contract with Lanzo Construction Co., Florida, for the construction of right-of-way infrastructure improvements under the Venetian Islands Bid Package 13C (The Project), in the amount of $11,373,491 including contingency (The Contract); and WHEREAS, on February 12, 2014, the City Commission approved Resolution No. 2014- 28491, recommending Change Order No. 1 to the Contract, for a total cost of $215,085, including contingency; and WHEREAS, on February 12, 2014, consistent with the recommendation of the Mayor's Blue Ribbon Panel on Flooding and Sea Level Rise and the Flooding Mitigation Committee, the City Commission approved Resolution No. 2014-28499, amending the City's Storm Water Management Master Plan; and WHEREAS, the Public Works Department (PWD) requested that staff implement the enhanced stormwater system criteria; and WHEREAS, the new criteria required the Project's Engineer of Record, Schwebke- Shiskin &Associates (SS&A), to revise the design approved under the Contract; and WHEREAS, the City also retained AECOM to assist in the implementation of a Citywide comprehensive flood management plan and to review stormwater improvement plans prepared by the City's consultants; and WHEREAS, SS&A completed its redesign, and negotiations began with Lanzo to implement the revised design criteria into the right-of-way infrastructure improvements under Lanzo's contract; and WHEREAS, on February 18, 2015, SS&A responded to additional comments issued by AECOM and finalized the enhanced stormwater drainage design modifications and, on February 23, 2015, submitted the 100% documents to PWD for final review; and Page 1of3 WHEREAS, the Office of Capital Improvement Projects (CIP) contacted the twelve (12) property owners that reside adjacent to the six (6) street ends where the stormwater pump stations are proposed to be located, for the purpose of discussing the stormwater pump station design and the process of constructing the improvements within the street ends; and WHEREAS, meetings with these residents took place between February through March 2015, resulting in the residents expressing concern on the visual impacts from the proposed structures and equipment components associated with the pump station installations; and WHEREAS, on April 1, 2015, a subsequent meeting was held with concerned residents, where the City stated that it would explore possible design alternatives, in an attempt to minimize the visual impact of the stormwater pump stations and related components; and WHEREAS, on May 6, 2015, the City Commission adopted Resolution No. 2015-29022, approving Change Order No. 2 to the Contract, for the drainage conveyance construction work associated with the enhanced stormwater criteria, in the not-to-exceed amount of $4,499,103, including contingency, along with an associated time extension of 422 calendar days; and WHEREAS, the scope of the work for Change Order 3, includes work associated with the installation of the six (6) pump stations, and the associated pipes, structures and electrical control panels to each pump station; and WHEREAS, on September 16, 2015, the City Administration met with the affected residents (and their representatives) to demonstrate the key improvements to the previous design, in order to address the concerns brought to the City's attention during the April 1, 2015 meeting; and WHEREAS, SS&A enumerated each item where improvements were made to the current design, showing reduction of overall panel height, removal of all raised platforms, and separation of electrical panels from adjoining properties to allow a buffer for landscape screening; and WHEREAS, the residents in attendance requested that the City attempt to relocate the proposed pump stations to the Venetian Causeway Right-of-Way; and WHEREAS, on October 8, 2015, the City Administration and members of the Venetian Neighborhood met with Miami-Dade County Public Works staff to determine if installing the stormwater pumps along the Venetian Causeway would be a viable solution; and WHEREAS, the City and Miami-Dade Public Works staff discussed various options and concluded that the placement of several pump stations and related appurtenances and piping on the Venetian Causeway would require extensive due diligence, relocation of a multitude of utilities, and could have significant structural impact on the bridge abutments; and WHEREAS, at the•City's direction, SS&A analyzed four (4) alternative solutions for the placement of the pump systems along with equipment and components at different locations throughout the islands and the Venetian Causeway to discharge the stormwater to the Bay, and a fifth alternative to maintain the stormwater drainage system as a gravity discharge (if none of the four alternatives were chosen); and WHEREAS, Alternatives 3 and 4, do not appear to provide a viable alignment for the proposed improvements on the Venetian Causeway; and Page 2 of 3 WHEREAS, the Administration recommends Alternative 1, as to the installation of six (6) pump stations at the street ends, as the most viable option, because it has already been designed; it is the current design approved by SS&A and AECOM; it would take the shortest time for completion of the work; it meets the enhanced stormwater criteria; and it is best engineering practice to locate the pump station as close to the discharge point as possible, and WHEREAS, Lanzo presented a proposal for implementing Alternative 1 as reflected on the attached Change Order No.3, for $12,257,864, plus ten percent (10%) contingency of $1,225,787, for a total price of $13,483,651, plus a construction time extension of 365 days beyond March 1, 2016; and WHEREAS, based on the numerous cost reviews and negotiation sessions throughout the development of the design of these revised storm water improvements over the last several months and the examination of supporting documentation presented by Lanzo, SS&A and the Administration have found the proposal acceptable and recommends approval of Change Order No. 3; and WHEREAS, this $13,483,651 Change Order is being funded by $1,950,366 from previously appropriated funding and $11,533,285 from the Stormwater Master Plan Program; the acceptance of this $11,533,285 for the Venetian Island Project reduces the available stormwater bond funds from $60,266,296 to $48,733,011; and WHEREAS, the total amount of the Contract with Lanzo, should Change Order No.3 be approved, would be $29,571,330. NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND CITY COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, that the Mayor and City Commission of the City of Miami Beach, Florida, approving "Alternative No. 1" and authorizing the Mayor and City Clerk to execute Change Order No. 3 to the March 13, 2013 construction contract between the City of Miami Beach, Florida and Lanzo Construction Co., Florida, for right-of-way infrastructure improvements under the Venetian Islands Bid Package 13C; which change order includes: 1) construction work associated with six (6) new stormwater pump stations that meet the City' enhanced stormwater criteria, in the not-to-exceed amount of $12,257,864, 2) a time extension of 365 calendar days required to complete the scope of work within San Marino, Dilido and Rivo Alto Islands; and 3) an increase to the owner's contingency of $1,225,787; all for a total change order of$13,483,651. PASSED AND ADOPTED this /5 day of _Jun047 , 2016 , SAV Philip L '".r-;.- Mayor ATTEST: • . . At I ` 3 ����••••••m�l„„t�l� , t APPROVED AS TO 1 / FORM & LANGUAGE �;. P�- '� � �/ ,,, &FOR EXECUTION Raf.el E. Gra -ado, itr k ••. ���• 1 %.. 00 4 • ' 2.61/C ♦ * • ity Attorney..-, Dote :INCORP ORATED: T:\AGENDA\2016\Janus \CI I a iC.o\ITB ,: -12-Vin4tiiiislands ROW-Resoluti• .doc 4411,CH 2 '.;be 3 of 3 h-' ..%%o COMMISSION ITEM SUMMARY Condensed Title: A Resolution Of The Mayor And City Commission Of The City Of Miami Beach, Florida,Approving And Authorizing The City Manager To Execute Change Order No. 3 To The Construction Contract Between The City Of Miami Beach, Florida, And Lanzo Construction Co., Florida, For The Construction Of The City Of Miami Beach Right-Of-Way Infrastructure improvement Program, Venetian Islands Bid Package 13C(Project), Dated March 13,2013(The Contract);The Change Order includes: 1)Construction Work Associated With Six(6) New Stormwater Pump Stations That Meet The Enhanced Stormwater Criteria in The Not-To-Exceed Amount•Of$12,257,864 Plus Time Extension Of 365 Calendar Days Required To Complete This Work Within San Marino,Diiido And Rivo Alto Islands;And 2)increasing The Owner's Contingency in The Amount Of$1,225,787;The Resulting Amount Of$13,483,651 Will Be Added To The Construction Contract, Key Intended Outcome Supported: Build and maintain priority Infrastructure with full accountability. • Supporting Data(Surveys, Environmental Scan, etc.): The 2014 Customer Satisfaction Survey indicated that over 77%of residents rated recently completed capital improvement projects as"excellent"or"good". Item Summary/Recommendation: On March 1r,2013,pursuant to Invitation to Bid(ITB)No.49-11/12,for the Right-of-Way Infrastructure Improvement Program—Venetian Islands Bid Package 13C,the City Commission approved Resolution No:2013-28163,recommending the award of a construction contract to Lanzo Construction Co.Florida,(Lanzo)for a total construction cost of$11,373,491 including contingency. On February 12, 2014, the City Commission approved Resolution 2014-28491, recommending Change Order No. 1 to the construction contract with Lanzo,for a total of$215,085 including contingency. On February 12,2014, as recommended by the Mayor's Blue Ribbon Panel on Flooding and Sea Level Rise and the Flooding Mitigation Committee, the City Commission approved Resolution 2014-28499 to amend the City's Storm Water Management Master Plan.The new criteria required the Engineer of Record,Schwebke-Shiskin,&Associates(SS$■ )to revise the design.. SS&A completed their redesign and negotiations began with Lanzo.The City retained AECOM to assist in the Implementation of a citywide comprehensive flood management plan and to review stormwater-improvement-plans-prepared-by-the-City's-ConsultantsrBased-on-the- j-- comments issued by the City Engineer, SS&A was directed to again revise the stormwater drainage plans to meet the new criteria implemented by the City Engineer and AECOM. • Once the redesign was completed, CIP contacted the twelve property owners that reside adjacent to the six easements where the stormwater pump stations are proposed to be located. The residents expressed great concern on the visual impacts from the proposed structures and equipment components associated with the pump station installations. • On May 6,.2015,the City Commission adopted Resolution No.2015-29022•approving Change Order No.2 to the construction contract with Lanzo,for the drainage conveyance construction work associated with the enhanced stormwater criteria in the not-to-exceed amount of $4,499,103 Including contingency and a time extension of 422 calendar days. On September 16, 2015, the City met with residents and their representatives that reside adjacent to the