HomeMy WebLinkAbout2003-25119 Reso
RESOLUTION NO. 2003-25119
A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF
MIAMI BEACH, FLORIDA, APPROVING AND AUTHORIZING THE MAYOR AND
CITY CLERK TO EXECUTE AMENDMENT No.3 TO THE CURRENT
PROFESSIONAL SERVICES AGREEMENT BETWEEN THE CITY AND THE FIRM
OF MCHARRY AND ASSOCIATES, INC., DATED JULY 12, 2000, IN THE
AMOUNT OF $64,791, FOR THE PROVISION OF ADDITIONAL
ARCHITECTURAL, ENGINEERING AND LANDSCAPE ARCHITECTURAL
SERVICES TO COMPLETE THE DESIGN, CONSTRUCTION DOCUMENTATION,
CONSTRUCTION ADMINISTRATION, AND TO DEVELOP SPECIFICATIONS FOR
THE PROPOSED IMPROVEMENTS TO FIRE STATION NO.4; AND
APPROPRIATING $25,711 FROM THE UNDESIGNATED FUND BALANCE, TO
BE REIMBURSED BY OTHER PROJECT FUNDS WHICH WILL BE
APPROPRIATED AT TIME OF CONSTRUCTION CONTRACT AWARD; IN
ADDITION, DIRECTING THE ADMINISTRATION TO ISSUE AN UPDATED
PROJECT'S BUDGET STATUS REPORT TO THE MAYOR AND CITY
COMMISSION VIA LETTER TO CITY COMMISSION.
WHEREAS, on March 1,2002, pursuant to an extensive planning and programming period,
City staff reached a consensus to approve the sixth option presented by the City's consultant, MC
Harry and Associates Inc., to improve Fire Station NO.4 (the Project); and
WHEREAS, unlike the five (5) previous options developed by the consultant, Option 6 was
deemed compliant with the Project's programmatic needs, and was designed in accordance with the
Project's site restrictions; and
WHEREAS, the scope included in this new option generally consists of the relocation of the
existing historic Fire Station structure to a southwesterly position on the site, and construction of a
new state-of-the-art three (3) bay apparatus Fire Station in a northerly position, near 69th Street; and
WHEREAS, the City's consultant, MC Harry and Associates, Inc. will be required to gerform
additional architectural and engineering design services to re-grade a portion of the 69 Street
street-end to achieve a safe and practical entryway for both, pedestrians and motor vehicles,
including the emergency fire trucks, to the new building; and
WHEREAS, the relocation of the historic structure to a new position on the site will also
require additional architectural and engineering design work, not contemplated in the current
Professional Services Agreement between the City and MC Harry and Associates, Inc,; and
WHEREAS, during the course of the design development, Capital Improvement Projects
(C I P) and U RS Corporation staffs met on several occasions with the consultant to discuss what was
the most logical and efficient critical path to follow, to successfully complete the construction of the
project on time and within budget; and
WHEREAS, subsequently it was determined that the most efficient way is to construct the
project in two (2) phases; and
WHEREAS, the first phase, Bid Package 1, will generally consist of the relocation of the
existing building, including demolition of the new addition to the historic structure, and repair of the
existing structure to make it weather tight, as well as of the removal of the red tag (structural
violations); and the second phase, Bid Package 2, will generally consist of the construction of the
new Fire Station No 4, including appurtenant site work, landscaping, and site lighting; and
WHEREAS, consequently the City's consultant will be required to produce and administrate
two (2) bid packages, therefore additional professional services, not covered under the current
Agreement, will be required from the consultant to complete the revised scope; and
WHEREAS, in the interim City staff held a series of meetings with the consultant to confirm
the revised scope and negotiate a proposed professional services fee increase for MC Harry and
Associates, Inc.; and
WHEREAS, MC Harry and Associates, Inc. reached an agreement with the City to perform
the additional work for $64,791; and
WHEREAS, funding, in the total amount of $64,791, is comprised as follows: $39,080 in the
previously appropriated General Obligation Bond Fund resulted from the savings made after the
purchase of five (5) Fire Rescue vehicles; and $25,711 to be appropriated from the General
Undesignated Fund Balance;
NOW, THEREFORE BE IT DULY RESOLVED BY THE MAYOR AND CITY COMMISSION
OF THE CITY, OF MIAMI BEACH, FLORIDA, that the Mayor and City Commission adopt a
Resolution to approve and authorize the Mayor and City Clerk to execute Amendment NO.3 to the
current Professional Services Agreement between the City and the firm of MC Harry and Associates,
Inc" dated July 12, 2000, in the amount of $64,791, for the provision of additional architectural,
engineering and landscape architectural services to complete the design, construction
documentation, construction administration, and to develop specifications for the proposed
improvements to Fire Station No, 4; and appropriate $25,711 from the Undesignated Fund Balance,
to be reimbursed by other project funds which will be appropriated at time of construction contract
award; in addition, directing the Administration to issue an updated project's budget status report to
the Mayor and City Commission via Letter to Commission.
