LTC 220-2002
CITY OF MIAMI BEACH
C I V D Office of the City Manager
m
02 SFP ? 6 PML?eft~r to Commission No. O?~ - ~COd-
: ~ ! T' I-"'! [-'I''' 5 8 r" I e r
'.of , ~ ~,.!' L ',_ " ~, \ i Ii_
From:
Mayor David Dermer and Members of the City Commission
Jorge M. Gonzalez \ ,~'
City Manager 0 ,.;.r 0
2001 Collins Avenue - Sasson Hotel
Emergency Demolition Order Status Report
pate: September 20,2002
To:
Subject:
On October 10, 1995, the former Joint Design Review/Historic Preservation Board (Joint
Board) approved the Setai development project (ORB File No. 6647 J), which consisted of
a 36 story condominium tower and the restoration of the Sasson Hotel (formerly
Dempsey's Vanderbilt Hotel). The project was approved with a Floor Area Ratio (FAR) of
3.93 and a maximum building height of approximately 400 feet.
The project was eventually permitted and construction began. The project became legal
non-conforming in 1998 when the City Commission adopted comprehensive revisions to
the City Code that substantially lowered maximum allowable densities and height
throughout the City. Under the current code, the maximum allowable FAR for the project
would be 2.0 and the maximum height would be 13 stories/120 feet.
Although the project experienced a temporary suspension of construction during a change
in ownership, the developer was able to maintain the original Building Permit and
construction of the project has resumed. As work on the restoration of the existing Sasson
Hotel progressed, the Building Official received three (3) structural reports delineating the
severe structural deterioration of the Sasson building. Such reports also identified the
significant risk that would be created during the process of removing and rebuilding the
deteriorated structural components of the building's exterior facade.
Additionally, neither the Engineer of record nor the remedial work Engineer of record would
guarantp.e the life expectancy of the restored existing structure. All of the engineer~
concluded that the structure is an imminent danger to the public safety and that the
building should be demolished.
The Building Official and the City's Chief Structural Engineer reviewed the reports and
inspected the structure and concurred with the findings of the professional Engineers.
Pursuant to the requirements of the Florida Building Code, the Building Official issued an
Emergency Demolition Order on September 12, 2002 for the total demolition of the
building.
The Historic Preservation Board held an emergency meeting on September 17, 2002 to
discuss the demolition order. The matter will be coming back before the Historic
Preservation Board on October 8, 2002 as a formal application for an "after-the-fact
Page: 2
Date: September 20, 2002
LTC - Sasson Hotel Emergency Demolition - Status Report
Certificate of Appropriateness for Demolition, as well as a modification to the project to
reconstruct the building.
JMG:i1t~M
F:\PLAN\$ALLICM_RESPlSASOONDEMO.L TC.DOC
c: Murray Dubbin, City Attorney
Gary Held, First Assistant City Attorney
Rhonda Montoya, First Assistant City Attorney
Bob Parcher,CltyCterk
Phil Azan, Building Official
Jorge G. Gomez, Planning Director
William Cary, Director of Design, Preservation and Neighborhood Planning
Thomas R. Mooney, Design and Preservation Manager
City of Miami Beach
Memo
To: Philip Azan Building OfficiaV Director
From: Mohammed Partovi, P.E. Chief Structural Engineer
cc: Richard McConachie Chief Building Inspector
Date: 09/12102
Re: Setai Hotel
Based on the Structural observation of the above project on Friday August 23, 2002,
as well as reports by:
1. Robert H. Schuler, P.E. of Wingerter Laboratories Inc. dated July 17, 2002.
2. Eric L. Edelson, P.E. of Tadjer-Cohen-Edelson Associates, Inc. dated September
6,2002 (Engineer of record for the exterior wall, delegated by Raul Puig, P.E.).
3. Raul A. Puig, P.E. of The Raul Puig Group, P.A. dated September 11, 2002
(Engineer of record).
My opinion is that the structure located at 2009 Collins Avenue is a major threat to
public as well as the workers safety and could collapse at any time without a
waming.
With a continued possibility of structural failure, my recommendation is to demolish
, the entire structure under a supervision of Special Inspector holding a Professional
Engineering license as soon as possible.
. Page 1
.
. ..'
.' / /' ~1]E!J
(9.
