Loading...
LTC 133-2018 Property Managemen Monthly Construction Projects UpCity of Miami Beach, 1700 Convention Center Drive, Miami Beach FL 33139 LTC# 133-2018 LETTER TO COMMISSION TO: Mayor Dan Gelber and Members oithe City Cmmission FROM: Jimmy L. Morales, City Manager DATE: March 09, 2018 SUBJECT: PROPERTY MANAGEMENT MONTHLY CONSTRUCTION PROJECTS UPDATE The purpose of this LTC is to update the Mayor and City Commission of the Capital Renewal and Replacement projects being conducted by Property Management. In 2004, the Mayor and City Commission authorized the establishment of a permanent Capital Renewal and Replacement Fund that would provide dedicated funding for capital renewal and replacement projects that would extend the useful life of general fund assets by more than five (5) years. The City's real property assets include over 84 municipal buildings and properties; the Lincoln Road District; 39 bridges; 15 monuments; 23 fountains; 3 swimming pools; over 6 miles of pedestrian areas along the beaches and boardwalk; and lifeguard stands. Property Management has over 100 active projects (attachment A) and below are key project highlights that are underway. 28th Street Obelisk Restoration Scope: Restoration of the obelisk, base building and the surrounding plaza. Status: At current, the Architect of Record is addressing plan review comments issued by the CMB Building Department. Given the Classification of Work for the project, a requirement for vertical accessibility has been triggered. A waiver application has been filed with the Florida Building Commission and will be heard April 8-10. Estimated completion for this project is September 2018. 42nd Street Garage Lighting Scope: Retrofit all interior garage lighting to LED fixtures. Status: The manufacturer, Holophane has begun to produce LED retro fit kits for their 100W HPS Bantam Fixture. These kits will be a newly installed system. The 42nd Street Garage will be a pilot for the new fixtures. Upon their successful implementation at 42nd Street garage, the new retro fit kits will be installed at remaining garages. Estimated start date is April 1st and estimated completion is May 2018. 777 4th Floor HVAC Replacement Scope: Installation of new variable air volume dampers, replacement of HVAC ductwork, air handlers and vents. LTC: Property Management Monthly Construction Report Page: 2 of 7 Status: Signed and sealed drawings have been received and were sent to the Building Department for review on 2/28/2018.The estimated completion for this project is May 2018. Bass Museum Emergency Generator Replacement Scope: Replace the existing generator and associated switch gear with a new, more efficient unit. Status: Project permit has been finalized. Bid packages have been sent to the Gordian Group. The estimated completion for this project is May 2018. Beach Shower Replacement (Phase II) Scope: Replace and remodel 17 beach showers from South Pointe to 81st Street. Status: Currently going through the permitting process. Completion for this project is now dependent on project funding in FY18/19. City Hall Air Handling Unit Replacement Scope: Replacement of 10 air handling units at City Hall. Status: The project is currently nearing the end of completion. Currently, there are only two final inspections missing in order to close out the project. The estimated completion for this project is March 31, 2018. Fleet Management HVAC Control Replacement Scope: New controls will be integrated into the existing citywide BMS system. There will be new floor plan graphics showing equipment locations and mechanical equipment graphics, allowing remote access to view operational data and adjustment