PASSED AND ADOPTED this
ATTEST:
(JJ~ ~~
CITY LERK
F:\CAPI\$aU\MAGMtC\GOBOND\MCHARRYAMENDMEN 3 resorevised 2-20
APPROVED AS TO
FORM & LANGUAGE
& FOR EXECUTION
1-/)--))']
0818
CITY OF MIAMI BEACH
COMMISSION ITEM SUMMARY
lQ
-
Condensed Title:
A Resolution of the Mayor and City Commission, approving and authorizing the Mayor and City Clerk to execute an
amendment to the current professional services agreement with MC Harry and Associates, Inc. in the amount of
$64,791 for the provision of additional services regarding the Fire Station No, 4 Project, to be funded by savings from
the 1999 General Obli ation Bonds for the urchase ot Fire A aratus and the Undesi nated Fund Balance.
Issue:
Should the Mayor and City Commission adopt the aforementioned Resolution to amend MC Harry and Associates
current scope of work, and as a result, should the Mayor and City Commission approve an increase to the
consultant's fee to perform the additional architectural, engineering and landscape architectural services tor the
Proiect?
Item Summary/Recommendation:
Pursuant to an extensive period of planning and programming, on March 1,2002, City staff reached a consensus to
approve a sixth option presented by the consultant to improve the Fire Station NO.4 site, Unlike the previous five (5)
options, Option 6 was deemed compliant with the project's programmatic needs, and was developed in accordance
with the project site's restrictions. It generally consists in the relocation of the existing Fire Station to a southwesterly
position on the site and construction of a new state-of-the-art three (3) bay apparatus Fire Station in a northerly
position, near 69th Street. It must be noted that Option 6 was adopted after the execution of a previous Amendment
No.2 to the consultant's contract, which did not include the relocation of the existing Fire Station. Although the
project team deemed Option 6 to be the most efficient for the site, additional architectural and engineering design
work to re-grade a portion of the 69th Street street-end was necessary to allow a safe and practical entryway to
pedestrians and motor vehicles alike, including the emergency fire trucks,
Moreover, the relocation of the historic structure to a new location also generated additional design work not
contemplated in the current Agreement between the City and MC Harry and Associates Inc,
During the course otthe design, CIP and URS staffs met on several occasions with the consultant to discuss the most
logical and efficient sequential path for the construction to follow to successfully complete the project. A number of
factors were considered, and options were examined. The consensus reached was that the most efficient way to
carry out the construction phase consists in dividing the project in two (2) bid packages, Bid Package No.1 will be
generally the relocation ot the existing building, including demolition of the new addition to the historic structure, repair
of the existing structure to make it weather tight and removal of the red tag (structural violations). Bid Package No, 2
is generally the construction of the new Fire Station No.4, including appurtenant site work, landscaping, and site
lighting.
