312-99 RDA
RESOLUTION
312-99
A RESOLUTION OF THE CHAIRMAN AND MEMBERS OF THE MIAMI
BEACH REDEVELOPMENT AGENCY, APPROPRIATING $78,500 FROM
THE CITY CENTER REDEVELOPMENT AREA CONSTRUCTION FUND
TO IMPLEMENT THE ARCHITECTURAL AND ENGINEERING DESIGN
AGREEMENT WITH ROBERT A.M. STERN ARCHITECTS FOR THE
PROPOSED REGIONAL LIBRARY PROJECT.
WHEREAS, on September 23,1998, the Mayor and City Commission adopted Resolution
No, 98-22904, authorizing the Administration to execute an Agreement with the firm of Robert A.
M. Stem Architects (the Agreement) for the architectural and engineering design of a Regional
Library; a 400-space Parking Garage; and Park and Streetscape Improvements in the area
surrounding Collins Park (the Project); and
WHEREAS, the proposed 400-space Parking Garage must be deleted from the scope of the
Project; and
WHEREAS, two surface parking lots will be provided in place of the proposed 400-space
Parking Garage; and
WHEREAS, the Administration is requesting the appropriation of $1,370,000 to implement
the Agreement; and
WHEREAS, a portion of this appropriation is comprised of $78,500, to be appropriated
from the City Center Redevelopment Area Construction Fund.
NOW, THEREFORE BE IT DULY RESOLVED BY THE CHAIRMAN AND
MEMBERS OF THE MIAMI BEACH REDEVELOPMENT AGENCY, that the Chairman
and Members of the Miami Beach Redevelopment Agency authorize the appropriation of $78,500
from the City Center Redevelopment Area Construction Fund to implement the Architectural and
Engineering Agreement with Robert A.M. Stern Architects for the proposed Regional Library
Project.
PASSED AND ADOPTED this 6th
day ofJanuary1999. ~ A
MAYOR
:~ fcuck-
CITY CLERK
APPROVED AS TO
FORM & LANGUAGE
& FOR EXECUTION
F:\A TTO\TURN\RESOS\L1BRFUND,ARC
~ IJI.U-:- 1~7l' I
dy ~omey fI!!
Miami Beach
Redevelopment Agency
1700 Convention Center Drive
Miami Beach, Florida 33139
Telephone: (305) 673- 7295
Fax: (305) 673- 7772
REDEVELOPMENT AGENCY MEMORANDUM NO. 99-3
January 6, 1999
TO:
Chairman and Members of the
Miami Beach Redevelopment Agency
FROM:
Sergio Rodriguez
Executive Director
SUBJECT:
A RESOLUTION OF THE AIRMAN AND MEMBERS OF THE MIAMI
BEACH REDEVELOPMENT AGENCY, APPROPRIATING THE FUNDING
NECESSARY TO IMPLEMENT THE ARCHITECTURAL AND
ENGINEERING DESIGN AGREEMENT WITH ROBERT A. M. STERN
ARCHITECTS FOR THE PROPOSED REGIONAL LIBRARY PROJECT IN
THE AMOUNT OF $78,500.
ADMINISTRATION RECOMMENDATION:
Adopt the Resolution.
BACKGROUND:
On June 3, 1998, a recommendation was made by the City Manager to the Mayor and City
Commission for authorization to negotiate an agreement with the firm of Mateu, Carreno, Rizzo
and Partners for the architectural and engineering design of a regional Library, a 400-space Parking
Garage and Park and Streetscape Improvements in the area surrounding Collins Park, After
substantial discussion, the Mayor and City Commission recommended that the Administration
negotiate with the top ranked firm of Robert A. M. Stem Architects (Stem).
On September 23, 1998, the Administration presented a resolution to the Mayor and City
Commission requesting authorization to execute an agreement with Stem for a Regional Library,
a 400-space Parking Garage and Park and Streetscape Improvements in the area surrounding Collins
Park. The total negotiated fee was $1,570,000 which included basic design services for the Library
and a 400-space Parking Garage, park schematics, landscaping, and schematic design for the
Rotunda Building in Collins Park. The Mayor and City Commission adopted Resolution No. 98-
22904 authorizing the Administration to execute the agreement.
S()IJTti V()I~T~
l?edevel()pment Ulstrict
Agenda Item 36
V.Date~ -Co -99
On November 18, 1998, the City Commission directed the Administration not to proceed with the
design of a 400-space Parking Garage and to instead design two surface lots in parcels 2 and 4.
ANALYSIS:
The City's Administration is presenting a companion resolution on the January 6th Commission
Agenda, requesting the appropriation of funds from the General Fund Reserve for the above
described agreement with Stern for A&E (Architectural and Engineering) design services, as
modified by the change in scope of the project. The 400-space Parking Garage has been deleted
from the scope and the two surface lots have been added in its place, The agreement with Stern in
the original amount of $1,570,000 has been modified to reflect the changes in scope and the new
contract amount of$I,370,000,
The proposed A&E budget is as follows:
Regional Library
Surface Lots
Site/Landscape Design
Master Plan Schematics for Rotunda
Interior Design
Public Reviews and Meetings
Reimbursables
Project Funding:
$915,000
$ 10,000
$ 55,000
$ 65,000
$ 60,000
$ 60,000
$ 205,000
$1,370,000
The proposed funding for the A&E services contract with Stern is comprised of $1,281,500 in
available General Fund Reserve for Capital Improvements - (Library funds of $11.5 Million);
$10,000 from the $21 million Parking Revenue Bond issue; and $78,500 from the City Center RDA
Construction Fund. The total amount of$1,370,000 will be appropriated and a work order will be
established to pay the A&E design fees for the Cultural Campus/Regional Library,
CONCLUSION:
The Chairman and Members of the Miami Beach Redevelopment Agency should appropriate the
necessary share of funding in the amount of $78,500 from the City Center RDA construction fund
to implement the architectural and engineering design agreement with Robert A. M, S~em Architects
for the proposed Regional Library and Park and Streetscape Improvements in the area surrounding
Collins Park.
SR/CC/KOB