HomeMy WebLinkAbout2002-24989 Reso
RESOLUTION NO. 2002-24989
A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF
THE CITY OF MIAMI BEACH, FLORIDA, AUTHORIZING AN
AMENDMENT IN THE AMOUNT OF $43,750 TO THE
PROFESSIONAL SERVICES AGREEMENT BETWEEN THE CITY
OF MIAMI BEACH AND THE STATE OF FLORIDA, DEPARTMENT
OF MANAGEMENT SERVICES, FOR CONSTRUCTION
MANAGEMENT OF THE COLONY THEATER RENOVATION
PROJECT.
WHEREAS, on October 6, 1999, the Mayor and City Commission adopted
Resolution No. 99-23348, authorizing the City to execute a Professional Services
Agreement (Agreement) with the State of Florida, Department of Management Services
(DMS) for construction management of the Colony Theater; and
WHEREAS, at the time DMS was engaged by the City to manage the design
and construction of the Colony Theater, the total estimated cost of the project, based upon
an early conceptual design by Zeidler Roberts, Inc., was $1,750,000; and
WHEREAS, the Agreement between DMS and the City provides for DMS to
receive a fee equivalent to 2.85% of the total budget and 2.5% of the budget in excess of
$1,750,000; and
WHEREAS, on May 14, 2001, the City's Finance and Citywide Project
Committee voted to recommend a request for additional funding for the Colony Theater
Project, in the amount $1,415,000 from the RDA to Qegin bridging an estimated
$2,415,000 shortfall between the original concept budget and the actual preliminary cost
estimate; and
WHEREAS, On June 27, 2001, the RDA appropriated said funding and
approved an amendment to DMS's fee in the amount of $61,436, pursuant to the
provisions of the Agreement; and
WHEREAS, on June 28, 2002, the Finance and Citywide Projects Committee
voted to recommend a second funding request for the Colony Project, in the amount of
$1,750,000, to address significant unforeseen plan modifications mandated by certain
regulatory entities, including but not limited to, the City's Historic Preservation and Design
Review Boards, the Building and Fire Departments, Accessibility, the State Historic
Preservation Officer, the Florida Building Commission, and Miami-Dade County's Board
of Rules and Appeals; and
WHEREAS, subsequent to the favorable recommendation by the Committee,
the RDA appropriated the requested funding on July 10, 2002; and
WHEREAS, this second increase in the projectcost also took into consideration
certain increases in architectural and engineering fees as well as a second amendment to
DMS's fees in accordance with the Agreement; and
WHEREAS, based upon the second increase in the project cost, the Agreement
provides for DMS' fees to increase by $43,750.
NOW, THEREFORE, BE IT DULY RESOLVED BYTHE MAYOR AND MEMBERS
OF THE CITY COMMISSION OF THE CITY OF MIAMI BEACH, FLORIDA, that the
Mayor and City Commission hereby authorize a second amendment, in the amount of
$43,750, to the Professional Services Agreement, between the City of Miami Beach and
the State of Florida, Department of Management Services, for construction management
of the Colony Theater.
PASSED AND ADOPTED this 25th day of Se e b
ATTEST:
~a PM~
CITY CLERK
APPROVED AS TO
FORM & LANGUAGE
& FOR EXECUTION
0).... 1- d .. Or
Date
JMG/CMC:KOB
T:\AGENDA\2002lSEP2502IRDA\OMS_Contracl.RES.doc
CITY OF MIAMI BEACH
REDEVELOPMENT AGENCY ITEM SUMMARY
~
Condensed Title:
A Resolution approving an amendment in the amount of $43,750 to the Professional Services Agreement
between the City of Miami Beach and the State of Florida, Department of Management Services (DMS) for
construction management of the Colony Theater.
Issue:
On July 10, 2002, pursuant to the recommendation of the Finance and Citywide Projects Committee, the
RDA appropriated $1,750,000 towards the Colony Theater Project, in order to address increases In
construction costs resulting from certain design, programmatic, code and regulatory mandates imposed on
the Project. This appropriation also took into account increases in soft costs, including, but not limited to,
an amendment to the management fee payable to DMS. The Agreement provides for a fee increase
eauivalent to 2.5% of the increase in bud~et, or $43,750.