After a series of negotiation sessions with the consultant, CIP, assisted by the program manager for the project (URS
Corporation) agreed the negotiated amount of $64,791 was fair and reasonable for the amount of additional work
required from the consultant to complete the project. The Administration concurs, and therefore recommends
aooroval of the attached Resolution bv the Mavor and City Commission.
Advisory Board Recommendation:
I N/A
Financial Information:
Source of
Funds:
1
Amount
$39,080
$25,711
Approved
rnance Dept.
2
3
4
Total
$64,791
City Clerk's Office Legislative Tracking:
I Michel Magloire
Si n-Offs:
Department Director
TH
Assistant City
ReM
~713
J~5-o3
DATE
CITY OF MIAMI BEACH
CITY HALL 1700 CONVENTION CENTER DRIVE MIAMI BEACH. FLORIDA 33139
www.ci"miami-beach.fl.us
Mayor David Dermer and Date: February 5, 2003
Members of the City Commission
Jorge M, Gonzalez ~
City Manager O. U
A RESOLUTION OF THE MAYOR AND CITY COMMISSION OF THE CITY OF
MIAMI BEACH, FLORIDA, APPROVING AND AUTHORIZING THE MAYOR
AND CITY CLERK TO EXECUTE AN AMENDMENT TO THE CURRENT
PROFESSIONAL SERVICES AGREEMENT BETWEEN THE CITY OF MIAMI
BEACH AND THE FIRM OF MCHARRY AND ASSOCIATES, INC., IN THE
AMOUNT OF $64,791, FOR THE PROVISION OF ADDITIONAL
ARCHITECTURAL, ENGINEERING AND LANDSCAPE ARCHITECTURAL
SERVICES TO COMPLETE THE DESIGN, CONSTRUCTION
DOCUMENTATION, CONSTRUCTION ADMINISTRATION, AND TO
DEVELOP SPECIFICATIONS FOR THE PROPOSED IMPROVEMENTS TO
FIRE STATION NO.4; AND APPROPRIATING $25,711 FROM THE
UN DESIGNATED FUND BALANCE, TO BE REIMBURSED BY OTHER
PROJECT FUNDS WHICH WILL BE APPROPRIATED AT TIME OF
CONSTRUCTION CONTRACT AWARD.
ADMINISTRATION RECOMMENDATION:
To:
From:
Subject:
COMMISSION MEMORANDUM
Adopt the Resolution.
FUNDING:
Funding in the amount of $39,080 is available from the previously appropriated 1999 General
Obligation (G.O.) Bond Fund as savings from the purchase of the previously approved Fire
Apparatus. Further funding in the amount of $25,711 is available from the General Fund
undesignated fund balance, to be reimbursed by other project funds which will be
appropriated at the time of construction contract award.
ANALYSIS:
Pursuant to an extensive period of planning and programming, on March 1, 2002, City staff
reached a consensus and approved the sixth option presented by the City's consultant, MC
Harry and Associates Inc., to improve the Fire Station NO.4 site. Unlike the five (5) previous
options developed by the consultant, Option 6 was deemed compliant with the project's
programmatic needs, and was designed in accordance with the project's site restrictions. Its
scope generally consists of the relocation of the existing historic Fire Station structure to a
southwesterly position on the site, and construction of a new state-of-the art three (3) bay
apparatus Fire Station in a northerly position, near 69th Street. It must be noted that the
City Commission Memorandum
February 5, 2003
MC Harry Additional Services for Fire Station No.4
Page 2 of 4
consensus was reached after the execution of Amendment NO.2 to the consultant's contract
by the Mayor and City Clerk. Amendment No.2 does not include the relocation of the existing
Fire Station.
Although Option 6 was determined to be the most efficient design solution for the project site,
additional architectural and engineering design services to re-grade a portion of the 69th Street
street-end will be necessary to achieve a safe and practical entryway for pedestrians and
motor vehicles alike, including the emergency fire trucks, to the new building.
