LTC 074-2018 Miami Beach Convention Center Project Update No. 22MIAMI BEACH City of Miami Beach, 1700 Convention Center Drive, Miami Beach, Florida 33139, www.miamibeachfl.gov OFFICE OF THE CITY MANAGER LTC # 074-2018 LETTER TO COMMISSION TO: Mayor Dan Gelber and Members o the City mmission FROM: Jimmy L. Morales, City Manage DATE: February 15, 2018 SUBJECT: Miami Beach Convention Cente Construction Project Update No. 22 The purpose of this LTC is to update the Mayor and City Commission on the Miami Beach Convention Center (MBCC) Renovation and Expansion Project. The financial information provided is through December 31, 2017. Project Dashboard is attached as Exhibit A and corresponding Budget Summary Breakdown is attached as Exhibit B. SCHEDULE UPDATE & PROJECT MILESTONES Construction of the project commenced in December 2015 and is 72% complete. Schedule A is a summary of remaining work. The MBCC building and adjoining streets and green spaces remain on schedule for a substantial completion target date of August 2018. The P-Iot Park is scheduled for completion by mid -2019 and the Carl Fisher Clubhouse will not be completed until mid -2019. For a more detailed update for the Carl Fisher and the P -lot Park refer to pages 3 and 4 of this report. Phase I East Lobby Renovation East Exhibition Halls North Loading Dock 21st Street Pump Station 2015T._ Schedule A 2016 1 2017 11 1.2 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 Phase II West Exhibition Halls -- �n West Concourse / Grand Lobby -- o 2nd Floor Grand Ballroom -- Convention Center Drive -- m Phase III <[ Rooftop Ballroom 10K s.f. Ballroom Kitchen -- 21st Street Park -- Building TCO -- Carl Fisher Clubhouse* Art Basel 2016 9 10 11 12 1 2 ` Phase IV P -Lot Park* `Separate Projects not under Clark's Contract. 2018 1 2019 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 Miami Beach Convention Center Monthly Construction Project Update No. 22 February 15, 2018 Page 2 of 5 Project Status / Events Since the load -out of the 2017 Art Basel show, the building will remain closed for construction until the recommencement of two -hall events in mid-March. There will be a total of six two -hall events, with entrance from Washington Avenue, during 2018. The Tissue World event is scheduled for load -in on March 17th, followed by 4 two -hall events in the month of April, and two more events over the summer. 2018 Construction Completion Plan With approximately six months remaining, the project team is looking towards substantial completion and working on completing areas of the building and turning them over to the City and building operator. In order to accomplish this goal, the flow of work has commenced in the southeast corner of the building, north through the halls and the east concourse to the north addition, continuing down to the new west concourse and south addition and will be finishing in the new 10,000 sf kitchen in the northwest addition. Additional Funding for Hurricane Irma and August 1 "Rain Bomb" Impacts On December 13,, 2017 the City Commission adopted resolution no. 2017-30119 approving a fourth amendment to the RDA agreement with Miami -Dade County to provide additional funding in the amount of $6,914,221 from excess RDA trust fund revenues to pay for costs associated with impacts resulting from Hurricane Irma and from the August 1 rain bomb event. The item is pending Miami -Dade County approval. 2018 Building Substantial Completion The project is currently scheduled to be substantially completed by no later than August 23, 2018. The first 4 -Hall event of 2018 will be the American Health Information Management Systems Association (ANIMA) Convention scheduled for September 23, 2018. P -Lot Park Revision On July 26, 2017 the City Commission adopted resolution 2017-29964 approving a revised concept design for the urban park to replace the existing surface parking lot known as the preferred parking lot, or P -Lot. The revised design needed to include an open area large enough to accommodate staging for the annual Design Miami show, and the revision required Design Review Board (DRB) approval. The DRB approved the design at their February 6th, 2017 meeting. The need to revise the design has postponed construction commencement of the Park from mid -2018 to early 2019. To see the approved Park design renderings refer to Exhibit 1. FINANCIAL UPDATE TO DECEMBER 31, 2017 The project is currently on budget. The usual project dashboard with updated financial information is attached as Exhibit A. A corresponding Budget Summary Breakdown is attached as Exhibit B. Narrative updates are as follows: CONSTRUCTION DRAW Taking into account direct purchases and payments for the construction, a total of $403.2 million, or 73.7%, of the total updated GMP amount of $546.8 million has been paid through December 31, 2017. Fora detailed breakdown, refer to Exhibit B (GMP + Direct Purchases Line Item). Construction Manager's (CM) Contingency Refer to Exhibit B1 for a summary of the total CM Contingency use to date. For the month of December, $750K was added as a result of unused contract allowances, bringing the total to $28.7 million out of the $29.7 million CM contingency. A total amount of Miami Beach Convention Center Monthly Construction Project Update No. 22 February 15, 2018 Page 3 of 5 $24.9 million has been utilized under the "Trade Cost" category. Direct Purchase The City continues its direct purchase of materials for the project originally budgeted at a sales tax savings of approximately $6 million. Through December 31, the City has directly purchased $62.8 million in materials resulting in sales tax savings of $4.6 million. There are certain materials that were planned for direct purchase that have not materialized due to a variety of reasons such as risk to the City, disagreement on purchasing terms, and disagreement on early deposit requirements. Although the City and the construction team pursued as many direct purchase opportunities as possible, it is currently estimated that there will be a shortfall amount of approximately $1.4 million, which will be funded from the Owner's Contingency. OWNER COSTS A total of $47 million, or 70%, of the owner cost budget has been expended to date. Below are more detailed updates for two major components of the project being funded by Owner Costs. Art in Public Places (AIPP) A total of $1.6 million out of the $7.1 million has been expended to date. 1. Franz Ackermann (Berlin), Southeast Corner Exterior Walls Ackermann conducted a site visit on November 30, 2017 to finalize the surface treatment of the Southeast Corner Exterior Wall. Ackermann has been working with a team of local and internationally based conservators to conduct paint test studies to ensure the longevity of the mural. In response to the paint studies, the team has developed a new, highly pigmented paint that will be used for the mural. Franz Ackermann is arriving to Miami Beach on February 26th and is scheduled to begin painting the mural on March 5, 2018. The mural will be complete on March 30, 2018 and will be immediately covered to protect the work until the Convention Center construction is complete. 2. Michael Elmgreen and Ingar Dragset (London/Berlin), Convention Center Park Sculpture The artists conducted a site visit on October 27, 2017. During this meeting, the artists presented a maquette that is being used to assess ADA requirements and siting of the work. The artists are working with a conservation team to evaluate UV standards, durability and anti -graffiti properties. Coordination of the project is dependent upon the final design of the Convention Center Park, which is estimated to be completed in summer 2019. Art in Public Places staff is working closely with the project team to ensure utilities and landscaping will not interfere with the foundation or visibility of the work. It is anticipated the sculpture will be installed in Summer 2019. 3. Ellen Harvey (Brooklyn), Grand Ballroom Pre -Function Room Ellen Harvey is now working with Franz Mayer of Munich to fabricate the art glass panels and the structural system to support the glass panels. The artist has completed studies of the work and fabrication of the art glass is in progress. It is anticipated the work will be installed in October 2018. 4. Joseph Kosuth (New York/London), West Lobby Kosuth studio and the Art in Public Places project team had great concern regarding the visibility of the four walls (North Junior Ballroom, South Junior Ballroom) that were originally suggested to house Kosuth's work. Kosuth studio conducted a site visit on October 3, 2017 to further assess the visibility and concurred with staff recommendation to relocate the work Miami Beach Convention Center Monthly Construction Project Update No. 22 February 15, 2018 Page 4 of 5 to the soffit that runs the entire length of the West Lobby. Neonlauro submitted electrical requirements for the soffit area to the project team on November 30, 2017. Once a permit is obtained, the electrical components will take two weeks to install. A neon maquette has been developed for the soffit area for purposes of scale. Kosuth will submit a finalized artistic concept for the new location in late February 2018. It is anticipated the work will be installed in September 2018. 