Item Summary/Recommendation:
The Administration therefore recommends amending the Professional Services Agreement with the State of
Florida, Department of Management Services for construction management of the Colony Theater in the
amount of $43,750. Funding for this request has already been appropriated as noted above.
Advisory Board Recommendation:
I N/A
Financial Information:
Source of
Funds:
~
L:J
Finance Dept.
City Center RDA (Appropriated on
July 10, 2002)
City Clerk's Office Legislative Tracking:
I Kent O. Bonde
T:\AGENDAI2002ISEP2502\RDAldms.SUM.doc
AGENDA ITEM
DATE
C71<
?-olS--cJ :L
CITY OF MIAMI BEACH
CITY HALL 1700 CONVENTION CENTER DRIVE MIAMI BEACH, FLORIDA 33139
www.ci.miami-beach.fl.us
COMMISSION MEMORANDUM
From:
Mayor David Dermer and Date: September 25, 2002
Members of the City Commission
Jorge M. Gonzalez \ ~
City Manager () fr U
A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY
OF MIAMI BEACH, FLORIDA, AUTHORIZING AN AMENDMENT IN THE
AMOUNT OF $43,750 TO THE PROFESSIONAL SERVICES AGREEMENT
BETWEEN THE CITY OF MIAMI BEACH AND THE STATE OF FLORIDA,
DEPARTMENT OF MANAGEMENT SERVICES, FOR CONSTRUCTION
MANAGEMENT OF THE COLONY THEATER RENOVATION PROJECT.
To:
Subject:
ADMINISTRATION RECOMMENDATION
Adopt the Resolution.
ANALYSIS
On October 6, 1999, the Mayor and City Commission adopted Resolution No. 99-23348,
authorizing the City to execute a Professional Services Agreement (Agreement) with the
State of Florida, Department of Management Services (DMS) for construction management
of the Colony Theater. At the time DMS was engaged by the City to manage the design
and construction of the Colony Theater, the total estimated cost of the project was
$1,750,000. This figure was at best, a rough estimate based on an earlier conceptual
design by Zeidler Roberts, Inc. The Contract Agreement between DMS and the City
provides for DMS to receive a fee equivalent to 2.85% of the total budget, or $49,900,
which was based on this early estimate.
On May 14, 2001, the Administration went before the City's Finance and Citywide Project
Committee to request additional funding for the Colony Theater Project, in the amount
$1,415,000 from the RDA. The Committee voted in favor of recommending the
appropriation. Subsequent to the Committee's recommendation, the RDA appropriated the
funding on June 27,2001. The additional funding was necessary in order to begin bridging
an estimated $2,415,000 shortfall between the original concept budget and the actual
preliminary cost estimate, based on the design drawings and programmatic requirements.
The RDA also approved an amendment to OMS's fee in the amount of $61 ,436, pursuant
to a provision in the Agreement, which provides for a fee increase equivalent to 2.5% of the
revised budget in excess of $1,750,000. The fees were based on a revised project cost of
$4.2 Million.
On June 28, 2002, in response to revised project cost estimates based on 100%
construction drawings, the Administration presented a second funding request to the
Finance and Citywide Projects Committee, in the amount of $1,750,000. Since the initial
funding request, the plans had to undergo significant modifications, to address a variety of
design, code-related and programmatic issues, mandated by certain regulatory entities,
including but not limited to, the City's Historic Preservation and Design Review Boards, the
Building and Fire Departments, Accessibility, the State Historic Preservation Officer, the
Florida Building Commission, and Miami-Dade County's Board of Rules and Appeals.
The cost of implementing these modifications, many of which were unforeseen, resulted in
the significant cost increase to the Project. Subsequent to a favorable recommendation by
the Committee, the RDA appropriated the requested funding on July 10, 2002.