Moreover, the relocation of the historic structure to a new position will also generate additional
architectural and engineering design work, not contemplated in the current Agreement
between the City and MC Harry and Associates Inc.
During the course of the design development phase, CIP and URS staffs met on several
occasions with the consultant to discuss what was the most logical and efficient critical path to
follow, to successfully complete the construction ofthe project on time and within budget. A
number of factors were considered, and several options were examined. At the end, it was
determined that the most efficient way is to construct the project in two (2) phases. The first
phase - Bid Package 1 - will consist of the relocation of the existing building, including
demolition of the new addition to the historic structure, and repair of the existing structure to
make it weather tight, as well as removal of the red tag (structural violations). The second
phase - Bid Package 2 - will generally consist of the construction of the new Fire Station No.
4, including appurtenant site work, landscaping, and site lighting.
Therefore, the consultant will be required to produce and administrate two (2) bid packages.
Bid Package 1, and Bid Package 2 will be permitted, bid, awarded, and constructed
separately. City staff recognized that additional effort, not covered under the initial
Agreement, will be required from the consultant to complete the revised scope, as defined
above.
Consequently, a series of meeting sessions were held with the consultant to discuss and
confirm the revised scope as well as to negotiate a potential increase requested by the
consultant to perform the additional work. MC Harry and Associates Inc.'s initial request for
additional services was $103,651. The Administration reached an agreement with the
consultant, subject to the Mayor and City Commission's approval, for $64,791. A credit in the
amount of $22,410 is included in the above negotiated amount. The credit is for work that
was previously removed from the scope of the original agreement due to budgetary
constraints. They are generally as follows:
. CIP and Parking Department personnel discussed and agreed in principle for the
proposed improvements to the parking lot adjacent to the Police Sub-Station be
funded by the Parking Department's budget. The scope of this improvement generally
consists in the re-striping of the lot. Minor modifications shall be necessary to make fit
21 cars in the lot, in lieu of the current 19 cars.
City Commission Memorandum
February 5, 2003
MC Harry Additional Services for Fire Station No.4
Page 3 of 4
. The renovation of the existing building's interior remains un-funded. Therefore this
scope was deleted from the original agreement with MC Harry. As a result, a credit for
associated architectural, landscape architectural, mechanical, electrical, plumbing, and
civil engineering design work was due, and issued to the City.
Moreover, the project's schedule was modified to reflect the project's scope amendment
described above. The following tables (Tables No.1 and 2) represent the updated schedules
for the project based on the two (2) bid packages' option.
On November 2, 1999, the citizens of Miami Beach approved the issuance of a $92 Million
General Obligation Bond to fund several needed improvements to City's parks and facilities,
neighborhoods and streetscapes, as well as fire safety facilities, and equipment. $2,700,000
in G.O Bond Fund was earmarked for the replacement of five (5) Fire Rescue vehicles. The
purchase of the new equipment was completed, and savings to cover the proposed additional
services fees was made. Savings in the amount of $39,080 is currently available, and the use
of such funds to pay for additional fire safety facilities and equipment improvements is
consistent with the citizens' expressed intention when the 1999 G.O. Bond was passed.
At this time, it is projected that there is a shortfall in the project funding, such that the
construction dollars are insufficient for the project design. If necessary, at the time of
construction contract award, the Administration will recommend an appropriate funding source
to make up the anticipated shortfall. At this time, the Administration recommends that
$25,711 be appropriated from the General Fund undesignated fund balance to complete the
funding of the Additional Services. At the time of the construction contract award, this amount
will be reimbursed by whatever funding source is identified to make up the anticipated project
shortfall.
CONCLUSION:
The Administration requests the Mayor and City Commission's approval and authorization to
pay the aforementioned additional services for Fire Station No.4 in the amount of $64,791
from the above savings.