5. Joep Van Lieshout (Netherlands), Northeast Park Collins Canal Van Lieshout has submitted his final design and permit documents for placement of the nine sculptures to be located in the 21st Street Park along the Collins Canal. The project team is working with West 8, the landscape architect, to determine proper plantings surrounding the sculptures. It is anticipated the work will be installed in November 2018. 6. Sarah Morris (New York), Northeast Corner Exterior Walls On August 17, 2017, Art in Public Places staff coordinated a surveying crew to scan the west facing walls on behalf of the artist, as exact measurements are needed to fabricate the tiles. Morris was able to complete the measurements of the two north facing walls on February 5, 2018. Additionally, Morris has specified surface treatment of the wall, lighting and landscaping for the northeast corner exterior walls. Morris is now in the process of hiring a general contractor and has begun fabrication of the tiles with the selected manufacturer located in Guadalajara, Mexico. It is s anticipated the tile mural will be completed in October 2018. Carl Fisher Clubhouse Historic Restoration The City's CIP Department is managing the project for the MBCC project team and a total amount of 422K out of the $2.5 million budget has been expended. The Invitation to Bid (ITB) for the Carl Fisher Clubhouse Restoration, was issued on October 19, 2017 with an opening date of November 20, 2017. The notices resulted in the receipt of four (4) responses with bid prices from all bidders exceeding the City's budget amount. Pursuant to the City of Miami Beach Code, the City Manager rejected the bids and the project team has revised the bid documents in order to re -advertise the item. The project's architect of record, RJ Heisenbottle Architects, has determined that revisions to certain building systems can be made to help mitigate the budget shortfall. In addition, necessary revisions to the site plan, east of the Carl Fisher Clubhouse building, are currently being prepared by the Convention Center project team and will be included in the bid documents. The project team anticipates reissuing the ITB in April, presenting the contract to the City Commission for award in June, and commencing construction in September. The renovation will take approximately 10 months and will be open prior to the 2019 Art Basel Fair. OWNER CONTINGENCY For a full detailed breakdown of all Owner costs and credits, refer to Exhibit B2. A total of $27 million of the available owner contingency of $35 million has been utilized. OVERALL COSTS From an overall project perspective, $441.7 million, or 72.19% has been spent on the $620 million project. LOCAL HIRE Clark Construction continues their commitment to maximizing workforce opportunities for City of Miami Beach and Miami -Dade County residents. A total of 5,264 workers have been employed by the project. This includes all certified payroll from October 2015 to December 31, 2017. The Miami Beach Convention Center Monthly Construction Project Update No. 22 February 15, 2018 Page 5 of 5 labor force includes full-time, part-time, temporary labor, and includes daytime and nighttime shifts. Attached, as Exhibit C, is a summary of the local hiring efforts to date, for Clark and its subcontractors. The current report shows a summary of all employees on the project thus far, sorted by zip code. Clark is currently 64% local hire by individual (Miami Beach, with 87 employees, and Miami -Dade County with 3,306). CONSTRUCTION MATERIAL DIVERSION / RECYCLING The City continues to be on track to exceed the goals of the Silver LEED designation for diversion / recycling of waste. Over 95% of the material demolished is being recycled and / or diverted, which exceeds the target goal of 75%. PUBLIC INFORMATION Various weekly advisories and postings for the month were sent on the City's social media outlets including Twitter, Facebook, and Constant Contact and are attached as Exhibit D. If there are any questions, please do not hesitate to contact myself or Maria Hernandez at Extension 2584. Attachments: Exhibit 1 — Revised P -Lot Park Renderings Exhibit A — Project Dashboard and Site Photos Exhibit B — Budget Summary Breakdown Exhibit B1 — Contractor Contingency Log Exhibit B2 — Owner Contingency Log Exhibit C — Clark Construction Local Hiring Summary Exhibit D — Public Outreach Report JLM / MH F:\cmgr\$ALL\Convention Center\Commission Updates\2017 December Monthly\LTC - December 2017 MBCC Update.docx EXHIBIT 1 SOIAFE PARW U* 1 UE*CH COPNEitT01 COM I2 MIAMI BUCK 1 !OTAMILAL & RAEN 1 1 CIT! HAIL 1 •.4d d i W w r CC I— r ri.11 KIN N[aHF x..10.01 IFLEIEVLE !GGm M SPi is t 1 V ours / j7 ,o.o..os• WeAREAS : [ ! i • R • • 1 CENTRAL LAWN 2. WPM'S AMA . FLEXIBLE FFl�GA hl�lI AitFA 4, FLA'Y1TITT4e'SS POQ4fT 5. SCLUTILRE H AVRE A .1111"1.1.14111 • •••••w...1. a,. r.. ra w4+0010••.0010 s. •••• *MN r 110 M in.. e. (4.00.400.00(.r,td Amy s4M . Rr4ww( -0•• . f♦Fry40000.Yl•MW.•wr►• 10400 W 00.! i.s A0.0 wWrl+ e1000. 014 w•r PA VIR 5 411 W 661 1 L10.04 PLAI1 CHANGES • Car 0 0 MIllIIAn, r -:..Y. CHANGESkFle ' 1. G NIF1AL LAYIT4 - v-r,cco so 1 2. RAISED PLANTERS - 11,OM SO FT 3 VE I FRAN'S PLAZA - n. coo SI fl 1 PAVILION i sLDING 22 OO S4 FT Critti Orf MIMES: 1. DNLARGED iT:04. LAWN . 154.000 SG FT 2 e1ANTl144 FAS - 11.000 SO FT V5E1WCS LitEl.10.3441 PLAZA - 2,60:1 SO FT +4-1180BLE PROGIAPAIENS SP CE - N:06O SOFT FlAY/'FITTCSS POW- 1,060 SO FT 0. Of WILMA 250 SO FT T. U1g3TIS 6 INFNISTRUCTUIE it PURA RESTROOM = 360 SO FT a- ►.1.+vi m••.i f. •IL. •gyyY n--1r-+F rrk*0.1.1. 1 4 ..•1140, ..1.116m re -m maa ea 11,0 1 111. 3 PARK ENTRANCE FR QM 19 Thi R1REE.T • _,�_ ,y .�.•••••.....i,«_ 3, PARK ENTRN' CE FRC61 igTH WEE' (744,11441141r %eV! .r40114. higliligr PIA111.C.I*Di 1 Rpm- - PEI* 1101111E • 'Ow" - +NW PL - PLAN. HdGHLIG1-4 MG SRN PLAITING BEDE . OW* r.v�w uA.♦«•ogw uu.r.w 4-ea*.r ..0-N . .. I..'F- PAR1{ENTRANCE nom 19THSiktI Id 13I]1 vEITRAssQM CELE - Eh1#Fd FROM MIN STREET ROYAL NTINC LANA TME WRDATOXRF6�Ai VETERAN'S MEMORIAL PLAZA Pool Fixiciarta trBe (Odom tow sarvista paw* Ides z 1 Emma TO PLAZA Fstiki WIMP? Cain DOM AND 1 nil 5-141-1 ETCHED NIEUALUDN GRANI1L 0 M.1it_i KhU.IOW I!4 al T r4. RRA Olt" brei !I par "Ma Pilaf Pam MI tart wu, r®iwwiink' rmilk kfliLNMU" itEItia JMIrt.T.1 iirMi_sar: 9101111si 4110 Fm inn rF f MOM OWL 4511111 ROVA§ Q:041.1. idALOILINE ee CLK L:A:t W la` Tf ritrAB ME GYM rilb M ld.[ tallMRg ►MLSual 1.10021, IDGE MIMffif'?AT. L'ii°wW.i:rle-RlfAhlcYi; liar" L rsY/J-READ, lilenin MOW. Poen ."..y, 0-.. .N +tia., .f 4- m- rte -". .r ... 2 2 1.! V Ai 3 FLEXIBLE PROGRAMMING SPACE BLS LD D% IN FRONT 0; FLE%ELE FclIYIRAMIVINE SPfiri treJ C W LL PCIOTNESS ROCTETOCATIIA'' 1 WPITTESS" MOTT gESERVPION2UNE VE -LEVEL WA' NESTED IN 11 -IE GREEN 6e ar oie r •11. •01.1 • •115* OM* 101, • ***Os.= 40,0•614,01111114164 ibril 4.6.4 owlrd .41. gm, II -.J.. 4,4 ••-, • ••••• e- 6 a . . . 16 ii 1 VIEW RF kfr COMER OF CONVENTIDUCENTER£IIYEAND1tt!HSTREET 3 6 1 j e L17.011 Mona amusi ism nm • Lielm1=111_111.1Vilirt*.. • 1 • • • IMLAW1.11•••111LLMInt 1.• • • ••••rt t••••• ammsrmano mrsamm‘r"... OMITS ANC 11490STRLICTI/RE LOCATION Wei OFSOON RCM ,),. 4€T •• SCJ1WJIIFWL&FUfI JISE INFRASTRICURE • • •••• .1' • ts It out •-•.- ‘. • tr.* • 4•••• Am. 4,4mt •at a•• = m.t ••• • •• •••-• ....Wk. • #.0.•,• . • No e.• mt,•l• el •• • • •.• 11 , OS•80, .1-.-n-'1!N OF gEF,TROON1 VIEW RESTFOOM FRDM EAST $1. .1%••••• • • • •••• ,•A • •••• •••• ••• •••• ••• •• • M... • ••••••l '• •••• ••• • ,,1•••••'• h•t• 41•••4 • ••••••••••14* ••• • • %MOT RESTROLIM FROM ii STREET • i• CC LL 011En REPVVA'I volv CF=am . sro. n P mp kis s■ NEW INTRODUCED MATERIAL dfM/APOSEDEAT REOR11 PIVGITAIMANG SPAIN COW SAMDSTQhE PAYtRS M VE #K N'S KA �4Y44 .0 .wee4,.1I. Not, Ms.ta.m.w. reg AO 41 AM. rt....4•.141 4.h. * r . n *4- 41.1...* AWai 4l,... e.4M• 4*444•..[4141•sF.♦IF+r•ti.....1..4•.. #MM.• •••• •N w,r..ww.r e.....r 0,140 err+.—.�. N1p 1J 'I I 11,03 2016 (25 Events) $0m $100m $200m $300m $400m $500m $600m Total Project Cost 72.19% Expended D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S 2017 (8 Events)2018 (13 Events) $0m $50m $100m $150m $200m $250m $300m $350m $400m $450m $500m $550m Net GMP Draw 73.74% Expended* $0m $10m $20m $30m $40m $50m $60m $70m Owner Costs 69.91% Expended $0m $5m $10m $15m $20m $25m $30m $35m Owner Contingency $0m $5m $10m $15m $20m $25m $30m CM Contingency* (Included in Net GMP) Total Project Notes: •72.19% of the total budget has been expended. Construction GMP Notes: •73.74% of the total GMP budget has been expended. •$28.7M (97%) of CM contingency has been utilized. Refer to LTC narrative and Exhibit B1 for description and detail •*For a breakdown of construction completed by Discipline refer to Dashboard chart Exhibit A1. Owner Budget Notes: •69.91% of owner budget has been expended. •$27M (77%) of the owner’s contingency budget has been expended. Other Notes: •Building is closed to events until March 17, 2018. •4 out of the 13 scheduled events of 2018 will be 4-hall shows. BLACK OUT (not included in Owner Cost) Convention Center Renovation & •ansion Project Dashboard EXH January 2017 -199.01 Open Stair 1.25.01 -'View S frorn Grids 19 & B 0-199.02 0-199.