THE RAUL PUIG GROUP, P.A./CONSULTING ENGINEERS
9200 SOUTH DADELAND BLVD. · SUITE 710 · MIAMI, FLORIDA 33156
TELEPHONE (305) 670-9858 · FAX (305) 670-9862
-
September 11, 2002
Mr. Philip Azan
Building Director/ Official
City of Miami Beach Building Department
1700 Convention Center Drive, 200 Floor ,
Miami Beach, FL 33139
RE: The Setai Hotel
Dear Mr. Azan,
The Raul Puig Group as the Engineer of Record has been involved in the Setai Hotel
project for the past 5 years. We performed the original inspection of the Sasson Hotel
existing structural condition in 1998. Our report based on visual observations indicated
that the structural components of the building had signs of concrete deterioration and
delamin~tion. Even though a significant repair scope was required at that time, it was our
belief that the building was in acceptable condition as a restoration project. In 1998
Wingerter Laboratories Inc. inspected the building and performed Swiss Hammer testing
as well as Subsurface Interface Radar survey, and gave their recommendations on the
repair procedures required to restore the building.
The Setai Owners retained Tadjer-Cohen-Edelson Associates, Inc. (TCE) who specializes
in the project reStorations and developed the repair design required to restore the Setai
Hotel. TeE acting as a specialty engineer on the project performed a number of site visits
in order to evaluate the building structural condition, and developed the facade
restoration scope including the required ~ade bracing. However it was impossible for
TCE to predict the exact extent of deterioration prior to the beginning of the repair
process. Since the commencement of repairs parts of the fa~e separated from the
building and fell down on the ground without warning, creating an imminent danger and
threat to public safety.
At the same time Wmgerter Laboratories performed structural re-inspection of the
project to determine the magnitude of the building deterioration at the present time. The
report dated July 17, 2002 prepared by Wmgerter Laboratories concluded that,the
present extent of the building deterioration will require virtually the entire replacement of
the building structural elements including the fayade framing.
Based on the existing condition of the Setai Hotel building, the report prepared by the
W..!l!B~~~~~~~ben-~eIsonAssociat~we
beti~e::tlii:, e:,.entiie.'exig~~jhJmd~.J;t~o1isli@~Our mam concern, which I
.
;-.-, B]E!J "'H~~E" RAU L PlJlG GROUP, P.A.I CONSULT'Ne ENe'NEEAS
~... 9200 SOUTH DADELAND BLVD.'.Sl.IITE 710'. MIAMI, FLORIDA 33156
~ TELEPHONE (305) 670-9858 · FAX (305) 670-9862
~
.'
am sure we all agree o~~"e"~~t4jf.f~t<rp.u1iIi~..s.!Ls~~f6'y the Setai Hotel
existing condition. ' ;
7
/L
:7
" :44
rrcm-ridJ.r Ceh.n Edllsen Asseclitls
301-588-186&
T-711 P.DDZ/DDZ F-745
I.
/0'.
"\
'-
September 6, 2002
Tadjer.cohen-Ede/son Associates. Inc.
Consulting Structural Engineers
www.radjcrco.com
01l('r Four [)~cad~J OfSupn-ior Scrr,i(;!
Mr. Phil Azan
Building Official
City of Miami Beach
1700 Convention Center Drive
Miami Beach, FL 33139
Re: The Setai Hotel
2009 Collins Avc.
Dear Dan:
Pursuant to our meeting with the City of Miami Beach Official5 on August 26. let me share my
concerns.
An entirely new facade will have numerous advantages over a re:.tored facadc;
· All materials will be new. Although the stroctuTal integrity would be restored and in the
repaired facade with all columns being replaced and more than 50% of lhe bt.cun
reinforcement either cleaned of rust or replaced, some cars with the potential for future
corrosion damage will remain. Thus in the repaired facade. future repairs will be
necessary_
· The repaired facade must always be monitored for possible damage and deterioration. As
future damage occurs it must be corrected before safety is compromised and the facade
poses an imminent danger to the public. A repaired tacade can be safely maintained and
even though a new facade still requires so.me maintenanc:, the advantage of a new facade
, is an increase in public safety with less uncertainty.
· SiJ::oce commencement of the repairs, at least one piece of the facade weighing several
hundred pounds dislodged and fell to the ground without warning. Currently; the facade
poses an imminent danger to the public. Until repair of the facade is completed, there is a
continued possibility of imminent danger and a threat to public safety.