TABLE -1
TENTATIVE PROJECT SCHEDULE UPDATE - BID PACKAGE 1: HISTORIC
BUILDING RELOCATION
Tasks Estimated Taraet date
100% Construction Documents Februarv 2003
City Review and Permittina March I April 2003
Bid Notice Aoril 2003
Construction Notice to Proceed June 2003
Construction close-out November 2003
City Commission Memorandum
February 5, 2003
MC Harry Additional Services for Fire Station No, 4
Page 4 of 4
TABLE-2
TENTATIVE PROJECT SCHEDULE UPDATE - BID PACKAGE 2: NEW FIRE
STATION NO.4
Tasks Estimated Taraet date
100% Construction Documents Mav 2003
City Review and Permittina Mav I June 2003
Bid Notice Julv 2003
Construction Notice to Proceed SeDtember 2003
Construction close-out September 2004
JMG/RCMrrH/MM
T:\AGENDA\2003\feb0503\regularlMCHARRYAMEDMENT3COM MEMO,doc
AMENDMENT NO.3
TO THE
PROFESSIONAL SERVICES AGREEMENT
BETWEEN
CITY OF MIAMI BEACH, FLORIDA
AND
MC HARRY ASSOCIATES, INC., DATED JULY 12, 2000; SAID AMENDMENT
IN THE AMOUNT OF $64,791, FOR THE PROVISION OF ADDITIONAL
ARCHITECTURAL, ENGINEERING AND LANDSCAPE ARCHITECTURAL
SERVICES TO COMPLETE THE DESIGN, TO DEVELOP SPECIFICATIONS
AND CONSTRUCTION DOCUMENTATION, TO PROVIDE CONSTRUCTION
ADMINISTRATION, FOR THE RELOCATION AND STRUCTURAL
RESTORATION OF THE EXISTING FIRE STATION NO.4 AND THE
CONSTRUCTION OF A NEW FIRE STATION FACILITY ADJACENT TO THE
EXISTING STRUCTURE.
THIS AMENDMENT NO.3, DATED AS OF FEBRUARY 5,2003, TO THAT CERTAIN
AGREEMENT, DATED JULY 12, 2000, BY AND BETWEEN THE CITY OF MIAMI
BEACH, FLORIDA (CITY), AND MC HARRY ASSOCIATES, INC. (CONSULTANT).
RECITALS
WHEREAS, on January 20,2000, Request for Qualifications (RFQ) No. 41-
99/00, was issued for architectural and engineering services for design and construction
administration for the rehabilitation of the existing building and an addition to Fire
Station No.4; and
WHEREAS, on July 12, 2000, the Mayor and City Commission approved a
Professional Services Agreement, in the amount of $160,636, with the firm of MC Harry
Associates, Inc. (Consultant), for design and construction administration services for the
rehabilitation of the existing Fire Station No.4, as well as an addition to the building to
house dormitories and fire apparatus, plus a not to exceed amount of $5,000, for
reimbursable expenses, (the Agreement); and
WHEREAS, on June 6, 2001, the Mayor and City Commission approved an
Amendment to the Agreement and appropriated $21,794, from the $92 Million General
Obligation Bond Program, to cover the costs of additional testing services; and
WHEREAS, on September 20, 2001, the City Commission approved a
Resolution instructing the City Administration to explore design options for the relocation
of the new combined Fire Station and Police Substation facility to a northerly position on
the site, for the restoration and renovation of the existing Fire Station NO.4 facility; and
WHEREAS, on January 22, 2002, the Planning Board recommended the historic
designation of the site; and subsequently, on January 25, 2002, City staff reached a
consensus to have the Consultant study the relocation of the existing building, proposed
for historic designation, to a southwesterly location on the site; and
WHEREAS, on March 20, 2002, Fire Station NO.4 was designated historic by
the Mayor and City Commission; and subsequently, on July 9, 2002, the Historic
Preservation Board approved the design concept for the Project, consisting generally of
the relocation of the existing building to a southwesterly location within the site, and the
construction of a new state-of-the-art 3 bay apparatus Fire Station in its place; and
WHEREAS, this new scope will require the consultant to provide additional
architectural and engineering services to complete the Project; and
WHEREAS, the City wishes to again amend the Agreement with Consultant, and
increase funds, in the amount of $64, 791, available as follows: $39,080, from the 1999
General Obligation (G.O.) Bond, and $25,711 from the Undesignated Fund Balance to
cover the additional architectural and engineering fee for the Project.