@3 Meeting Pref 2-13-03 -View E from Grids D & 11 HR 1.09.45 - View W from Grids 4 & G 0-199.04 0-199.05 0-199.06 Meeting Pref 2 -25.05 -View SE from Grids 17 & C_62 Public C c nc 2.26.04 - View VII from Grids P.33 & 24 Prefunciion 4.30.07 - View N from Grids 23.73 A C 0-199-07 West Roof Parking -View N from G's 10.52 & NW2 0-199.08 West Roof Parg iag - View N from Grids 7.57 & D.49 0-199.69 Parking 5.0.01 -View W from Grids IJ & NE1 Convention Center Renovation & Expansion Project Dashboard EX January 2017 / Att 0-198.01 Jr Ballroom 1.30.02 — View E from 0's 22.78 & C,46 0-198.02 Half C — View S from Grids 22 & G 4 0-198.04 0-198.05 Exhibit Pre 1.25 03 — View SW from G's 17.83 & D.45 Public RR 1.14.03 View N from Grids 15 & F 0-198.07 0-198.08 0-198.03 Hall C — View N from Grids 19.9 & G 0-198.06 Halle D — View NE from Grids 9 & G.3 0-198.09 West Conc. Ext. Facade — View E from Grids 10 & A Service Corr 2.08.19 —View NE from Grids P & 10 West Roof Parking — View S from Grids E & F W1 Convention Center Renovation & Expansion Project DashboardEXHIBIT A' January 2017 0-198.14 Public Conc 2,28.01 - View W from Grids J & 24 0-199E_10 Parking 5.08.01 -View W from Grids Q.451 S 4 0-198.11 Prnction 4.30.07 - View SW from G's 23.42 & G.7 ]-199.11 South Exl. Facade - V ew'h from Grids U S. 25 0-196.02 0.198.12 Meeting 2.19.15 -View N from Grids 19.34 & E.1 0-199.12 Stair 1.08..41 - View NE from Grids K & 8 0-196.03 Jr Ballroom t25.06 -View SE from G's C.5 & 21.38 Exhibit Pref 1.25.03 - View S from Grids 19.34 & C Hall D - View SE from Grids G & 10 Dashboard Summary Trade Costs $410,205,803 66.62%1,202,676 $411,408,479 66.37% Direct Purchase 0 0.00%-66,938,921 -66,938,921 -10.80% Storm Water Drainage Culvert 0 3,309,692 3,309,692 0.53% Recon 50,803,086 50,803,086 8.20% Change Orders 0 0.00%9,824,958 9,824,958 1.58% Subtotal 410,205,803 66.62%-1,798,509 408,407,294 65.88%292,275,473 71.56%116,131,821 Contractor Soft Costs General Conditions (Clark Staffing)24,465,886 3.97%3,700,000 28,165,886 4.54%24,180,390 85.85%3,985,496 General Requirements 14,760,103 2.40%2,545,258 17,305,361 2.79%12,987,083 75.05%4,318,278 Payment & Performance Bond 3,708,000 0.60%42,495 7 3,750,495 0.61%3,696,811 98.57%53,684 GL Insurance 1,807,650 0.29%259,446 2,067,096 0.33%1,618,989 78.32%448,107 CMr Fees (3.8%)17,288,003 2.81%2,668,942 19,956,945 3.22%13,941,236 69.86%6,015,709 CCIP GL Wrap 0 0.00%4,740,576 8 4,740,576 0.76%4,740,576 100.00%0 CM Contingency 29,747,613 4.83%-28,721,088 9 1,026,525 0.17%0 0.00%1,026,525 Base GMP 501,983,058 81.53%-16,562,881 485,420,178 78.31%353,440,557 72.81%131,979,620 Other GMP Items (Including all mark ups) P-Lot Park (allowance)10,000,000 1.62%-10,000,000 14 0 0.00%0 0.00%0 Storm water Drainage Culvert 3,475,000 0.56%-3,475,000 0 0.00%0 0.00%0 Subtotal 13,475,000 2.19%-13,475,000 0 0.00%0 0.00%0 Total GMP (Clark)515,458,058 83.72%-30,037,881 485,420,178 78.31%353,440,557 72.81%131,979,620 Direct Purchase Tax Savings -6,000,000 -0.97%4,593,738 16 -1,406,262 -0.23%0 0.00%-1,406,262 16 Total Net GMP 509,458,058 82.74%-25,444,143 484,013,915 78.08%353,440,557 73.02%130,573,358 Direct Purchases 0 0.00%62,825,608 62,825,608 10.13%49,773,027 79.22%13,052,581 GMP + Direct Purchases 509,458,058 82.74%37,381,465 546,839,524 88.21%403,213,585 73.74%143,625,939 Owner's Cost City Staffing & Expenses 1,561,000 0.25%793,318 5 2,354,318 0.38%1,795,439 76.26%558,879 Consultant Fees (SAG)1,047,725 0.17%160,000 1,207,725 0.19%1,078,963 89.34%128,762 Owner's Rep (Hill)5,585,673 0.91%0 5,585,673 0.90%4,684,787 83.87%900,886 Design Fees (Fentress)26,669,442 4.33%1,222,461 10 27,891,903 4.50%26,653,033 95.56%1,238,870 Owner's Cost Estimator (US Cost)400,030 0.06%709,326 6 1,109,356 0.18%1,009,249 90.98%100,107 Pre GMP CM Fee (Clark)2,594,073 0.42%-1,037,629 1,556,444 0.25%1,556,444 100.00%0 Testing & Inspections 2,328,943 0.38%831,520 3,160,463 0.51%1,748,046 55.31%1,412,417 Permit & Plan Reviews 2,400,000 0.39%746,074 13 3,146,074 0.51%2,988,766 95.00%157,308 Other 783,526 0.13%1,686,015 3 2,469,541 0.40%1,212,372 49.09%1,257,169 Other - Legal / DAP Board 63,515 0.01%260,000 11 323,515 0.05%214,822 66.40%108,693 Other - Spectra 0 0.00%292,000 12 292,000 0.05%291,950 99.98%50 Other - Design Miami 0 0.00%0 0 0.00%0 0.00%0 Public Art (AIPP)6,900,000 1.12%220,422 2 7,120,422 1.15%1,600,249 22.47%5,520,173 2 MBCC FF&E 6,830,945 1.11%0 6,830,945 1.10%34,811 0.51%6,796,134 Insurance: OCIP GL Wrap 9,000,000 1.46%-9,000,000 4 0 0.00%0 0.00%0 Builder Risk/Building (net)1,600,000 0.26%-450,000 1,150,000 0.19%1,150,000 100.00%1 0 1 Professional Liability Umbrella 1,000,000 0.16%-382,117 617,883 0.10%617,883 100.00%0 Carl Fisher Renovation Allowance 2,500,000 0.41%0 2,500,000 0.40%422,093 16.88%2,077,907 Subtotal 71,264,872 11.57%-3,948,610 67,316,262 10.86%47,058,907 69.91%20,257,355 P-Lot Park (allowance)0 0.00%4,650,924 14 4,650,924 0.75%0 0.00%4,650,924 Escalator/Elevator/Kitchen Upgrades 0 0.00%3,106,729 18 3,106,729 0.50%0 0.00%3,106,729 Reimbursement from other CMB Funds 0 0.00%-9,979,820 17 -9,979,820 -1.61%-8,538,994 85.56%-1,440,826 Total Without Owner's Contingency 580,722,930 94.32%31,210,688 611,933,618 98.71%441,733,498 72.19%170,200,120 Owner's Contingency 0.00%-27,028,613 7,971,387 1.29%0 0.00%7,971,387 Total Owner's Contingency 35,000,000 5.68%-27,028,613 15 7,971,387 1.29%0 0.00%7,971,387 Total Budget With Owner's Contingency $615,722,930 100.00%$4,182,075 19 $619,905,005 100.0%$441,733,498 72.19%$178,171,507 1. The property insurance portion of the Builders Risk policy to be reimbursed $68,501 by CMB Risk Dept. 2. A portion of the savings from insurance was allocated to AiPP to provide for actual costs. Pursuant to Sec. 82-587 of the CMB Code, the total amount allocated to AiPP has been transferred to the Art in Public Places Fund. 3. Miscellaneous costs such as surveys, studies, public information officer (PIO), and utility fees. 4. Insurance Savings as a result of implementing a CCIP (Contractor Controlled Insurance Program) rather than an OCIP (Owner Controlled Insurance Program). 5. A portion of the savings from insurance was allocated to City Staffing to cover costs from Fiscal Year 2014 through December 2018. The previous budget estimate included only Fiscal Years 2015 through part of 2018. 6. Additional Cost Estimating services to support GMP reconciliation negotiations with Construction Manager. 7. Credit balance due to savings from Clark Bond on Direct Purchases executed to date. 8. $4.7M in general liability insurance was originally to be purchased directly by the owner, but was actually purchased by the contractor. Also refer to Footnote No. 4. 9. Total use of Contractor Contingency to Date. Refer to Exhibit B1 for detailed summary. 10. Additonal fees for miscellaneous design revisions and extra site visits requested by Contractor; approx. $384K of the total has been deducted from Clark's Contract. 11. Additional Costs for Dispute Avoidance Panel and outside legal counsel. 12. Moving expenses, parking fees and other expenses for relocation of building operator. 13. Costs for additional permitting fees. 14. P-Lot Park Allowance temporarily deducted from Clark's Contract. $5M remains in allowance and $5M moved to owner's contingency. 15. Total use of Owner Contingency to Date. Refer to Exhibit B2 for detailed summary. 16. Projected Sales Tax Savings from submitted Direct Purchase Orders; Future anticipated $1.5M shortfall in Direct Purchase of materials. 17. Reimbursement for operational expenses (Reso 2017-29830), stormwater culvert (2017-29829) & re-roofing of existing building previously allocated under separate projects. 18. Additional improvements (Reso 2017-29829) for Escalator/Elevator/Kitchen Upgrades to be added to GMP. 19. Total budget variance includes additional bond proceds of $147,449 + Additional funding in the amount of $4,034,625 per April 26, 2017 budget amendment. % Total Approved Budget Balance Remaining Budget Variance EXHIBIT B Current Budget % Current Expenses % Spent Current Forecasted Budget 10/7/15 Original Budget Miami Beach Convention Center Expansion & Renovation Project Page 1 of 1 EXHIBIT B1 Miami Beach Convention Center Expansion & Renovation Project Construction Manager's (CM) Contingency Report thru December 31, 2017 SUMMMARY Total CM Contingency $29,747,613.00 USES May 2016 **3,516,099.28$ Jun 2016 3,539,694.47$ Jul 2016 2,345,812.72$ Aug 2016 678,014.32$ Sep 2016 1,373,672.04$ Oct 2016 555,095.86$ Nov 2016 1,453,031.74$ Dec 2016 82,810.97$ Jan 2017 1,491,842.15$ Feb 2017 2,008,667.81$ Mar 2017 1,413,331.31$ April 2017 - Interim 5,226,384.54$ Apr 2017 3,075,943.46$ May 2017 (1,130,888.46)$ Jun 2017 447,556.19$ Jul 2017 398,299.40$ Aug 2017 1,094,342.36$ Sep 2017 222,823.27$ Oct 2017 755,676.28$ Nov 2017 923,164.89$ Dec 2017 (750,286.09)$ Total Uses 28,721,088.50 REMAINING CM CONTINGENCY $1,026,524.50 Settlement Agreement - Increase to Contingency $963,391.00 REVISED REMAINING CM CONTINGENCY $1,026,524.50 Trade Contract Buyout - 2016 MONTH SUBCONTRACTOR DESCRIPTION AMOUNT CSI CODEMARK-Ups*TOTAL COST MAY ACOUSTI Temporary Walls $1,706,560.00 $84,734.24 $1,791,294.24 MAY ALPHA DEMO Demolition -203,020.00 -10,080.36 -213,100.36 MAY AMERICAN FIRE PROFF Spray Fireproofing -177,812.00 -8,828.73 -186,640.73 MAY BANKER Structural Steel -334,138.00 -16,590.64 -350,728.64 MAY BARING INDUSTRIES Food Service 33,244.00 1,650.63 34,894.63 MAY CAMARATA Masonry -171,200.00 -8,500.43 -179,700.43 MAY CDPW Dewatering -118,399.00 -5,878.76 -124,277.76 MAY DAVID ALLEN Tile -142,590.00 -7,079.89 -149,669.89 MAY DUFFY & LEE Carpet -19,965.00 -991.30 -20,956.30 MAY FORD AV Audio/Visual -10,642.00 -528.40 -11,170.40 MAY HAYWOOD BAKER Soil Stabilization 434,185.00 21,558.18 455,743.18 MAY HONEYWELL Low Voltage -713,361.00 -35,419.85 -748,780.85 MAY HUFCOR Operable Partions -267,272.00 -13,270.61 -280,542.61 MAY ISEC Expansion Joints 160,317.00 7,960.07 168,277.07 MAY JAFFER Dewatering - Wells 1,421.00 70.56 1,491.56 MAY *NASH Dewatering - Underground Utility 95,531.00 4,743.31 100,274.31 MAY NFP Fire Suppression -102,500.00 -5,089.34 -107,589.34 MAY RITE HITE Loading Dock -6,600.00 -327.70 -6,927.70 MAY R&M Structural Concrete 1,115,752.00 55,399.40 1,171,151.40 MAY SPECIFIED ARCH SYS Operable Partions -4,568.00 -226.81 -4,794.81 MAY TECTA Roofing 9,075.00 450.59 9,525.59 MAY TRIDENT Resilient Flooring -25,560.00 -1,269.11 -26,829.11 MAY WON DOOR Operable Doors 5,650.00 280.53 5,930.53 MAY WPM Site Civil 1,164,378.00 57,813.78 1,222,191.78 SUBTOTAL 2,428,486.00 120,579.36 2,549,065.36 JUNE LOUVERS (Nash Mech.)Louvers -433,354.00 -21,516.92 -454,870.92 JUNE WPM Site Civil -429,292.00 -21,315.24 -450,607.24 SUBTOTAL -862,646.00 -42,832.16 -905,478.16 Exhibit B1 1 of 9 EXHIBIT B1 MONTH SUBCONTRACTOR DESCRIPTION AMOUNT CSI CODEMARK-Ups*TOTAL COST JULY ACOUSTI Temporary Walls 4,480.00 222.44 4,702.44 JULY AERIAL PHOTOGRAPHY INC.Aerial Job Site Photos 43.00 2.14 45.14 JULY GEOSYNTEC Environmental Consultant 5,800.00 287.98 6,087.98 JULY MICHEAL WOOD FDEP Consultant 10,200.00 506.45 10,706.45 JULY MODSPACE Owner Trailer -3,197.00 -158.74 -3,355.74 JULY GOAL ASSOCIATES MOT 46,500.00 2,308.82 48,808.82 JULY SMITH FENCE Fencing -367.00 -18.22 -385.22 JULY TR PERMITTING Permitting 66,000.00 3,277.04 69,277.04 SUBTOTAL 129,459.00 6,427.91 135,886.91 AUGUST NO CHANGES 0.00 0.00 SUBTOTAL 0.00 0.00 0.00 SEPTEMBER NO CHANGES 0.00 0.00 SUBTOTAL 0.00 0.00 0.00 OCTOBER EVENSTAR Decking 3,000.00 148.96 3,148.96 SUBTOTAL 3,000.00 148.96 3,148.96 NOVEMBER NO CHANGES 0.00 0.00 0.00 SUBTOTAL 0.00 0.00 0.00 DECEMBER HOISTWAY MODIFICATION (3b) Modifications for EL16.02 not used -150,000.00 -7,447.81 -157,447.81 DECEMBER FIREPROOFING Scraping (3c) Related to elevator only -4,571.00 -226.96 -4,797.96 DECEMBER PILING UNBOUGHT (16A) Additional length per GMP Clarification -176,952.00 -8,786.03 -185,738.03 DECEMBER POCKET DOOR (42b) Pocket Door for WON DOOR -5,000.00 -248.26 -5,248.26 DECEMBER SPOIL REMOVAL (16c) Spoil removal for jet grouting -2,500.00 -124.13 -2,624.13 DECEMBER UNDERPINNING (16d) Underpinning for East Concourse -4,000.00 -198.61 -4,198.61 DECEMBER EXISTING STRUCTURE (16e) Monitoring of existing structure -25,000.00 -1,241.30 -26,241.30 DECEMBER DEWATERING EQUIPMENT (19f) Dewatering Equipment Temp Power & Fuel -140,000.00 -6,951.29 -146,951.29 DECEMBER SECONDARY ELEC SERV (84.31) With MEP Subs, from GR to CM -255,000.00 -12,661.28 -267,661.28 DECEMBER OPPORTUNITY TRAILER (84.36d) Moved from GR's to CM -30,000.00 -1,489.56 -31,489.56 DECEMBER ALUMINIUM STEPS (84.36e) Moved from GRs to CM -21,600.00 -1,072.48 -22,672.48 DECEMBER TEMP TRAILER (84.36f) Permitting -10,000.00 -496.52 -10,496.52 DECEMBER TR PERMITTING Permitting -66,000.00 -3,277.04 -69,277.04 SUBTOTAL -890,623.00 -44,221.28 -934,844.28 JANUARY '17 DEWATERING EQUIPMENT (19f) Dewatering Equipment Temp Power & Fuel 140,000.00 6,951.29 146,951.29 JANUARY '17 SECONDARY ELEC SERV (84.31) With MEP Subs, from GR to CM 255,000.00 12,661.28 267,661.28 SUBTOTAL 395,000.00 19,612.57 414,612.57 TOTAL SINCE INCEPTION $1,202,676.00 $59,715.35 $1,262,391.35 Trade Costs MONTH SUBCONTRACTOR DESCRIPTION AMOUNTCSI CODE MARK-Ups*TOTAL COST MAY BARING INDUSTRIES Temporary Kitchen $321,004.66 $0.00 $321,004.66 MAY *CDPW Cost associated with dewatering due to the tremmie seal pumping water disposal - Initial set up and monthly disposals. 186,092.37 9,239.87 195,332.24 MAY *HAYWOOD BAKER Additional costs for soil stabilization at the northwest Florida Power & Light vault that was unable to be quanitified at the time of GMP. 23,000.00 1,142.00 24,142.00 MAY *HJ FOUNDATION Additional costs for soil stabilization at the northwest Florida Power & Light vault that was unable to be quanitified at the time of GMP. 33,846.80 1,680.56 35,527.36 MAY *HJ FOUNDATION Additional costs for soil stabilization at the northwest Florida Power & Light vault that was unable to be quanitified at the time of GMP. 38,823.07 1,927.65 40,750.72 MAY HONEYWELL Building Separation 289,721.73 289,721.73 SUBTOTAL 892,488.63 13,990.08 906,478.71 JUNE ACOUSTI Additional costs for the mechanical fastening of the insulation due to inability to remove via air compressors by demo subcontrcator 300,000.00 14,895.62 314,895.62 JUNE ALPHA WRECKING INTERIM FUNDING - costs associated with extended dump hours, additional demolition or parapet walls, structural members abd block removal 420,000.00 20,853.87 440,853.87 JUNE BARRING INDUSTRIES Cost reallocated to GR Life Safety line item -321,004.66 0.00 -321,004.66 JUNE CDPW Cost associated with dewatering due to the tremmie seal pumping water disposal - monthly expenses and contaminated water fees. 89,312.00 4,434.53 93,746.53 JUNE HARMON INTERIM FUNDING - Costs associated with the design and engineering associated with modifications to the exterior of the building 160,000.00 7,944.33 167,944.33 JUNE HONEYWELL Cost reallocated to GR Life Safety line item -289,721.73 0.00 -289,721.73 Exhibit B1 2 of 9 EXHIBIT B1 MONTH SUBCONTRACTOR DESCRIPTION AMOUNT CSI CODEMARK-Ups*TOTAL COST JUNE HJ FOUNDATION INTERIM FUNDING - Costs for work in place associated with the additional piles and ties from the design completion 141,000.00 7,000.94 148,000.94 JUNE JAFFER INTERIM FUNDING - Costs associated with the 3 additional dewatering required for the project 85,000.00 4,220.43 89,220.43 JUNE NASH Additional dewatering costs associated with the temporary FPL ductbank being routed from Washington Ave to NW FPL Vault 221,426.00 10,994.26 232,420.26 JUNE NASH INTERIM FUNDING - Costs associated with work in place for replacement of the existing restrooms, misc material changes to the sanitary, storm and chilled water systems made during design completion, and new duct Heaters 500,000.00 24,826.04 524,826.04 JUNE NATIONAL FIRE PROTECTION INTERIM FUNDING - Costs associated with work in place for the implementation and installation of the higher density sprinklers requested by the AHJ 400,000.00 19,860.83 419,860.83 JUNE ROBINS & MARTIN INTERIM FUNDING - Costs for completed work for tremmie seals as requested by CM and rebar bending; costs for work in place including structural changes to the vault, shearwalls, footings and elevated beams. 2,000,000.00 99,304.14 2,099,304.14 SUBTOTAL 3,706,011.61 214,334.98 3,920,346.59 JULY ALPHA WRECKING INTERIM FUNDING - costs associated with extended dump hours, additional demolition or parapet walls, structural 330,000.00 16,385.18 346,385.18 JULY ALPHA WRECKING Deletion of scope for the removal of the insulation.-396,962.00 -19,709.99 -416,671.99 JULY CAMARATA Deletion of intregal water repellant per contract -163,000.00 -8,093.29 -171,093.29 JULY FL CIVIL Dewatering permit 23,452.21 1,164.45 24,616.66 JULY XMCDEAN INTERIM FUNDING -FPL ductbank 250,000.00 12,413.02 262,413.02 JULY XMCDEAN INTERIM FUNDING - Costs for completed work for electrical changes to the FPL vaults and camera infrastructure. 500,000.00 24,826.04 524,826.04 JULY R&M INTERIM FUNDING - Costs for completed work for structural changes to the vault, shearwalls, footings and elevated beams. 700,000.00 34,756.45 734,756.45 JULY WPM / R&M SCOPE CHANGE - Fine grading -766.71 -38.07 -804.78 SUBTOTAL 1,242,723.50 61,703.80 1,304,427.30 AUGUST JAFFER Additional drainage wells - Phase 2 358,500.00 17,800.27 376,300.27 AUGUST TRU-STEEL Miscellaneous metals scope 50,000.00 2,482.60 52,482.60 SUBTOTAL 408,500.00 20,282.87 428,782.87 SEPTEMBER HONEYWELL INTERIM FUNDING - Engineering 200,000.00 9,930.41 209,930.41 SEPTEMBER HONEYWELL INTERIM FUNDING - Equipment 250,000.00 12,413.02 262,413.02 SEPTEMBER ACOUSTI INTERIM FUNDING - Additional drywall scope 500,000.00 24,826.04 524,826.04 SEPTEMBER ALPHA INTERIM FUNDING - credit for moneys paid under OCO #35 for z-wall scope -42,821.00 -2,126.15 -44,947.15 SEPTEMBER ALPHA INTERIM FUNDING - additional demo scope 42,821.00 2,126.15 44,947.15 SEPTEMBER R&M SCOPE GAP - Additional labor for floor boxes formwork 69,998.00 3,475.55 73,473.55 SEPTEMBER BANKER SCOPE CHANGE - Cutting out grating for new AHU 152,037.00 7,548.95 159,585.95 SEPTEMBER NFP/MARDALE SCOPE GAP - Installation for fire extinguisher cabinets 35,513.00 1,763.29 37,276.29 SUBTOTAL 1,207,548.00 59,957.26 1,267,505.26 OCTOBER R&M Temp work for Art Basel - Transition slab 408,604.00 20,288.03 428,892.03 OCTOBER ACOUSTI Temp work for Art Basel - NW egress tunnel 180,001.30 8,937.44 188,938.74 OCTOBER ACOUSTI Electrical room 1.7.07 build out 18,609.80 924.02 19,533.82 OCTOBER RITE HITE Dock leveler size 1,770.00 87.88 1,857.88 SUBTOTAL 608,985.10 30,237.37 639,222.47 NOVEMBER WPM Import fill for NE helix 79,128.00 3,928.87 83,056.87 NOVEMBER FLORIDA BLACKTOP Temp work for Art Basel - temp asphalt 366,867.42 18,215.73 385,083.15 NOVEMBER TECTA Temp work for Art Basel - waterproofing for metal deck at north loading dock 73,669.00 3,657.82 77,326.82 NOVEMBER ACOUSTI Temp work for Art Basel - patch & repair throughout 127,553.62 6,333.30 133,886.92 Exhibit B1 3 of 9 EXHIBIT B1 MONTH SUBCONTRACTOR DESCRIPTION AMOUNT CSI CODEMARK-Ups*TOTAL