of set points. Status: Final installation of ductwork connection and fresh air dampers for control. The estimated completion for this project is March 2018. Marine Patrol Emergency Generator Installation Scope: Install a new emergency generator for the Marine Patrol building. Status: Currently in the process of finalizing the drawings for the new generators. The estimated completion for this project is July 2018. Miami Beach Police Department Generators Replacement Scope: Replace the existing emergency generators for two new 500 KVA generators that are EPA Tier 4 certified; ensuring the new equipment meets the EPA's most stringent regulations for emissions reductions. Status: City of Miami Beach Procurement Department is currently finalizing a Piggyback Analysis for the purchase of the new emergency generators and switchgear equipment. Concurrently, proposals have been solicited for the electrical and mechanical scopes of the project. The estimated completion for this project is June 2018. Miami City Ballet Window Replacement Scope: Replace all existing windows at the Miami City Ballet with new, impact resistant, energy efficient windows and doors capable of rejecting solar heat gain. Status: At current, the Engineers of Record for the project are incorporating the comments received from the Miami City Ballet's consultants. The drawings will be submitted for permitting once all comments are incorporated. The estimated completion for this project is September 2018. LTC: Property Management Monthly Construction Report Page: 3of7 North Shore Youth Center A/C Replacement Scope: Replace two air handling units at North Shore Youth Center. Status: A purchase order has been issued and the vendor is in the process of ordering the new units. Installation is scheduled for April 2nd and will take approximately 2 weeks. The estimated completion is May 2018. Property Management Facility Generator Installation Scope: Installation of a new generator, fuel tank and transfer switch. Status: Purchase Order received on February 23, 2018. Then engineering firm is working on the design and should be submitting them by March 15, 2018.The estimated completion is June 2018. Public Works Facility Generator Replacement Scope: Installation of a new generator, fuel tank and transfer switch. Status: Purchase Order received on February 23, 2018. Then engineering firm is working on the design and should be submitting them by March 15, 2018.The estimated completion is June 2018. Scott Rakow Youth Center Generator Installation Scope: Installation of a new generator, fuel tank and transfer switch. Status: Purchase Order received on February 23, 2018. Then engineering firm is working on the design and should be submitting them by March 15, 2018.The estimated completion is June 2018. South Shore Community Center Flooring Replacement Scope: Removal and replacement of the existing vinyl floors and baseboards throughout with new vinyl flooring and baseboards. Status: Installation has been pushed back to April 14 since many of the departments cannot close during the week for the floor to be installed. The estimated completion is April 2018. Project Project Title Number 62570 62418 62118 61660 60130 62218 61718 61818 61918 1100 Block of Lincoln Road Updates 12TH STREET PARKING GARAGE ROOF AND PARKING DECK COATING 12TH STREET PARKING GARAGE UPGRADE LIGHTING (LED) 13th St PARKING GARAGE - ELEVATOR 13th St PARKING GARAGE - FIRE ALARM 13TH STREET PARKING GARAGE UPGRADE LIGHTING (LED) 16TH STREET PARKING GARAGE FIRE SPRINKLER RENEWAL 16TH STREET PARKING GARAGE RENEWAL OF PEDESTRIAN COATING IN STAIRWAYS 16TH STREET PARKING GARAGE ROOF AND PARKING DECK COATING Project