NOW, THEREFORE, The City and Consultant agree to amend the Agreement as
follows:
1. ABOVE RECITALS
The above recitals are true and correct and are incorporated as a part of this
Amendment NO.3.
2. MODIFICATIONS
The Agreement is amended to include the Additional Services, as described in
Exhibit "A" entitled "Scope of Services/Compensation for Additional Services",
attached hereto.
3. RATIFICATION.
The City and Consultant ratify the terms of the Agreement, as amended by this
Amendment NO.3.
IN WITNESS WHEREOF, the parties hereto have caused this Amendment No.3 to be
executed in their names by their duly authorized officials as of the date first set forth
above.
ATTEST: Q
~AJ,l \ {CLt ~
CITY CLERK
ATTEST:
By
F:\CAPI\$aIl\MAGMIC\GOBONDlMCHARRYAMENDMENT NO 3.dac
CONSULTANT
MC HARRY AND ASSOCIATES, INC.
~~
~~ A~l.
Print Name
APPROVED AS TO
FORM & LANGUAGE
& FOR EXECUTION
r Lf~ r <::;03
u.
Exhibit "A"
To Amendment No.3
Scope of Services/ Compensation for Additional Services
Scope of Services:
The scope of the Consultant's services shall include but not be limited to the
following:
Preparation of schematic design, design development, construction documents, bid
specifications, provisions of construction administration services and cost estimates
necessary to complete the improvements to the Fire Station No.4. The total project
should not exceed the new construction of 9,258 gross square feet and include the
relocation and limited renovation of a 3,500 square foot historic building and will be
bid and awarded in (2) phases. The improvements to Fire Station NO.4 shall include
the following:
I. Buildinqs
A. Demolition of the 1960's addition to the original 1930's Fire Station NO.4
building.
B. Relocation of the existing Fire Station to a southwesterly position on the
site consistent with the approval and order of the Historic Preservation
Board regarding the project and minor renovations of the original 1930's
Fire Station No.4 building.
1. Structural renovations required such that the existing building meets
current building codes.
2. Renovation of the exterior finishes consistent with the historic
character of the building, and necessary improvements to the systems,
to make the building weather tight.
3. Provide for all available utilities (entrance to building/make taps &
valves/do not activate).
4. Necessary site improvements in the areas immediately adjacent to the
relocated building to avoid hazardous conditions.
C. Construction of new facilities to include:
1. Three (3) bay "back in" apparatus facility (not drive thru configuration).
2. Program elements as per the design concept approved by the City
Commission, and by the Historic Preservation/ Design Review Board
on July 9, 2002, totaling 9,258 square feet (all elements except
apparatus bays, to be contained within a one story building).
II. Entrvwavs
A. Vehicular entryways for emergency vehicles, including the 69th street
street-end re-grading and any other appurtenant streetscape and
engineering improvements required by code and the entities having
jurisdiction to allow a safe, and practical vehicular and pedestrian
entryway to the new building, excluding Traffic Engineering or
Signalization.
B. Entranceways and walkways for pedestrians leading into the new Fire
Station.
III. Site Liqhtinq
A. Site and security lighting around the new Fire Station and as required by
code around all improvements.
IV. Landscapinq
A. New landscaping and irrigation around the new Fire Station and sod all
disturbed areas.
Compensation:
Original Agreement amount $165,636.00
Amendment No.1 $21.794.00
Amendment NO.2 $54.247.00
Amendment No.3 $64.791.00
Revised Agreement amount $306.468.00
F:\CAPI\$aIl\MAGMIC\GOBDNO\MCHARRY ATTACH Arrendrrent NO.3.doc