COST NOVEMBER ACOUSTI Temp work for Art Basel - temp tunnels for NW egress 184,843.37 9,177.86 194,021.23 NOVEMBER DASH DOORS Temp work for Art Basel - repair exist. storefront 43,835.87 2,176.54 46,012.41 NOVEMBER ACOUSTI Temp work for Art Basel - temp walls for north loading dock dry-in 21,530.33 1,069.03 22,599.36 NOVEMBER XMCDEAN Floor box shims 188,643.00 9,366.52 198,009.52 NOVEMBER TECTA Temp work for Art Basel - electrical room 1.07.07 waterproofing 8,997.00 446.72 9,443.72 NOVEMBER JAFFER Scope reduction - base contract -17,000.00 -844.09 -17,844.09 NOVEMBER JAFFER New scope - Additional transport of pile spoils 17,000.00 844.09 17,844.09 NOVEMBER TECTA Temp work for Art Basel - electrical room 1.06.04 waterproofing 5,212.00 258.79 5,470.79 NOVEMBER ALPHA Asbestos abatement 65,452.00 3,249.83 68,701.83 NOVEMBER ALPHA Lead Paint abatement 151,500.00 7,522.29 159,022.29 SUBTOTAL 1,317,231.61 65,403.28 1,382,634.89 DECEMBER CAMARATA Existing conditions - Z wall infil & patching 71,868.00 3,568.40 75,436.40 DECEMBER ALPHA West Concourse - Acceleration 100,000.00 4,965.21 104,965.21 DECEMBER ALPHA Temporary separation - GL-7 125,000.00 6,206.51 131,206.51 DECEMBER ALPHA Hall C/D SOG demo acceleration 100,000.00 4,965.21 104,965.21 DECEMBER EUGENIO PAINTING Temp work for Art Basel - to be voided 23,916.00 1,187.48 25,103.48 DECEMBER MCDEAN Temp work for Art Basel - to be voided 77,123.00 3,829.32 80,952.32 DECEMBER PJ STRIPPING Temp work for Art Basel 2,915.54 144.76 3,060.30 DECEMBER UNDERPOWER Repair of damaged traffic signals Wash Ave 1,938.00 96.23 2,034.23 DECEMBER DUFFY & LEE Temp work for Art Basel - floor prep for carpet 7,431.00 368.96 7,799.96 DECEMBER STAGING CONCEPTS Temp work for Art Basel - infill plexi panels for new guardrails at east concourse 7,776.00 386.09 8,162.09 DECEMBER EAST COAST METALS Temp work for Art Basel - to be voided 20,600.00 1,022.83 21,622.83 DECEMBER WPM Temp work for Art Basel - subgrade prep for temp asphalt for loading dock and east sidewalk 192,869.95 9,576.39 202,446.34 DECEMBER AMERICAN FIREPROOFING Temp work for Art Basel - fire proofing shear wall braces and beam in elec room 24,619.40 1,222.40 25,841.80 DECEMBER TECTA Waterproofing north elec room & FPL vault 35,049.01 1,740.26 36,789.27 DECEMBER DAVID ALLEN Acceleration for AB16 - terrazzo stairs & restrooms tile instal. 5,783.37 287.16 6,070.53 DECEMBER NFP Replace & repair exist. fire hose & nozzles 7,428.00 368.82 7,796.82 SUBTOTAL 804,317.27 39,936.02 844,253.29 JANUARY MCDEAN Relocation of TC-D3 Telcom Room 75,761.00 3,761.69 79,522.69 JANUARY WPM Fix Storm Box Culvert 4,685.00 232.62 4,917.62 JANUARY OTIS Rembursement to Elevator Pit 2,696.00 133.86 2,829.86 JANUARY DUFFY LEE Remove and reinstall carpet - due to asbestos removal 8,939.00 443.84 9,382.84 JANUARY ACOUSTI Temp work for Art Basel 23,501.00 1,166.87 24,667.87 JANUARY EAST COAST METALS Temp work for Art Basel - Change Order Not Executed -20,600.00 -1,022.83 -21,622.83 JANUARY DECON Rejected Change Order - Lead Paint Abatement 815,476.00 40,490.07 855,966.07 SUBTOTAL 910,458.00 45,206.13 955,664.13 FEBRUARY DECON Rejected Change Order - Lead Paint Abatement 833,128.28 41,366.54 874,494.82 FEBRUARY AMERICAN FIREPROOFING Rejected Change Order - Additional fireproofing on exisiting members 79,335.06 3,939.15 83,274.21 FEBRUARY GLE ASSOCIATES Asbestos abatement 5,872.50 291.58 6,164.08 FEBRUARY GLE ASSOCIATES Lead abatement 27,537.72 1,367.30 28,905.02 FEBRUARY WPM Fillmore parking modifications 1,405.00 69.76 1,474.76 FEBRUARY WPM Dewatering for MC Dean ductbank 4,931.00 244.83 5,175.83 FEBRUARY WPM Pump Roof Drain Manhole 3,994.00 198.31 4,192.31 FEBRUARY WPM Pump Roof Drain Manhole 5,883.00 292.10 6,175.10 FEBRUARY FLORIDA BLACKTOP Fillmore parking modifications 4,552.00 226.02 4,778.02 FEBRUARY ACOUSTI East Façade Exterior Stucco (810135)312,004.51 15,491.67 327,496.18 FEBRUARY BANKER Fabrication and Installation of Floor Boxes 200,000.00 9,930.41 209,930.41 FEBRUARY BRAZOS Spray Fireproofing - Pending OCO 83,000.00 4,121.12 87,121.12 FEBRUARY EUGENIO PAINTING Temp work for Art Basel - Dec C/O to be voided -23,916.00 -1,187.48 -25,103.48 FEBRUARY MCDEAN Temp work for Art Basel - Dec C/O to be voided -77,123.00 -3,829.32 -80,952.32 FEBRUARY CAMARATA December amount adjusted - correct typo -300.00 -14.90 -314.90 FEBRUARY JAFFER Correction - November CO reversal was incorrectly listed - C/O to subcontractor was issued. 17,000.00 844.09 17,844.09 FEBRUARY JAFFER Scope Reducion -24,000.00 -1,191.65 -25,191.65 FEBRUARY FLORIDA CIVIL Dewatering plan modification 9,202.00 456.90 9,658.90 FEBRUARY BANKER East façade acceleration 150,338.00 7,464.59 157,802.59 FEBRUARY BANKER Supply floor opening penetration north addition 100,000.00 4,965.21 104,965.21 SUBTOTAL 1,712,844.07 85,046.26 1,797,890.33 MARCH BRAZOS Scope Change - Interim Funding -83,000.00 -4,121.12 -87,121.12 MARCH CAMARATA Z-Wall Infills & Patching 5,309.00 263.60 5,572.60 MARCH ACOUSTI Temp work for Art Basel 8,765.10 435.21 9,200.31 MARCH ACOUSTI East Concourse - Unforseen conditions 88,210.00 4,379.81 92,589.81 MARCH DECON Lead abatement 219,342.00 10,890.78 230,232.78 Exhibit B1 4 of 9 EXHIBIT B1 MONTH SUBCONTRACTOR DESCRIPTION AMOUNT CSI CODEMARK-Ups*TOTAL COST MARCH EAST COAST METALS Temp work for Art Basel 20,600.00 1,022.83 21,622.83 MARCH BANKER Supply Floor opening penetration - N. Addition 133,253.00 6,616.29 139,869.29 MARCH BANKER CM RFI 2575 Beam @ Level 3 4,608.00 228.80 4,836.80 MARCH BANKER CM - RFI 2617 East Façade Plates 7,804.00 387.48 8,191.48 MARCH NFP Settlement - Reverse Interim Funding (June)-400,000.00 -19,860.83 -419,860.83 MARCH NFP Settlement - CM Contribution 600,415.00 29,811.85 630,226.85 MARCH NASH Settlement - Reverse Interim Funding (June)-721,426.00 -35,820.30 -757,246.30 MARCH NASH Settlement - CM Contribution 1,260,871.89 62,604.90 1,323,476.79 MARCH HJ Foundation Plant fee for opening 1,150.00 57.10 1,207.10 SUBTOTAL 1,145,901.99 56,896.41 1,202,798.40 APRIL - Interim NASH Settlement - CM Contribution - Settlement correction -59,643.89 -2,961.44 -62,605.33 APRIL - Interim NFP Settlement - CM Contribution - Settlement correction -28,402.18 -1,410.23 -29,812.41 APRIL - Interim ALPHA Settlement - Reverse Interim Funding (June)-420,000.00 -20,853.87 -440,853.87 APRIL - Interim ALPHA Settlement - Reverse Interim Funding (July)-330,000.00 -16,385.18 -346,385.18 APRIL - Interim ALPHA Settlement - CM Contribution 285,709.00 14,186.04 299,895.04 APRIL - Interim WPM Settlement - Reverse Interim Funding (Jan)-4,685.00 -232.62 -4,917.62 APRIL - Interim WPM Settlement - Reverse Interim Funding (Feb)-5,883.00 -292.10 -6,175.10 APRIL - Interim WPM Settlement - Reverse Interim Funding (Dec)-192,869.95 -9,576.39 -202,446.34 APRIL - Interim WPM Settlement - Reverse Interim Funding (Feb)-4,931.00 -244.83 -5,175.83 APRIL - Interim WPM Settlement - CM Contribution 814,668.00 40,449.95 855,117.95 APRIL - Interim R&M Settlement - Reverse Interim Funding (July)-700,000.00 -34,756.45 -734,756.45 APRIL - Interim R&M Settlement - Reverse Interim Funding (June)-2,000,000.00 -99,304.14 -2,099,304.14 APRIL - Interim R&M South FP&L Vault - Added Mat for Footing & Walls 94,098.00 4,672.16 98,770.16 APRIL - Interim R&M Settlement - CM Contribution 2,408,478.00 119,585.92 2,528,063.92 APRIL - Interim CAMARATA Temporary work for Art Basel 16 1,806.31 89.69 1,896.00 APRIL - Interim CAMARATA Settlement - Reverse Interim Funding (April)-1,806.31 -89.69 -1,896.00 APRIL - Interim CAMARATA Settlement - Reverse Interim Funding (March)-5,309.00 -263.60 -5,572.60 APRIL - Interim CAMARATA Settlement - CM Contribution 331,166.00 16,443.08 347,609.08 APRIL - Interim CM Fee Settlement - Change Order 34 6,000.00 297.91 6,297.91 APRIL - Interim CM Fee/Banker Settlement - Change Order 43 96,710.00 4,801.85 101,511.85 APRIL - Interim Banker Settlement - CM Contribution 3,712,187.00 184,317.77 3,896,504.77 APRIL - Interim TruSteel Settlement - CM Contribution 71,953.00 3,572.62 75,525.62 APRIL - Interim American Fireproofing Settlement - CM Contribution 34,622.00 1,719.05 36,341.05 APRIL - Interim Agyle Settlement - CM Contribution 301,060.00 14,948.25 316,008.25 APRIL - Interim OTIS Elevator 16.02 pit fill - Reclassed to CM from Allowance 2,696.00 133.86 2,829.86 APRIL - Interim Eugenio Settlement - CM Contribution 53,589.00 2,660.80 56,249.80 APRIL - Interim SAS Settlement - CM Contribution 40,441.00 2,007.98 42,448.98 APRIL - Interim Honeywell Settlement - Reverse Interim Funding (Sept)-450,000.00 -22,343.43 -472,343.43 APRIL - Interim Honeywell Settlement - CM Contribution 873,073.00 43,349.88 916,422.88 APRIL - Interim HJ Foundation Settlement - Reverse Interim Funding (June)-141,000.00 -7,000.94 -148,000.94 APRIL - Interim HJ Foundation Settlement - Reverse Interim Funding (March)-1,150.00 -57.10 -1,207.10 APRIL - Interim HJ Foundation Settlement - CM Contribution 119,311.00 5,924.04 125,235.04 APRIL - Interim HAYWARD BAKER Settlement - CM Contribution 77,272.00 3,836.71 81,108.71 SUBTOTAL 4,979,158.98 247,225.56 5,226,384.54 APRIL EAST COAST METALS Settlement - Reverse CM Contribution (March) -20,600.00 -1,022.83 -21,622.83 APRIL EAST COAST METALS Settlement - CM Contribution 112,897.00 5,605.57 118,502.57 APRIL Staging Concepts Settlement - CM Contribution 36,127.00 1,793.78 37,920.78 APRIL Tecta Settlement - CM Contribution 