I believe this requires you immediate attention. If needed, please do not hesitate to call me.
SLnCu ~
Eric L. Edelson, P .E.
Vice President
Ke .
t:;\Word Oocs\Sc1lli Jolotd\Setai Cil)' ofMiomi resporue rt".doc
livan Con en. P.E. Eric L Edel,on. P.E. Varinder M. Abn:J1. P.E. Mit:.....cl T.,Wssi. P.E.
J, Ketley Whice AJi R, Tah/:Jal. P.E. Sanjay Khanna. P.E. Yenudet NorrJmi.fn. P.E.. S.E. Oipalt M. Shan. P.E.
1109 Spring SUeer. Silver Spring. Maryli'nd 709\ 0-4087
Phone 3011587-1820 Fax 3011588-1966
.
,.
~/
/' ,
.
:
WINGERTER
LABORATORIES INC.
Engineering Testing and InspecIion Service
Established 1949
. \
July 17,2002
Setai Owners L.L.C.
Attention: Mr. Daniel R. Koffsky
2009 Collins Avenue
Miami Beach, Florida 33139
Project:
Setai Resort & Residences
2009 Collins Avenue
Miami Beach, Florida
~~@JmITWIDJ~
JUL 29 2002
THE RAUL PUIG GROUP. PA
FC, '~,}
'......,.,
Gentlemen:
1.0 BACKGROUND
In August, 1998, Robert H. Schuler, P .E., P .G., performed a stnictural inspection of the above
referenced hotel, then identified as Sasson on the Ocean Hotel. This nine story hotel was built in an
Art Deco style and is considered historically significant. City of Miami Beach Building Department
records indicate the original hotel building was constructed in 1936, with the south wing added in
1938. At the time of our 1998 inspection, the then-vacant building was undergoing interior
demolition and contained large amounts of structural debris.
In July, 2002, we conducted structural re-inspections of the project, now identified as Setai Resort,
to determine the locations of the delaminated and deteriorated concrete in the floor slabs, beams,
columns and exterior walls. The building's interior finishes and windows have been removed.
2.0 STRUCTURAL DESCRIPTION
The building is constructed on spread footings with a concrete frame and block in-fill construction.
Within the original building, which is the wing located north of column line Q, are reinforced
concrete columns, beams and floor slabs from the second floor up to the penthouse for a total of
seven full floors. There are also a penthouse floor, an elevator and a roof tower which contains a
o water tower.
18:!0 N.E. 144th St. . P.O. BOX 611450 . North Miami, FL 33261-1450 . (305) 944-3401 . 1-800-345-SOIL . Fax: (305) 949-8698
Broward: (954) 764-0472 . Dispatch Fax: (305) 949-1328
STEEL. CEMENT .. CONCRETE. PAVEMENT INSPECTIONS. TEST BORINGS. SPECIFICATIONS. CONSULTATIONS
Florid" Certificate # F-614
".J
/'''''\
-'
l':'~
'<:...)
':'~'~/. "':' ~ .....-.
. ~ &.
.-
"
~ ~I
.
Win~erter Laboratories, Incorporated
Pa~e 2
The south wing of the building was added several years later and consists of concrete and steel
columns on the first floor and large riveted steel beams to create a large open room on the first floor.
The floors in the south wing are constructed with steel open web joist system and metal decking with
concrete topping. A center line of concrete columns are supported by the steel beam above the first
floor.
Exterior walls are concrete frame with cement block and stucco finish. Interior walls have been
removed in order to provide access to the columns for repair and to decrease the dead load on the
building floors. The new design calls for the removal of all existing stairs and elevators, and the
replacement of two staircases and two areas of elevators. In general, interior demolition has been
completed. Interior steel bracing has been installed to assist in building stabilization.
3.0 STRUCTURAL INSPECTION
3.1 Foundation
An exterior inspection of the foundation did not reveal indications of deterioration or significant
settlement. The interior of the foundation is not accessible. However, since the building is over
sixty years old, the footings will not be used for the renovated building. The new design calls for
a mat foundation slab to replace the footings.
3.2 Columns
The columns appear to be in uniformly deteriorated condition. Many columns have indications of
significant spalling which will require repair or replacement. The removal of the wall plaster during
the demolition uncovered spalling on almost all of the columns. J This situation was anticipated.