proposed pump stations to • demonstrate the key improvements to the design in order to address the noted concerns brought to the City on April 1, 2015. SS&A enumerated each Item where Improvements were made to the current design showing reduction of overall panel height,removal of all raised • platforms and separation of electrical panels from adjoining property,to allow a buffer for landscape screening.The residents in attendance requested that the City of Miami Beach attempt to relocate the proposed pump stations to the Venetian Causeway Right-Of-Way. The Causeway is under the jurisdiction of the Miami-Dade Public Works Department. On October 8,2015,the City and members of the Venetian Neighborhood met with Miami-Dade County Public Works staff to determine if installing the stormwater pumps along the Venetian Causeway would be a viable solution. The City and Miami-Dade Public Works staff discussed various options and concluded that the placement of several pump stations and related appurtenances and piping on the Venetian Causeway would require extensive due diligence, relocation of a multitude of utilities and could have significant structural impact on the • bridge abutments. At the City's direction, SS&A analyzed four alternative solutions for the placement of the pump systems along with equipment and components to discharge the stormwater to the bay and a fifth alternative to maintain the stormwater drainage system as a gravity discharge (if none of the four alternatives were chosen). However, we do not believe there is currently a viable alignment for the proposed improvements on the Venetian Causeway The recommended alternative is the installation of six pump stations at the existing street-end easements.This alternative remains the most viable because it Is the most cost effective,is the current design,it would take the shortest time for completion,is best engineering practice to locate the pump station as close to the discharge point as possible,and it meets the enhanced stormwater criteria.As such, Lanzo has presented a proposal for Change Order No.3 at a cost of$12,257;864, plus 10%contingency$1,225,787,for a total price of$13,483,651 and a time extension of 365 days beyond the current project completion date of March 1, 2016. After numerous cost reviews and negotiations,SS&A and the administration have found the proposal acceptable and recommend approval of the change order. The Administration recommends approval of the resolution. Advisory Board Recommendation:N/A Financial Information: Source o f Funds: M Y 0 ,, :i l '\,,r1r 1F I 44)513;358 otnt,.., .:s&..1' ,'4s.3?-s2,.`.•2.;s1'�.2 7:,v40:6ne 9.r 3 5k78•-t.�.o rrttn.:w:. a.t;e'..r..B"...o..nt.dr:sARCCeOsoU,tNito,•'.. :2 0 1,5289.8B • t\) $ 11;633,285 Stormwater Master Plan Program • OBPI ' ' 'Yo tai:.:;:: $ 13,483,651 Financial Impact Summary:N/A City Clerk's Office Legislative Tracking: Sign Offs: :'1,':::1)e-Part ,11 .-. Department IIr.: tor DM A,1 ETC L.; ' - !:Teik T:VIGENDAl20181JanuarylClPlLanzo C.OUTB 49.11-12-Venetian Islands ROW-Summary.doox AGENDA 1TEM IR-7 C-- MIAMi A DATE f y A t 3yz rtH fiI City of Miami Beach, 1700 Convention Center Drive,Miami Beach, Florida 33139,www.miamibeachfl.gov COMMISSION MEMORANDUM TO: Mayor Philip Levine and Members o the City C,t'mmission FROM: Jimmy L. Morales, City Manager --- DATE: January 13, 2016 SUBJECT: A RESOLUTION OF THE MAY■ R AND CITY COMMISSION OF THE CITY OF MIAMI BEACH, FLORI A, APPROVING AND AUTHORIZING THE CITY MANAGER TO EXECUTE CHANGE ORDER NO. 3 TO THE CONSTRUCTION CONTRACT BETWEEN THE CITY OF MIAMI BEACH, FLORIDA, AND LANZO CONSTRUCTION CO., FLORIDA, FOR THE CONSTRUCTION OF THE CITY OF MIAMI BEACH RIGHT- OF-WAY INFRASTRUCTURE IMPROVEMENT PROGRAM, VENETIAN ISLANDS BID PACKAGE 13C (PROJECT), DATED MARCH 13, 2013 (THE CONTRACT); THE CHANGE ORDER INCLUDES: 1) CONSTRUCTION WORK ASSOCIATED WITH SIX NEW STORMWATER PUMP STATIONS THAT MEET THE ENHANCED STORMWATER CRITERIA IN THE NOT-TO-EXCEED AMOUNT OF $12,257,864 PLUS TIME EXTENSION OF 365 CALENDAR DAYS REQUIRED TO COMPLETE THIS WORK WITHIN SAN MARINO, DILIDO AND RIVO ALTO ISLANDS; AND 2) INCREASING THE OWNER'S CONTINGENCY IN THE AMOUNT OF $1,225,787; THE RESULTING AMOUNT OF $13,483,651 WILL BE ADDED TO THE CONSTRUCTION CONTRACT. ADMINISTRATION RECOMMENDATION The Administration recommends adopting the Resolution. KEY INTENDED OUTCOME Build and maintain priority infrastructure with full accountability. FUNDING $ 1,950,366 Stormwater Bonds Reso No. 2015-28988 $ 11,533,285 Stormwater Master Plan Program $ 13,483,651_ Total Change Order No.3 to Lanzo Construction Co.,for Venetian Islands project-Memorandum January 13,2016 Page 2 Of 5 BACKGROUND On March 13th, 2013, pursuant to Invitation to Bid (ITB) No. 49-11/12, for the Right-of- Way Infrastructure Improvement Program —Venetian Islands Bid Package 13C, the City Commission approved Resolution No. 2013-28163, recommending the award of a construction contract to Lanzo Construction Co. Florida, (Lanzo) in the amount of $11,373,491 including contingency. On February 12, 2014, the City Commission approved Resolution 2014-28491, recommending Change Order No. 1 to the construction contract with Lanzo, for a total of $215,085 including contingency. On February 12, 2014, as recommended by the Mayor's Blue Ribbon Panel on Flooding and Sea Level Rise and the Flooding Mitigation Committee, the City Commission approved Resolution 2014-28499 to amend the City's Storm Water Management Master Plan. The Public Works Department (PWD) requested that staff implement the enhanced stormwater system criteria. The