Manager Adrian Morales Jorge Guanchez Mark Morgan Jorge Guanchez Jorge Guanchez Mark Morgan Mark Morgan Jorge Guanchez Jorge Guanchez Estimated Completion Date TBD 07/30/18 07/01/18 07/30/18 06/30/18 07/01/18 04/01/18 05/30/18 07/30/18 LTC: Property Management Monthly Construction Report Page: 4 of 7 62518 61930 26290 20110 69380 69370 60227 62100 67240 69310 61118 61218 20001 60190 62530 28000 26030 25960 67360 25980 25970 62510 26010 67100 27710 27970 63090 68760 1755 MERIDIAN PARKING GARAGE ROOF AND PARKING DECK COATING 17th St PARKING GARAGE - ELEVATOR 17th ST. PARKING GARAGE - MAINTENANCE - 4th floor drains 28th St OBELISK STABILIZATION (RESTORATION) 42nd St PARKING GARAGE - ELEVATOR REPLACEMENT 42nd St PARKING GARAGE - FIRE ALARM SYSTEM 42nd St PARKING GARAGE - LIGHTING FIXTURES 42nd St PARKING GARAGE - MAINTENANCE 777 BUILDING - HVAC 4th FLOOR 7th St PARKING GARAGE - FIRE ALARM SYSTEM 7TH STREET PARKING GARAGE UPGRADE LIGHTING (LED) 7TH STREET PARKING GARAGE VESTIBULE ROOFTOP RENEWAL ALTON ROAD FOUNTAIN AT 20TH STREET 16 St - ANCHOR GARAGE ELEVATOR REPLACEMENT BASS MUSEUM - HEAT PUMP REPLACEMENT BASS MUSEUM - HVAC Replacement BASS MUSEUM - Light Control Replacement BASS MUSEUM ELECT. BREAKER BOX REPLACEMENT BASS MUSEUM EMERGENCY GENERATOR BASS MUSEUM EMERGENCY GENERATOR BASS MUSEUM EXTERIOR LIG REPL. REPAIR BASS MUSEUM HVAC CONTROLS BASS MUSEUM HYDRAULIC ELEVATOR BASS MUSEUM - Exterior Walls & Paint BASS MUSEUM WEATHER SEAL BEACH SHOWER DRAINAGE CITY HALL - AIR HANDLING UNIT REPLACEMENT CITY HALL - ELECTRICAL UPGRADES Jorge Guanchez Jorge Guanchez Jorge Guanchez Frank Garcia Jorge Guanchez Jorge Guanchez Mark Morgan Mark Morgan Lily Alvarez Jorge Guanchez Mark Morgan Jorge Guanchez Frank Garcia Jorge Guanchez Lily Alvarez Lily Alvarez Lily Alvarez Lily Alvarez Lily Alvarez Lily Alvarez Lily Alvarez Lily Alvarez Lily Alvarez Lily Alvarez Lily Alvarez Jorge Guanchez Jorge Guanchez Oniel Toledo 07/30/18 07/30/18 08/30/18 09/01/18 07/30/18 06/30/18 05/01/18 09/30/18 05/01/18 06/30/18 07/01/18 05/31/18 11/01/18 07/30/18 05/01/18 05/01/18 05/01/18 05/01/18 05/01/18 05/01/18 05/01/18 05/01/18 09/01/18 05/01/18 05/01/18 08/31/18 03/31/18 03/31/18 LTC: Property Management Monthly Construction Report Page: 5 of 7 61290 67210 62940 60637 60117 62060 62070 62080 63770 68530 62918 60077 67220 60167 62818 60057 67200 61018 60918 60587 23118 62130 69470 60618 60418 60518 69480 60097 CITY HALL - FIRE ALARM SYSTEM REPLACEMENT CITY HALL - ROOF & SKYLIGHT RESTORATION CITYWIDE PARKING LOT LIGHTING COLONY THEATER HVAC FIRE 1-12 F2020- HAZARDOUS COMPONENTS FIRE STATION #1 - CARPET REPLACEMENT FIRE STATION #1 - ELECTRICAL REPLACEMENT FIRE STATION #1 - FLOOR REPLACEMENT FIRE STATION #1 - FY 08 FIRE STATION #1 - INTERIOR & EXTERIOR DOOR REPLACEMENT FIRE STATION #1 INTERIOR & EXTERIOR PAINTING FIRE STATION #2 - ALARM SYSTEM FIRE STATION #3 - EMERGENCY GENERATOR FIRE STATION #2 - ENGINE BAY ALARM FIRE STATION #2 - GARAGE DOORS REPLACEMENT FIRE STATION #3 - EMERGENCY GENERATOR FIRE STATION #3 - FIRE ALARM UPGRADE FIRE STATION #3 - KITCHEN RENEWAL FIRE STATION #4 - KITCHEN EQUIPMENT RENEWAL FIRE STATION #4 ROOF REPLACEMENT FIRE STATION #4 SECURITY ENHANCEMENT FLEET MGMT HVAC CONTROLS REPLACEMENT FLEET/SANITATION FIRE ALARM SYSTEM HISTORIC CITY HALL FIRE ALARM SYSTEM RENEWAL HISTORIC CITY HALL HVAC FRESH AIR UNIT HUMIDITY CONTROL HISTORIC CITY HALL PRESSURE BOOSTER PUMP MARINE PATROL - EMERGENCY GENERATOR MIAMI CITY BALLET - EMERG. LIGHT REPLACEMENT (BATTERY PACK) Frank Garcia Oniel Toledo Mark Morgan Adrian Morales Jorge Guanchez Jorge Guanchez Jorge Guanchez Jorge Guanchez Oniel Toledo Oniel Toledo Oniel Toledo Rene Guerra Ramon Duarte Rene Guerra