Drawings have been prepared with notations of the identified deterioration. In general, the interior
columns in the north end of the building have comers spalled in those columns which were adjacent
to the pipe chases. Significantly, the exterior columns were found to have over ninety percent of the
columns affected, with a minimum of partial spalling on the comers. Inspections utilizing the
Subsurface Interface Radar (SIR) revealed that the spalling is also present on the exterior columns
and beams of the building. Columns with square reinforcing steel appear to be more susceptible to
corrosion damage, at least partially due to the fact the corrosion products create a wedge which
permits more significant deterioration to continue.
The columns on the "T" line, particularly T -6, T -8 and T -10, are severely deteriorated with the full
face of the columns spalled off on the lower floors. Column T -6 on the second floor is showing
some bowing of the reinforcing steel and breaking of the column ties. The comer columns appear
to be extremely corroded. These columns have been shored by the erection of a steel framework
installed on the north wall and on the east wall.
'~,.
,; ,.}
-.-.
,-"f'"
'_J
,..:', ')
~""- ,;,;,
~~;~:"'~\/;. .
, >
, k'
Win~erter Laboratories, Incorporated
Page 3
During the construction of the south wing portion of the building, it appears that the floor slabs were
installed and poured as the colwnns were being erected. Unfortunately, it appears that they failed
to cut the slab to remove the interfering decking from the columns. lIDs situation has resulted in a
two to three inch gap on the interior half of the columns, causing considerable weakening of these
columns and subsequent deterioration.
3.3 Tie Beams
The tie beams around the entire perimeter of all floors were found to be over seventy-five percent
corroded on the bottom two reinforcing steel bars and about twenty percent corroded on the top
reinforcing steel. Also, many diagonal bars were also exposed and often found to be corroded away.
The tie beams are very deep and combine the function of the tie beam and the window lintel. Due
to this extra dep~ none of the beams have broken under the load and are being repaired. However,
the tie beams at the corner windows are more significantly deteriorated and will require replacement
along with the corner columns.
With the previous SIR surveys, we were able to determine that visible interior fractures within the
window lintels and tie beams extend to the exterior of the beams. Although the stucco has minor
cracks or no cracks, the concrete beam is fractured. Since that time, repairs have started on the lintel,
which consists of removing a one foot high section of the wall for the full length of the lintels.
Most beam stirrups are so deteriorated, they are no longer functional. The depth of the beams may
make this problem less significant than if these were the usual small tie beams.
The columns have ties at twenty-four inch spacing. These ties are severely corroded in many
columns. The columns will need to be removed and replaced.
3.4 Floor Slabs with Concrete Joists
The floor slabs are supported by eight inch wide joists spaced about three feet apart. Many of these
joists have severe corrosion with approximately forty percent of the joists showing spalling. Many
of these joists have been repaired. However. the reinforcing steel was not properly cleaned during
the last repair and the repaired joists did not achieve full size. All floor slabs, joists and beams will
need to be replaced.
3.5 Floor Slabs with Steel Joists
The south half of the building has open web steel joists with metal deck and about a two and one-half
inch concrete topping. Most of the steel decking is under the concrete slab. There is no reinforcing
in the concrete except in some bathrooms and the stair areas. The steel joists are corroded and in
poor condition. There is a single row of columns and concrete beams on the south side of the
corridor.
.
OJ
Win2erter Laboratories, Incorporated
Pa2e 4
The reinforcement for this slab continues to function. There are numerous areas where the deck is
corroded and several areas where the deck has corroded away.
The cracks at the south and west comers do indicate some movement of the comer columns. Current
plans include replacement of the columns and slabs.
3.6 Swiss Hammer Testing
The Swiss hammer was used to test the strength of the existing concrete to determine the location
of the four proposed concrete cores. Our findings were that in the areas where concrete was
significantly damaged, the concrete strength was similar to the areas which did not have significant
damage. The columns and beams are damaged by the corrosion of the reinforcing steel and by a lack
of concrete strength. We were not able to locate areas for concrete cores that would provide
significant additional information beyond what is already availabl~ based on the previous reports.
We examined the results. The test results provided by Law Engineering indicate that the concrete
strength in the building is generally less than 2,500 psi.
(".' "'~
!' ":J
..........
The Swiss hammer tests only the top surface of the concrete, and therefore frequently underestimates
the strength of the concrete. Since the results of the Swiss hammer tests performed indicated
concrete strengths from 2,800 to 4,000 psi, we do not believe that there is a significant problem with
low strength concrete. However, there is a problem with some columns due to the loss of cross
sectional area. The attached table indicates column sizes on the second floor and some of the
reinforcing as determined by field measurements.
