LTC 123-2017 CIP Monthly Construction Projects UpdateOFFICE OF THE CITY MANAGER NO. LTC# 123 -2017 LETTER TO COMMISSION TO: Mayor Philip Levine and Members of he City Co j ission FROM: Jimmy L. Morales, City Manager DATE: March 3, 2017 SUBJECT: CIP Monthly Construction Project '+ Update Below please find the monthly update for active City of Miami Beach construction projects under the purview of the Office of Capital Improvement Projects. Allison Park Redesign Scope: Create a boundless ADA park with an accessible route from the play area and beach area to the existing restrooms building. Status: Construction began December 2016. Project is 10% complete and scheduled for completion June 2017. Beach Lifeguard Towers Replacement Scope: Construction of 35 lifeguard towers. Status: Construction began March 2015. Thirteen towers have been completed and placed at their permanent location. Two towers are currently in progress and are scheduled for completion March 2017. Seven more towers have been contracted and materials ordered and are scheduled for completion September 2017. Biscayne Point Island Entry Scope: Beautification project of the neighborhood entryway to Biscayne Point Island. Status: Construction began September 2016. Concrete curbs and sidewalks have been completed. Project is 43% complete overall and scheduled for completion summer 2017. Central Bayshore South Neighborhood Improvements Scope: Neighborhood improvements bounded by 34th St. to the north, Pine Tree Dr. to the east, 28 St. to the south and Prairie Ave to the west and Meridian Ave from 28 St. to Dade Blvd. Status: Water main design completed and construction is ongoing. Drainage design is currently at a 75 %, however the City is re- evaluating the impact of the proposed road elevations to the neighborhood homes. Espanola Way Conversion Scope: Conversion of Espanola Way into a pedestrian mall. Status: Construction began August 2016. Project is 70% complete and scheduled for substantial completion April 2017. Flamingo Park Restroom Facility Scope: Demolition of existing restrooms and construction of a new restroom /office building. Status: Construction began June 2016. Project is 75% complete and scheduled for substantial completion spring 2017. Kayak Launch Docks — Dickens & 73 Street Scope: Construction of kayak launch with accessible gangway and floating platform. Status: Construction began December 2016. Project is 5% complete and scheduled for completion April 2017. Muss Park Pavilion Scope: Demolition of the existing pavilion and the construction of a new pavilion. The new pavilion will be LEED Silver certified. Status: Construction began January 2017. Project is 7% complete and scheduled for completion August 2017. Palm & Hibiscus Island Neighborhood Improvements Scope: Neighborhood improvements on Palm and Hibiscus Islands. Status: Construction began January 2016. Project is 39% complete and scheduled for completion late summer 2017. South Pointe Drive Medians Uplighting Scope: Installation of uplighting at the South Pointe Drive medians. Status: Construction began March 2017. Project is scheduled for substantial completion May 2017. South Pointe Park Remediation — Water Feature Scope: Construction of 4 new water features and plaza. Status: Construction began January 2016. Project is 57% complete and scheduled for completion summer 2017. Stormwater Pump Station at 19th Street Scope: Installation of Stormwater Pump Station at 19th Street East of Meridian Avenue. Status: Currently 60% Design. City and Design - Builder are exploring options for alternate locations of the pump station site. Sunset Islands 3 & 4 Neighborhood Improvements Scope: Sunset Islands 3 & 4 — Neighborhood improvement. Status: Construction began June 2015. Project is 75% complete and scheduled for completion summer 2017. Venetian Islands Neighborhood Improvements Scope: Neighborhood improvements on San Marino, Dilido and Rivo Alto Islands. Status: Construction began May 2013. Project is 66% complete and scheduled for completion summer 2017. JM/