Rene Guerra Jorge Guanchez Rene Guerra Rene Guerra Rene Guerra Oniel Toledo Rene Guerra Oniel Toledo Lily Alvarez Frank Garcia Oniel Toledo Oniel Toledo Jorge Guanchez Frank Garcia 06/15/18 05/31/18 09/30/18 06/11/18 09/30/18 06/30/18 09/30/18 09/30/18 09/30/18 09/30/18 04/30/18 05/30/18 09/30/18 05/01/18 05/01/18 07/30/18 05/30/18 05/01/18 05/01/18 06/01/18 09/01/18 03/30/18 09/30/18 06/15/18 09/30/18 05/28/18 07/30/18 05/01/18 LTC: Property Management Monthly Construction Report Page: 6 of 7 27760 27780 63018 63118 67050 60718 67070 68720 63350 60030 60007 21918 21818 69210 69220 64220 61518 61618 62410 27350 60087 60037 60018 60318 61318 67080 60127 69250 MIAMI CITY BALLET - EXT. CONCRETE RESTORATION MIAMI CITY BALLET - WINDOW REPLACEMENT NORMANDY SHORES GOLF CLUB NC AND KITCHEN REFRIGERATOR REPLACEMENT NORMANDY SHORES GOLF CLUB RESTROOM ROOF REPLACEMENT NORTH END SUBSTATION - RESTROOM RENOVATION NORTH SHORE PARK YOUTH CENTER NC REPLACEMENT P.A.L. BUILDING - EXTERIOR PAINT, Exit signs, Emergency lights & interior paint. POLICE HQ & PARKING GARAGE- FIRE ALARM REPLACEMENT POLICE HQ ELEVATOR & FIRE ALARM REPLACEMENT POLICE STATION MEN'S LOCKER ROOM POLICE STATION NEW GENERATOR PROPERTY MANAGEMENT FACILITY CARPENTRY SHOP DUST CONTROL SYSTEM PROPERTY MANAGEMENT FACILITY NEW 500KW GENERATOR AND TRANSFER SWITCH PUBLIC WORKS MAINT. FACILITY EXTERIOR WINDOW REPLACEMENT PUBLIC WORKS MAINT. FACILITY GENERATOR PUBLIC WORKS OPERATIONS -EXTERIOR RESTORATION PUMP STATION 28 STORAGE TANK REPLACEMENT PUMP STATION 29 STORAGE TANK REPLACEMENT REPLACE SOUTH SHORE COMM. CARPET VINYL TILE SANITATION - INTERIOR REPLACEMENT SCOTT RAKOW CENTER ALARM SECURITY SY REP SCOTT RAKOW CNTR. FIRE ALARM REPLACEMENT SCOTT RAKOW COMMUNITY CENTER ALUMINIUM WINDOWS RENEWAL SCOTT RAKOW YOUTH CENTER EMERGENCY GENERATOR SOUNDSCAPE PARK AIR CONDITIONING SYSTEM REPLACEMENT SOUTH SHORE COMM. CNTR ELASTOMERIC COAT SOUTH SHORE COMM. CNTR. SWITCH GEAR REPLACEMENT SOUTH SHORE COMMUNITY CENTER - CHLLD WTR PUMP Frank Garcia Frank Garcia Rene Guerra Rene Guerra Frank Garcia Rene Guerra Jorge Guanchez Frank Garcia Frank Garcia Frank Garcia Frank Garcia Ramon Duarte Ramon Duarte Jorge Guanchez Ramon Duarte Jorge Guanchez Lily Alvarez Lily Alvarez Lily Alvarez Lily Alvarez Lily Alvarez Lily Alvarez Ramon Duarte Ramon Duarte Adrian Morales Lily Alvarez Lily Alvarez Lily Alvarez 09/15/18 09/15/18 Completed 04/30/18 04/15/18 05/01/18 05/30/18 06/15/18 06/15/18 04/15/18 06/01/18 06/30/18 06/30/18 04/30/18 09/30/18 05/30/18 06/30/18 06/30/18 04/01/18 08/01/18 08/01/18 08/01/18 06/30/18 06/30/18 05/01/18 04/01/18 Com pleted 05/31/18 LTC: Property Management Monthly Construction Report Page: 7 of 7 60038 60218 60647 62220 67040 68520 69960 64120 63750 60067 64140 64150 20557 60187 SOUTH SHORE COMMUNITY CENTER FIRE ALARM SYSTEM RENEWAL STORAGE TANK REPLACEMENT WHEELCHAIR LIFT N. SHORE BANDSHELL POLICE STATION NC REPLACEMENT NORMANDY ISLE PARK & POOL FIRE STATION 3 INTERIOR AND OVERHEAD DOOR REPLACEMENT SOUTH SHORE COMMUNITY ELEVATOR POLICE ST PNEUMATIC CONTROLS REPLACEMENT POLICE STATION BUILDING -VARIOUS PROJECTS POLICE EXIT SIGN RENEWAL POLICE VARIABLE AIR VOLUME DAMPERS POLICE VARIABLE FREQUENCY DRIVES ANCHOR GARAGE LIGHTING 171" STREET GARAGE LIGHTING FIXTURE Lily Alvarez 08/01/18 Lily Alvarez 08/01/18 Valeria Mejia 04/01/18 Frank Garcia 05/01/18 Rene Guerra 06/01/18 Jorge Guanchez 09/30/18 Lily Alvarez 09/01/18 Frank Garcia 03/15/18 Frank Garcia Completed Frank Garcia Completed Frank Garcia 03/15/18 Frank Garcia 03/15/18 Mark Morgan Completed Mark Morgan Completed Should you have any additional questions, please contact Adrian Morales at 305.673.7000 ext. 2932.8 JLM% IIT/AMNPC