new criteria required the Engineer of Record, Schwebke-Shiskin & Associates (SS&A) to revise the design. SS&A completed their redesign and negotiations began taking place with Lanzo. The City retained AECOM to assist in the implementation of a citywide comprehensive flood management plan and to review stormwater improvement plans prepared by the City's Consultants. Based on the comments issued by the City Engineer and AECOM, SS&A was directed to again revise the stormwater drainage plans to meet the new criteria implemented by the City Engineer. On February 18, 2015, SS&A responded to additional comments issued by AECOM and finalized the enhanced stormwater drainage design modifications and on February 23, 2015, they submitted the 100% documents to PWD for final review. Once the redesign was completed, the Office of Capital Improvement Projects (CIP) contacted the twelve property owners that reside adjacent to the six easements where the stormwater pump stations are proposed to be located. The meetings with residents took place from February through March 2015. The residents expressed great concern on the visual impacts from the proposed structures and equipment components associated with the pump station installations. As a result, on April 1, 2015, a meeting was held with the concerned residents, their legal counsel, and staff from CIP, PWD, the City Attorney's Office and the City Manager's Office. It was determined that the City administration would explore alternatives attempting to minimize the visual impact of the stormwater pump stations and related components. On May 6, 2015, the City Commission adopted Resolution No. 2015-29022 approving Change Order No. 2 to the construction contract with Lanzo, for the drainage conveyance construction work associated with the enhanced stormwater criteria in the not-to-exceed amount of $4,499,103 including contingency and a time extension of 422 calendar days. ANALYSIS and to minimize potential cost In order to enable the 'ro'ect to achieve full completion p p J impacts on the project, this change order will capture all the necessary infrastructure components to fully complete the stormwater drainage system on the Venetian Islands Change Order No. 3 to Lanzo Construction Co.,for Venetian Islands project-Memorandum January 13,2016 Page 3 Of 5 Neighborhood. The scope of work, for this change order includes; six pump stations with all associated pipes, structures and electrical control panels to each pump station. On September 16, 2015, the City met with residents and their representatives that reside adjacent to the proposed pump stations to demonstrate'the key improvements to the design in order to address the noted concerns brought to the City on April 1, 2015. SS&A enumerated each item where improvements were made to the current design showing reduction of overall panel height, removal of all raised platforms and separation of electrical panels from adjoining property, to allow a buffer for landscape screening. The residents in attendance requested that the City of Miami Beach attempt to relocate the proposed pump stations to the Venetian Causeway Right-Of-Way. The Causeway is under the jurisdiction of the Miami-Dade Public Works Department. On October 8, 2015, the City and members of the Venetian Neighborhood met with Miami-Dade County Public Works staff to determine if installing the stormwater pumps along the Venetian Causeway would be a viable solution. The City and Miami-Dade Public Works staff discussed various options and concluded that the placement of several pump stations and related appurtenances and piping on the Venetian Causeway would require extensive due diligence, relocation of a multitude of utilities and could have significant structural impact on the bridge abutments. At the City's direction, SS&A analyzed four alternative solutions for the placement of the pump systems along with equipment and components to discharge the stormwater to the bay and a fifth alternative to maintain the stormwater drainage system as a gravity discharge (if none of the four alternatives were chosen). Description of each alternative is as follows: Alternative No.1 Install six Pump Stations at the existing street-end easements, as per plans submitted to PWD on August 2015; at a cost of $12,257,864, plus 10% contingency $1,225,787, for a total price of $13,483,651, including a construction time extension of twelve months beyond the current project completion date of March 1, 2016. Alternative No. 2 Install six Pump Stations within the Right-of-Way (ROW) at the Terraces nearest the street-ends and discharge the stormwater runoff to the Bay at the current outfall locations, i.e. at the street-ends. The width of the ROW for both San Marino and Dilido Drives (Terraces) is 55', with roadway widths of 22' and 26' respectively. The width of the ROW for Rivo Alto Drive (Terrace) is 75'. The roadway consists of a 13' center median strip and two 15' roadways. SS&A has estimated an Order of Magnitude Cost of $14,959,000, plus 10% contingency $1,496,000, for a total price of $16,455,000. The estimate includes construction, re-design and construction administration (6 months for design and permitting and 2 additional months of construction time). The overall impact on the contract schedule will be extended by twenty months beyond March 1, 2016. Alternative No. 3 Install six Pump Stations within the ROW at the Terraces nearest the street-ends and discharge the stormwater runoff to the Bay at the Venetian Causeway and maintain the gravity overflow at the street-ends, although we do