118,919.00 5,904.57 124,823.57 APRIL ISEC Settlement - CM Contribution 60,212.00 2,989.65 63,201.65 APRIL Harmon Settlement - Reverse Interim Funding (June)-160,000.00 -7,944.33 -167,944.33 APRIL Harmon Settlement - CM Contribution 782,755.00 38,865.41 821,620.41 APRIL Acousti Settlement - Reverse CM Contribution (Sept) -500,000.00 -24,826.04 -524,826.04 APRIL Acousti Settlement - Reverse CM Contribution (March) -23,501.00 -1,166.87 -24,667.87 APRIL Acousti Settlement - Reverse CM Contribution (Feb) -312,005.00 -15,491.69 -327,496.69 APRIL Acousti Settlement - CM Contribution 1,655,829.00 82,215.34 1,738,044.34 APRIL MCDean Settlement - Reverse CM Contribution (July & Nov)-938,643.00 -46,605.57 -985,248.57 APRIL MCDean Settlement - CM Contribution 2,108,923.00 104,712.39 2,213,635.39 APRIL Trident CM Interim Funding - CCD 21 - Kitchen Floor 30,000.00 1,489.56 31,489.56 APRIL Arazoza Settlement - CM Contribution -20,472.00 -1,016.48 -21,488.48 SUBTOTAL 2,930,441.00 145,502.46 3,075,943.46 MAY Tate Ornamental Settlement - CM Contribution 50,369.00 2,500.93 52,869.93 MAY Hollywood Woodwork Settlement - CM Contribution -1,204.00 -59.78 -1,263.78 MAY Won-Door Settlement - CM Contribution 30,106.00 1,494.83 31,600.83 MAY Over head door Settlement - CM Contribution 21,545.00 1,069.75 22,614.75 MAY Dash Door Settlement - CM Contribution 6,021.00 298.96 6,319.96 MAY Florida Blacktop Settlement - Reverse Interim Funding (June)-366,867.00 -18,215.71 -385,082.71 MAY Florida Blacktop Settlement - CM Contribution -4,552.00 -226.02 -4,778.02 MAY Florida Blacktop Settlement - Reverse CM Contribution (Sept) 106,876.00 5,306.61 112,182.61 MAY Duffy Lee Settlement - Reverse CM Contribution (March) -36,127.00 -1,793.78 -37,920.78 MAY David Allen Settlement - Reverse CM Contribution (Feb) 16,558.00 822.14 17,380.14 MAY HUFCOR Settlement - CM Contribution 13,758.00 683.11 14,441.11 MAY Baring Settlement - Reverse CM Contribution (July & Nov)38,235.00 1,898.45 40,133.45 MAY Decon Settlement - Reverse CM Contribution (July & Nov)-833,128.00 -41,366.53 -874,494.53 Exhibit B1 5 of 9 EXHIBIT B1 MONTH SUBCONTRACTOR DESCRIPTION AMOUNT CSI CODEMARK-Ups*TOTAL COST MAY Decon Settlement - Reverse CM Contribution (March)-219,342.00 -10,890.78 -230,232.78 MAY Decon Settlement - Reverse CM Contribution (July & Nov)-815,476.00 -40,490.07 -855,966.07 MAY Decon Settlement - Reverse CM Contribution (July & Nov)752,649.00 37,370.58 790,019.58 MAY CDPW Settlement - Reverse CM Contribution (July & Nov)-275,404.00 -13,674.38 -289,078.38 MAY CDPW Settlement - Reverse CM Contribution (July & Nov)78,655.00 3,905.38 82,560.38 MAY CDPW Settlement - Reverse CM Contribution (July & Nov)-4,243.00 -210.67 -4,453.67 MAY Florida Civil CM Interim Funding - CCD 21 - Kitchen Floor 22,920.00 1,138.03 24,058.03 SUBTOTAL -1,418,651.00 -70,438.96 -1,489,089.96 JUNE WPM Crane Pads @ west Side & South Loading dock 204,791.41 10,168.32 214,959.73 JUNE OTIS Settlement - CM Contribution 86,770.00 4,308.31 91,078.31 JUNE Underpower Settlement - CM Contribution 1,204.00 59.78 1,263.78 JUNE Underpower Settlement - Reverse CM Contribution (Dec)-1,938.98 -96.27 -2,035.25 SUBTOTAL 290,826.43 14,440.13 305,266.56 JULY R&M AESS Steel Shoring 166,517.00 8,267.91 174,784.91 JULY R&M AESS Steel Shoring 72,242.00 3,586.96 75,828.96 JULY Banker CM - RFI 2396 Baseplate conflict w/ rainwater pipes - ECO #21 3,681.00 182.77 3,863.77 JULY Banker CM - RFI 2465.1 Steel Support Beam Conflict - CR 303 - ECCO #22 7,656.00 380.14 8,036.14 JULY Tru-Steel Reinstallation and Repair of Catwalk - CO#8 86,885.37 4,314.04 91,199.41 JULY Tru-Steel Field Order 4 Revisions at the East Helix Roof - CO#9 Partially paid via CM 36,669.67 1,820.73 38,490.40 JULY NASH PH 2 Dewatering for Plumbing Work - ECO #21 129,367.22 6,423.35 135,790.57 JULY Ford AV Global Settlement - CM Settlement Adjustment ECO #2 -72,584.00 -3,603.95 -76,187.95 JULY FL Blacktop Temp Asphalt for May 2017 Turnover 55,233.86 2,742.48 57,976.34 JULY Smith Fence Barricades - ECO#8 192,556.47 9,560.83 202,117.30 JULY Smith Fence Fence Reconciliation through Feb 2017 - ECO#9 53,050.13 2,634.05 55,684.18 JULY Smith Fence Allowance for Future Fence Work - ECO#10 125,000.00 6,206.51 131,206.51 SUBTOTAL 856,274.72 42,515.81 898,790.53 AUGUST Alpha ECO#19 CM Settlement 376,600.00 18,698.97 395,298.97 AUGUST Camarata Masonry May 2017 Turnover Premium Time 15,701.00 779.59 16,480.59 AUGUST Banker Steel ECO#24 - CM RFI 2415 CMU Pocket Alternate Detail 32,724.00 1,624.81 34,348.81 AUGUST Banker Steel ECO#25 - CM RFI 2565 East Facade Differing Site Conditions at Top of Wall 3,537.00 175.62 3,712.62 AUGUST Banker Steel ECO#27 - CM Banker Settlement 460,000.00 22,839.95 482,839.95 AUGUST Banker Steel ECO#28 - Banker scope Deduct for Allowance 5 -250,000.00 -12,413.02 -262,413.02 AUGUST TRUSTEEL ECO#10 CM Settlement 33,017.15 1,639.37 34,656.52 AUGUST Acousti ECO#25 - CM PH1 Water Damage Drywall & Temp Roof Repairs at East Concourse 17,442.93 866.08 18,309.01 AUGUST Acousti ECO#28 CM Settlement 329,000.00 16,335.53 345,335.53 AUGUST Florida Blacktop ECO#05 Asphalt Patching on Washington Ave for MLB Fanfest Show 1,271.05 63.11 1,334.16 AUGUST CDPW ECO#5 - Phase 2 Area A1 West Damaged Suction and Layflat Hoses 4,402.65 218.60 4,621.25 AUGUST CDPW ECO#6 - Phase 2 Dewatering Zone 4 & 7 Septic Tank Installation 10,545.00 523.58 11,068.58 AUGUST CDPW ECO#7 - Phase 2 Dewatering Zone 2 Sanitary Run 8,335.51 413.88 8,749.39 SUBTOTAL 1,042,576.29 51,766.07 1,094,342.36 SEPTEMBER American Fireproofing ECO#06 - CM Settlement 20,774.00 1,031.47 21,805.47 SEPTEMBER Argyle ECO#04 - CM Settlement for door replacements &, adjustments 76,508.98 3,798.83 80,307.81 SEPTEMBER MC Dean ECO#21 - CM Settlement 145,000.00 7,199.55 152,199.55 SEPTEMBER Trident ECO#02 - Reverse Interim funding for CCD-21 - kitchen floor -30,000.00 -1,489.56 -31,489.56 SUBTOTAL 212,282.98 10,540.29 222,823.27 OCTOBER WPM ECO#23 - CM Settlement for various sitework issues 243,000.00 12,065.45 255,065.45 OCTOBER East Coast ECO#05 - CM Settlement for miscellaneous metals scope 54,720.93 2,717.01 57,437.94 OCTOBER Tecta ECO#11 - CM Settlement for various roofing issues 50,000.00 2,482.60 52,482.60 OCTOBER MC Dean ECO#21 - September CM Settlement - reversed -145,000.00 -7,199.55 -152,199.55 OCTOBER MC Dean ECO#21 - CM Settlement 151,000.00 7,497.46 158,497.46 OCTOBER Brazos ECO#05 - CM Settlement 4,140.00 205.56 4,345.56 OCTOBER Harmon ECO#08 - CM Settlement for various curtainwall issues 60,000.00 2,979.12 62,979.12 OCTOBER Acousti ECO#39 - RFI 2846 Ceiling enclosure for chiller plant 52,745.02 2,618.90 55,363.92 OCTOBER Duffy Lee ECO#05 - CM Settlement for extra floor leveling and transitions 19,935.00 989.81 20,924.81 OCTOBER Eugenio ECO#08 - CM Settlement for additional painting scope due to field conditions 31,255.00 1,551.88 32,806.88 OCTOBER CDPW ECO#08 - CM Settlement for additional dewatering scope 53,394.30 2,651.14 56,045.44 OCTOBER R&M ECO#28 - Acceleration and interim funding for hurricane prep 144,740.00 7,186.64 151,926.64 SUBTOTAL 719,930.25 35,746.03 755,676.28 Exhibit B1 6 of 9 EXHIBIT B1 MONTH SUBCONTRACTOR DESCRIPTION AMOUNT CSI CODEMARK-Ups*TOTAL COST NOVEMBER East Coast ECO#07- CM Settlement - MEP Frames/OHD Openings 77,971.31 3,871.44 81,842.75 NOVEMBER Tru-Steel ECO#13- CM Settlement - Miscellaneous welding 11,818.48 586.81 12,405.29 NOVEMBER Tru-Steel ECO#14- CM Settlement - Elec Feeder Supports/Extend Partition 12,853.00 638.18 13,491.18 NOVEMBER Tru-Steel ECO#14- Pre-Funding of Owner Changes (RFIs)182,147.00 9,043.98 191,190.98 NOVEMBER Thermo Seal ECO#02- U-Line East Façade Joint Sealing 17,372.00 862.56 18,234.56 NOVEMBER Superior Landscaping ECO#04 Global Settlement 28,601.00 1,420.10 30,021.10 NOVEMBER Jaffer Issue VOID- REVERSAL 24,000.00 1,191.65 25,191.65 NOVEMBER Jaffer ECO#06- Global Settlement 29,383.00 1,458.93 30,841.93 NOVEMBER Jaffer ECO#06- Reverse Interim Funding for CCD 21 -85,000.00 -4,220.43 -89,220.43 NOVEMBER PJ Striping ECO#02- Global Settlement- CM Contribution 1,781.00 88.43 1,869.43 NOVEMBER Rite Hite ECO#02- Global Settlement- CM Contribution 452.00 22.44 474.44 NOVEMBER Big Picture ECO#01- Global Settlement- CM Contribution -9,254.00 -459.48 -9,713.48 NOVEMBER Homestead Paving ECO#01- Global Settlement- CM Contribution -20,582.00 -1,021.94 -21,603.94 NOVEMBER Florida Civil ECO#04- Reverse Interim Funding -9,202.00 -456.90 -9,658.90 NOVEMBER Florida Civil ECO#04- Global Settlement - CM Contribution 10,330.00 512.91 10,842.91 NOVEMBER Acousti ECO#42- Additional work on Z-Walls 1,494.62 74.21 1,568.83 NOVEMBER Acousti ECO#42- Level 3 - Repair Several Areas @ Bridge 3,251.68 161.45 3,413.13 NOVEMBER Acousti ECO#42- Phase 1 - Service Corridor 22,944.92 1,139.26 24,084.18 NOVEMBER Acousti ECO#42- Repair of framing Elect room 1.29.35 & TR Room 1.29.12 3,510.08 174.28 3,684.36 NOVEMBER Acousti ECO#22- CM - Interim Funding - CCD 102- Art Basel 2017 Temp. genorator -810534 100,000.00 4,965.21 104,965.21 NOVEMBER MC Dean ECO#22- CM - Interim Funding - CCD 102- Art Basel 2017 Temp. genorator -810534 475,624.00 23,615.72 499,239.72 SUBTOTAL 879,496.09 43,668.80 923,164.89 DECEMBER Mardale ECO#05 CM Settlement- Restroom rework cuting of pilasters 1.27.02 & 03, costs to uninstall and reinstall floor matts do to concrete issues. 