This increase in project cost also took into consideration certain increases in architectural
and engineering fees as well as a second amendment to DMS's fees in accordance with
the Agreement. Based on the $1,750,000 increase in the project cost, DMS's fees will
increase by $43,750. The Administration therefore recommends amending the
Professional Services Agreement with the State of Florida, Department of Management
Services for construction management of the Colony Theater in the amount of $43,750.
The total overall cost of the Project stands at $6.3 million, of which the RDA is funding
$3,165,000, or 50 percent. The balance of the Project is being funded through a
combination of federal, state and county grant sources.
Since the last project update provided with the appropriation memo in the July 10, 2002,
agenda package, the permitting of the Project encountered delays with the structural
review process, which were resolved at the beginning of September. As of the writing of
this report, the final permit was pending approval by Concurrency and Zoning, and was
anticipated to be issued before the end of September. Since the closing of the Colony in
mid-July, theater staff has been disassembling and cataloging equipment, including
lighting, rigging, projectors and sound equipment, for storage and/or for rental to outside
theatrical facilities. The Contractor was in the process of finalizing staging and fencing
permits.
The Administration recommends amending the Professional Services Agreement with the
State of Florida, Department of Management Services for construction management of the
Colony Theater in the amount of $43,750.
JMG/~:KOB
T:IAGENDAI2OO2\SEP2502\RDA\DMS_ Contract.doc
Attachments
STATE OF FLORIDA
DEPARTMENT OF MANAGEMENT SERVICES
BUILDING CONSTRUCTION (Be)
4030 ESPLANADE WAY, SUITE 360
TALLAHASSEE, FLORIDA 32399-0950
AMENDMENT TO AGREEMENT BETWEEN
CLIENT AND AGENT
BC PROJECT NUMBER:
COMB-99042000
PROJECT NAME AND LOCATION: Renovations and Restoration
The Colony Theatre
City of Miami Beach, Florida
CLIENT:
City of Miami Beach
Miami Beach Redevelopment Agency
1700 Convention Center Drive
Miami Beach, Florida 33139
Jeb Bush
Governor
Cynthia A. Henderson
Secretary
99042000COMB_AMD2.DOC
Amendment No.2
Amendment No.: 2
THIS AMENDMENT
made this 16th day of September in the year Two Thousand and Two
BY AND BETWEEN BUILDING CONSTRUCTION (Be), DEPARTMENT OF MANAGEMENT SERVICES,
STATE OF FLORIDA, hereinafter called the AGENT or BC, and
City of Miami Beach
Miami Beach Redevelopment Agency
1700 Convention Center Drive
Miami Beach, Florida 33139
herinafter called the CLIENT or OWNER.
WITNESSETII, that whereas the Client entered into Agreement with the Agent on the 20th day of October, 1999
for the purpose of implementing this project; that whereas on June 7, 2001 the Client and Agent amended the
Agreement to add additional funding in the amount of $2.814.711.00; that whereas the Client now wishes to
amend the agreement to add additional funding in the amount of $1.750.000.00 to fund the Construction
Manager's latest construction cost estimate; that whereas this is the reason for this Amendment.
NOW THEREFORE, BC and the Client, for the considerations hereinafter set forth, agree as follows:
GENERAL: All Articles and Exhibits not specifically addressed in this Amendment shall remain in full force.
1. Article 2. The Project Budget is as shown in the attached Exhibit n, which by reference and attachment
hereto forms a part of this Agreement.
3. Article 7. BC's administrative fees for the various project management services are based on services as
shown in Exhibit n and shall be as follows:
ONE HUNDRED FIFTY FIVE TIIOUSAND EIGHTY SIX DOLLARS ($155,086.00)
If the Project Budget is increased in excess of $6.064.711.00. BC's fee may be increased by 2.5% of the
revised budget in excess of$6.064.711.00.
4. Article 8. The balance of BC's administrative fees prescribed in Article 7 hereinabove, will be invoiced
once for the total amount due and the CLIENT will issue a Purchase Order to BC. The Purchase Order
will identify a Fiscal Contact Representative to be responsible for all payments under this Agreement.