not believe there is currently a viable alignment for the proposed improvements on the Venetian Causeway. SS&A has estimated an Order of Magnitude Cost of $18,047,000, plus 10% contingency Change Order No.3 to Lanzo Construction Co.,for Venetian Islands project-Memorandum January 13,2016 Page 4 Of 5 $1,805,000, for a total price of $19,852,000. The estimate includes construction, re- design and construction administration (8 months for design and permitting and 3 additional months of construction time). The overall impact on the contract schedule will be twenty-three (23) months beyond March 1, 2016. Alternative No. 4 Install three large pump stations (one per island) on the Venetian Causeway ROW and discharge to the bay, although we do not believe there is currently a viable alignment for the proposed improvements on the Venetian Causeway. SS&A has estimated an Order of Magnitude Cost of $19,469,000, plus 10% contingency $1,947,000, for a total price of $21,416,000. The estimate includes construction, re- design and construction administration (6 months for design and permitting and 8 additional months of construction time). The overall impact on the contract schedule will be twenty- six months beyond March 1, 2016. Alternative No. 5 If none of the alternatives above are plausible in the immediate future, and in order to complete the project with the current contractor, this would require eliminating the Pump Stations' scope from the current project, and modifying the current stormwater conveyance system to a gravity discharge through new outfalls located on the street- ends. This will avoid potential cost impacts for demobilizing and remobilizing due to delays on the approval of the pump stations. However, this conversion will not meet the City's enhanced storm water management criteria. The gravity discharge system will allow the pump stations to be interconnected to the system in the future once a resolution on their location is achieved. SS&A has estimated an Order of Magnitude Cost of $1,443,000, plus 10% contingency $144,300, for a total price of$1,587,300. Price includes construction, re- design and construction administration (3 months for design and permitting and 6 additional months of construction time). The project time extension for this alternative is nine months beyond March 1, 2016. In light of the presented analyses, Alternative No. 1 (current design) remains the most viable, because it is the most cost effective, it is the current design, it would take the shortest time for completion, it is best engineering practice to locate the pump station as close to the discharge point as possible, and it meets the enhanced stormwater criteria. As such, Lanzo has presented a proposal for change order No.3, (Attachment A) that addresses the following: • Additional scope relating to six new storm water pump station installations to comply with the City's enhanced storm water criteria. This includes allowances to provide adequate pre-treatment to each pump station. The selected pump manufacturer will be Flygt, which is the preferred supplier of PWD-Operations. • Exercising the provision of Article 38.1.1 of their contract with the City of Miami Beach that allows for the adjustment of unit prices from the original contract wherever the unit quantities are adjusted in excess of 20% of the original amount. • Effects of imposed weight restrictions on the Venetian Causeway bridges. • Time extension of 365 days. Change Order No.3 to Lanzo Construction Co.,for Venetian Islands project-Memorandum January 13,2016 Page 5 Of 5 The resulting costs are as follows: • Pump Stations $ 12,125,260 • Bridge Weight Restriction Cost Impact $ 82,977 • Unit quantities greater than 20% $ 49,627 Sub-Total $ 12,257,864 • Contingency at 10% $ 1,225,787 Grand Total $ 13,483,651 Based on the numerous cost reviews and negotiation sessions throughout the development of the design of these revised storm water improvements, over the last several months and the examination of supporting documentation presented by Lanzo, SS&A and the administration has found the proposal acceptable and recommends approval of the change order (Attachment B). Currently the project is scheduled for final completion on March 1, 2016. Adding the necessary time for pump manufacturing and installation of the remaining related appurtenances, the revised final project completion will be March 2017. During the adoption of the FY 2015/16 Capital Budget, a new programmatic approach for managing bond proceeds for capital projects in the Stormwater and Water & Sewer funds was instituted. The new approach creates a system-wide master program for each fund. The overall budget control for these funds will be in the master programs. Whenever a contract is awarded for a project during the fiscal year, an administrative budget amendment will be processed to move the necessary amount of funding from the master program to the individual project budget. The necessary budget amendments will not need to be approved by Commission, but will reflect any contracts awarded by Commission for these funds. This approach will maintain maximum flexibility while facilitating the timely spending of bond funds. This $13,483,651 change order is being funded by $1,950,366 from previously appropriated funding and $11,533,285 from the Stormwater Master Plan Program. The acceptance of this $11,533,285 for the Venetian Island project reduces the available stormwater bond funds from $60,266,296 to $48,733,011. The total amount of the contract with Lanzo, should this change order No.3 be approved, would