47,901.00 2,378.38 50,279.38 DECEMBER Nash ECO#33 Additional Natural Gas System Reactivation & Drop Test 1,658.53 82.35 1,740.88 DECEMBER American Fire ECO#08 Fireproofing Patching - BC &CM 19,741.00 980.18 20,721.18 DECEMBER Acousti ECO#49 CM - Level 3 - Repair Several Areas at Bridge 10,508.47 521.77 11,030.24 DECEMBER Acousti ECO#56 CM: Studs damaged at Level 2- Area 14 1,034.65 51.37 1,086.02 DECEMBER Acousti ECO#56 PH 2 Area 19 Level 1 Electrical Room 1.19.04 - Drywall Overtime Work 970.09 48.17 1,018.26 DECEMBER Acousti ECO#56 Area 19 West POD Wall Damage 13,387.46 664.72 14,052.18 DECEMBER SC Railings ECO#05 Field Orders-17 thru 22 Stair Railing Area 16 Lvl 3, SS Clading E Concourse, Glass remake E. Concourse, SS Gate remake, E Concourse glass remake #2. Lvl. 1 Area 7 Loading dock ramp mod. 23,542.63 1,168.94 24,711.57 DECEMBER Camarata ECO#09 CM Settlement- Back Charges, Elect Rm 1.09.10, Hall C Chilled Water pipes, RFI 2215.1 CMU Infill, Exposed clips @ FPL vault,Add- CMU Elect Rm. 1.06.04 & 1.09.10 93,725.13 4,653.65 98,378.78 DECEMBER Clark CM ContrClark Global Settlement- CM Contribution- GR 36,127.00 1,793.78 37,920.78 DECEMBER Clark CM ContrClark Global Settlement- CM Contribution- GMP Allowances -963,391.00 -47,834.36 -1,011,225.36 SUBTOTAL -714,795.04 -35,491.05 -750,286.09 TOTAL SINCE INCEPTION $23,734,550.48 $1,178,469.59 $24,913,020.07 General Requirements MONTH SUBCONTRACTOR DESCRIPTION AMOUNTCSI CODE MARK-Ups*TOTAL COST MAY GEOSYNTEC DERM approval $57,690.75 $2,864.47 $60,555.22 SUBTOTAL 57,690.75 2,864.47 60,555.22 JUNE LIFE SAFETY Costs associated with the separation and life safety costs 500,000.00 24,826.04 524,826.04 SUBTOTAL 500,000.00 24,826.04 524,826.04 JULY ACOUSTI Procurement realocation from CM cont. for temporary wall 132,953.01 6,601.39 139,554.40 JULY BISCAYNE ENGINEERING Procurement realocation from CM cont. for Surveying - Increase Contract 75,000.00 3,723.91 78,723.91 JULY GEOSYNTEC Procurement realocation from CM cont. for NPDES permits 13,348.06 662.76 14,010.82 JULY GEOSYNTEC Procurement realocation from CM cont. for NPDES permits 88,355.59 4,387.04 92,742.63 JULY HURRICANE PROTECTION Procurement realocation from CM cont. for Hurricane Preparation 50,000.00 2,482.60 52,482.60 JULY MICHEAL WOOD Procurement realocation from CM for FDEP permits 3,192.90 158.53 3,351.43 Exhibit B1 7 of 9 EXHIBIT B1 MONTH SUBCONTRACTOR DESCRIPTION AMOUNT CSI CODEMARK-Ups*TOTAL COST JULY MODSPACE Procurement realocation from CM for Owner Trailer 30,893.69 1,533.94 32,427.63 JULY OWNER COST Realocation from CM for Life Safety expenses (ie Fire Watch) 320,922.14 15,934.45 336,856.59 JULY OWNER - Fentress Architects Onsite Visits CM expense for additional Design Team site visits and alternate design configurations 148,000.00 7,348.51 155,348.51 SUBTOTAL 862,665.39 42,833.12 905,498.51 AUGUST BISCAYNE ENGINEERING Procurement realocation from CM for additional Surveying - contract increase 150,000.00 7,447.81 157,447.81 AUGUST VALLEY FIELD Cost for the repair of damaged irrigation lines at Filmore 1,538.00 76.36 1,614.36 AUGUST OWNER COST Realocation from CM for Life Safety expenses (ie Fire Watch) -320,922.14 -15,934.45 -336,856.59 AUGUST OWNER COST Realocation from CM for Life Safety expenses (ie Fire Watch) 370,138.10 18,378.12 388,516.22 AUGUST BRAND ENERGY Procurement realocation from CM for scaffolding 35,689.00 1,772.03 37,461.03 AUGUST OWNER - Fentress Architects Onsite Visits CM expense for additional Design Team site visits and alternate design configurations - ERROR -148,000.00 -7,348.51 -155,348.51 AUGUST OWNER - Fentress Architects Onsite Visits CM expense for additional Design Team site visits and alternate design configurations - ACTUAL 148,999.00 7,398.11 156,397.11 SUBTOTAL 237,441.96 11,789.49 249,231.45 SEPTEMBER OWNER COST Realocation from CM for Life Safety expenses (ie Fire Watch) -370,138.10 -18,378.12 -388,516.22 SEPTEMBER OWNER COST Realocation from CM for Life Safety expenses (ie Fire Watch) 391,261.00 19,426.92 410,687.92 SEPTEMBER MICHEAL WOOD Procurement realocation from CM for FDEP permits 10,080.00 500.49 10,580.49 SEPTEMBER BRAND ENERGY Procurement realocation from CM for scaffolding -35,689.00 -1,772.03 -37,461.03 OCTOBER ACOUSTI Temp exterior impact partition - GR 87,060.84 4,322.75 91,383.59 SEPTEMBER GLE Haz-mat survey west concourse 18,570.00 922.04 19,492.04 SUBTOTAL 101,144.74 5,022.05 106,166.79 OCTOBER GLE Haz-Mat survey west concourse -18,570.00 -922.04 -19,492.04 OCTOBER OWNER COST Realocation from CM for Life Safety expenses (ie Fire Watch) -391,261.00 -19,426.92 -410,687.92 OCTOBER OWNER COST Realocation from CM for Life Safety expenses (ie Fire Watch) 401,877.54 19,954.05 421,831.59 OCTOBER ACOUSTI Temp exterior impact partition - GR -87,060.84 -4,322.75 -91,383.59 OCTOBER ACOUSTI Credit for Bond Rate Adjustment -431.00 -21.40 -452.40 OCTOBER ACOUSTI Hurricane Matthew Preparation - October 16 12,298.16 610.63 12,908.79 SUBTOTAL -83,147.14 -4,128.43 -87,275.57 NOVEMBER ACOUSTI Hurricane Matthew Preparation - October 16 -12,298.16 -610.63 -12,908.79 NOVEMBER HURRICANE PROTECTION Additional funds for Hurricane Protection 15,000.00 744.78 15,744.78 NOVEMBER HURRICANE PROTECTION Additional funds for Hurricane Protection 16,000.00 794.43 16,794.43 NOVEMBER SCAFFOLDING SHRINKWRAP Temp work for Art Basel - Engineering for NE egress tunnel 2,875.00 142.75 3,017.75 NOVEMBER SCAFFOLDING SHRINKWRAP Extended rental for East Concourse 33,535.00 1,665.08 35,200.08 NOVEMBER SCAFFOLDING SHRINKWRAP Adjustments to East Concourse 11,955.00 593.59 12,548.59 SUBTOTAL 67,066.84 3,330.01 70,396.85 DECEMBER EVENTSTAR Temp work for Art Basel - metal stairs 56,828.00 2,821.63 59,649.63 DECEMBER HURRICANE PROTECTION Additional funds/NASH 20,000.00 993.04 20,993.04 DECEMBER HURRICANE PROTECTION Additional funds for Hurricane Protection 15,000.00 744.78 15,744.78 DECEMBER GEOSYNTEC Environmental Consultant 8,545.00 424.28 8,969.28 DECEMBER OWNER COST Reallocation from CM for Life Safety expenses (ie Fire Watch) -401,877.54 -19,954.05 -421,831.59 DECEMBER OWNER COST Reallocation from CM for Life Safety expenses (ie Fire Watch) 464,173.00 23,047.15 487,220.15 DECEMBER TRUSTEEL Temporary Bracing 2,531.00 125.67 2,656.67 SUBTOTAL 165,199.46 8,202.50 173,401.96 JANUARY OWNER COST Reallocation from CM for Life Safety expenses (ie Fire Watch) -464,173.00 -23,047.15 -487,220.15 JANUARY OWNER COST Reallocation from CM for Life Safety expenses (ie Fire Watch) 509,844.00 25,314.81 535,158.81 JANUARY FPL/FILMORE VAULT Vault upgrade at Fillmore 70,144.00 3,482.79 73,626.79 SUBTOTAL 115,815.00 5,750.45 121,565.45 Exhibit B1 8 of 9 EXHIBIT B1 MONTH SUBCONTRACTOR DESCRIPTION AMOUNT CSI CODEMARK-Ups*TOTAL COST FEBRUARY OPTIKA Misc Invoices - Art Basel 2016 9,588.00 476.06 10,064.06 FEBRUARY OWNER - Fentress Architects Onsite Visits CM expense for additional Design Team site visits and alternate design configurations 112,649.00 5,593.26 118,242.26 FEBRUARY GLE October - GLE correction no credit was given 18,570.00 922.04 19,492.04 This is GLE Base Contract FEBRUARY Hurricane Protection Credit for monies not used -15,000.00 -744.78 -15,744.78 FEBRUARY TRUSTEEL Rein. Existing Catwalk Grating 75,000.00 3,723.91 78,723.91 SUBTOTAL 200,807.00 9,970.48 210,777.48 MARCH BISCAYNE ENGINEERING Survey - Contract increase 135,574.00 6,731.53 142,305.53 MARCH Walter P Moore Weekly site visits 65,000.00 3,227.38 68,227.38 SUBTOTAL 200,574.00 9,958.91 210,532.91 MAY Acousti FO #5 - Temporary Lid for Electrical Room 1.06/1.09 41,125.00 2,041.94 43,166.94 MAY Acousti May 2017 Turn over 300,132.37 14,902.19 315,034.56 SUBTOTAL 341,257.37 16,944.14 358,201.51 JUNE Tecta Temp Waterpffoing - May Turnover 30,000.00 1,489.56 31,489.56 JUNE Eugenio Painting of AESS Welds - GR 105,558.85 5,241.22 110,800.07 SUBTOTAL 135,558.85 6,730.78 142,289.63 JULY Acousti FO #5 - Temporary Lid for Electrical Room 1.06/1.09 (Reverse - Paid thru GR) -41,125.00 -2,041.94 -43,166.94 JULY Acousti May 2017 Turn over (Reverse - Paid thru GR)-300,132.37 -14,902.19 -315,034.56 JULY Tecta Temp Waterpffoing - May Turnover (Paid thru GR)-30,000.00 -1,489.56 -31,489.56 JULY Eugenio Painting of AESS Welds - GR -105,558.85 -5,241.22 -110,800.07 SUBTOTAL -476,816.22 -23,674.91 -500,491.13 TOTAL SINCE INCEPTION $2,425,258.00 $120,419.08 $2,545,677.08 TOTALS Buyout $1,202,676.00 $59,715.35 $1,262,391.35 Trade Costs 23,734,550.48 1,178,469.59 24,913,020.07 General Requirements 2,425,258.00 120,419.08 2,545,677.08 Total CM Contingency Use $27,362,484.48 $1,358,604.02 $28,721,088.50 * Mark ups include insurance, bond and CM fees. **May amounts are $156,070 lower than reported in May due to the reconciliation/audit process. Exhibit B1 9 of 9 EXHIBIT B2 Miami Beach Convention Center Expansion & Renovation Project Owner's Contingency Report Through December 2017 SUMMMARY ORIGINAL OWNER'S CONTINGENCY $35,000,000 MODIFICATIONS (ADDS) Bond offering additional proceeds $147,449 Total Modifications $147,449 USES Jun 2016 4,630 Jul 2016 - Aug 2016 29,967 Sep 2016 - Oct 2016 2,518,080 Nov 2016 (96,710) Dec 2016 179,685 Jan 2017 794,486 Feb 2017 (58,386) Mar 2017 4,321,164 Apr 2017 16,125,999 May 2017 - Jun 2017 78,710 Jul 2017 (16,224) Aug 2017 (1,465,262) Sep 2017 131,865 Oct 2017 4,378,844 Nov 2017 300,000 Dec 2017 (50,785) Total Use 27,176,062 TOTAL CONTINGENCY USE ($27,028,613) REMAINING OWNER'S CONTINGENCY $7,971,387 MONTH CHANGE ORDER #DESCRIPTION Trade Cost Mark-ups AMOUNT June 32 Deductive change order against CM's contingency for extra site visits by design team - -148,999 June 34 Deductive change order against's CM's fee for design remediation work - -6,000 June 35 Additional fire rated 2nd floor service corridor wall 107,849.83 5,354.97 113,205 June 36 Additional construction fence panels 44,228.45 2,196.03 46,424 SUBTOTAL 152,078.28 7,551.00 4,630 August 40 New 8” sanitary sewer line on Washington Avenue 28,549.47 1,417.54 29,967 SUBTOTAL 28,549.47 1,417.54 29,967 October N/A US Cost - GMP Reconciliation 945,080 October N/A Permit & Plan Reviews 855,000 October N/A Design Miami 2016 - Generators 408,000 October N/A Additional amount needed for the first 12 months of warehouse lease payments for Spectra Staff (Total costs of months 1-12: 531,316.50)287,800 October N/A Spectra - Cost associated with relocation of the warehouse equipment 22,200 SUBTOTAL - - 2,518,080 November 43 Clark / Banker backcharge for additional structural engineering services approved for Fentress in Amendment 20.