Nautilus Neighborhood ProjectNautilus Neighborhood Complete Streets Project
Phasing and Estimates
Reduced Phase I Components
Estimated Cost
Demonstration Projects
- Nautilus Drive /42nd Street/ Michigan Avenue Traffic
Circle
- Meridian Avenue and 42nd Street Intersection
Modification
- Meridian Avenue and 47th Street Intersection
Modification
$25,000
Reduce Speed Limit Neighborhood Wide to 25
MPH
$8,000
Implement Green Bicycle Lanes along Meridian
Avenue
$190,000
Perform Warrant Analysis for All -Way Stop at
Michigan Avenue and 46th Street
$5,000
Shift Stop Signs on 44th Street and Jefferson
Avenue to Jefferson Avenue
$7,500
TOTAL
$235,500
Other Improvements in Phase 1 (Received Strong Neighborhood Support)
Speed Tables
- Meridian Avenue
- Nautilus Drive
-47th Street
-46th Street
$120,000
Additional Phase 1 Improvements excluded from Phase
Traffic Circles
-44th Street and Adams Avenue
$40,000.00
-44th Street and Michigan Avenue
$40,000.00
-47th Street and Michigan Avenue
$40,000.00