Payments are to be made in ~ quarterly payments against the invoicelPurchase Order.
2
Amendment No.2
The Client agrees to pay the Agent a total administrative fee of $155.086.00 for its services prescribed in
Article 7. As of this date, BC has already invoiced the CLIENT for $111.336.00 based on the original
agreement and Amendment Number I. As of August 31, 2002, $91.107.00 has been received, with a balance
due of $20.229.00. BC will invoice the CLIENT for the additional $43.750.00 fee upon execution of this
Agreement and the CLIENT agrees to pay BC the remaining $63.979.00 in ~ quarterly payments as follows:
$63,979.00 + 5 Quarters = $12,795.80
4 Equal Quarterly Payments of$12,795.00
I Final Quarterly Payment of $12,799.00
3
Amendment No.2
IN WITNESS WHEREOF, the parties hereto have executed this Agreement the day and year fITst written above.
CLIENT
CITY OF MIAMI BEACH
BY~~ f~
Robert Parcher, City Clerk
APPROVED AS 10
FORM & LANGUAGE
"FOR EXECUTION
4AJ IMI~l.PJ,y (Q_rr..-Oy
v ~ Date
As Witnessed:
By
~/A'-
/
/
AGENT
BUILDING CONSTRUCTION
DEPARTMENT OF MANAGEMENT SERVICES
STATE OF FLORIDA
As Witnessed:
APPROVED:
By
BY~C. W
Cynthia A. Henderson, e
Approved As To Form and Legality:
By
4
Amendment No.2
EXHIBIT n
OWNER'S PROJECT BUDGET
CONSTRUCTION AGREEMENT (McCARTNEY ONSTRUCTION)
PROGRAMMING
ARCHITECT-ENGINEER BASIC SERVICES
AUTHORIZATION #1 - MEASURED DRAWING
AUTHORIZATION #2 - ESTIMATING
AUTHORIZATION #3 - SCHEMATIC DESIGN & CONSTRUCfION ESTIMATE
AUTHORIZATION #4 - COST ESTIMATES
AUTHORIZATION #5 - TSG DESIGN SOLUTIONS
AUTHORIZATION #6 - MEASURED DRAWINGS
AUTHORIZATION #7 - LANDSCAPE DESIGN
AUTHORIZATION #8 - COST ESTIMATES FOR DD & CD
AUTHORIZATION #9 - THRESHOLD INSPECfION SERVICES
AUTHORIZATION #10 -ARTEC ACOUSTIC CONSULTANTS
AUTHORIZATION #11 - STRUCTURAL UPGRADES 25% RULE
AUTHORIZATION #12 - INTERIOR DESIGN SELECfION
AUTHORIZATION #13 R- OBTAINING APPROVAL FROM COMB
AUTHORIZATION #14 - SURVEY
AUTHORIZATION #15 - SOIL BORINGS
AUTHORIZATION #16 - REIMBURSABLE EXPENSES
AUTHORIZATION #17 - OBTAIN WAIVER FROM COMB
AUTHORIZATION #18 - STRUCTURAL ANALYSIS
AUTHORIZATION #19 - REPLACEMENT COST ESTIMATE
AUTHORIZATION #20 - ADDITIONAL DESIGN OF THEATER EQUIPMENT
AUTHORIZATION #21 - Architectural & Engineering Services
INDEMNIFICATION
CONSTRUCfION COST ALLOWANCE
DMS FEE
TOTAL
5
$3,100,000.00
3,500.00
313,690.00
3,000.00
3,000.00
7,840.00
3,000.00
16,765.00
8,000.00
4,000.00
8,500.00
7,500.00
67,045.00
10,000.00
7,500.00
21,111.00
2,058.00
1,146.00
10,000.00
20,000.00
7,606.00
3,013.00
6,884.00
48,200.00
10.00
2,226,257.00
155.086.00
$6,064,711.00