2002-24797 Reso
RESOLUTION NO. 2002-24797
A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF
THE CITY OF MIAMI BEACH, FLORIDA, AUTHORIZING THE
APPROPRIATION OF FUNDS IN THE AMOUNT OF $650,000 FOR
THE REPLACEMENT OF EXISTING HANGERS SUPPORTING A
20-INCH WATER MAIN AT THE SOUTH SIDE OF THE EAST
MACARTHUR CAUSEWAY BRIDGE, REQUIRED AS A RESULT
OF EMERGENCY BRIDGE REHABILITATION WORK TO BE
CONSTRUCTED BY THE STATE OF FLORIDA DEPARTMENT OF
TRANSPORTATION; SAID FUNDS TO BE OBTAINED FROM FUND
425, WATER AND SEWER RETAINED EARNINGS.
WHEREAS, the Florida Department of Transportation (FDOT) will be repairing the
East Mac Arthur Causeway bridge to take care of structural deficiencies and to add additional
service years to its life; and
WHEREAS, the repairs require jacking of the bridge deck and girders; and
WHEREAS, the City has a 20 inch water main attached to the bridge deck system,
which was constructed in 1957; and
WHEREAS, the process of lifting the bridge deck will cause additional stresses in the
water main hangers, which due to their corroded condition, may fail during this operation;and
WHEREAS, it was evaluated that the replacement of the hangers, estimated at
approximately $650,000, must be completed prior to FDOT's commencement of the bridge
repairs; and
WHEREAS, such funds for the replacement of hangers are available from Fund 425,
Water & Sewer retained earnings.
NOW, THEREFORE, BE IT DULY RESOLVED BY THE MAYOR AND CI'IY
COMMISSION OF THE CIlY OF MIAMI BEACH, FLORIDA, the authorization to
appropriate funds in the amount of $650,000 for the replacement of existing hangers
supporting a 20.inch water main at the south side of the East Mac Arthur Causeway bridge.
~~p~
CIlY CLERK
APPROVED
FORM a LANG BE
a FOR EXECUTION
PASSED and ADOPTED this 20th day of
ATTEST:
~ !i.-a-or
F:\WORK\$ALL\VGK\COMMEMO\MacArthurR ~ ...
CITY OF MIAMI BEACH
COMMISSION ITEM SUMMARY
m
~
Condensed Title:
A Resolution authorizing the appropriation of funds in the amount of $650,000 for the replacement of
existing hangers supporting a 20-inch water main at the south side of the East Mac Arthur causeway
bridge,
Issue:
Shall funds in the amount of $650,000 be appropriated from fund 425 for the replacement of the water
main hangers on the east Mac Arthur Causeway bridge?
Item Summary/Recommendation:
The Florida Department of Transportation is planning an emergency bridge repair of the east Mac Arthur
Causeway bridge. The repairs require jacking of the bridge deck system, which supports the City's 20"
water main, The lifting of the bridge sections will cause higher than normal stresses on the water main
hangers, which due to their corroded condition may fail during the bridge jacking operation, Structural
failure of the support hangers will result in catastrophic collapse of the water main, therefore, the support
hangers must be replaced prior to the start of the emergency bridge repairs.
The Administration's recommendation is to appropriate funds in the amount of $650,000 from fund 425,
water and sewer retained earnings.
Advisory Board Recommendation:
I
Financial Information:
Amount to be expended:
~
Finance Dept.
Fund 425 Water & Sewer Retained
Earnin s
Source of
Funds:
F:\WORK\$ALLWGK\COMMEMO\CS- MacArthurWM.doc
AGENDA ITEM
DATE
c.7V
3-Jo -02-
CITY OF MIAMI BEACH
CITY HALL 1700 CONVENTION CENTER DRIVE MIAMI BEACH, FLORIDA 33139
www.ci.miami-beach.f1.us
m
~
COMMISSION MEMORANDUM
From:
Mayor David Dermer and Date: March 20, 2002
Members of the City Commission
Jorge M. Gonzalez ~ ~J
City Manager 0 ~ 0
A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY
OF MIAMI BEACH, FLORIDA, AUTHORIZING THE APPROPRIATION OF
FUNDS IN THE AMOUNT OF $650,000 FOR THE REPLACEMENT OF
EXISTING HANGERS SUPPORTING A 20-INCH WATER MAIN AT THE
SOUTH SIDE OF THE EAST MACARTHUR CAUSEWAY BRIDGE,
REQUIRED AS A RESULT OF EMERGENCY BRIDGE REHABILITATION
WORK TO BE CONSTRUCTED BY THE STATE OF FLORIDA
DEPARTMENT OF TRANSPORTATION; SAID FUNDS TO BE OBTAINED
FROM FUND 425, WATER AND SEWER RETAINED EARNINGS.
To:
Subject:
ADMINISTRATION RECOMMENDATION:
Adopt the Resolution.
MAL YSIS:
The East Mac Arthur causeway bridge constructed in 1957, has a 20 inch water main
running under the south side of the bridge and attached to it by metal hangers. The water
main, which was also installed around 1957-58. is the main water supply to the South
Beach area,
In August of 2001, the Florida Department of Transportation (FOOT) contacted the City to
inform us that an emergency bridge repair was needed to take care of structural
deficiencies. The work includes the replacement of all the expansion joints and steel span
bearings, and the repair of the bulkhead wall and fender system. The steel span bearings
are located in between the deck girders and the support pier bents. To replace the steel
span bearings, sections of the bridge will have to be jacked up at the supports. the old
bearings taken out, and new ones installed in their place.
The process of lifting the bridge deck will cause additional stresses in the water main
hangers (see photograph below), which due to their corroded condition, may fail during the
bridge jacking operation, Structural failure of the support hangers will result in catastrophic
collapse of the water main. therefore, the support hangers must be replaced prior to the
start of the emergency bridge repairs. The City has evaluated and prepared plans for the
replacement of these water main hangers. The replacement of the hangers should be
completed before the commencement of FOOT's project for the rehabilitation of the bridge.
I '
which is scheduled to begin in late October 2002. Construction is expected to be
completed within 4 to 5 months from then.
The work for the replacement of the hangers may require minimal traffic interruption. with
expected one-lane closures on the eastbound right lane, for short distances at the work
zone. During FOOT's work in October/November, the replacement of the expansion joints
will require closing two of the three existing lanes in each direction. The lane closures will
only occur at night, thus, minimizing the effects on the traffic. In addition, the lane closures
will not occur during the weekends during the heavy night traffic.
Marine traffic is not anticipated to be affected by the repair work below the bridge, as well
as the painting and replacement of the bearings. which will be performed from below the
bridge. The contractor is required to maintain a minimum horizontal distance to allow for
uninterrupted marine traffic.
The replacement of the 20" water main hangers is estimated to cost between $500,000 to
$650,000. The work will be performed by a contractor to be selected by competitive bidding
process.
Once the funds have been appropriated an invitation for bids will be issued for the
installati n of water main hangers.
South elevation of the East Mac Arthur bridge
Side view of East Mac Arthur Causeway bridge. showing the 20" water main and hangers
;
~: ,'\i~':;'