LTC 143-2018 CIP Monthly Construction Projects UpdateMIAMIBEACH
OFFICE OF THE CITY MANAGER
NO. LTC# 143-2018 LE R TO COMMISSION
TO: Mayor Dan Gelber and Members of :he City C mission
FROM: Jimmy L. Morales, City Manager
DATE: March 15, 2018
SUBJECT: CIP Monthly Construction Projec s Update
Below please find the monthly update for active City of Miami Beach construction projects under
the purview of the Office of Capital Improvement Projects.
Altos Del Mar Park
Scope: Park Improvements include new landscape, irrigation, site lighting, volleyball
courts, walkways, terraced lawn, accessible playground, restroom, and storage facility.
Status: Commission approved award to West Construction on October 18, 2017. Contract
has been executed and NTP has been issued. Construction is anticipated to commence
late March 2018. Project completion anticipated Fall 2018.
Beach Lifeguard Towers Replacement
Scope: Construction of 35 lifeguard towers.
Status: Construction began March 2015. Nineteen towers have been completed and
placed at their permanent location. Three additional towers have been completed and will
be placed at their permanent location March 2018. Construction of an additional seven
towers is scheduled for completion Spring 2018 bringing the total to be completed to 29.
Beachwalk II — Phase 2
Scope: Construction of an on -grade ADA compliant pedestrian paver walkway running
from 3rd ST to 5th ST, with turtle friendly lighting, landscaping and irrigation.
Status: Contract for construction services was awarded to West Construction at the
December 2017 commission meeting. Contract has been executed and construction
began March 6, 2018 and is scheduled for completion December 2018.
Biscayne Point Island Entry
Scope: Beautification project of the neighborhood entryway to Biscayne Point Island.
Status: Concrete curbs and sidewalks have been completed. Landscaping and
guardhouse renovation has commenced. Request for additional services was approved
at the March 7 Commission Meeting. Project is 80% complete overall and scheduled for
substantial completion May 2018.
Collins Park Parking Garage
Scope: The project, located at 300-340 23rd Street, consists of a six (6) level parking
garage with 466 parking spaces and approximately 14,560 SF of retail spaces on the
ground level.
Status: Project is a design build and has been awarded. NTP #1 was issued on March 8,
2018.
Central Bayshore South Neighborhood Improvements
Scope: Neighborhood improvements bounded by 34th St. to the north, Pine Tree Dr. to
the east, 28 St. to the south and Prairie Ave to the west and Meridian Ave from 28 St. to
Dade Blvd.
Status: Water main installation is ongoing and 98% complete. Drainage design is
currently at 75%. At the December 2017 commission meeting the project was referred to
the Sustainability and Resiliency Committee for review and evaluation of the stormwater
program being conducted.
Espanola Way Bollards
Scope: Installation of protective bollards at each end of Espanola Way (Washington
Avenue and Drexel Avenue).
Status: Commission approved a supplemental work order for construction on October 18,
2017. Construction is anticipated to commence late April 2018. Project is scheduled for
substantial completion Fall 2018.
Fleet Management Seawall
Scope: Complete replacement of approximately 200 feet of seawall to protect upland
structures.
Status: Construction began late June 2017 as an emergency repair. Anticipated
completion date is April 2018.
Lower North Bay Road Street Lighting
Scope: Installation of decorative street lighting system along Lower North Bay Road.
Status: Notice to Proceed was issued October 25, 2017. Anticipated completion March
2018.
Middle Beach Recreational Corridor Ph. 2 - Section 1 (Beachwalk)
Scope: Construction of an on -grade pedestrian walkway encompassing eleven (11) City
blocks or approximately 134,500 square feet from 53 St to 64 St.
Status: Contractor has cleared non-native/invasive landscaping and has commenced with
preparation of sub -base. Contractor is currently laying out paver path. Contractor is
continuing to pour curbs and lay irrigation pipe and has commenced electrical work.
Project is scheduled for completion August 2018.
Middle Beach Recreational Corridor Ph. 2 — Section 2 (Beachwalk)
Scope: Construction of an on -grade pedestrian walkway from 46 St to 53 St.
Status: Commission approved award to JRT Construction on October 18, 2017. Contract
has been executed. Construction is scheduled to start March 2018. Project is scheduled
for completion December 2018.
Palm & Hibiscus Island Neighborhood Improvements
Scope: Neighborhood improvements on Palm and Hibiscus Islands.
Status: Construction began January 2016. Project is 77% complete and scheduled for
completion Spring 2018.
Stormwater Pump Station at 19th Street
Scope: Installation of a stormwater pump station, including an emergency generator and
seawall reconstruction along Collins canal.
Status: Design is complete. Construction of the pump station and seawall began January
2018. Project is scheduled for completion late November 2018.
Sunset Islands 3 & 4 Neighborhood Improvements
Scope: Neighborhood improvements on Sunset Islands 3 & 4.
Status: Construction began June 2015. Project is 97% complete and scheduled for
completion late April 2018.
Surface Parking Lot P2 — Nikki Beach (Penrods)
Scope: Reconstruction of the parking lot that includes landscaping, turtle friendly lighting,
improvements to storm water drainage, irrigation, paving and signage, and infrastructure
for future electric car charging stations.
Status: Contract for construction services was awarded to West Construction at the
December 2017 commission meeting. Contract has been executed. Construction is
anticipated to begin May 2018 and is scheduled for completion November 2018.
Venetian Islands Neighborhood Improvements
Scope: Neighborhood improvements on San Marino, Dilido and Rivo Alto Islands.
Status: Construction began May 2013. Project is 88% complete. San Marino Island
anticipated completion March 2018; Dilido Island anticipated completion April 2018; and
Rivo Alto Island anticipated completion July 2018.
West Avenue Phase II Improvements - North of 14th Street
Scope: Neighborhood Right of Way improvements north of 14th Street to Lincoln Lane.
Status: Notice to Proceed #1 was issued July 31, 2017. Currently design is at 60%
development. At the December 2017 commission meeting, the project was referred to the
Sustainability and Resiliency Committee for review and evaluation of the stormwater
program being conducted.
West Avenue Phase II Improvements - South of 14th Street
Scope: Neighborhood Right of Way improvements south of 14th Street to 6th Street.
Status: Notice to Proceed #1 was issued July 31, 2017. Currently design is at 60%
development. At the December 2017 commission meeting, the project was referred to the
Sustainability and Resiliency Committee for review and evaluation of the stormwater
program being conducted.
JLM/EC/DM