LTC 054-2017 CIP Monthly Construction Projects UpdateMIAMIBEACH
OFFICE OF THE CITY MANAGER
NO. LTC# 054-2017 LETTER TO COMMISSION
TO: Mayor Philip Levine and Members of the City Com ission
.FROM: Jimmy L. Morales, City Manager
DATE: January 31, 2017
SUBJECT: CIP Monthly Construction Project Update
Below please find the monthly update for active City of Miami Beach construction projects under
the purview of the CIP Office.
Espanola Way Conversion
Scope: Conversion of Espanola Way into a pedestrian mall.
Status: Construction began August 2016. Project is 55% complete and scheduled for
completion March 2017.
Beach Lifeguard Towers Replacement
Scope: Construction of 35 lifeguard towers.
Status: Construction began March 2015. Thirteen towers have been completed and
placed at their permanent location. Two towers are currently in progress and are
scheduled for completion February 2017.
South Pointe Park Remediation — Water Feature
Scope: Construction of 4 new water features and plaza.
Status: Construction began January 2016. Project is 57% complete and scheduled for
completion April 2017.
Sunset Islands 3 & 4 Neighborhood Improvements
Scope: Sunset Islands 3 & 4 — Neighborhood improvement.
Status: Construction began June 2015. Project is 75% complete and scheduled for
completion summer 2017.
Venetian Islands Neighborhood Improvements
Scope: Neighborhood improvements on San Marino, Dilido and Rivo Alto Islands.
Status: Construction began May 2013. Project is 64% complete and scheduled for
completion spring 2017.
Central Bayshore South Neighborhood Improvements
Scope: Neighborhood improvements bounded by 34th St. to the north, Pine Tree Dr. to
the east, 28 St. to the south and Prairie Ave to the west and Meridian Ave from 28 St. to
Dade Blvd.
Status: Project design is 80% complete and construction of watermain is expected to
commence in February 2017 due to delays with permitting from Miami -Dade DERM.
Project is scheduled for completion January 2018.
Biscayne Point Island Entry
Scope: Beautification project of the neighborhood entryway to Biscayne Point Island.
Status: Construction began September 2016. Concrete curbs and sidewalks have been
completed. Project is 40% complete overall and scheduled for completion summer 2017.
Flamingo Park Restroom Facility
Scope: Demolition of existing restrooms and construction of a new restroom/office
building.
Status: Construction began June 2016. Project is 60% complete and scheduled for
substantial completion end of spring 2017.
Palm & Hibiscus Island Neighborhood Improvements
Scope: Neighborhood improvements on Palm and Hibiscus Islands.
Status: Construction began January 2016. Project is 37% complete and scheduled for
completion summer 2017.
JM/