be $29,571,330. CONCLUSION The Administration recommends approval of the Resolution. ATTACHMENTS: Attachment A - Lanzo Construction change order proposal Attachment B - SS&A— Redesign proposal analysis letter JLM\ETC\DM T:\AGENDA\2016\January\CIP\Venetian Islands\Venetian Islands.CO 3.Memo.docx ATTACHMENT A it- L .,. . L , COMPANIES Building and restoring sustainable Infrastructure to support the needs of our commUnitles I • September 17,2015 s L.iusieon `,Aisistan' iii president Schwebke-Shiskin.ez Associates,Inc, 3240 Corporate Way - . Miramar,FL 33025 Re: Venetian islands Bid Package 1 3 C—ITB No.49-11/12—Change Order No.3 Proposal— Revised Pump Stations Price Dear Mr.Leon, The purpose of this letter is to present,the cost to install the proposed six(6)pump stations as noted in the plans received.on 08/31/2015,along with the remaining items to fully complete the Venetian .. Islands,Neighborhood 13"C",project. As requested,here are the options using three different pump .... ,... .... L......-manufac ttuers:,...... ............w._....._....._.......-_..._.�.-. �_ __._.�� ___,.._.- �..... _.-....___..........._.._..._.�._._._....—..__.�W... • Exhibit A,using FLYGT pumps,for a total of$12,257,863.17 • Exhibit B,using WILO pumps,for a total of$11,625,446.11 • Exhibit C,.rising ABS pumps,for a total of$11,440,665.28 Please,note that in an effort to simplify and speed up the review process,Lanzo has decided to honor most of the unit prices given earlier this year. Should you have any questions,.please,refer to the information already given. Also,based on the information received from each of the requested pump manufacturers,and considering a notice to proceed of October 14th,here,is these .pected.time extension required; . • Using FLYGT or ABS pumps,the time extension required to the current.contract time is of exactly 12 months,365 calendar days,with a final completion date of 03-01-17. The current final completion is 03-01-16. - . 6 ..Llaing... ILO.:pumps,..the.:time.extension-required to the:eurientocontiact,tune I;.&14..months, 418 calendar days,,with a final completion date of 04-23-17. The current final completion is 0.3-01-16.. Lanzo reserves the right to withdraw the proposal for the remaining,work if not accepted and received formally within thirty(30)days. In the event the scope of work is changed by the owner or .Beach,FL 3 139 Phone 305 548-878-5 Fax.786)476-0368 407.�,inoal►j Road,Suite 1 OR,Miami 3 ( ) � www.tanzo.net by the municipality,,or municipalities involved,Lanzo reserves the right to review and approve any changes prior'to inclusion to this proposal,: Should you have any questions,comments,and/or jl concerns,please,do not hesitate to contact us. Respectfully, LANZO CONSTRUCTION CO.,FL 1.1-44,1tr4L Pablo C.Rial"io Project Manager CC:DI rk Toupczyk,.i',G.,City of Mlalh113each C1P(via e-mail) . _.._.___.__..____...----_._._.�.� �__,...��ula n Ltnn;P:B:;fibhwebkvShl akin-8nkatuclaws.-ina-(via-c=mail)' — _. • • • ((1. 407 Lincoln ROW,Suite 10R,Miami Beach,FL 33139 Phone(3.05)548-8785 Fax(786)476-0368 !. www,lanzo.net - s LANZO CONSTRUCTION CO.,FLORIDA 09/17/18 Venetian Islands,Neighborhood 13"C" REVISED PUMP STATION PRICES ITB 49-11/12 FLYGHT PUMPS City of Miami Beach . , I DESCRIPTION•• QUANTITI(• UNIT Unit Price .Total-Price• •; Division 2-Sltework General Conditions 1 LS $298,972.27 $298,972.27 FURNISH ANS INSTALL SUITABLE BACKFILL MATERIAL 300 CY $37.00 $11,100.00 PLUG EXISTING OUTFALL(ALL SIZES) 6 EA $1,631.86 $9,791.16 24"A2000 456 LF $121,48 $55,394.88 ,• 30"A2000 834 LF $98.02 $81,748.68 36"A2000 • 774 LF $181.83 $140,736,42 42"PP 209 LF $356.37' $74,481,33 48 PP 50 LF $595.53 $29,776,50 20"DIP 384 LF $270.26 $103,779.84 24"DIP • 275 LF • $330.52 $90,893,00 34X53 RCP 98 LF $239.56 $23,476.88. .. . ._-----.W.,..._•g8X60-RCP°. ... ..-. .....- 108—..----- LF-•-. .._.._....-....-$2.66,87 --•$28,821.•96._._.... _— • MANHOLE(TYPE"C"84°DIA) 1 EA $10,369.82 $10,369.82 MANHOLE(TYPE"C"60"DIA) 1 EA •$4,061.90 $4,061.90 INLET(TYPE"C"72"DIA) 1 EA $7,505.47 $7,505.47 96"X 120"DISSIPATOR BOXES 6 EA $74,250.00 $445,500,00 108"X 120"RECTANGULAR GRATE BOX STRUCTURE 6 EA $43,114.95 $258,689.70 96"ROUND(CDS ROUND WATER QUALITY UNIT,SAN MARINO) . 4 EA $85,54930 $342,198.00 • • 120"ROUND(CDS ROUND WATER QUAUTY UNIT,DILIDO&RIVO ALTO) 8 EA $99,850.05 $798,800.40 CORE DRILL EXISTING SEA WALL AND INSTALL NEW OUTFALL CULVERT 12 EA $3,795,00 $45,540.00 • INSTALL MANATEE GRATES 6 EA $1,900.00 $11,400.00 • STORMWATER PUMP STATIONS(SAN MARINO)INCLUDING WET WELLS, • VALVE VAULTS,CONTROL PANEL SLABS AND ELECTRICAL CONTROLS WITH ALL OF THEIR APPERTENANCES,INCLUDING BUT NOT LIMITED TO, - PUMPS,VFD'S,TAP BOXES,FLOATS,CABLES,CONDUITS,MOUNTING POSTS,PANELS,LIGHTNING ARRESTORS,GROUND RODS,HANDRAILS, STAIRS,HATCHES,ETC. 2 EA $1,485,269.60 $2,970,539.20 STORMWATER PUMP STATIONS(DILIDO)INCLUDING WET WELLS,VALVE VAULTS,CONTROL PANEL SLABS AND ELECTRICAL CONTROLS WITH ALL • OF THEIR APPERTENANCES,INCLUDING BUT NOT LIMITED TO,PUMPS, VFD'S,TAP BOXES,FLOATS,CABLES,CONDUITS,MOUNTING POSTS, PANELS,LIGHTNING ARRESTORS,GROUND RODS,HANDRAILS,STAIRS, HATCHES,ETC. 2 EA $1,667,574.50 $3,335,149.00 1 STORMWATER PUMP STATIONS(RIVO ALTO)INCLUDING WET WELLS, VALVE VAULTS,CONTROL PANEL SLABS AND ELECTRICAL CONTROLS WITH ALL OF THEIR APPERTENANCES,INCLUDING BUT NOT LIMITED TO, PUMPS,VFD'S,TAP BOXES,FLOATS,CABLES,CONDUITS,MOUNTING POSTS,PANELS,LIGHTNING ARRESTORS,GROUND RODS,HANDRAILS, • STAIRS,HATCHES,ETC. 2 EA $1,438,190.33 $2,876,380.66 • TURF BLOCKS (24"X 16"BLOCK) 8100 EA $3,06 $24,786.00 INLINE TIDE FLEX VALVES 6 EA $17,626.52 $105,759.12 2.1N WATER SERVICE(WET TAP).1"RPZ&HOSE BIB ASSEMBLY 6 EA $3,701.83 $22,210,98 Ailowance:`Wstoratiorrat OUtfa11iOW 1 LS • 50;O110:130 IS0;1)09:120 TOTAL: $12,257,863.17 • Exhibit"A"-FLGHT PUMPS LANZO CONSTRUCTION CO.,FLORIDA 09/17/15 Venetian Islands,Neighborhood 13"C" REVISED PUMP STATION PRICES 1T8 4941/12 WILD PUMPS City of Miami Beach •DESCRIPTION I. ' . , - QUANTITY UNIT. Unit Price Total Price'• • Division 2-Sltework General Conditions 1 L5. $283,547,47 $283,547.47 FURNISH ANS INSTALL SUITABLE BACKFILL MATERIAL 300 CY $37,00 $11,100.00 PLUG EXISTING OUTFALL(ALL SIZES) 6 EA $1,631.86 $9,791.16 24"A2000 456 LF $121.48 $55,394.88 30"A2000 834 LF $98.02 $81,748.68 36"A2000 774 LF $181.83 $140,736.42 • 42"PP 209 LF $356.37 $74,481.33 48 PP 50 LF $595.53 $29,776.50 20"DIP 384 LF $270.26 $103,779.84 24"DIP .275 . LF,. $330.52 . $90,893.00 34X53 RCP 98 LF $239.56 $23,476.88 _ - .33XE R P 198 _. LF ..._._ _...... .$ 87. ..e.,..... ... .. $28,821.96...-..., -- MANHOLE(TYPE"C"84"DIA) 1 EA $10,369.82 $10,369.82 MANHOLE(TYPE."C"60"DIA) 1 EA $4,061.90 $4,061.90 INLET(TYPE"C"72"DIA) 1 EA $7,505.47 $7,505.47 96"X 120"DISSIPATOR BOXES 6 EA $74,250.00 $445,500.00 108"X 120"RECTANGULAR GRATE BOX STRUCTURE 6 EA $43,114,95 $258,689.70 96"ROUND(CDS ROUND WATER QUALITY UNIT,SAN MARINO) . , .. - 4 .. .EA...- . $85,549,50 . $342,198.00 120"ROUND(CDS ROUND WATER QUALITY UNIT,DILIDO&RIVO ALTO) 8 EA $99,850.05 $798,800,40 CORE DRILL EXISTING SEA WALL AND INSTALL NEW OUTFALL CULVERT 12 EA $3,795.00 $45,540.00 INSTALL MANATEE GRATES 6 EA $1,900.00 $11,400.00 STORMWATER PUMP STATIONS(SAN MARINO)INCLUDING WET WELLS,VALVE VAULTS,CONTROL PANEL SLABS AND ELECTRICAL CONTROLS WITH ALL OF THEIR APPERTENANCES,.INCLUDING BUT NOT LIMITED TO,PUMPS,VFD'S,TAP BOXES,FLOATS,CABLES, - - --- CONDUITS,MOUNTING POSTS,PANELS,LIGHTNING ARRESTORS, GROUND RODS,HANDRAILS,STAIRS,HATCHES,ETC. 2 EA. • $1,389,028.40 $2,778,056,80 STORMWATER PUMP STATIONS(DILIDO)INCLUDING WET WELLS, VALVE VAULTS,CONTROL PANEL SLABS AND ELECTRICAL CONTROLS WITH ALL OF THEIR APPERTENANCES,INCLUDING BUT NOT LIMITED TO,PUMPS,VFD'S,TAP BOXES,FLOATS,CABLES,CONDUITS, MOUNTING POSTS,PANELS,LIGHTNING ARRESTORS,GROUND RODS,HANDRAILS,STAIRS,HATCHES,ETC. 2 EA $1,554,988.35 $3,109,976.70 STORMWATER PUMP STATIONS(RIVO ALTO)INCLUDING WET WELLS,VALVE VAULTS,CONTROL PANEL SLABS AND ELECTRICAL CONTROLS WITH ALL OF THEIR APPERTENANCES,INCLUDING BUT NOT LIMITED TO,PUMPS,VFD'S,TAP BOXES,FLOATS,CABLES, CONDUITS,MOUNTING POSTS,PANELS,LIGHTNING ARRESTORS, GROUND RODS,HANDRAILS,STAIRS,HATCHES,ETC. 2 EA $1,338,521.55 $2,677,043.10 TURF BLOCKS (24"X 16"BLOCK) 8100 EA $3.06 $24,786.00 INLINE TIDE FLEX VALVES 6 EA $17,626.52 $105,759.12 2-IN WATER SERVICE(WET TAP)1"RPZ&HOSE BIB ASSEMBLY 6 EA $3,701.83 $22,210.98 Allowance;Restoration at Outfall ROW 1 L5 $50,000.00 $50,000.00 TOTAL: $11,625,446.11 Exhibit"B"-WILD PUMPS 1 , . LANZO CONSTRUCTION CO.,FLORIDA 09/17/15 Venetian Islands,Neighborhood 13"C" REVISED PUMP STATION.PRICES ITS 49-11/12 ABS PUMPS City.of Miami Beach • DESCRIPTION` ,,• • '. :r " '-4 • , .QUANTITY .UNIT • Unit Price • Total-Price ' Division'2-Sitework General Conditions 1 l5 $279,040.62 $279,040.62 FURNISH ANS INSTALL SUITABLE BACKFILL MATERIAL 300 CY $37.00 $11,100.00 PLUG EXISTING OUTFALL(ALL SIZES) 6 EA $1,631.86 $9,791.16 24"A2000 456 LF $121.48 $55,394.88 30"A2000 834 LF $98.02 $81,748.68 • 36"A2000 774 LF $181.83 $140,736.42 42"PP 209 LF $356.37 $74,481.33 48 PP • 50 LF $595.53 $29,776.50 20"DIP 384 IF $270.26 $103,779.84 24"DIP . , . . . 275 LF $330.52 $90,893.00 34X53 RCP 98 LF $239.56 $23,476.88 . . . ......... 3AX6Q_CP - ..- - aQ8 LF 5266.87 $28.021.96 ---- . 8 82 MANHOLE(TYPE"C"84"DIA) 1 ' EA $10,369.82 $10,369.82 MANHOLE(TYPE"C"60"DIA) 1 EA $4,061.90 $4,061.90 INLET(TYPE"C"72"DIA) 1 EA $7,505.47 $7,505.47 • 96"X 120"DISSIPATOR BOXES 6 EA $74,250.00 $445,500.00 • 108"X120"RECTANGULAR GRATE BOX STRUCTURE 6 EA $43,114.95 $258,689.70 96"ROUND(COS ROUND WATER QUALITY UNIT,SAN MARINO) 4 EA $85,549.50 $342,198.00 120"ROUND(CDS ROUND WATER QUALITY UNIT,DILIDO&RIVO ALTO) 8 EA $99,850.05 $798,800.40 CORE DRILL EXISTING SEA WALL AND INSTALL NEW OUTFALL CULVERT 12 EA $3,795.00 $45,540.00 INSTALL MANATEE GRATES 6 EA $1,900.00 $11,400.00 STORMWATER PUMP STATIONS(SAN MARINO)INCLUDING WET WELLS,VALVE VAULTS,CONTROL PANEL SLABS.AND ELECTRICAL CONTROLS WITH ALL OF THEIR APPERTENANCES,INCLUDING BUT NOT LIMITED TO,PUMPS,VFD'S,TAP BOXES,FLOATS,CABLES, - -- - • -- ----- -- -- CONDUITS,MOUNTING POSTS,PANELS,LIGHTNING ARRESTORS, • GROUND RODS,HANDRAILS,STAIRS,HATCHES,ETC. 2 EA $1,264,578.85 $2,529,157.70 STORMWATER PUMP STATIONS(DILIDO)INCLUDING WET WELLS, VALVE VAULTS,CONTROL PANEL SLABS AND ELECTRICAL CONTROLS • WITH ALL OF THEIR APPERTENANCES,INCLUDING BUT NOT LIMITED TO,PUMPS,VFD'S,TAP BOXES,FLOATS,CABLES,CONDUITS, MOUNTING POSTS,PANELS,LIGHTNING ARRESTORS,GROUND RODS,HANDRAILS,STAIRS,HATCHES,ETC. 2 EA $1,665,775.33 $3,331,550.66 STORMWATER PUMP STATIONS(RIVO ALTO)INCLUDING WET WELLS,VALVE VAULTS,CONTROL PANEL SLABS AND ELECTRICAL • CONTROLS WITH ALL OF THEIR APPERTENANCES,INCLUDING BUT NOT LIMITED TO,PUMPS,VFD'S,TAP BOXES,FLOATS,CABLES, CONDUITS,MOUNTING POSTS,PANELS,LIGHTNING ARRESTORS, GROUND RODS,HANDRAILS,STAIRS,HATCHES,ETC. 2 EA $1,262,047.13 $2,524,094.26 TURF BLOCKS (24"X 16"BLOCK) 8100 EA $3.06 $24,786.00 INLINE TIDE FLEX VALVES 6 EA $17;626.52 $105,759.12 2-IN WATER SERVICE(WET TAP)1"RPZ&HOSE BIB ASSEMBLY 6 EA $3,701.83 $22,210:98 Allowance;Restoration at Outfall ROW 1 LS $50,000.00 $50,000.00 TOTAL: $11,440,665.28 Exhibit"C"-ABS PUMPS . ATTACHMENT B _ScAw-ES E-S'Lkir2 & vg1.s:oeiaLEl,ine. . • Principals Civil Engineers-Land Planners-Surveyors • Luis F.Leon,P.E. Hernando J.Navas,P.E. Alberto A.More,P.E. Mark S.Johnson,P.S.M. 3240 Corporate Way•Miramar, Florida 33025 John C.Telco,P.E. • Phone:(954)435-7010•Fax:(954)438-3288 Ronald A.Fritz,P.S.M. Of Counsel • Raymond F.Mlelke,P.S.M. • Alfonso C.Telco,P.E.,P.S.M. Michael J.Alley,P.S.M. September 24,2015 Mr. David Martinez,P.E.,Director of CIP City of Miami Beach • Capital Improvement Projects Office : • • . •' 01-Meridian A enue;Suite 300 --- .