3.7 Subsurface Interface Radar (SIR)
The SIR was originally used to determine the condition of floor slabs and to locate reinforcing steel
in some columns. During this inspection, much of the steel has been exposed. Some of the column
steel findings are also presented on the attached table. The determination of all the reinforcing steel
is beyond the scope of this inspection.
The SIR survey found that the floor slabs were not delaminated. However, the reinforcing mesh in
the north wing is on the bottom of the slab with little or no concrete cover. Subsequent removal of
the slab in areas where diagonal bracing was installed has found that the welded wire fabric is
significantly corroded.
3.8 Roof
During our inspection, we were able to access the roof area and inspect the multiple roof areas.
Visual inspections indicate that the roofs are completely deteriorated, Ponding stormwater is
f) accumulated on and under the roof.
. '
r ~'
,---
, )
J
rt'?\
":-.:7
Wingerter Laboratories, Incorporated
Page 5
4.0 CONCLUSIONS
Our re-inspection found that most of our recommendations proposed in our 1998 report have been
performed or are underway.
Based on the condition of the reinforcing steel which has been exposed on the exterior of the
building, we can see that virtually all of the steel in the lintels and the columns has a coating of
corrosion which prevents bonding between'the reinforcing steel and the concrete. We believe that
it will be necessary to chip out and treat the existing reinforcing steel and.~d additional reinforcing
to prevent continued deterioration of the facade.
We anticipate that the footings will have similar deterioration which will require replacement of the
,foundation. The interior columns would need to be replaced or resupported. Considering the poor
condition of the columns and beams as well as the deterioration of the steel joists and metal decking,
it is our opinion that the interior of the building ,will need to be replaced.
The penthouse structure for the north wing is supported by two beams which are completely spalled
and, at the present time, two columns on the north face which, on some floors, have significant
deterioration. Currently the lintel between the two north columns has been removed on the sixth and
seventh floors. Shores are in place on the interior of the lintel. However, these loads still are
transferred to the deteriorated columns. This situation creates a significant risk during the process
of removing and replacing all the structural components of the building's exterior facade. The facade
will then need to be supported during the demolition of the interior slabs and columns.
We understand the desire to maintain the penthouse structures, but it is evident that besides the east
and west facades, the remainder of the walls will need to be essentially rebuilt since they were found
to be cracking at this time, and the stucco is loose in many areas. Much of the architectural detail
is deteriorated and will need to be reconstructed. The comer details consisting of three eyebrows
have been removed in one location. In the other two locations, they are deteriorated to the extent that
they will need to be removed and rebuilt.
The risks associated with attempting to retain the penthouses when the entire roof of the building
needs to be replaced is, in our opinion, not justified. Based on a past survey of the building stucco,
the areas to be removed have been marked. In addition, we believe that the columns and beams will
need to be removed from the facades. We anticipate that twenty-five to forty percent of the facade
will need to be reconstructed and restuccoed. The loss of the penthouse original walls would not be
significant.
Since the restoration process will essentially cut the facade into sections, we questions whether or
not it would be more appropriate to use moldings and selective removal of significant architectural
elements which could be reinstalled on a new structure. This method would still preserve those
.
. ,
I ,,~
~3
, Wingerter Laboratories, Incorporated
Page 6
sections and the original appearance of the building without the risks and costs associated with
supporting the structure, removing and replacing the existing structural frame.
The attached photographs are examples of only a few of the deteriorated conditions we found,
,including reinforcement splices which have no strength on a first floor column and a failed column
on the second floor where the north and east facades intersect.
Whichever method of preservation is utilized, it is obvious that the cost of restoration and
preservation will be significantly higher than the cost of building a new structure. The only question
is the extent of reliance which can be placed in the existing strength of this sixty year old structure,
considering its deteriorated state.
We appreciate this opportunity to be of service to you. If you have questions regarding this report,
or if we can be of further assistance to you, please contact our office.
Respectfully submitted,
() Wingerter Laboratories Incorporated
o rt H. Schuler, P.E., P.G.
Florida Professional Engineer No. 34715
Florida Professional Geologist No. 1030
Florida Special (Threshold) Inspector No. 0400
.("'1\
~~