-96,710 SUBTOTAL - - -96,710 December N/A Design budget adjustment to increase Fentress PO through Amendment 23. 179,685 SUBTOTAL - - 179,685 January N/A Design budget adjustment to increase Fentress PO through Amendment 24 18,625 January 52 Additional cost of generator 319,160.50 15,846.98 335,007 January 57 Honeywell Interim Funding 420,000.00 20,853.88 440,854 SUBTOTAL 739,160.50 36,700.86 794,486 February 54 Clark backcharge for additional structural engineering services required due to non- conforming work -20,000 February 55 Clark backcharge for extra design team site visits and additional structural engineering design changes requested by Clark -112,649 February 56 Switchgear replacement due to arc flash incident 70,750.00 3,512.89 74,263 SUBTOTAL 70,750.00 3,512.89 -58,386 March 58 Nash - GMP Reconciliation 2,729,128.11 198,112.05 2,927,240 March 61 NFP - GMP Reconciliation 1,299,584.82 94,339.08 1,393,924 Exhibit B2 Page 1 of 2 EXHIBIT B2 MONTH CHANGE ORDER #DESCRIPTION Trade Cost Mark-ups AMOUNT SUBTOTAL 4,028,712.93 292,451.13 4,321,164 April 64 Reverse Nash - GMP Reconciliation (2,729,128.11)(198,112.05) -2,927,240 April 64 Reverse NFP - GMP Reconciliation (1,299,584.82)(94,339.08) -1,393,924 April 65 Removal of Park Allowance from Clark's GMP (10,000,000.00)- -10,000,000 April 66 GMP Reconciliation 37,627,222.00 1,808,836.00 39,436,058 April 67 GMP Reconciliation - Pre-Construction Services fee balance 1,037,626.00 - 1,037,626 April N/A Reimbursement of Design Miami 2016 generators cost per Resolution 2017-29830 - -408,000 April N/A Reimbursement of temporary FPL service for Art Basel 2016 per Resolution 2017-29830 - -148,726 April N/A Reimbursement of Spectra's building operation costs per Resolution 2017-29830 - -518,000 April N/A Remove additional funds previously allocated to FF&E -250,000 April N/A Remove additional funds previously added to raise Carl Fisher Clubhouse -1,000,000 April N/A Close PO for Clark Pre-GMP CM Fee -1,037,629 April N/A Reimbursement of stormwater infrastructure / road raising per Resolution 2017-29829 -4,513,591 April N/A Re-roofing of existing building structure (funded from separate capital renewal and replacement project)-1,689,254 April N/A Reimbursement of temporary kitchen trailer costs for Art Basel 2016 per Resolution 2017- 29830 -76,267 April N/A Reimbursement of temporary partition per Resolution 2017-29830 -1,010,500 April N/A Reimbursement of Art Basel temporary work for 2016 show per Resolution 2017-29830 -2,542,220 April N/A P-Lot Park allowance 5,000,000 April N/A Additional allocation for permit fees 39,800 April N/A Design budget adjustment to increase Fentress PO through Amendment 26 27,610 April N/A Cost estimating budget reduction -302,202 April N/A Budget reduction for miscellaneous (Other) costs -1,597,542 SUBTOTAL 24,636,135.07 1,516,384.87 16,125,999 June N/A JLL Amendment No. 9 - Additional consulting services - 160,000 June N/A Fentress Amendment 28 - design revisions associated with relocation of 19th St pump station - 2,585 June N/A Mark-ups associated with re-roofing scope of work - funded from separate capital renewal and replacement project -83,875 SUBTOTAL 0.00 0.00 78,710 July 68 Additional power requirements necessary in the DMARC room 4,812.00 238.93 5,051 July 73 Reverse CO 56 - MC Dean (70,750.00)(3,512.89) -74,263 July 75 Additional door hardware at East Concourse to accommodate the needs of the events, building operator and project phasing. 50,481.00 2,506.49 52,987 SUBTOTAL -15,457.00 -767.47 -16,224 August 76 Scope removal - Canal Seawall (1,500,000.00)(74,478.10) -1,574,478 August 77 Addition of a drywall soffit at East Concourse - work associated with acoustical panel ceiling connection issues. 45,990.16 2,283.51 48,274 August 78 Deductive change order to cover additional arch / eng services performed by A/E due to non conforming field conditions related to RFI 3251 / NCR 1255 -20,875 August 79 Installation of water meters 1,959.00 97.27 2,056 August 81 Field modification of urinal screens as directed by the A/E for ADA compliance 1,226.00 60.88 1,287 August 82 Construction Change Directive #022 - new sanitary sewer line for Carl Fisher Clubhouse 74,315.00 3,689.90 78,005 August 87 Repairs to fire protection line in north loading dock damaged during an event 447.00 22.20 469 SUBTOTAL -1,376,062.84 -68,324.34 -1,465,262 September 88 Deductive change order against CM Contingency for additional design services - -10,000 September 89 Cost above the GMP allownance for the rooftop ballroom trellis 22,651.99 1,124.72 23,777 September 90 Additional cost associated with weatherproofing the rooftop parking crash walls 60,955.00 3,026.54 63,982 September 92 Fire rated enclosure around gas line in egress area required by Code 10,848.94 538.67 11,388 September 94 AIPP - De-scope expansion joint covers for Sarah Morris walls (1,420.00)(70.48) -1,491 September N/A Design budget adjustment to increase Fentress PO through Amendment 33 44,210 SUBTOTAL 93,035.93 4,619.45 131,865 October 74 CCD 021 - DRER Sewer main revisions, Convention Center Dr. and Meridian Road grading and reconfiguration revisions, and south dock grading revisions 360,980 17,924 378,904 October 96 Builders Risk Claim - Rain Event 8/1/17 1,696,601 84,240 1,780,841 October N/A Budget reallocation to Other for utilities bills 1,277,579 October N/A Budget reallocation to Legal for monthly outside legal council 110,000 October N/A Budget reallocation for Testing / Inspections 831,520 SUBTOTAL 2,057,581 102,163 4,378,844 November N/A Art Basel expenses incurred in connection to the west side entrance and concourse - - 300,000 SUBTOTAL - - 300,000 December 100 Deductive change order against CM Contingency for additional submittal reviews by Fentress Architects. - - -50,785 SUBTOTAL - - -50,785 TOTAL SINCE INCEPTION 30,414,483.62 1,895,709.15 27,176,062 Exhibit B2 Page 2 of 2 Area % of Total Workers Total Hours Worked Zip Lists Miami Beach 1 %39,858 Miami Dade County 63 %1,461,149 Total Local Area Workers 64 %1,501,007 Employees Not In Specified Zip Lists 36 %1,080,232 Demographic Profile African American 19.05 %324,383 Native American 0.19 %6,148 Asian 0.23 %4,063 Hispanic 40.84 %1,110,094 Caucasian 12.04 %284,124 Other 27.64 %852,427 Male 96.58 %2,527,321 Female 3.42 %53,918 Veteran 0.04 %800 Disadvantaged 0.02 %18 Total Employees 2,581,239 EXHIBIT C LOCAL WORKER UTILIZATION REPORT From Date: 10/1/15 To Date:12/31/2017 5,264 1 0.00 % 2 0.03 % 180 2.09 % 5,084 97.91 % 1,455 33.02 % 634 11.01 % 2,150 43.01 % 12 0.16 % 10 0.24 % 1,003 12.57 % 1,897 41.85 % 3,367 58.15% 3,306 56.61 % 87 1.54 % Total Number of Workers % of Total Hours Worked Page 1 of 1 City of Miami Beach | 1700 Convention Center Drive Miami Beach, FL 33139 | 305.673.7010 | www.mbccfuture.com Miami Beach Convention Center Renovation Project December 2017 - Media Report Social Media Posts for December 2017 Posted to Twitter - Published December 18, 2017Posted to Twitter - Published December 18, 2017 EXHIBIT D City of Miami Beach | 1700 Convention Center Drive Miami Beach, FL 33139 | 305.673.7010 | www.mbccfuture.com Newsletter & Infographic: Sent via E-blast Sent via E-blast - Published December 5, 2017 December 5, 2017 - Newsletter City of Miami Beach | 1700 Convention Center Drive Miami Beach, FL 33139 | 305.673.7010 | www.mbccfuture.com December 15, 2017 - Newsletter Sent via E-blast - Published December 15, 2017 City of Miami Beach | 1700 Convention Center Drive Miami Beach, FL 33139 | 305.673.7010 | www.mbccfuture.com December 15, 2017 - Newsletter Sent via E-blast - Published December 15, 2017 City of Miami Beach | 1700 Convention Center Drive Miami Beach, FL 33139 | 305.673.7010 | www.mbccfuture.com December 15, 2017 - Newsletter Sent via E-blast - Published December 15, 2017 City of Miami Beach | 1700 Convention Center Drive Miami Beach, FL 33139 | 305.673.7010 | www.mbccfuture.com December 29, 2017 - Newsletter Sent via E-blast - Published December 29, 2017 City of Miami Beach | 1700 Convention Center Drive Miami Beach, FL 33139 | 305.673.7010 | www.mbccfuture.com December 29, 2017 - Newsletter Sent via E-blast - Published December 29, 2017 City of Miami Beach | 1700 Convention Center Drive Miami Beach, FL 33139 | 305.673.7010 | www.mbccfuture.com December 29, 2017 - Newsletter Sent via E-blast - Published December 29, 2017