�._ .. . _ _ _ ___.______.._.__.._.�.._— Miami Beach,Florida 33139 • Re: Venetian Island Neighborhood 13 BID Package "C"—Drainage Redesign Proposal Analysis(Pump Stations and Outfalls Only). . . . ... . .... .. .... ... ._. .. . . . ... .. .... .... ... . • Dear David, As requested,we have completed our review of the Change Order proposal provided by Lanzo Construction Company for a portion of the drainage improvements designed to comply with the City's sea level rise criteria. The portion of the drainage improvements in Lanzo's proposal includes.all ., drainage construction downstream of the designed,and including,the water quality units for each respective island. - .- • Based on the most recent information provided to us in a proposal by Lanzo Construction Company dated September 17,2015 and in summary of our review of the project costs: • • • • Total Stormwater Redesign Improvements(Pump Stations&Outfalls Only)= $12,125,259.76 Bridge Weight Restriction Cost Impact= $82,977.24 Unit quantity increases/decreases greater than 20%= $49,626.17 Original Contract Amount,including change orders= $15,678,669.13 • The change order proposal submitted by Lanzo Construction Company included a combination of Unit Price and Lump Sum values for change order work. • - Pursuant to Article 38,1.1 of the contract between the City of Miami Beach and Lanzo Construction Company(1TB 49-11/12)we found that unit prices from the original contract were used wherever the unit quantities did not exceed 20%of the original amount, However due to - ••••reeently-i nip esed weight•testrictionstn'theVenetian t'auseway Utinzo'Construetion.Company provided supporting documentation used to determine the additional cost of construction to comply with the regulated bridge weight restrictions, Based on the documentation provided,the weight restrictions on the Venetian Causeway require that the number of trips needed to import and export materials to and from the project be increased to transport the mentioned materials in ' lighter loads,•We find that the documentation provided clearly defines the impacts of the bridge loading restrictions,however,please note that the change order proposal and supporting documentation provided by Lanzo Construction Company was not independently verified by this • • Mr.David Martinez,P.E. September 24,20.15 Page 2 oft firm and that our firm does:not have information available on the pricing structure and comparison of Lanzo's truck capacities used in the original contract. As such,for our review of li the supporting documentation,we could only assume that the truck capacities used to.bid the project.were based on full truck loads as shown in the supporting documentation, - Pursuant to Article 38,7 of the contract between the City of Miami Beach and Lanzo Construction Company(ITB 49-11/12),where unit quantities increased or decreased more than 20%of the contracted quantities,we found.that Lanzo Construction Company adjusted unit prices based on. negotiated values. It is our.opinion,to the best of our knowledge,that the negotiated values of these items are within an acceptable value, • • • • Pursuant to Article 3.8,1:2 of the contract between the City of Miami Beach and Lanzo Constructions.Conan 1TB 49-:11/1.2 a change order for individual items proposed for Company� �� _..�_ . p p _ construction that were not included in the original bid.cctiments was provided; The proposal provided by Lanzo Construction Company included furnishing and installing FPL conduits,. transformer and pullboxes for the anticipated electrical systems needed for the pump stations. • Based on our review of the change order proposal for these items it is our understanding that a • coinponent for overhead and profit is Included and to the best of our knowledge it.:is our opinion that the unit prices for these item are within an acceptable value for the work proposed; I I . 1 1 1 • 1 consideration the unique Our review consisted of an independent cost analysis.while also taking into q circumstances regarding the bridge loading restrictions of the Venetian Causeway. Using these factors we determined that the cost proposed by Lanzo Construction.Company an acceptable value for the • proposed work, It is our understanding that the project duration is anticipated not to exceed 12 months from the date of that s t 'ons an otttfal(s. As such„.it is our understanding ..,,�,..• �,. ....�......_.._....._.,. Notice to Emceed eed fob_con�truct�on of�la@ pt m,p s ate..,�._....�........�,. w.,...__ .�..�.tl.�.....,......,.w...,.,_.w�..�...�g ..._..._�.,��.,�.. the total project duration shall be 365 days from last day of the modified contract date for the installation of the collection system(3/1/2016). Based on this duration,we find that the Final Completion date of the • • project shall'be March 1,2017. As always,if you have any questions;please contact the, • Respectfully subrrritted, .Scfiuretk&-.Sig2d. In 6-o ssoatates,Llna. L( z1sopE.• Assistant Vice'President Cti k:13253421 v1-sm-di•rn\dooumeiitsloutgoing\david martinez-cmbcip06.doo r •